Slab Openings PDF
Slab Openings PDF
Slab Openings PDF
Solutions
solutions for the practicing
structural engineer
Creating an Opening in
Existing Floors
From Planning
to Completion
R
T
S
C
U
E
R
U
T
Once the opening is located, relevant existing floor structures must be carefully assessed.
The proposed opening may affect existing floor
structures in one or all of the following ways:
(1) the design live load is increased at the new
stair landing area, thereby overloading adjacent
portions of the floor; (2) the original structural
design assumptions (e.g., continuous beam, arch
action, etc.) will not be satisfied after the opening
is made; (3) in the case of a T-beam, the flange is
partially or completely removed at the opening
side, thereby reducing flexural resistance and stiffness; and (4) structural capacities are undermined
when floor reinforcement is eliminated or cut
off when creating an opening in a concrete slab.
Actual effects on any existing floor structures are
dependent on its construction type.
Masonry arch floor construction, made of hollow
tiles or terra cotta, was very popular for buildings
constructed from the late 1800s to early 1900s.
The segmental masonry pieces work together, and
span between adjacent steel beams by using arch
action with tie rods to resist the tension thrust.
Once some segments are removed for an opening,
the corresponding arch action will be lost. The
remaining pieces will not be stable and should
be removed. If a tie rod is to be cut off, it may be
necessary to install a new steel beam beforehand,
unless field conditions suggest that the required
tension thrust is properly resolved by the stability
of the adjacent spans or bays.
Steel wire catenary floor construction became
popular in 1910 and disappeared gradually after
World War II. The steel wires are draped and continuous over steel beams so that gravity loads are
sustained by the tension in the suspended wires,
which are encased in cinder concrete mainly for
the purpose of fire protection. When an opening
is to be made in this system, it is inevitable that
some wires will need to be cut, which will disrupt
the continuity and stability of the system. In order
e
n
i
z
a
g
Planning of an Opening
14 April 2013
R
T
S
C
U
a
U
T
z
a
g
15
E
R
e
n
i
STRUCTURE magazine
April 2013
R
T
S
C
U
a
U
T
e
n
i
z
a
g
STRUCTURE magazine
16
E
R
April 2013
Summary
Each building is unique, and there is no
one universal method by which to create
openings in every building type. In this
article, we have discussed basic principles
that should be respected when considering a proposed opening. There will arise
many deviations when facing actual projects. A structural engineer, with appropriate
knowledge and experience, will be required
to coordinate thoroughly with the owner,
architect and other relevant parties in order
to evaluate and implement an appropriate
and economical proposal, design and construction for a new floor opening.