Project Report Power Plant
Project Report Power Plant
NTPC
LIMITED
RIHAND
SUPER
THERMAL
POWER PROJECT,
RIHAND NAGAR SONEBHADRA (U.P.)
SUBMITTED BY:
GUIDANCE OF:
RAHULRAIKWAR
(B.M.D)
(B.M.D)
OF
ACKNOWLEDGEMENT
With feelings of joy and thanks, I placed in your hand my
Project report. It is my pleasant privileges to thank all those
who have help me in molding and shaping my project. Without
their guidance, cooperation and best wishes it would have been
impossible for me to complete my dissertation report. A big
thanks to all those who helped me by sparing time amidst their
busy schedule and for being kind enough to help me whenever
I needed them.
I feel grateful and wish to express my gratitude to MR. , HOD
of mechanical department of ST. ALOYSIUS INSTITUTE OF
TECHNOLOGY for providing me an opportunity to do the
project in my field of interest. I would also like to
acknowledge special thanks for his continual support and for
the creation of friendly environment in my work places.
As man is a social animal. He requires the
encouragement and affection of his parents and friends to
accomplish his goal and I have been Lucky to get it and make
this project report a success.
Finally, I am thankful to all the respected Executive
employees of N.T.P.C RIHAND, RIHAND NAGAR, for providing
me the necessary information, cooperation in VOCATINAL
TRAINING. I thank god almighty for his abundant blessing
because without it this project was only a dream.
DATE: 26TH JULY 2014
RAHUL RAIKWAR
CERTIFICATE
Approving Authority:
Guide:
CERTIFICATE
Approving Authority:
Guide:
CONTENTS
ABOUT NTPC
RIHAND SUPER POWER PROJECT INTRODUCTION
ABOUT N.T.P.C.
The NTPC was formed in 1975 to meet the power requirement challenge
faced by the nation during the period. N.T.P.C. (National Thermal Power
Corporation) is an Indian Govt. undertaking. Present installed capacity of
INTRODUCTION
2.1 SALIENT FEATURE
Location:
Present capacity:
UP
4680
Power Evacuation:
MP
1752
Total
6432
Beneficiary States:
Financing:
Major Resources:
COAL:(a) Source-
Amlori mines.
Chimney:
Ash disposal:
Commencement of work:
Rihand super thermal power project (RhSTPP) has the current generation
capacity of 3000MW. There are six Units where each Unit has the capacity of
500MW. Units 1 & 2 were commissioned in 1989 and Unit 3 & Unit 4 were
commissioned recently in August 2005. The power plant has two switchyards of
400KV & 132KV which are interconnected to each other. These switchyards feed
the northern power grid form where the transmission of power is done. One
400KV bus is used for H.V.D.C. transmission which delivers power from Rihand
to Dadri near Delhi. The thermal plant intakes water from the near by water
reservoir the Govind Vallabh Pant Reservoir based on Rihand river. The
reservoir rests on the dam named Rihand dam, which also powers the Hydro
power station of 250MW. The requirement of coal is fulfilled from Amlori coal
mines which are situated in Madhya Pradesh. The Rh.S.T.P.P. powers various
States such as Uttar Pradesh, Delhi, Punjab, Himachal Pradesh, Rajasthan etc.
New technology
ABSTRACT
Any thermal power plant is converting the chemical energy of fossil fuel (coal) into electrical
energy. The process involved for this conversion is based upon the Modified Rankine Cycle. The
major components that are used to accomplish the Modified Rankin Cycle are
Environment management
T
1
6
S
TURBINE
GENERAL DESCRIPTION
CLASSIFICATION OF TURBINE
IMPULSE URBINE
REACTION TURBINE
Based on Compounding:
Pressure compounded
Velocity compounded
IMPULSE URBINE
An impulse turbine uses the impact force of the steam jet on the blades to turn the
shaft. Steam expands as it passes through the nozzles, where its pressure drops and
its velocity increases. As the steam flows through the moving blades, its pressure
remains the same, but its velocity decreases. The steam does not expand as it flows
through the moving blades.
i.e IMPULSE TURBINE = In a stage of Impulse turbine the pressure/Enthalpy
drop takes place only in Fixed blades and not in the moving blades
REACTION TURBINE
In the reaction turbine, the rotor blades themselves are arranged to form convergent
nozzles. This type of turbine makes use of the reaction force produced as the steam
accelerates through the nozzles formed by the rotor.
i.e REACTION TURBINE = In a stage of Reaction Turbine the
Pressure/enthalpy drop takes place in both the fixed and moving blades.
HP TURBINE
The outer casing of the HP turbine is of the barrel type and has neither axial nor a
radial flange. The guide blade carrier is axially split and kinematically supported.
The space between the outer casing and the inner casing is fed from admission
steam to HP turbine. This steam is drained through HP casing drain during start up
which promotes quicker heating of inner casing which results in lesser problems of
differential expansion. The inner casing is attached in the horizontal and vertical
planes in the barrel casing so that it can freely expand radials in all directions and
axially from a fixed point. The HP turbine is provided with a balance piston in the
admission side to counter act the axial thrust caused by steam forces. HP turbine is
provided with 17 stages of reaction blades.
IP TURBINE
It is of double flow construction and consists of two casings. Both are axially split
and inner casing kinematically supported and carries the guide blades. The inner
casing is attached to the outer casing in such a manner as to be free to expand
axially from a fixed point and radials in all directions. IP turbine is having 12X2
reaction stages per flow.
LP TURBINE
The casing of the double flow LP cylinder is of three-shell design. The shells are
axially split and of rigid welded construction. The inner shell taking the first rows of
the guides blades is attached kinematically in the middle shell. Independent of the
outer shell, the middle shell, is supported at four points on longitudinal beams. Two
rings carrying the last guide blade rows are also attached to the middle shell. LP
turbine is provided with 6 reaction stages/flow.
Condensate system
LOCATION
LP FEED SYSTEM
HP FEED SYSTEM
FEED WATER HEATERS
EXTRACTIONS FOR HEATERS
DRIP SYSTEM
OPERATIONAL CONCEPT
CEP MOTOR
Make
BHEL Bhopal
Rating
Type
Voltage
11 KV 3 phase
Number Of Poles
Frequency
50 Hz
Stator Current
58.5 Amps.
Insulation Class
cage)
Self Air-Cooled.
OPERATING PARAMETER
LINE UP
Startup of BFP
Loading
Operation of MCV and ACV
Shut down
MD BFP operation requirement.
Charging
Extraction steam
Drip path
Care while bypassing HP HEATER
LP HEATER
Charging
Extraction steam
Drip path
BHEL
3 phase AC
10 MW
11 kv
601.5 amps
1495 rpm
DERATER TANK
1400C
BFP
FEED
REGULATION
STANDERED
H P HEATER
2580C
ECNOMISER
3000C
BOILER DRUM
CONDENSATE POLISING
UNIT
L P HEATER
CEP
H P TURBINE
170 Kg/CM2
5400C
HOT WELL
REHEATER
5400 C /40 Kg
CONDENSER
I P TURBINE
40Kg/CM2 5400C
L P TURBINE
TURBINE AUXILIARIES
Turbine casing
Steam turbine casings are the massive steel casings that encase the internal
stationary and rotating components of the turbine. Turbine casings have two critical
functions:
a) Containing the steam pressure and
b) Maintaining support and alignment of the internal components.
There are generally two casings:
i) Outer casing
The outer casing is divided on the horizontal centerline into top and bottom half
casings. Both the halves are bolted together with bolts and cap nuts at their
horizontal joint flanges.
ii) Inner casing
The inner casing is subjected to the highest temperatures and pressures, is also
divided at the horizontal centerline into top and bottom half casings, which are
bolted together in a similar manner at their horizontal joint flanges.
The inner casing is supported within the outer casing in such a manner as to
maintain proper alignment and allow thermal expansion. Cracking of the casing
can lead to steam leaks and, in extreme situations, to bursting. Cracks in casings
are typically located at the inlets of HP and IP turbine sections, where the local
thermal stresses are higher.
Turbine Blades
Blades are the single most costly parts of the turbine. The function of the turbine
blades is to convert the available heat energy carried by the steam into mechanical
energy. Blades fitted in the stationary part are called guide blades or nozzles and
those fitted in the rotor are called moving blades.
Steam chests and valves
Each of the HP, IP, LP cylinders of the turbine has four steam chests two on each
side of the turbine. Steam chests are the pressure vessels or steam carrying spaces,
which performs the function of both carrying as well as transferring the steam at
high pressure and high temperature via valves into the turbine cylinders. These
steam chests comprises of a stop valve and a governing valve.
The steam from the superheaters outlets is admitted to the HP steam chests via four
HP steam mains. The steam from the steam chests is admitted to the HP turbine
steam inlet pipe through the emergency stop valves and the associated governing
valves which are housed in steam chests. After expansion in the HP turbine the
steam is fed into the reheater and then to IP steam chests, through HP turbine steam
outlet pipe. The steam from IP steam chests is fed into the IP turbine via IP stop
valve and IP governing valves and then to LP steam chests.
Stop valves
The stop valves are emergency valves placed in the steam chests and are provided in
the main steam line. The purpose of the emergency stop valves is to cut off the
steam supply during periods of shutdown and to provide prompt interruption of
steam flow through the turbine cylinders in an emergency trip.
Normally, these valves are kept open fully but during emergencies these valves are
fully closed (100%). During such conditions, the plant is producing no power
because no input is given to the turbine.
Governing valves
The governing valves are also situated in the steam chests. These are the control
valves i.e. they provide accurate control of the steam flow rate into the turbine, thus
controlling the generator load when the machine is synchronized to the grid.
HP governing valves are the most important valves. They controls the amount of
power produced by the plant or unit. For a unit producing 500 MW power, the HP
governing valve opening is kept as 40-45% of the total valve opening.
Turbine Oil System:
OIL SUPPLY SYSTEM
The oil supply system fulfills the following functions:
a) Lubricating and cooling the bearings.
b) Driving the hydraulic turning gear during interruptions to operation, on start
up and shut down [1].
c) Jacking up the shaft at low speeds (turning gear operation, start up and shut
down) [1,2].
OIL SYSTEM
Under normal operating conditions, the main oil pump (1) situated in the bearing
pedestal and coupled directly to the turbine shaft draws oil from the main oil tank (26)
and conveys it to the
pressure oil system.
The suction of the main oil pump is aided by two injectors (25). The injectors produce
pressure at the suction connection to the main oil pump sufficient for all types of
operation. This guarantees that the main oil pump takes over the safe supply of oil and
cavitations that could occur due to greater suction heads are avoided. The amount of
oil required for driving is extracted from the pressure oil circuit and adjusted by
means of the throttle (31).
The oil for the turning gear (7) is also extracted from the pressure oil system. Oil is
admitted to the nozzles by opening the shut off valve (33). The pressure oil is cooled
in the oil coolers (19) and reduced to lubricating oil pressure in the throttle (18). The
throttle is adjusted on the initial start-up. The amount of oil required for each bearing
is adjusted on start up by means of the oil throttles (15).
MODE OF GOVERNING
PROTECTION
WIDE RANGE (Run-up) 40 TO 2960rpm
NARROW RANGE 40 TO GRID FREQ
HPGV-VALVE POSITION FIXED
PAY OFF VACUUM LOW
RAMP-UP
GOVERNING SYSTEM
GOVERNING MODULE
ARMING (COMPUTING, PROTECTION & VALVE POSITION)
RUN-UP (BARRING TO NORMAL SPEED)
CONTROL (COMPUTING CHANNEL TO EXTERNAL SIGNAL)
POTENTIOMETER (HPGV LIMIT, BIASING, DROOP, TSS)
OLT
DUMP SOLENIOD BIN INTERFACE (VALVE CTRL DUMP)
VALVE POSITION (LVDT FEEDBACK)
WRG, NRG, HPGV & SPEED MEAS.
ALARM SYSTEM (PAY OF < 120mmHg, MOD fail, VAC
Discprancy>12mmHg VALVE Position Discprancy >10% Mismatch )
The suction piping to the pumps is vented back to the condenser, to insure that the
non-operating pumps stays completely flooded. These vent lines include manual
valves on the vent for each pump.
A minimum flow (350 T/hr) recirculation line for each pump is provided, returning to
the condenser via a flow control valve and a locked open shut off valve.
The shaft seals of these pumps are the water-injected type fed from a header to
prevent the suction of air, particularly the pump that is not operating while the
condenser is under vacuum.
Condensate Extraction Pump:
The function of Condensate extraction pumps is to pump out the condensate to the
deaerator through gland steam cooler, and LP heaters. The steam from the LP
cylinders exhausts into the condenser shells where it is constrained to flow across
the water tubes, through which cooling water is circulated.
The steam condensed on the tubes drain to the bottom of the shell .The condensate
is retained in the condenser shell bottom by means of the condenser level control
valve. The water in a condenser provides a head of water for the condensate
extraction pump to suppress cavitations in its suction impellers.
There are two 100% duty extraction pumps, one remains in duty and one remains
stand by. With all the necessary instruments such as suction and discharge valve
isolating and dump valves to insure efficient operation.
The thrust bearings in the driving motors have temperatures sensor, which can trip
the motors automatically.
The pump discharge the condensate via the gland steam condenser and the
condensate polishing plant to the LP feed heating system.
Air Extraction Pump:
The function of the air extraction pump is to raise and maintain the vacuum
conditions in the turbine main condensers, and to remove air and other noncondensable gases vented to the condenser from various parts of the turbine and
feedwater heating system.
Gland steam condenser:
An automatic turbine gland sealing system is used to prevent the escape of steam
into the turbine hall, where it would condense on the walls and the plant.
It also prevents the ingress of air at the rotor ends of all the turbine cylinders. This is
done by using the gland steam condenser.
The function of the gland steam condenser is to maintain a sub-atmospheric
pressure at the outermost leak-off belt of the glands and thereby prevent the leakage
of steam from the glands into the turbine hall. The gland steam condenser condenses
the steam from the steam/ air mixture drawn from the outer pocket of the gland.
This heat given by the steam is absorbed by the feedwater. Condensate formed in
the shell drains to the gland steam condenser drain tank. This is again recirculated
back to the condensers.
Continuous
In order to properly select a boiler feed pump five key points must be
considered:
Will the pumps operation be continuous or intermittent?
This is an operational question and is often answered by the type of level control
found on the boiler that the pump will be servicing. As a general rule of thumb, boilers
with a capacity of 10,000 lbs./hr. or less utilize a float type switch that starts and stops
the boiler feed pump to satisfy a predetermined water level within the boiler. This is a
classic intermittent operation.
Boilers with capacities exceeding 10,000 lb./hr. typically employs a modulating feed
water regulator and will continuously feed water to the boiler at various rates depending
upon the water level in the boiler.
By knowing which operation you are to satisfy, you can determine which pump design
is best suited for your application. As a general rule of thumb a turbine pump is used in
an on-off situation and a centrifugal pump is used for continuous operation. But
remember, this is a general rule and is some cases a centrifugal could be used for an
on-off application and a turbine for continuous.
What is the temperature of the water being pumped?
It is also important to know the temperature of water you intend to pump. Most pumps
can usually handle 215F to 230F, other pumps are available that can handle higher
temperatures by using external water-cooling. Keep in mind that a deaerator pump
must be able to handle higher temperatures because they operate at a 5 psi or 227F.
drain is collected as clean drain into drain tank and dirty drain flows into common
drain header.
3) Steam System
For TDBFP there is three sources for steam namely 1. Auxiliary steam 2. Cold
reheat line 3. IP-LP cross over steam. Extraction steam parameters are maintained
at 4.0 kg/sq cm. & 300 degree centigrade. During cold start when CRH or IP-LP
steam is not available, Aux. Steamis used for rolling of TDBFP for initial boiler
filling. Once steam is insufficient for increasing the speed beyond 3500 rpm, CRH
steam is automatically cut off.
4) Feed Water System
Water from deaerator is taken through two suction into booster pump and then fed
into BFP suction. Drains & vents are provided in FW system for initial charging
and venting of BFP during rolling.
5) Gland Sealing of Turbine
Downstream steam from main turbine gland sealing is used for TDBFP sealing.
Before opening of exhaust valve gland sealing should be done as this is line is
connected to condenser.
6) Governing System
For having the required flow through BFP, speed of turbine has to be adjusted and
for what we need perfectly efficient governing system. Governing system is using
the control oil at 9 kg/sq cm. which in turn depending on the position of starting
device and speeder gear, will develop secondary oil and auxiliary secondary oil
pressure for operating the 4MCVs and one ACV thereby adjusting the steam flow
speed change is effected. Governing is achieved with the help of two governors
namely hydraulic and Electrohydraulic governors having EHG control and HG
follows it up.
BOOSTER PUMP:
Each boiler feed pump is provided with a booster pump in its suction line which is
driven by the main motor of the boiler feed pump. One of the major damages which
may occur to a boiler feed pump is from cavitation or vapour bounding at the pump
suction due to suction failure. Cavitation will occur when the suction pressure at the
pump suction is equal or very near to the vapour pressure of the liquid to be pumped
at a particular feed water temperature. Therefore all the three feed pumps are
provided with a main shaft driven booster suction line for obtaining a definite
positive suction pressure. The boiler feed pump is coupled with its driving motor
through hydraulic coupling. The hydraulic coupling serves the purpose of
controlling the speed of feed pump for maintaining a definite delivery head and
delivered quantity of the feed water as per the requirement of the boiler.
Deaerator:
Deaerators are used to remove oxygen from boiler feed-water. It performs the following
functions:
It serves as a feedwater heater.
Feedwater is deaerated by the removal of non-condensable gases present in the
feedwater and reduce the oxygen content to a level of about 0.007 ppm.
It acts as a buffer to the fluctuations of condensate feedwater flow that occur in service
durations.
The tank height provides a hydrostatic head to satisfy the suction pressure requirements
of the boiler feed pumps.
The presence of non-condensable gases in the feedwater causes the waterside corrosion or
thinning of the boiler tube walls and this further leads to the rupture of walls by the internal
fluid pressure.
Here steam injection-type deaerator is used to deaerate the feedwater. Feedwater from LP
heaters is admitted to the deaerator tank and steam is bled from two sources, one from the
HP turbine (which is known as cold reheat steam), and the other from the IP turbine
exhaust. When this steam and feedwater come in direct contact with incoming water is
heated and also gets deaerated.
Steam initially enters the deaerator through a special, stainless steel Jet Spray atomizing
valve. This valve is designed to fully atomize and provide complete deaeration under all
load conditions. This design insures that the purest steam comes in contact with the purest
water. Once this high velocity steam mechanically shakes out the last traces of noncondensable gases from the water, it flows upward into the pre-heater area where it meets
the incoming make-up water and pumped returns. This water continuously condenses the
steam, which preheats and releases the non-condensable gases into the internal vent
condenser where they are metered harmlessly to the atmosphere. This action causes more
steam to be drawn into 6the system to complete the cycle.
From the bottom of the deaerator, feedwater is piped through three outlet pipes, each with a
strainer, to the three boiler feed pumps and the used up steam is recirculated back to
condenser.
The deaerator is mounted at a high-level with its centerline 34.65 m above the datum level.
The deaerating heater utilizes steam by spraying the incoming water into an atmosphere of
steam in the preheater section (first stage). It then mixes this water with fresh incoming
steam in the deaerators section (second stage).
In the first stage the water is heated to within 2 C of steam saturation temperature and
virtually all of the oxygen and free carbon dioxide are removed. This is accomplished by
spraying the water through self adjusting sprat valves which are designed to produce a
uniform spray film under all conditions of load and consequently a constant temperature
and uniform gas removal is obtained at this point.
From the first stage the preheated water containing minute traces of dissolved gases flows
into the second stage. This section consists of either distributor or a several assemblies of
trays.
Here the water is in intimate contact with an excess of fresh gas/free steam. The steam
passes into this stage and it is mixed with the preheated water. Deaeration is
accomplished at all the rates of flow if conditions are maintained in accordance with
design criteria. Very little steam is condensed here as the incoming water has high
temperature caused by the preheating. The steam then rises to the first stage and carries
small traces of residual gases. In the first stage most of the steam is condensed and the
remaining gases passes to the vent where the non-condensable gases flow to the
atmosphere.
The water, which leaves the second stage, falls to the storage tank where it is stored for
use. At this time the water is completely deaerated and is heated to the saturated steam
temperature corresponding to the pressure within the vessel.
The condensate pressure just before the entry to deaerators shall be 3 psi more than the
deaerator steam pressure.
FEEDWATER HEATERS
A feed water heater is a special form of a shell and tube heat exchanger designed for
the application of recovering the heat from the turbine extraction steam by preheating
the boiler feed water. Its principal parts are a channel and a tube sheet, tubes, and a
shell. The tubes may be either bent tubes or a straight tubes. Feed water heaters may
be defined as high-pressure heaters when they are located in the feed water circuit
upstream from the high pressure feed water pump. Low-pressure feed water heaters
are located upstream from the condensate pump, whichs takes its suction from the
condenser hot well. Typically low pressure feed water heaters are designed for feed
water pressures between 27 kg/cm sq. and 57 kg/cm sq., high pressure feed water
heaters range from 112 kg/cm sq. to 335 kg/cm sq. for super critical boilers.
Each feed water heater bundle will contain from one to three separate heat transfer
areas and zones. These are condensing, desuperheating, and sub-cooling zones.
Economics og design will determine what combination of the three is provided in
each heater.
A condensing zone is present in all feed water heaters. Large volumes of steam are
condensed in this zone and most of the heat is transferred here.
The desuperheating zone is a separate heat exchanger contained within the heater
shell. This zones purpose is to remove superheat present in the steam. Because of the
high steam velocities employed, condensation within the desuperheating zone is
undesirable.
The sub-cooling zone is another separate counter heat flow heat exchanger whose
purpose is to sub-cooling incoming drains and steam condensate.
HEATER OPERATION:
Prior to opening the feed water valve, the channel start up vents are to be
opened and remain open until all passages have been purged and feed water begins to
discharge.
To remove air from the shell sides of a heater, which does not operate under
vacuum, the shell start up vent valves should be opened prior to the admission of the
steam to the feed water heater. The extraction lines must be free of all the
condensate to prevent the damage to the heater internals by slug flow.when the
drains outlet valve is opened, the shell start up vent valves are to be closed and the
operating air vent valves are to opened. Continuous venting of air and other noncondensable is assured by keeping the shell operating vent valves open.
On initial plant start up of the horizontal feed water heaters, having integral drain
coolers, the liquid level is to be kept just below the high-level alarm point.
On initial plant start-up of horizontal feed water heaters, having integral drain
coolers, the liquid level is to be kept just below the high-level alarm point. This will
avoid the possibility of flashing at the sub-cooler inlet and the possible tube damage
that can result. Approach temperature in excess of 8 degree centigrade indicate the
probability of flashing at the sub-cooler unit.
VENTING
Proper venting is necessary on feedwater heaters. All operating air vent
connections must be piped to permit continuous venting. The venting system in a
feedwater heater is designed to assure that all points where non-condensable gases
could collected are vented. Failure to utilize all of the operating air vents can lead to
corrosion damage and loss of performance due to air blanketing.
Vent lines of heaters operating at a different shell pressure must not be piped to a
common manifold. Failure to run individual vent lines from each heater has resulted
in inadequate or no venting of heater operating at a lower shell side than other heaters,
piped into a common manifold.
FEEDWATER BY-PASSING
A feedwater heater may be severely damaged by erosion and vibration, if it is
operated for any significant period or time with the next lower heaters feedwater flow
by passed. When a heater is by passed, its normal feedwater is passed on to the next
higher heater. This next higher heater will come close to making up the duty of both
the heaters. This single heater will tend to draw a total amount of extraction of steam
approx. equal to the flow of both the heaters.
In case of heaters with desuperheating zones, the increased steam load due to by
passing the previous heater can cause an excessive pressure drop in the
desuperheating zones, which can cause an excessive pressure drop in the
desuperheating zone, which in turn can cause condensation. The condensate flowing
at high velocity can lead to severe tube erosion.
Excessive steam flow to a heater, resulting from by passing the feedwater side of the
previous heater, can result in:
a) Localized high velocity leading to vibration of the tubing.
b) Flows, which cannot be adequately handled by the drain, control valve.
c) Condensation in the desuperheat zone and high velocity impingement.
LP Feed Heating System
The low-pressure (LP) feedwater heating system is provided to improve the thermal
efficiency of the heat cycle by heating condensate from the condenser with lowpressure steam bled from the LP cylinder.
Low-pressure (LP) feedwater heaters are basically simple straightforward tube and
shell heat exchangers, with the condensate passing through the tubes and the bled
steam being admitted to the shell.
There are total three LP heaters used in the feed heating cycle. Since, there is a
significant volume of unused space between the exhaust of a double-flow LP
cylinder and on the top of under slung condenser, this space is utilized by inserting
two LP heaters in a horizontal altitude. This results in the low-pressure drop and
high temperature for the bled steam, which is used for heating the condensate, with
consequential improvement in cycle efficiency. The LP heater No. 3 is located
outside the periphery of the condensers.
The heaters are stacked so that the ultimate LP heater can drain its bled-steam
condensate into the condenser above the working level of condensate in its base.
HP Feed Heating System
The high-pressure (HP) feedwater heating system is provided to improve the
thermal efficiency of the heat cycle by raising the temperature of the feedwater
before it enters the boiler. Like LP heaters HP feedwater heaters are also of
traditional form, but are arranged in a horizontal altitude to ensure free gravity
drainage of their bled-steam lines and heater-to-heater drainage. Bled steam to No. 6
HP heaters is fed from the HP turbine exhaust system and to No. 5 HP heaters from
IP turbine.
The system contains four HP heaters arranged horizontally in pairs with a drain
flash vessel situated above and between each pair. The pairs are identified as bank
A and bank B and each contains a No. 5 HP heater, a No. 6 HP heater and the
associated drain flash vessel. In the HP feed heating system, water is supplied from
the boiler feed pumps via the boiler feed regulating station and is piped through
three ways; one to each bank of heaters and one to the bypass pipe. When this
feedwater is passed through the HP heaters, its temperature is increased.
Each heater bank has its own feedwater inlet and outlet isolating valves, which,
with the bypass pipe and its spring-loaded valve, permits either bank to be taken out
of service for minor maintenance or repairs while plant is on load.
Drains from the HP heaters are taken either to the deaerator or to condenser A,
depending on the levels of water and pressures existing in the heaters, which in turn
depends on the generator load. The drains are controlled by level controllers and at
normal loads pass to the deaerator. At low loads, drains are diverted to the
condenser.
HP By-pass system
This system comprises of the operation of bypassing the HP steam without being
passed through the HP turbine. The HP steam is taken from each of the main steam
lines after the HP steam stop valves. The main steam passes into the cold reheat inlet
pipes via four pressure control valves and their associated isolating valves. The valve
include the spray water supply and control equipment .The H.P. valve will operate
automatically to maintain upstream pressure on start .In addition upon rapid load
rejection .These valves will operate to relieve 60% of MCR rated steam flow to the
reheat system .The H>P>relive valve mounted on the main steam pipe work will
operate to relive excess steam to atmosphere
LP By-pass system
The LP by-pass system consists of four lines taken from the four hot reheat pipes
(upstream of the IP turbine control valves). These four lines are then converged into
two. The steams in each line flows through an isolating valve, a pressure control
valve and then into the condenser dump tube, bypassing the IP, LP turbines.
Generator
The two 514 MW turbine-generator sets are set axially in line in the turbine hall.
The generator is a 2-pole, 3-phase, hydrogen and water-cooled machine, driven
from the turbine. The main exciter is solidly coupled to the rear end of the generator
shaft. A brush less main exciter provides the excitation power for the generator. The
output from this exciter is fed to the generator rotor.
The exciter line is directly coupled to the turbine generator shaft and is driven at
generator speed.
Each generator has its own independent stator windings.
Hydrogen is used to cool the generator rotor winding and stator core, the stator
winding is directly water-cooled.
Generator operational limits:
Rated output
Rated output
Nominal stator voltage
Speed
Power factor
514 MW
605 MVA
20 kV
3000 r/min
0.85 Lag
Frequency
50 Hz
U
P
E
R
H
E
A
T
E
R
HIGH PRESSURE
TURBINE
DESUPER HEATER
COLD REHEAT LINE
HOT REHEAT LINE
R
E
H
PRESSURE
E
A
T
I
N
R
E
H
E
A
T
IV
INTERMIDIATE
TURBINE
O
U
T
IV
DESUPER HEATER
TO LOW PRESSURE
TURBINE
MAIN BOILER
A. BOILER FUNDAMENTALS
Principles of combustion:
1. The primary function of oil and coal burning systems in the process of steam
generation is to provide controlled efficient conversation of chemical energy
of fuel into heat energy, which is then transferred to the heat absorbing
surfaces of the steam generator. When combustion is properly completed the
exhaust gases will contain, CO2, water vapour, sulphur dioxide and a large
volume of nitrogen, combining carbon and hydrogen with the oxygen in air
brings about combustion. When carbon burns incompletely it forms carbon
monoxide.
2. Composition of air:
a) 79% nitrogen and 21% oxygen by volume.
b) 77% nitrogen and 23% oxygen by weight.
3. Excess air:
In practice the theoretical quantity is not sufficient to ensure complete
combustion and extra air has to be supplied. This excess air is known as excess air.
4. Ignition:
Fuel must be ignited before it can burn. Raising the
temperature
of the fuel to its ignition temperature brings about combustion.
5. The following factors in efficient combustion are usually referred
to as The three TS.
a) TIME: It will take a definite time to heat the fuel to its ignition
temperature and having ignited, it will also take time to burn.
b) TEMPERATURE: A fuel will not burn until it has reached its ignition
temperature. Preheating the combustion air increases the speed at which
this temperature will be reached.
C) TURBULENCE:
Turbulence is introduced to achieve a rapid relative
motion between the air and the fuel particles. This produces a quick
propagation of the flame and its rapid spread throughout the fuel/air mixture in
the combustion chamber.
6) Combustion efficiency:
Maximum combustion efficiency depends on
c) Design of the boiler
d) Fuel used
e) Skill in obtaining combustion with the minimum amount of excess air.
7) Thermal efficiency of a boiler is measured by the amount of the heat
transferred to the water in the boiler by each Kg of the fuel used.
ARRANGEMENT OF THE MAIN BOILER:
DRUM INTERVALS:
Drum intervals are used to separate water from steam and to direct the flow of water
and steam in a manner so as to obtain the optimum distribution of drum matal
temperature in boiler operation.
The arrangement of drum normally consists of two or more integrated device,each of
which may be quite different in design and operate on totally different principles.Each
stage must have a higher separation efficiency.The greater the number of stages of
separation, the lower the required efficiency of each stage. Thus, two stages at 99%
efficiency, three stages at 90% efficiency and six stages at 70% efficiency will give
similar results.
Water level gauge is mounted on each end of the steam drum. If water level goes
outside of the prescribed operating limit then the boiler is tripped.Thus,with increase
in pressure,the separation of water from steam by simple devices become more
difficult.It become necessary to use more efficient apparatus if primary separation is to
be achieved in a confined area.
4) Economiser:
The purpose of the economizer is to preheat the boiler feed water
before it is
introduced into steam drum by recovering heat from the flue gases leaving the boiler.
Entering first, the economizer water is heated to about 30 to 40 deg C below
saturation temperature. From economiser the water enters the drum and thus joins the
circulation system. Water entering the drum flows down through the downcomer and
and entersring header at the bottom. It is located in the boiler second pass below the
superheater. The economizer is continuous loop type and water flows in upward
direction and gas in the downward direction. All tube circuits originate from the inlet
header and terminate at outlet headers which are connected with the economizer outlet
headers through three rows of hanger tubes.
5)Downcomers:
Down comers provide a passage for water from the boiler drum to bottom ring header.
From bottom ring header the water goes to water walls for heat absorption and
conversion into steam heating .To achieve the circulation of water into water wall
Boiler circulation pumps are provided in down comers.
6) Water walls:
Water walls are the necessary elements of the boiler. They serve as the means of
heating and evaporating the feed water supplied to the boiler from the economizers
via boiler drum and down comers.
In large boilers, water walls completely cover the interior surfaces of the furnace
providing practically complete elimination of exposed refractory surface. They
usually consist of vertical tubes membrane and are connected at the top and at the
bottom to headers. These tubes receive water from the boiler drum by means of down
comers connected between drum and water walls lower header.
Water walls absorb 50 percent of the heat released by the combustion of fuel in the
furnace, which is utilized for evaporation of feed water. The mixture of water and
steam is discharged from the top of the water walls into the upper wall header and
then passes through riser tubes to the steam drum.
The design and construction of the water walls depends upon the combustion and
steam conditions and the size of the boiler.
Orifices installed in the inlet of each water circuit maintain an appropriate flow of
water through the circuit.
7) Riser tubes:
A riser is a tube through which the mixture of water and steam pass from an upper
water wall header to the steam drum.
8) Super Heater:
There are three stages of super heater; the first stage consists of horizontal
superheater of convection mixed flow type with upper and lower banks located above
economizer assembly in the second pass. The upper bank terminates into hanger
tubes, which are connected into the outlet header of the first stage super heater. The
second stage superheater consists of a pendant platen, which is a radiant parallel flow
type. The third stage superheater pendant spaced is of convection parallel flow type.
In radiant super heaters heat is absorbed by direct radiation from the furnace and are
generally located at the top of the furnace. Since the furnace temperature, and
therefore the amount of available heat from radiation, does not rise as rapidly as the
rate of the steam flow, thus the steam temperature drops as the steam flow rises.
Convection superheaters absorb mainly by the impingement of flow of hot gases
around the tubes. A purely convection superheater has a rising steam temperature
characteristic i.e. the amount of available heat from convection, rise as rapidly as the
rate of steam flow.
9) Reheater:
The function of the reheater is to reheat the steam coming out from the high pressure
turbine to a temperature of 540C. The reheater is composed of two sections-one is
front pedant section and rear pedant section. The rear pedant section is located above
the furnace arc and the rear water wall and the front pedant section is located between
the rear water hanger tubes and the superheater platen section.
The cold reheat is the line from turbine to the boiler and is at a lower than the
reheat line from boiler to the turbine called hot reheat steam. Due to resistance of flow
through the reheat section, the hot reheat steam is at a lower pressure compared to the
cold reheat steam.
10) Burners:
There are forty total pulverized coal burners arranged on the corners at a height of 18
to 25 meters and twelve oil burners provided each in between corner two pulverized
two-fuel burner.
The pulverized coal burners are arranged in such a way that ten mills supply the coal
to burners at 4 corners, of the furnace. All the nozzles of the burners are interlinked
and can be tilted as a single unit from +30 to 30.
The oil burners are fed with the heavy fuel oil till boiler load reaches to about 25%.
11) Desuperheaters:
A. Superheater Desuperheater:
The superheater desuperheater is fitted between stages 4 and 5(on transfer pipe) to
control the superheated steam at the specified terminal temperature of 540 oC. The
the drum through the generating circuits and back to the drum where steam is
separated and directed to the superheater. The water leaves the drum through
the downcomers at a temperature slightly below the saturation. The flow
through the furnace wall is at saturation. Heat absorbed is the latent heat of
vaporization creating the mixture of steam and water.
At very a high pressure the density difference between steam and water becomes
progressively less and a point is reached where natural circulation is too slow. Natural
circulation is limited to boiler with drum operating pressure around 175 kg/cm-2.
To overcome this forced circulation is employed which uses pumps to speed up the
circulation of the water.
TECHNICAL DATA
Main boiler
500MW
Type
Nozzle.
Manufacturer
Furnace type
Controlled Circulation.
Drum
a. Overall length
b. Designed pressure
22070 mm
204.9 Ksc.
c. Designed temperature
366 oC.
Super heater
a. Number of stages
6 stages
Reheated
a. Number of stages
3 stages
1725 TPH
1530 TPH
1725TPH
316.4 TPH
178
At reheater outlet
At reheater inlet
43.46
45.85
From drum
193.5
Economizer inlet
196.6
BOILER AUXILIARIES
Arrangement of Boiler Auxiliaries
MILLING SYSTEM:COAL BUNKER: These are in-process storage silos used for storing crushed coal coming from the
coal handling plant through conveyor belts.
There are ten coal bunkers supplying coal to each mills and are located at top of the
mills to aid in gravity feeding of the coal. Each bunker can store coal, which can be
used for 12hrs.
COAL FEEDER: The purpose of coal feeder is to transfer coal at a pre- determined
rate, from coalbunker to the mill.
The coal feeder comprises two continuous chains with L sections flight bars
mounted between the chains at every fifth link .The chains runs on sprockets
mounted at each end of the feeder to given an upper strand movement towards the
driven ends and a lower strand movement in the opposite direction. The drive shaft
is supported on two self aligning bearing mounted in the Plummer block on support
out side the feeder casing, shaft sealing is achieved by the lip seals in the sealing
housing and mounted in board of the bearing to abut the feeder casing.
The tail sprocket shaft is mounted in adjustable bearing blocks adjacent to the feeder
casing with positioned which allow the feeder chain to be tensioned.
Both upper and lower strands run over full width carrying plates with the lower
strands located by angle section guides mounted on the feeder wall. The upper and
lower carrying plates and the inside wall are protected from wear by replace by
replaceable stainless steel panels, chains are kept clean by rubber wiper.
Feeder input is achieved by roller chain drive to the conveyor via a fixed speed
electric motor driving a variable speed gear box, torque limiter and fixed out put
gear box The electric motor is flanged mounted to variable speed gear box, coupled
to the fixed output gear box by a flexible coupling and torque limiter.
The principle of operation of coal feeder is that coal flows from the bunker into the
chain feeder via feed hopper and is conveyed to the mill feed inlet chute, when the
feeder is in the operation, the conveyor chain drag a fixed head of coal towards the
driven ends of the feeder. At the end of the carrying plates the coal falls through the
conveyor onto the bottom plate, where it is picked up by the returning flight bars
and dragged back along the feeder to fall into the mill feed chute.
MILL CHUTE: Mill chute trans port coal directly from the coal feeder to its associated mill, in
addition an emergency chute is incorporated to allow coal to be removed from the
coal bunker via coal feeder in the event that outage time is more than one month, or
if there is a danger from fire in the mill chute area, coal feeder, or coal bunker.
Each mill is provided which transport raw coal from the bunker to the inlet of mill at
the desired rate. The rate of feeding is controlled by variable speed gear box . Here
chain type feeder is present in which continuous chain is moving round sprockets in
which a sprocket is driven by a variable speed D.C motor and the other sprocket is a
return .Sprocket on this chain ,at different MS plates are connected which are called as
scrapers .This type chain feeder are called scraper feeder. The coal from the bunker
falls on a platform which is below the scrapper feeder. When the scraper moves it will
scrap the coal and at the end of platform the coal falls into the pulverizer.
PULVERISER MILL:There are ten mills for every 500 MW unit located adjacent to the furnace at 0 m level.
These mills pulverize coal to desired fineness to be fed to the furnace for combustion .
The main structure of the pulverisering mill is fabricated from mild steel in three
cylindrical sections, the bottom section (the mill housing support )which support the
entire unit and encloses the mill drive gear unit, a center section (the mill housing)that
contains the rotary grinding element and upper section (the classifier housing )
comprising an accommodate the gas loading cylinders of the mill loading gear .A
platform around the upper section provide an access to an inspection door and to the top
of the mill routine maintenance and is served by detachable ladder .
PULVERIZERS:
The pulverizser exclusive of its feeder, consists essentially of a grinding
chamber with a classifier mounted above it. The pulverizing take place in a rotating
bowl in which centrifugal force is utilized to move the coal, delivery by the feeder,
outwards against the grinding ring (buil ring). Rolls revolving on journals that are
attached to the mill housing pulverize the coal sufficiently to enable the air stream
through the pulverizer to pick it up. Heavy spring action through the journal saddles,
provide the necessary pressure between the grinding surfaces and the coal. The rolls
do not touch the grinding rings , even when pulverizer is empty. Tramp iron and
other foreign material is discharged through a suitable spout. The air and coal
mixture passes upward the classifier with its deflector blades where the direction of
the flow is changed abruptly, causing the coarse particles to be returned to the bowl
for further grinding. The fine particles, remaining in suspension, leave the classifier
and pass on through the coal piping to the windbox nozzles.
LOW SPEED MILL:
These are commonly known as tube ball mills and operate at approximately 17 to 20
rev/sec.Such slow speed is essential with these types of mills as otherwise the balls
will held along the rorating surface due due to centrifugal force and no milling takes
place.
Advantages of low speed mills:
(1). Wearable part which needs replacement between annual overhaulsis only the
ball and this can be done when mill is in operation.
(2). No maintenance for long period.
(3). this mill has no relects and does not give tramp iron problem.
(4). There is reverse of fuel within the mill which makes the mill output more stable.
Disadvantages of low speed mills:
(1). power consumed per ton of coal pulverised is nearly to that of economic mills.
(2). This mill consumes more power/ton coal ground especially when not loaded
fully as bulk of power is consumed in rotating mass of heavy ball charge.
BOWL MILL:
The ball mill is one of the most advanced designs of coal pulveriser. The advantages
of this mill are:
(1). lower power consumption.
(2). Reliability.
(3). Minimum maintenance.
(4). Wide capacity (1.7 t/hr. to100 t/hr.).
MILL TECHNICAL DATA:Manufacture--------------------------M/S BHEL
Type of pulveriser
1003x RP
No. of Mill / boiler
10
Base capacity of Mill
68Tonnes/Hr.
Speed of pulveriser
42rpm
Normal capacity with design coal
52.5 T/Hr
FANS
A fan is a device by which the air is made to flow at required velocity and pressure in
a defined path imparting K.E of its impellers to air/flue gases. This pressure boost is
used to create a draught in the air and flue gas system. Fans mainly perform two
functions:
i.
They supply air required for combustion in the furnace with required pressure
& flow.
ii.
They evacuate the product of combustion i.e. flue gases into the atmosphere
via chimney.
P.A FAN
The primary air fan supplies heated air to the coal mills to give dry and
pulverized coal to the furnace for efficient combustion. The P.A fan also supply fresh
air to prevent coal mills by overheating.
There are two P.A fans per boiler, each fan having pneumatically operated radial guide
vanes at the fan inlet to control the fan output. The fan impeller is a double inlet,
centrifugal wheel with backward curved plate blades.
Ambient air is drawn into the P.A duct by two 50% duty, motor driven
centrifugal fans. The air from each fan discharges into a hot air crossover duct via a
steam air heater. This duct extends around to each side of the boiler to supply the hot
air to mills duct, both of which are branched to supply hot air to four coal mills.
Salient feature of PA Fan
Type: Axial fan, constant speed, aerofoil, single stage with silencer & aerofoil
assembly in suction ducting.
Capacity
Total head
Medium handled
Fan Speed
Fan Regulation
Motor rating
170.5 m3/sec.
1183 mmwc
Air
1480 RPM
Blade pitch control
1817 KW
F.D Fan:
The forced draught fan system is provided to supply air required for pulverized coal
combustion in the furnace, air for fuel oil combustion and over fire air to minimize
Knox production.
The F.D fan system comprises of two single stage axial flow, constant speed, and auto
variable pitch fans per boiler. These fans provide pressurized atmospheric air to the
boiler for combustion.
Ambient air is drawn into the secondary air system by two 50% duty, motor driven,
axial flow forced draught fans with variable pitch control. The air from each fan
discharges into a hot air crossover duct via a main air heater.
This duct extends around to each side of the boiler furnace to form two secondary air
to burners ducts. At the sides of the furnace, each duct split to supply air to two
corners, then split again to supply air to each of the nineteen burner/air nozzle
elevations in the burner box.
Salient feature of FD Fan
Type: Axial fan, constant speed, aerofoil, single stage with silencer & aerofoil
assembly in suction ducting.
Capacity
Total head
Medium handled
Fan Speed
Fan Regulation
261.6 m3/sec.
391 mmwc
Air
980 RPM
Blade pitch control
Motor rating
1300 KW
F.D FAN
I.D Fan system:
The induced draught system comprises of three centrifugal double inlet fans per
boiler, two operating and one standby. Each fan unit consists of a backward curved
plate bladed impeller, which is driven by an electric motor through a variable speed
hydraulic coupling. The I.D fan serves the purpose of evacuating the products of
combustion or the flue gases in the atmosphere via chimney. The flue gases after
being cleaned in the precipitators is directed towards the atmosphere through the
chimney.
Scanner air fan:
Scanner fans are installed in the boiler for supplying continuously cooling air to the
flame scanner provided for the flame supervision. Normally one fan remains in
service while the other one remains available as standby.
Scanner air fan is centrifugal type. It takes suction from F.D fan outlet and boosts the
pressure further to provide cooling air to the scanners.
Seal air fan:
Seal air fan supplies sealing air, at a pressure higher than that inside the mill, to a
brush sealing around the stem of the coal mill yoke casting to prevent coal dust
escaping to atmosphere. There are eight seal air fans one per mill to provide sealing
air. Each fan is a close coupled, electrically operated, centrifugal fan unit operated as
part of the mill operating sequence, which incorporates an auto-start facility.
Purge or cooling air fan
The function of the purge/cooling air system is to provide a continuous supply of
clean air to cool all soot blowers in the retracted position, and to purge each
retractable soot blower lance whenever it is in the retracted position. There are two
fans (one operational, and one standby) to provide purging/cooling air to each of the
soot blowers, and also to prevent furnace gas blow-back into the sealing areas. Each
fan comprises a close coupled, electrically driven centrifugal fan unit, which initially,
is manually operated but which contains an automatic standby.
5. Electrostatic precipitators
The ash content in the Indian coal is of the order of 30% to 40%. When coal is fired
in the boiler, ashes are liberated and about 80% of ash is carried along with the flue
gases. If this ash is allowed to atmosphere, it is hazardous to health. So, it became
necessary to incorporate an electrostatic precipitator in the path of the flue gases
going in the atmosphere. The electrostatic precipitators are preferred to mechanical
precipitators because they are capable of precipitating particles from sub micron to
large sizes of particles. The efficiency of the modern ESPs is of the order of 99.9%.
In NTPC Rihand, the gas cleaning plant consists of two ESPs that operate on the
exhaust gases from each of the 500 MW steam generators.
The electrostatic precipitator consists of a large chamber, which comprises of
parallel rows of sheet type collecting electrodes suspended from the precipitator
casing with wire type discharge electrodes arranged mid-way between them. At the
inlet of the chamber, gas distributor screens for uniform distribution of the gases in
the chamber, are provided.
The collectors are connected to earth at positive polarity while the discharge
electrodes are connected to a high voltage dc supply at negative polarity. When
dust-laden gas flows between the electrodes, the corona discharge causes the dust
particles to become charged, the particles then being attracted towards and,
eventually, deposited on the collector electrodes.
This dust falls as the collecting electrodes are continuously rapped through a
rapping system and is collected into the pyramid type hoppers, located beneath each
collecting electrodes, from where it is removed by the ash handling system
6. Air heaters
Air heater is a heat transferring device in which air temperature is raised by
transferring heat from flue gases. Air heaters are capable of reclaiming heat from the
flue gases at low temperature levels and thus reducing the amount of heat rejected to
chimney. This results in increasing the boiler efficiency. For every 20 0C drop in flue
gas exit temperature, the boiler efficiency increases by about 1%. In NTPC Rihand,
recuperative type of air heaters is mainly used. In recuperative air heaters, the
heating medium i.e. flue gases flows through a closely packed matrix structure and
then air is passed through the matrix to pickup the heat. There are two recuperative
type of main air heaters for heating up the air from fans, two recuperative type air
heaters for mill air heating.
So, regular soot blowing is very necessary in the boiler. Similarly, soot is also
deposited on the air preheater baskets, which causes plugging of the baskets. Also in
case of oil firing during initial light-up unborn oil may deposit in baskets. This
deposited oil may cause fire hazard in air heater. To avoid these problems soot blowing
is done in air preheater also.
Soot blowing process:
The complete soot blowing process can be divided into following three major
sequential parts:
A. Shut down process- This part of the process step checks the close status of
all the valves.
B. Warm up process- In this step the valves according to the selected blower
group open to provide hot steam to the selected blower group at certain
pressure level.
C. Blowing process- In this sequence actual blowing of steam takes place.
The blower pairs under currently selected group when comes in to
operation carries the steam inside the boiler and continues to blow till it
returns to its park position.
The blowers are divided into groups, numbered from 1 to 9. Group 1 to 4 comprises of
wall blowers and group 5 to 9 comprises of long retractable soot blowers. The soot
blowers within each group are listed in pairs, with an odd numbered soot blower
paired with an even numbered soot blower.
Wall Blower:
Presently there are 88 wall blowers, which are numbered from 1 to 88. All wall
blowers are located at four levels, so grouped as group-1, group-2, group-3 & group-4,
of first pass of boiler each having 22 blowers. Group-1 is below furnace zone and
other three are above furnace zone.
Long Retractable Soot Blower:
LRSBs are kept in LHS and RHS of the boiler. Odd numbered LRSBs are kept in RHS
and even numbered LRSBs are kept in LHS. With an exception of group 6, all soot
blowers in a particular group are operated in synchronous pairs in an automatic
sequence i.e. an odd numbered soot blower with an even numbered soot blower
LRSBs are mainly used to penetrate between the tube banks of the economizer,
superheater etc. It consists of a fabricated box casing, steam lance tube, steam feed
tube, steam isolating valve, traverse and rotary chains, etc
Whenever the signal to operate the soot blower is given from the control room, an
electric motor drives the traverse reduction gearbox from its parked position, at a
preset distance the steam isolating valve opens to allow steam to flow through the feed
tube and out through the lance tube nozzles. The pattern of the steam jet from the
nozzles is helical with a different pitch on the inward stroke to that on the outward
stroke. At about mid-stroke a feed tube support rises to abut the feed tube preventing
sagging.
Whenever the extent of the stroke has been reached, a reverse limit switch is actuated
causing the main gearbox/lance tube to reverse and return to its parked position
engaging the stop limit ready for the next operation, having re-set the feed tube
support mechanism and isolated the steam isolating valve.
An air scavenge valve is fitted to the steam isolating valve which prevents the ingress
of boiler gases into the valve chest and provides a positive air flow when the soot
blower is in the parked position.
Air is also provided for the wall box to prevent gas leakage from the boiler.
23
24
25
26
27
28
45
46
47
49
50
48
12
17
13
14
15
16
34
35
36
37
38
39
58
59
60
61
56 57
67
68
69
70
71
72
FRONT WALL
WALL
REAR
123
124
78
83
WALL DESLAGGER
LONG RETRACTABLE SOOT BLOWER
125
126
AIR HEATER BLOWER
79
80
81
82
A thermal power plant is based upon the principle of conversion of heat energy into
mechanical energy. For this conversion of energy a power plant requires a turbo
machine.
A turbo machine is a power producing thermodynamic machine. In order to function, a
turbo machine requires a suitable working fluid, a source of high-grade energy and a
sink for low-grade energy. In a thermal power plant water is used as a working fluid
and it is converted into steam.
A steam turbine is a device that converts heat energy of the steam coming from the
boiler into the mechanical energy of shaft rotation.
NTPC Rihand has four 500 MW units. Each unit has one steam turbine.
For large turbo machines, multicylinder designs are used. The number of cylinder
depends on the terminal conditions of steam and speed of rotation. The turbine with a
number of cylinders on a single shaft is described as a Tandem compound machine.
NTPC Rihand is a fossil-fired power station using a typical turbine of 500 MW output
in each unit. Each of the two turbines consists of a single flow HP, a double flow IP
and two double flow LP turbines (cylinders) coupled to the generator shaft.
Each section of steam turbine consists of a rotor from which project several rows of
closely spaced blades. Between each row of moving blades there is a row of fixed
guide vanes (blades) that projects inward from circumferential housing. The vanes are
carefully shaped to direct the flow of steam against the moving blades at some angle
and at a high velocity that will maximize the energy conversion.
The cross-sectional diameter of a turbine section increases continuously and so the
steam expands. In this process the temperature and pressure of the steam decreases and
volume increases continuously. The LP section has the largest cross-sectional
diameter, whereas the HP has smallest cross-sectional diameter. Separate stop valves
and governing valves are provided to control the steam inlet and outlet from the
turbines.
The main auxiliaries of a steam turbine are the rotor, blades, guide vanes, casing,
bearings and couplings, bolting, steam chests, valves and critical piping.
INTRODUCTION TO 500 MW POWER PLANT
BOILER:
The boiler is a radiant, controlled circulation drum, dry bottom type unit. The boiler
units are designed for the following terminal conditions (mcr):
Evaporation a)SH outlet : 1,725 t/hr
The boilers are of single furnace design, circulating pumps to provide assisted
circulation.
Each Boiler corner is fitted with tilting tangential burner boxes comprising for high
energy igniters, four light-up heavy oil fired burners and eight pulverized coal burners.
The angle of tilt from the horizontal is about 30 deg to +30 deg.
Feed water to the boiler passes through HP feed heaters into the economizer and then to
the steam drum from where it flows into the suction manifold and furnace wall circuits
via the three boiler circulating pumps, returning to the steam drum as a water/steam
mixture. This mixture is separated into three stages and first two stages are incorporated
into the turbo separators and the final stage takes place at the top of the drum just before
the steam enters the connecting tubes comprising of first stage superheating.
Within the steam circuit there are a further four stages of superheating, making five in
total.
There are also three stages of reheat.
superheater temperature control is provided by spray attemperation situated in the
connecting link between the superheater low temperature pendant outlet header and the
superheater division panel inlet headers.
Pulverized coal system
The system for direct firing of pulverized coal utilizes bowl mills to pulverize the coal
and a tilting tangential firing system to admit the pulverized coal together with the air
required for combustion (secondary air) to the furnace.
As crushed coal is fed to each pulverize by the feeder, primary air supplied from the
primary air fans which dries the coal as it is being pulverized the transports the
pulverized coal through the coal piping system to the coal nozzles in the wind box
assemblies.
The pulverized coal and air discharged from the coal nozzles is directed towards the
center of the furnace to form firing circle.
Primary air system
The primary air draught plant supplies hot air to the coal mills to dry and convey
pulverized coal to the burners.
The P.A system comprises two P.A. fans, two steam coil air preheaters (SCAPH) and
two regenerative air preheaters. Each fans, which is of sufficient rating to support 60%
MCR load, discharges through a SCAPH into a common bus duct that has four outlets,
two directing air into the primary air preheater for heating, two direct cold air straight to
the pulverized mills.