Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

BQ

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 26

Item

Description
1

Unit

Qty

L.S

General Work
Site preparation and temporary works
including construction of two buildings
Contractor's office,hoarding, etc

Porter Way (West)

Fabrication of the RC hexagon pile 500 mm x


500 mm including rebar, formwork and
concrete

L.S

Pile driving and pile head treatment of the


500mm x 500mm RC hexagon pile

L.S

L.S

Slip Way
Fabrication of 400 x 400 RC rectangular pile
(exception of steel formwork)
pile driving, pile head treatment

L.S

Porter Way (East)

Fabrication of the RC hexagon pile 500 mm x


500 mm including rebar, formwork and
concrete

L.S

Pile driving and pile head treatment of the


500mm x 500mm RC hexagon pile

L.S

3
a

Total Amount (MMK)

Amount (MMK)

61,651,040.00

Remark

To approve payment
by JFE

43,973,140.00
170,709,552.00

15,035,800.00

Steel formwork supply


by JFE

154,968,320.00

27,973,140.00
167,038,352.00

641,349,344.00

reused steel formwork


from Poter Way (West)

BREAKDOWN OF TENDER PRICE


BILL OF QUANTITIES
Item

Description

Unit

Qty

Site preparation and temporary works including


installation & removal of Contractor's
1.1
office,quarters,stores,motor pool, workshop,guard
post, project information boards , and etc

Sum

Consultant's site office including construction ,


1.2 maintenance and removal including consultant's
facility and equipment.

Sum

Month

1.4 Environmental protection and monitoring

Month

Engineering preparation and control of work


including of shop-drawings, survey
1.5
works,laboratory test,inspection,reports and asbuilt drawings and etc..

Month

Manufacture and install construction sign board,


1.6 JICA ODA emblem and JICA project information
board

Sum

1.3

GENERAL

Safety equipment, security facilities, PPE, traffic


control, and etc

Subtotal 1
2

61,651,040.00

WEST & EAST PORTERWAY

2.1

Fabrication of the RC hexagon pile 500 mm x 500


mm including rebar, formwork and concrete

543

2.2

Pile driving and pile head treatment of the 500mm


x 500mm RC hexagon pile

No

28

2.3

Supply and installation of concrete for beam, slab,


pile head, abutment & curb

M3

340

2.4

Roofing including roof materials, hand rails,


painting, welding accessories and ancillary work

Unit

Subtotal 2
3

Amount (MMK)

337,747,904.00

###

STEEL BRIDGE

Fabrication of the steel bridge including materials,


3.1 connecting device to Porter Way and Pontoon ,
Welding works and etc

71,946,280.00

Unit

BREAKDOWN OF TENDER PRICE


BILL OF QUANTITIES
Item

Description

Unit

Qty

Unit

Unit

Unit

Install the existing Pontoon, Sponson and Steel


5.1 Bridge at the Porter Way West and move to MPA
dock yard

Sum

Removal of the existing Pontoon, Sponson and


5.2 Steel Bridge From Porter Way and move to MPA
dock yard

Sum

Sum

Construct New Slipway including fabrication pile,


installation, formwork installation, rebar
7.1
installation, supply and casting concrete, rubble
stone filling , and ancillary work

Sum

7.2 Construct staircase at the entrance of the Slipway

Sum

Installation of Steel bridge at the final position


3.2 including equipment and ancillary materials and
works

Amount (MMK)

Subtotal 3
4

PONTOON

Supply and installation concrete cover coating for


the Pontoon inculding reinforcement work,
4.1
formwork, casting concrete and ancillary works.
(The metalforms are provided by others)

4.2

Installation of the Pontoon including equipment and


provision of anchors, shackles and chains
Subtotal 4

6
6.1

TEMPORARY USE OF EXISTING STEEL BRIDGE,


PONTOON AND SPONSON

Subtotal 5
DEMOLISH OF EXISTING PORTER WAY
Demolish the existing Porter Way including
removing debris
Subtotal 6

SLIPWAY

Subtotal 7
8

WALKWAY

170,004,120.00

###

BREAKDOWN OF TENDER PRICE


BILL OF QUANTITIES
Item

Description

Unit

Qty

Supply and install ICB compacted formation base


8.1 course, sub grade, sand filling , curb stone lining
and repair of existing underlying drain pipes

M2

330

Supply and install concrete pavement including


compacted formation base course, sub grade, sand
8.2
filling , curb stone lining and repair of existing
underlying drain pipes

M2

130

50

60

Sum

Sum

Sum

Sum

Sum

Sum

Subtotal 8
9

REVETMENT
Repair of construct revetment including materials
9.1
and related works
9.2

Repair of construct fence along the existing


revetment including the foundation
Subtotal 9

10

PASSENGER TERMINAL BUILDING


Demolish existing Passenger Terminal Building
10.1
including removal of the debris
10.2

Construct new Passenger Terminal Buliding


including materials and related work

Construct and maintain Temporary Passenger


10.3 Terminal Shed, and remove after new Passenger
Terminal Building has been completed
Subtotal 10
11

PUBLIC TOILET
Demolish existing Public Toilet including removal of
11.1
debris
11.2

Construction of new Public Toilet including


materials and related works
Subtotal 11

12

UTILITIES

Electrical works for Passenger Terminal Building,


12.1 Public Toilet including power and lighting fixtures,
cable conduiting and wiring and external lighting

Amount (MMK)

BREAKDOWN OF TENDER PRICE


BILL OF QUANTITIES
Item

Description

Plumbing works for Public Toilet including sanitary


12.2 fitting inclusive of pipe works, tube well, pump ,
compressor, ground septic tank and ancillary works

Unit

Qty

Sum

Amount (MMK)

Subtotal 12
###

KDOWN OF TENDER PRICE


BILL OF QUANTITIES
KTCG Reply

Only construction of
Contractor's office

Only construction of
consultant's site office
Based on KTCG related
works
Withdraw
Based on KTCG related
works

Withdraw

Agreed
Agreed
Cancelled

Cancelled

Cancelled
Cancelled

KDOWN OF TENDER PRICE


BILL OF QUANTITIES
KTCG Reply
Cancelled

Cancelled

Cancelled

Cancelled

Cancelled
Cancelled

Cancelled

Cancelled
Cancelled

Pile driving work only

Withdraw

Cancelled

KDOWN OF TENDER PRICE


BILL OF QUANTITIES
KTCG Reply

Cancelled

Cancelled

Cancelled
Cancelled
Cancelled

Cancelled
Cancelled
Cancelled

Cancelled

Cancelled
Cancelled
Cancelled

Cancelled
Cancelled

KDOWN OF TENDER PRICE


BILL OF QUANTITIES
KTCG Reply

Cancelled

Kyaw Tha Construction Group Co., Ltd.

General Work

Item
1

10

11

12

Name of Work
- Site Clearing
- Labour Charges
- Site Office (1,160 Sq-Ft x 2 Nos.)
- Civil & M & E Work
- Office Facility
- 1.5 H.P Chigo Air Condition 3 Units & Accessories
- Carpet for Floor
- 15 KVA Generator Regulator
- Hoarding (Fencing)
- Civil Work
- Septic Tank
- Civil Work
- Piping Work
- Overhead Tank
- Civil + Steel Trestle Work + Fibre Water Tank
- Piping Work

Amount(MMK)
804,300.00

38,280,000.00

1,003,950.00
182,600.00
721,600.00

12,528,000.00

192,250.00
50,000.00

1,558,000.00
185,000.00

- Drilling Tube Well / Motor & Pump , Pump House


- Drilling Charges
- Motor & Pump , Pump House

81,000.00
300,000.00

- Rental Charges for Generator


- For 2 months (February + March)(59 Days)
- Diesel Consumption (200 - Gals x 4300 Ks)

860,000.00

- Electric Power Meter & M.E.P.E Power Line


- Registration & Deposit Fees
- Line Connection Charges
- Rental For Survey Group (February+March)
- Station Meter Rental Charges
- Survey Group

65,000.00
25,000.00

900,000.00
700,000.00

- Microsoft Software (Singapore)


- Project Software CD 2 Discs (2 x 766 S$ x 770 Ks)

1,179,640.00

- Access Road
- Material + Labour

1,399,000.00

Kyaw Tha Construction Group Co., Ltd.


1

General Work

Item
13

14

Name of Work

Amount(MMK)

- 9" Brickwall for Fence near Revertment


- Material + Labour

219,100.00

- Vinyl Signboard
- Material + Labour

416,600.00

Total Amount

61,651,040.00

Kyaw Tha Construction Group Co., Ltd.

Remarks

PAE = 16,500 Ks/Fs

FOC

Kyaw Tha Construction Group Co., Ltd.

Remarks

Porter Way (West)

Item

Description

Measurement
B
H

No

No

14

14

No
No

14
14

14
14

420,000
450,000

Formwork
formwork making for leader pile
formwork making for follower pile

No
No
No

4
4
4

4
4

2,000,000
2,000,000

Rebar
25 mm dia
10 mm dia

kg
kg

16000
3000

16000
3000

601
601

Steel Plate
12 mm thk steel plate
240 x 350 Cutting pieces
Slot - 4x50 x 100 on 240 x 350
4'x16'x16 mm thk steel plate
500 x 500 Cutting pieces
500 x 500 Cutting pieces- trimmimg 3mm all round
500 x 500 tapering

kg
No
No
No
No
No
No

1400
168
168
2.5
42
42
14

1400
168
168
2.5
42
42
14

795

m
Item
No
No
Gal
No
Gal
Item
Item
Item
No
No
No
Duty

14
1
14
2
1920
1
420
1
1
1
1
1
4
10

Qty

Unit Price
Labour

Unit

Material

2 Porter Way ( West)


A 500 x 500 mm RC hexagon Pile Casting
Concrete
Leader Construction
Follower Construction

500,000

Sub Total (A )
B Pile Driving
Driving charges
Mobilization, Demobilization of Pile Driving Machine
Diesel charges for pile machine
Rental fee to barge+tug
Diesel for Tug boat
Renal fee of services crane
Fuel charges for service crane
Mobilization and Demobilization of crane
Service fee of Pile driving crew
Surveyor Team
Preparation of Anchor, Anchor chain, winch
Installation and uninstallation of Diesel hammer and Crane
Bucker pile driving for anchor preparation on Land Side
Excavator for dredging

19.4

271.6
1
14
2
1920
1
420
1
1
1
1
1
4
10

43,500
5,000
5,000

2,500,000

Item

Description
Sleeper for pile stacking on land (5 layer)+ barge (5 layer)
Transportation for sleepers
Mobile crane for pile loading at High Tech (SPT)
Mobile crane for pile unloading at site
Transportation for piles
Night Lighting
Rent for pile location
Sub Total
Contingency and overhead (4%)
Sub Total (B)
Total Amount (A+B)

Unit

No

ton
No
Duty
Duty
Times
month
Item

4
2
10
15
7
1
1

Remark:
The above cost is not included for mooring charges at MPA buoy and other items related to Authorities permission.

Measurement
B
H

Qty
4
2
10
15
7
1
1

Material
700,000

Unit Price
Labour

Unit Price

Aount ( MMK)

Machine

Remark

5,880,000.00
6,300,000.00
8,000,000.00
8,000,000.00
57
50

700
2,800
3,000
3,000
8,000

10,526,640.00
1,951,500.00
1,113,000.00
117,600.00
470,400.00
1,250,000.00
126,000.00
126,000.00
112,000.00
43,973,140.00

28,000
2,100,000
25,000,000
24,000,000
1,700,000
6,000,000
5,000,000
3,200,000
2,500,000
800,000

7,604,800.00
2,100,000.00
609,000.00
50,000,000.00
9,600,000.00
24,000,000.00
2,100,000.00
1,700,000.00
6,000,000.00 including drinking water
5,000,000.00
2,500,000.00
3,200,000.00
10,000,000.00 Mob+Demob+
8,000,000.00 operation+fuel

Unit Price

Machine
365,000
800,000
800,000
600,000
3,000,000
1,000,000

Aount ( MMK)
2,800,000.00
730,000.00
8,000,000.00
12,000,000.00
4,200,000.00
3,000,000.00
1,000,000.00
164,143,800.00
6,565,752.00
170,709,552.00
214,682,692.00

Remark

Slip Way

Item

Description

Measurement
B

No

No

18

18

22 mm dia

kg

8000

8000

590

50

10 mm dia

kg

2000

2000

595

50

Steel Plate
12 mm thk steel plate
240 x 350 Cutting pieces
120 x 350 Cutting pieces
Slot - 2x50 x 100 on 120 x 350

kg
No
No
No

1400
36
36
36

1400
36
36
36

795

No
No
No

1
18
18

1
18
18

18

Mobilization, Demobilization of Pile Driving Machine

Item

Diesel charges for pile machine


Rental fee to barge+tug
Diesel for Tug boat
Renal fee of services crane
Fuel charges for service crane
Mobilization and Demobilization of crane
Service fee of Pile driving crew
Surveyor Team
Preparation of Anchor, Anchor chain, winch
Installation and uninstallation of Diesel hammer and Crane
Bucker pile driving for anchor preparation on Land Side

No
No
Gal
No
Gal
Item
Item
Item
No
No
No

18
2
1440
1
270
1
1
1
1
1
4

18
2
1440
1
270
1
1
1
1
1
4

Qty

Unit Price
Labour

Unit

Material

Machine

3 Slip Way
A Concrete
400 x 400 mm RC rectangal Pile Casting

380,000

Rebar

4'x16'x16 mm thk steel plate


400 x 400 Cutting pieces
400 x 400 Cutting pieces-trimming 3mm all round

700
700
1,400
500,000
2,000
2,000

Sub Total (A )
B Pile Driving
Driving charges

11.50

207

25,000
2,100,000
43,500
25,000,000
5,000
24,000,000
5,000
1,700,000
6,000,000
5,000,000
2,500,000
3,200,000
2,500,000

Excavator for dredging


Mobile crane for pile loading at High Tech (SPT)
Mobile crane for pile unloading at site
Transportation for piles
Night Lighting
Rent for pile location
Sub Total
Contingency and overhead (4%)
Sub Total (B)
Total Amount (A+B)

Duty
Duty
Duty
Times
month
Item

10
8
10
6
1
1

Remark: The above cost is not included for mooring charges at MPA buoy and other items related to Authorities permission.
The above cost is not included for mooring charges at MPA buoy and other items related to Authorities permission.

10
8
10
6
1
1

800,000
800,000
800,000
600,000
3,000,000
1,000,000

Aount ( MMK)

6,840,000.00

5,120,000.00
1,290,000.00

1,113,000.00
25,200.00
25,200.00
50,400.00
500,000.00
36,000.00
36,000.00
15,035,800.00

5,175,000.00
2,100,000.00
783,000.00
50,000,000.00
7,200,000.00
24,000,000.00
1,350,000.00
1,700,000.00
including
6,000,000.00
drinking water
5,000,000.00
2,500,000.00
3,200,000.00
10,000,000.00

Remark

Mob+Demob+
8,000,000.00
operation+fuel
6,400,000.00
8,000,000.00
3,600,000.00
3,000,000.00
1,000,000.00
149,008,000.00
5,960,320.00
154,968,320.00
170,004,120.00

Porter Way (East)

Item

Description

Measurement
B

No

No

14

14

No
No

14
14

14
14

Rebar
25 mm dia
10 mm dia

kg
kg

16000
3000

16000
3000

601
601

Steel Plate
12 mm thk steel plate
240 x 350 Cutting pieces
Slot - 4x50 x 100 on 240 x 350
4'x16'x16 mm thk steel plate
500 x 500 Cutting pieces
500 x 500 Cutting pieces- trimmimg 3mm all round
500 x 500 tapering

kg
No
No
No
No
No
No

1400
168
168
2.5
42
42
14

1400
168
168
2.5
42
42
14

795

m
Item
No
No
Gal
No
Gal
Item
Item
Item
No
No
No
Duty
Duty
Duty
Times
month
Item

14
1
14
2
1920
1
420
1
1
1
1
1
4
10
10
15
7
1
1

Qty

Unit Price
Labour

Unit

Material

4 Porter Way ( East)


A 500 x 500 mm RC hexagon Pile Casting
Concrete
Leader Construction
Follower Construction

420,000
450,000

500,000

Sub Total (A )
B Pile Driving
Driving charges
Mobilization, Demobilization of Pile Driving Machine
Diesel charges for pile machine
Rental fee to barge+tug
Diesel for Tug boat
Renal fee of services crane
Fuel charges for service crane
Mobilization and Demobilization of crane
Service fee of Pile driving crew
Surveyor Team
Preparation of Anchor, Anchor chain, winch
Installation and uninstallation of Diesel hammer and Crane
Bucker pile driving for anchor preparation on Land Side
Excavator for dredging
Mobile crane for pile loading at High Tech (SPT)
Mobile crane for pile unloading at site
Transportation for piles
Night Lighting
Rent for pile location
Total
Contingency and overhead (4%)

19.4

271.6
1
14
2
1920
1
420
1
1
1
1
1
4
10
10
15
7
1
1

43,500
5,000
5,000

2,500,000

Item

Description

Unit

No

Sub Total (B)


Sub Total (A+B)
Remark:
The above cost is not included for mooring charges at MPA buoy and other items related to Authorities permission.

Measurement
B

Qty

Material

Unit Price
Labour

Unit Price

Aount ( MMK)

Machine

Remark

5,880,000.00
6,300,000.00
57
50

700
2,800
3,000
3,000
8,000

10,526,640.00
1,951,500.00
1,113,000.00
117,600.00
470,400.00
1,250,000.00
126,000.00
126,000.00
112,000.00
27,973,140.00

28,000
2,100,000
25,000,000
24,000,000
1,700,000
6,000,000
5,000,000
3,200,000
2,500,000
800,000
800,000
800,000
600,000
3,000,000
1,000,000

7,604,800.00
2,100,000.00
609,000.00
50,000,000.00
9,600,000.00
24,000,000.00
2,100,000.00
1,700,000.00
6,000,000.00
5,000,000.00
2,500,000.00
3,200,000.00
10,000,000.00
8,000,000.00
8,000,000.00
12,000,000.00
4,200,000.00
3,000,000.00
1,000,000.00
160,613,800.00
6,424,552.00

including
drinking water

Mob+Demob+
operation+fuel

Unit Price
Machine

Aount ( MMK)
167,038,352.00
195,011,492.00

Remark

You might also like