BQ
BQ
BQ
Description
1
Unit
Qty
L.S
General Work
Site preparation and temporary works
including construction of two buildings
Contractor's office,hoarding, etc
L.S
L.S
L.S
Slip Way
Fabrication of 400 x 400 RC rectangular pile
(exception of steel formwork)
pile driving, pile head treatment
L.S
L.S
L.S
3
a
Amount (MMK)
61,651,040.00
Remark
To approve payment
by JFE
43,973,140.00
170,709,552.00
15,035,800.00
154,968,320.00
27,973,140.00
167,038,352.00
641,349,344.00
Description
Unit
Qty
Sum
Sum
Month
Month
Month
Sum
1.3
GENERAL
Subtotal 1
2
61,651,040.00
2.1
543
2.2
No
28
2.3
M3
340
2.4
Unit
Subtotal 2
3
Amount (MMK)
337,747,904.00
###
STEEL BRIDGE
71,946,280.00
Unit
Description
Unit
Qty
Unit
Unit
Unit
Sum
Sum
Sum
Sum
Sum
Amount (MMK)
Subtotal 3
4
PONTOON
4.2
6
6.1
Subtotal 5
DEMOLISH OF EXISTING PORTER WAY
Demolish the existing Porter Way including
removing debris
Subtotal 6
SLIPWAY
Subtotal 7
8
WALKWAY
170,004,120.00
###
Description
Unit
Qty
M2
330
M2
130
50
60
Sum
Sum
Sum
Sum
Sum
Sum
Subtotal 8
9
REVETMENT
Repair of construct revetment including materials
9.1
and related works
9.2
10
PUBLIC TOILET
Demolish existing Public Toilet including removal of
11.1
debris
11.2
12
UTILITIES
Amount (MMK)
Description
Unit
Qty
Sum
Amount (MMK)
Subtotal 12
###
Only construction of
Contractor's office
Only construction of
consultant's site office
Based on KTCG related
works
Withdraw
Based on KTCG related
works
Withdraw
Agreed
Agreed
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Withdraw
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
Cancelled
General Work
Item
1
10
11
12
Name of Work
- Site Clearing
- Labour Charges
- Site Office (1,160 Sq-Ft x 2 Nos.)
- Civil & M & E Work
- Office Facility
- 1.5 H.P Chigo Air Condition 3 Units & Accessories
- Carpet for Floor
- 15 KVA Generator Regulator
- Hoarding (Fencing)
- Civil Work
- Septic Tank
- Civil Work
- Piping Work
- Overhead Tank
- Civil + Steel Trestle Work + Fibre Water Tank
- Piping Work
Amount(MMK)
804,300.00
38,280,000.00
1,003,950.00
182,600.00
721,600.00
12,528,000.00
192,250.00
50,000.00
1,558,000.00
185,000.00
81,000.00
300,000.00
860,000.00
65,000.00
25,000.00
900,000.00
700,000.00
1,179,640.00
- Access Road
- Material + Labour
1,399,000.00
General Work
Item
13
14
Name of Work
Amount(MMK)
219,100.00
- Vinyl Signboard
- Material + Labour
416,600.00
Total Amount
61,651,040.00
Remarks
FOC
Remarks
Item
Description
Measurement
B
H
No
No
14
14
No
No
14
14
14
14
420,000
450,000
Formwork
formwork making for leader pile
formwork making for follower pile
No
No
No
4
4
4
4
4
2,000,000
2,000,000
Rebar
25 mm dia
10 mm dia
kg
kg
16000
3000
16000
3000
601
601
Steel Plate
12 mm thk steel plate
240 x 350 Cutting pieces
Slot - 4x50 x 100 on 240 x 350
4'x16'x16 mm thk steel plate
500 x 500 Cutting pieces
500 x 500 Cutting pieces- trimmimg 3mm all round
500 x 500 tapering
kg
No
No
No
No
No
No
1400
168
168
2.5
42
42
14
1400
168
168
2.5
42
42
14
795
m
Item
No
No
Gal
No
Gal
Item
Item
Item
No
No
No
Duty
14
1
14
2
1920
1
420
1
1
1
1
1
4
10
Qty
Unit Price
Labour
Unit
Material
500,000
Sub Total (A )
B Pile Driving
Driving charges
Mobilization, Demobilization of Pile Driving Machine
Diesel charges for pile machine
Rental fee to barge+tug
Diesel for Tug boat
Renal fee of services crane
Fuel charges for service crane
Mobilization and Demobilization of crane
Service fee of Pile driving crew
Surveyor Team
Preparation of Anchor, Anchor chain, winch
Installation and uninstallation of Diesel hammer and Crane
Bucker pile driving for anchor preparation on Land Side
Excavator for dredging
19.4
271.6
1
14
2
1920
1
420
1
1
1
1
1
4
10
43,500
5,000
5,000
2,500,000
Item
Description
Sleeper for pile stacking on land (5 layer)+ barge (5 layer)
Transportation for sleepers
Mobile crane for pile loading at High Tech (SPT)
Mobile crane for pile unloading at site
Transportation for piles
Night Lighting
Rent for pile location
Sub Total
Contingency and overhead (4%)
Sub Total (B)
Total Amount (A+B)
Unit
No
ton
No
Duty
Duty
Times
month
Item
4
2
10
15
7
1
1
Remark:
The above cost is not included for mooring charges at MPA buoy and other items related to Authorities permission.
Measurement
B
H
Qty
4
2
10
15
7
1
1
Material
700,000
Unit Price
Labour
Unit Price
Aount ( MMK)
Machine
Remark
5,880,000.00
6,300,000.00
8,000,000.00
8,000,000.00
57
50
700
2,800
3,000
3,000
8,000
10,526,640.00
1,951,500.00
1,113,000.00
117,600.00
470,400.00
1,250,000.00
126,000.00
126,000.00
112,000.00
43,973,140.00
28,000
2,100,000
25,000,000
24,000,000
1,700,000
6,000,000
5,000,000
3,200,000
2,500,000
800,000
7,604,800.00
2,100,000.00
609,000.00
50,000,000.00
9,600,000.00
24,000,000.00
2,100,000.00
1,700,000.00
6,000,000.00 including drinking water
5,000,000.00
2,500,000.00
3,200,000.00
10,000,000.00 Mob+Demob+
8,000,000.00 operation+fuel
Unit Price
Machine
365,000
800,000
800,000
600,000
3,000,000
1,000,000
Aount ( MMK)
2,800,000.00
730,000.00
8,000,000.00
12,000,000.00
4,200,000.00
3,000,000.00
1,000,000.00
164,143,800.00
6,565,752.00
170,709,552.00
214,682,692.00
Remark
Slip Way
Item
Description
Measurement
B
No
No
18
18
22 mm dia
kg
8000
8000
590
50
10 mm dia
kg
2000
2000
595
50
Steel Plate
12 mm thk steel plate
240 x 350 Cutting pieces
120 x 350 Cutting pieces
Slot - 2x50 x 100 on 120 x 350
kg
No
No
No
1400
36
36
36
1400
36
36
36
795
No
No
No
1
18
18
1
18
18
18
Item
No
No
Gal
No
Gal
Item
Item
Item
No
No
No
18
2
1440
1
270
1
1
1
1
1
4
18
2
1440
1
270
1
1
1
1
1
4
Qty
Unit Price
Labour
Unit
Material
Machine
3 Slip Way
A Concrete
400 x 400 mm RC rectangal Pile Casting
380,000
Rebar
700
700
1,400
500,000
2,000
2,000
Sub Total (A )
B Pile Driving
Driving charges
11.50
207
25,000
2,100,000
43,500
25,000,000
5,000
24,000,000
5,000
1,700,000
6,000,000
5,000,000
2,500,000
3,200,000
2,500,000
Duty
Duty
Duty
Times
month
Item
10
8
10
6
1
1
Remark: The above cost is not included for mooring charges at MPA buoy and other items related to Authorities permission.
The above cost is not included for mooring charges at MPA buoy and other items related to Authorities permission.
10
8
10
6
1
1
800,000
800,000
800,000
600,000
3,000,000
1,000,000
Aount ( MMK)
6,840,000.00
5,120,000.00
1,290,000.00
1,113,000.00
25,200.00
25,200.00
50,400.00
500,000.00
36,000.00
36,000.00
15,035,800.00
5,175,000.00
2,100,000.00
783,000.00
50,000,000.00
7,200,000.00
24,000,000.00
1,350,000.00
1,700,000.00
including
6,000,000.00
drinking water
5,000,000.00
2,500,000.00
3,200,000.00
10,000,000.00
Remark
Mob+Demob+
8,000,000.00
operation+fuel
6,400,000.00
8,000,000.00
3,600,000.00
3,000,000.00
1,000,000.00
149,008,000.00
5,960,320.00
154,968,320.00
170,004,120.00
Item
Description
Measurement
B
No
No
14
14
No
No
14
14
14
14
Rebar
25 mm dia
10 mm dia
kg
kg
16000
3000
16000
3000
601
601
Steel Plate
12 mm thk steel plate
240 x 350 Cutting pieces
Slot - 4x50 x 100 on 240 x 350
4'x16'x16 mm thk steel plate
500 x 500 Cutting pieces
500 x 500 Cutting pieces- trimmimg 3mm all round
500 x 500 tapering
kg
No
No
No
No
No
No
1400
168
168
2.5
42
42
14
1400
168
168
2.5
42
42
14
795
m
Item
No
No
Gal
No
Gal
Item
Item
Item
No
No
No
Duty
Duty
Duty
Times
month
Item
14
1
14
2
1920
1
420
1
1
1
1
1
4
10
10
15
7
1
1
Qty
Unit Price
Labour
Unit
Material
420,000
450,000
500,000
Sub Total (A )
B Pile Driving
Driving charges
Mobilization, Demobilization of Pile Driving Machine
Diesel charges for pile machine
Rental fee to barge+tug
Diesel for Tug boat
Renal fee of services crane
Fuel charges for service crane
Mobilization and Demobilization of crane
Service fee of Pile driving crew
Surveyor Team
Preparation of Anchor, Anchor chain, winch
Installation and uninstallation of Diesel hammer and Crane
Bucker pile driving for anchor preparation on Land Side
Excavator for dredging
Mobile crane for pile loading at High Tech (SPT)
Mobile crane for pile unloading at site
Transportation for piles
Night Lighting
Rent for pile location
Total
Contingency and overhead (4%)
19.4
271.6
1
14
2
1920
1
420
1
1
1
1
1
4
10
10
15
7
1
1
43,500
5,000
5,000
2,500,000
Item
Description
Unit
No
Measurement
B
Qty
Material
Unit Price
Labour
Unit Price
Aount ( MMK)
Machine
Remark
5,880,000.00
6,300,000.00
57
50
700
2,800
3,000
3,000
8,000
10,526,640.00
1,951,500.00
1,113,000.00
117,600.00
470,400.00
1,250,000.00
126,000.00
126,000.00
112,000.00
27,973,140.00
28,000
2,100,000
25,000,000
24,000,000
1,700,000
6,000,000
5,000,000
3,200,000
2,500,000
800,000
800,000
800,000
600,000
3,000,000
1,000,000
7,604,800.00
2,100,000.00
609,000.00
50,000,000.00
9,600,000.00
24,000,000.00
2,100,000.00
1,700,000.00
6,000,000.00
5,000,000.00
2,500,000.00
3,200,000.00
10,000,000.00
8,000,000.00
8,000,000.00
12,000,000.00
4,200,000.00
3,000,000.00
1,000,000.00
160,613,800.00
6,424,552.00
including
drinking water
Mob+Demob+
operation+fuel
Unit Price
Machine
Aount ( MMK)
167,038,352.00
195,011,492.00
Remark