Sewer Gravity Tunnel Breaks Through
Sewer Gravity Tunnel Breaks Through
Sewer Gravity Tunnel Breaks Through
KANEOHE
WASTEWATER
PRE-TREATMENT
FACILITY
KANEOHE
BAY DRIVE
AIKAHI
GARDENS
KANEOHE
BAY
KAILUA
REGIONAL
WASTEWATER
TREATMENT
PLANT
H3
Tunnel
route
KAILUA
KANEOHE
MOKAPU
BOULEVARD
KANEOHE WASTEWATER
PRE-TREATMENT
FACILITY
Estimated cost
NOVEMBER 2015
5,278
Approximate truckloads
of material excavated from tunnel
1,056
WHATS NEXT
Phase 1 continues with the installation of hundreds of pipe segments, each 10 feet
in diameter. Segments will be grouted into place to handle the wastewater flow.
KAILUA SHAFT
SHAFT SIZE: 87 feet wide
BELOW GROUND LEVEL: 95 feet
TBM reaches
midway point
of the tunnel
APRIL 2015
CRAIG T. KOJIMA / JAN. 12
Starts boring
with tunnel
boring machine
(TBM)
Artists
rendering
not to scale
TH
LENG
ET
20 FE
DIAMETER
10 FEET
com
com
Thickness: 3 inches
Weight: 18,000 pounds
Made of: Glass fiber-reinforced
thermosetting resin
885
Comparing loads
Average sewage
processed per day by
wastewater treatment
plants, in millions of
gallons:
PHASE 3: Facility
IN KANEOHE
Kailua
Regional
Honouliuli
Sand Island
12M
25M
62M
Project completion
After completion of the project,
the existing force main will be
decommissioned, and flow will be
redirected to the gravity tunnel.
2018
PROJECTED
COMPLETION
$371M
ESTIMATED
TOTAL COST
ity contractors have successfully bored a 3-mile tunnel beneath Oneawa Hills, a critical
component of the $371 million
Kaneohe-Kailua Waste Water
Conveyance and Treatment Facilities
Project, Mayor Kirk Caldwell announced
Tuesday.
It took roughly 13 months for the tunnel-boring machine to drill the
13-foot-diameter puka that eventually
will house a 10-foot pipe tasked with delivering sewage to the Kailua Regional
Wastewater Treatment Plant from the
Kaneohe Wastewater Pre-Treatment Facility by way of gravity.
The tunnel runs from a depth of 35
feet below ground level on the Kaneohe
side and travels down to a depth of 62
feet on the Kailua side, city officials said.
To complete the $200 million Phase 1,
contractors will now install 885 pipe
segments, each 10 feet in diameter and
20 feet long, that will carry the wastewater flow.
While the sewage will flow from
Kaneohe to Kailua, the boring actually
began from the shaft of the Kailua plant,
moved beneath the Aikahi Gardens subdivision through Halia Street, under the
Kailua side of H-3 freeway, crossed beneath Kaneohe Bay Drive and under the
Bay View Golf Course to reach the
Kaneohe facility.
In the $150 million Phase 2, a pump
station will be installed in the Kailua
shaft that will receive and move the flow
up to the treatment plant. In the $21 mil-
$200 million
gordonpang@staradvertiser.com
TUNNEL
LENGTH: About 3 miles
COMPLETED
KAILUA REGIONAL
WASTEWATER
TREATMENT PLANT
GROUND LEVEL
KANEOHE SHAFT
SHAFT SIZE: About 31 feet wide
BELOW GROUND LEVEL: 39 feet
OAHU
JANUARY 2015
Breaks through
the shaft wall
to begin boring
starter tunnel
JUNE 28
Tunnel boring
completed when
TBM meets
Kaneohe
excavator
A6