Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Sewer Gravity Tunnel Breaks Through

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

mile

KANEOHE
WASTEWATER
PRE-TREATMENT
FACILITY

KANEOHE
BAY DRIVE

AIKAHI
GARDENS

KANEOHE
BAY

KAILUA
REGIONAL
WASTEWATER
TREATMENT
PLANT

H3

Tunnel
route

KAILUA

KANEOHE
MOKAPU
BOULEVARD

KANEOHE WASTEWATER
PRE-TREATMENT
FACILITY

Pipe to carry wastewater from Kaneohe to Kailua will now be installed


GRAVITY-DR IVEN WASTEW
ATE R TO FLOW THIS WAY

PHASE 1: Digging the gravity sewer tunnel...

lion Phase 3, the final phase, a tunnel


influent facility will be built at the
Kaneohe facility.
The project, required by a court-mandated consent decree, began in 2013
and is expected to wrap up in 2018.
The tunnel-boring machine is nicknamed Pohakulani, Hawaiian for heavenly rock. Aikahi Elementary Schools
robotics team came up with the name.
Like other Honolulu sewer improvements, the project is funded by sewer
fees.
Caldwell, at a news conference, said
this is the first time the city has used
gravity tunnel technology, but it likely
wont be the last, adding that gravity
tunnels are preferable to force mains.
This is about living more sustainable
and more green, Caldwell said. When
you pump it under pressure, if theres a
force main break, a lot of sewage comes
out of the ground very quickly. But if its
gravity flow, theres no pressure, and
were not using any energy or electricity
to pump it.
Funding is in the 2017 budget for planning and design of a similar facility that
would take sewage from Waikiki to Ala
Moana, he said.
Don Painter, project manager for contractor Southland Mole, said the upfront
cost of gravity sewer technology might
be higher, but maintenance is cheaper
than force mains. A gravity sewer, once
its in the ground, its pretty much there
forever, and you dont have to do anything to it.

Estimated cost
NOVEMBER 2015

5,278
Approximate truckloads
of material excavated from tunnel

... and installing tunnel pipe lining

1,056

WHATS NEXT

Approximate truckloads of material


excavated from shafts on both ends

Phase 1 continues with the installation of hundreds of pipe segments, each 10 feet
in diameter. Segments will be grouted into place to handle the wastewater flow.

KAILUA SHAFT
SHAFT SIZE: 87 feet wide
BELOW GROUND LEVEL: 95 feet

TBM reaches
midway point
of the tunnel

APRIL 2015
CRAIG T. KOJIMA / JAN. 12

Starts boring
with tunnel
boring machine
(TBM)

Kane Pelkington moves a small


train through the tunnel of the
Kailua Regional Wastewater
Treatment Plant project site.

Artists
rendering
not to scale

PHASE 2: Pump station


IN KAILUA

TH
LENG

ET
20 FE

DIAMETER

10 FEET

com

com

The pipe will be


grouted in place inside
the bored tunnel
13 feet in diameter.

Thickness: 3 inches
Weight: 18,000 pounds
Made of: Glass fiber-reinforced
thermosetting resin

885

COURTESY BOWERS + KUBOTA

The pipes will be transported into the


tunnel using a special pipe carrier.

A construction worker is greeted on the Kaneohe side


of the tunnel Tuesday after emerging from an opening
in the tunnel-boring machine.

WASTEWATER TREATMENT PLANT

Comparing loads
Average sewage
processed per day by
wastewater treatment
plants, in millions of
gallons:

Video of the tunnel breakthrough


is available at staradvertiser.com.
MARTHA HERNANDEZ / MHERNANDEZ@STARADVERTISER.COM

PHASE 3: Facility
IN KANEOHE

A tunnel influent facility will be


constructed at the Kaneohe Pretreatment Facility.
TENTATIVE START .................................... 2017
ESTIMATED COST ......................$21 million

Steel ribs were installed


to support the tunnel wall.

Number of pipe segments


of varying length needed for
the 3-mile gravity tunnel

A tunnel influent pump station will


be installed in the Kailua shaft to
receive and pump the flows up to the
Kailua Treatment Plant.
TENTATIVE START ................................... 2016
ESTIMATED COST .................. $150 million

Kailua
Regional

Honouliuli

Sand Island

12M

25M

62M

Project completion
After completion of the project,
the existing force main will be
decommissioned, and flow will be
redirected to the gravity tunnel.

2018
PROJECTED
COMPLETION

$371M
ESTIMATED
TOTAL COST

Source: City and County of Honolulu

FROM PAGE ONE

ity contractors have successfully bored a 3-mile tunnel beneath Oneawa Hills, a critical
component of the $371 million
Kaneohe-Kailua Waste Water
Conveyance and Treatment Facilities
Project, Mayor Kirk Caldwell announced
Tuesday.
It took roughly 13 months for the tunnel-boring machine to drill the
13-foot-diameter puka that eventually
will house a 10-foot pipe tasked with delivering sewage to the Kailua Regional
Wastewater Treatment Plant from the
Kaneohe Wastewater Pre-Treatment Facility by way of gravity.
The tunnel runs from a depth of 35
feet below ground level on the Kaneohe
side and travels down to a depth of 62
feet on the Kailua side, city officials said.
To complete the $200 million Phase 1,
contractors will now install 885 pipe
segments, each 10 feet in diameter and
20 feet long, that will carry the wastewater flow.
While the sewage will flow from
Kaneohe to Kailua, the boring actually
began from the shaft of the Kailua plant,
moved beneath the Aikahi Gardens subdivision through Halia Street, under the
Kailua side of H-3 freeway, crossed beneath Kaneohe Bay Drive and under the
Bay View Golf Course to reach the
Kaneohe facility.
In the $150 million Phase 2, a pump
station will be installed in the Kailua
shaft that will receive and move the flow
up to the treatment plant. In the $21 mil-

$200 million

A tunnel-boring machine (TBM) drills a tunnel 13 feet in diameter and about


3 miles long from Kailua to Kaneohe. With the completion of the tunnel, the TBM
will be disassembled.

gordonpang@staradvertiser.com

TUNNEL
LENGTH: About 3 miles

COMPLETED

By Gordon Y.K. Pang

KAILUA REGIONAL
WASTEWATER
TREATMENT PLANT

GROUND LEVEL

KANEOHE SHAFT
SHAFT SIZE: About 31 feet wide
BELOW GROUND LEVEL: 39 feet

OAHU

JANUARY 2015

Breaks through
the shaft wall
to begin boring
starter tunnel

> > H O N O L U L U S TA R - A D V E R T I S E R > > W E D N E S D AY 6 / 2 9 / 1 6

JUNE 28

Tunnel boring
completed when
TBM meets
Kaneohe
excavator

A6

SEWER GRAVITY TUNNEL BREAKS THROUGH

You might also like