Item Particular Dedailed Specification 1 Site Clearing: Mortar
Item Particular Dedailed Specification 1 Site Clearing: Mortar
Item Particular Dedailed Specification 1 Site Clearing: Mortar
PARTICULAR
DEDAILED SPECIFICATION
Site Clearing
Excavation and
Foundation
Back Filling
Masonry work
Mortar
The mortar used in work shall have the strength not less
than 5 N/mm2 or 7.5 N/mm2 at 28 days as specified. Mortar
used should be of ratio 1:15.
Setting out Walling
The contractor shall provide proper setting- out rods and set
out all work on it for corners, openings, heights, and shall
build the walls.
Laying Brickwork
The brick shall be built in English bond with upwards facing
frog in case of 230mm thick brickwork.Each brick shall be
set with bed and vertical joints filled thoroughly
with mortar. Selected bricks shall be used for the exposed
brickwork as specified. The walls shall be taken up truly
plumb. All courses shall be laid truly horizontal and vertical
joints shall be truly vertical. Vertical joints in alternate
course shall come directly over
the other.
Joints
Bricks shall be laid that all joints are full of mortar. The
thickness of joints shall be not more than 10mm. The face
joints shall be raked to a minimum depth of 7mm by a
raking tool during the progress of the work when the mortar
is still green, so as to provide proper key for the plaster or
pointing to be done.Where plastering pointing is not to be
done, the joints shall be struck flush and finished at the time
of laying. The face of brickwork shall be kept cleaned and
mortar dropping removed.
Curing
Green work shall be protected from rain by suitable
covering.
Masonry work in cement mortar shall be kept constantly
moist on all faces for a minimum period of seven days. The
top of the masonry work shall be left flooded with water so
as not to disturb or washout the green mortar.
Concrete work
Compaction Of Concrete
Concrete shall be fully compacted throughout the full extent
Formwork
Construction of Formwork
Joints in formwork for exposed faces shall, unless otherwise
specified, be evenly spaced and horizontal or vertical and
shall be continuous in a regular pattern.All joints in
formwork shall be water tight. Where reinforcement projects
through formwork, the form shall fit closely round the bars.
Formwork shall be so designed that it may be easily
removed from the work without damage to the faces of the
concrete.
Preparation of Formwork
Before any reinforcement is placed into position within
formwork, the latter shall be thoroughly cleaned and then
dressed with a release agent. The agent shall be either
suitable oil incorporating a wetting agent, an emulsion of
water suspended in oil or low viscosity oil containing
chemical agents.
Removal of Formwork
The Contractor shall give 24 hour notice of his intentions to
strike any form works. Forms shall be removed without
shock vibrations or other damage to the concrete.
Formwork shall be carefully removed without shock or
disturbance to the concrete. No formwork shall be removed
until the concrete has gained sufficient strength to
withstand any stresses safely to which it may thereby be
subjected.
Flooring work
a)Concrete
flooring
Materials.
Cement: Portland cement as per specification under
Concrete Work
Aggregate of 12mm nominal gauge shall be properly
gauged.
Proportion.
The concrete shall be either 1:2:4 mix or 1:4:8 mix or as
specified in
the drawing. All mix shall be batched by volume except
cement, which
shall be proportioned by weight and as specified.
Mixing:
Mixing shall be done on a watertight platform. Material shall
be dry
mixed after accurately gauging different materials in
wooden boxes.
Preparation of Sub-grade
The sub-grade shall be cleared of all loose earth, rubbish,
and other
foreign matter. If necessary the sub-grade shall be cleaned
with wire
brushes. Cleaned sub-grade shall then be wetted with water
thoroughly, but no water pool shall be allowed.
Placing
Concrete shall be laid in horizontal layers and gently
Finishing
It shall be compacted first with wood float. The blows shall
be fairly
heavy but as consolidation takes place, light rapid strokes
shall be
given. Beating shall continue till all hollows in concrete are
filled with
mortar paste.The cement slurry shall be trawled smooth
with a steel float several times till approved finish is
achieved. The surface shall be without the float marks or air
holes.
Curing
Curing shall not be commenced until the top layer has
hardened.
Hardened concrete shall be kept wet for 15 days. Covering
with empty
cement gunnies shall be avoided, as the colour is likely to
bebleached with the remnants of cement matter from the
bag.
b)Mosaic/
Terrazzo Tile
Flooring
c)Tiling
Plaster Works
Windows and
Doors
Paint Works
Emulsion
Paints
Paint Application:
Painting Items as described hereafter shall comprise the
following,
and shall all include for preparing and priming surfaces as
above
described: Cement Paint : Apply two coats.
Plastic Emulsion : Apply a minimum of three coats, using a
thinning
medium or water only if and as recommended by the
manufacturer.
An approved plaster primer tinted to match may be
substituted for the
first coat.
Paint : Apply two undercoats and one finishing coat of
enamel gloss
oil paint.
Flat oil paint : Apply two coats of flat oil paint, using thinning
medium in accordance with the manufacturers
instructionsOil : Apply two coats of linseed oil.
Wax Polish : Apply a minimum of two coats to approval.
Lacquer : Apply three coats of Polythene lacquer as
described, to
approval.
Prime : Prepare and prime only before fixing
engineer.