API 510 Closed 4
API 510 Closed 4
API 510 Closed 4
Year
0
5
10
requires:
39. For Ammeter calibration for magnetizing equipment, the allowable tolerance is:
a. + or 5%
b. + or 10%
c. + or 15%
d. + or 20%
40. Which of the following are commonly preferred to know the process side degradation of pressure vessels?
a. On -stream inspection.
b. Internal inspection
c. External inspection as alternative to internal inspection
d. Any of above is OK
41. For MT examination by Prod technique the magnetizing current required depends on:
a. Prod Spacing
b. Thickness of item under Inspection
c. a & b above
d. None of above
42. While deciding the governing thickness for crown portion for corroded 2:1 ellipsoidal head, API 510 stipulates that & crown
thickness shall be calculated:
a. According to relevant ellipsoidal dished head formula
b. According to code formula for spherical heads with head radius equal to 0.9 D, where D is shell dia meter.
c. Thickness of crown shall be same as knuckle thickness.
d. None of the above.
43. For a vertical column, Internal dia. = 48" and height (T-T) = 80ft, The vessel MAWP is 60 psi. The vessel part MAWP for
bottom dished head (2:1 Ellip type) will be:
a. 94.6 psi
b. 82.8 psi
c. 95.5 psi
d. None of above
44. How is hammer testing utilized?
a. As a preliminary survey for thinned areas.
b. As a independent test method for which ASNT Certification in NDT is available
c. As a important tool in the hands of the Authorized inspection only
d. To carry out Charpy impact test
45. Which of the following represent grouping of weld-metals in ASME IX?
a. P - Nos.
b. F - Nos.
c. S - Nos.
d. A - Nos.
46. Which is/are advantage of magnetic particle testing over penetrant testing?
a.
b.
c.
d.
Less than 7
Greater than 7
It is 7
Greater than 10
54. The non-metallic coating dis-bonding in a vessel can be better detected by:
a. Eddy current testing
b. Holiday detection
c. Ultrasonic testing
d. Acoustic emission testing
55. External inspection of a pressure vessel starts with:
a. Ladder, stairs, walkway and platforms of the vessel
b. Insulation, skirt and foundation
c. The external surfaces, of vessel
d. Dimensional check of the vessel
56. Before carrying out an interior service inspection on a vessel put in-service for quite some time what should the inspector
should do first?
a. Check the material in which it is constructed.
b. Check the permanent file of the vessel.
c. Check the progressive history file of the vessel.
d. Check the original thickness report.
API 510
Closed Book-4
Answer Key
Q.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
ANS.
A
B
A
C
B
D
C
B'
C
B
B
C
B
C
C
A
A
REFERENCE
General Knowledge
API 510, 4.4
API 510. 6.3
API 510, 6.4
API 510 6.7
API 510 6.2
API 572 8.2.1
API 572 8.2.9
IRE II. 202.064
API 510, 5.2
API510 5.7 (d)
ASME VIII, UG - 16 (c)
API 510 7.11
API 510 5.2
IRE. Ch. II, 202.023
IRE. Ch. II page 12
API 572 Page 29
Q.
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
ANS.
C
B
B
B
C
B
B
B
C
B
B
B
C
B
C
A
D
18
46
19
20
21
22
23
24
25
26
27
28
B
A
D
C
B
C
B
D
B
C
47
48
49
50
51
52
53
54
55
56
B
D
C
B
C
C
A
B
A
C
REFERENCE
API 510 5.7 (e)
API 510 3.19
API 510 6.3 6.4
ASME VIII. UG - 11 (a)
API 510 6.4
API 510 6.4
API 510 6.3 6.4
ASME IX.OW - 163
ASME V. Art. 6, ADD. II
ASME V, Art. 1, Scope
ASME V. Art. 7. T-761
API 510 6.1
ASME V. Art. 7, T-752.2
API 510 5.7 (e)
BOK 80 + '2 x 0.433
API 572 10.8.1
ASME IX. Table QW - 442
ASME V, Art. 7, Scope & General
Knowledge
ASME V. Art. 2. T-271 (b)
ASME VIII. UG - 99
BOK 10 x 0.7 = 7 mm
API 572. 10.38
IRE II 203.02
API 572. Page 31
IRE II. Page 10
API 572. 10.4.6
API 572. 10.3.2
API 572. 10.4.3