03-4000mw Mundra Ultra Mega Power Project Brief Overview-Brrangaswamy
03-4000mw Mundra Ultra Mega Power Project Brief Overview-Brrangaswamy
03-4000mw Mundra Ultra Mega Power Project Brief Overview-Brrangaswamy
India has launched Ultra Mega Power Projects (UMPP). Mundra UMPP in Gujarat is
the first such project which is scheduled for commissioning in early 2011. Coastal
Gujarat Power Limited, a TATA Power Company has won the contract to construct
the first UMPP and Tata Consulting Engineers are involved in engineering the plant.
This paper discusses the many firsts in the country that this plant takes pride in,
scale of the project and salient features. The paper also discusses civil engineering
highlights related to certain critical systems and studies conducted in engineering the
plant and its systems. The systems / studies discussed include geological features,
plot plan, turbine building, and turbine foundation, cooling water system, concrete
volute pumps and reinforced concrete chimneys. The intent of the discussion is to
highlight challenges faced and enormity of scale to the civil engineering community
participating in this conference.
INTRODUCTION[1,2,3,4]
Power sector reforms were initiated in 1991 to encourage competition
and seek private participation in each sub-element of the sector,
namely generation, transmission and distribution. Fast Track private
sector projects with Government guarantees followed by the Mega
Power Policy were announced to attract large-scale private investment
into the sector. A major, new initiative for promoting competition and
attracting private investment in the power sector launched in the last
year of the Tenth Plan was the Ultra Mega Power Projects (UMPP)
program.
coal-based plants with a capacity of 4000 MW or above through tariffbased competitive bidding. The projects will include development of
power projects as well as associated coal mines in respect of pithead
sites and imported coal sourcing in respect of coastal sites. These
projects will be awarded to developers on BOO basis.
Nine Ultra Mega Power Projects (UMPPs) of 4000 MW each have been
originally identified for development under international competitive
bidding route. These include 4 pit head and 5 coastal sites.
Four
Andhra
830 MW. The zero date (start date) for the project was September 01,
2007.
2011. The other four units are planned for commissioning at 4 months
interval successively thereafter.
As this is the first UMPP in the country, a total of 55 basic studies have
been performed on engineering of various systems and subsystems in
the
major
engineering
disciplines
involved
mechanical,
civil,
The quantity of
Coal is transported to
site through a conveyor system from the New Adani Port directly to
the plant.
used for raw water requirements. Total water requirement for the five
units is about 730,000 m3 per hour.
The total length of cables laid in the plant area amounts to 1000km.
The distributed control system (DCS) is designed for an input / output
signal count of 50000. Power evacuation is through 400kV lines.
Some of the first times in the country for this plant are:
P92 material is being used for the main steam and hot reheat
piping
aspects
and
geotechnical
exploration
studies
were
performed
geological
with
reference
to
background
of
softer
Bathymetric survey for the sea and intertidal area was carried out to
get the data for bed contours, sea bed samples, sea water samples
and tidal current. This was carried out
Site specific
seismic study was carried out. This study has revealed that the seismic
values are less than the codal (IS 1893 ) values. However in view of
the
order
to
finalize
plot
plan,
around
25
different
alternate
water system and closed loop cooling system, as also both Merry Go
Round system for coal handling and new coal jetty conveyor systems.
The other systems were placed at different locations on the plot to
arrive at the most economical layout. The different alternatives were
evaluated in terms of area utilization, length of inlet / outlet CW
piping, length of outlet channel, effect of dust from coal yard, effect of
dust from ash disposal area, space for fabrication yard during
construction, space for lay down areas during operations maintenance,
space available for construction activities, corridor to be provided for
overhead
transmission
lines,
length
of
railway
track,
overall
appearance of the plant and costs. Finally, the option chosen was the
optimum in terms of evaluated parameters.
Figure 1 depicts a view of the chosen plot plan.
TURBINE BUILDING GENERAL ARRANGEMENT STUDIES[7,8,9]
Turbine Generator (TG) Building is one of the major entities of a power
plant.
steam
condenser,
flash
tanks,
air
washers,
plate
hear
deaerator and feed water storage tanks, air washer room etc. Erection
guidelines were formulated for each of the equipment.
A techno-
was
decided
to
go
ahead
with
structural
steel
framing
arrangement.
Generator stator is one of the heaviest parts that need to be handled
in the building.
response
(ii)
(CW) from the sea which calls for careful planning of the layout and
other design features of the CW system.
A separate study was carried out to formulate an optimum layout for
the system right from the CW intake up to the hot water outfall, to
study the oceanographic conditions prevalent in the offshore area with
respect to bathymetry, tide levels, currents, waves etc., to identify
alternatives available for the various sub-systems of the CW system
and
lagoon
(Bhavnagar)
and
Open
channel
(Tarapur).
From the main intake channel, water is pumped from CW pump house
through 10 pipes of diameter 2.8m to the condensers. Similarly, hot
water from condenser is conveyed to discharge channel through
similar pipes. The pipes are protected by 50mm guniting outside and
1:1 cement mortar of 20mm thickness. Suitable external protection by
RC jackets is provided for the pipes. The discharge channel itself is of
different widths varying from 80m to 200m in different reaches.
Hydraulic model studies have been performed to confirm assured
availability of water over complete tidal cycle and to assess sediment
transport.
Other
recirculation
and
model
thermal
studies
conducted
dispersion
studies,
include
model
hot
water
studies
for
which
eliminates
potential
corrosion
problems
often
all locations are within the permissible limits specified in IS: 456.
Tensile stresses are resisted by reinforcements. Bending moments are
worked
out
based
on
the
stress
diagram
and
the
required
previously, the Mundra chimneys are the largest built in the country.
The shell thickness varies from 900mm at the base to 400mm 160m
from the base and the shell is cylindrical from thereon.
studies,
turbine
building,
turbine
foundation,
CW
system,
congratulate every one of them for their efforts. Further, the author
duly acknowledges the permission granted by the management of Tata
Consulting Engineers and Coastal Gujarat Power Limited to make this
presentation.
REFERENCES
1. Eleventh Five Year Plan, Volume I Inclusive Growth, Planning
Commission, Government of India.
Five
Year
Plan,
Volume
III
Agriculture,
Rural
Consulting Engineers
12.
Stress
Analysis
of
Concrete
Volute
Pump,
Internal
15.
VOLUTE
CASING
SUCTION
DRAFT TUBE