Power System Stability Studies
Power System Stability Studies
Power System Stability Studies
Chrispin Singoyi
Division of Electric Power Engineering
Department of Environment and Energy
CHALMERS UNIVERSITY OF TECHNOLOGY
Gteborg, Sweden, November 2011
i
Chrispin Singoyi
In partial fulfillment for the award of Master of Science degree in Electric Power
Engineering, in the Department of Environment and Energy, Division of Electric Power
Engineering, Chalmers University of Technology, Goteborg, Sweden
Supervisor:
Kennedy Mwanza
ZESCO ltd
Engineering Development Directorate
Lusaka-Zambia
ii
Abstract
The purpose of this work is to look at the short term stability studies on 330 kV, 220 kV
and 88 kV transmission system of the whole ZESCO Power System in terms of voltage
and rotor angle stability after being exposed to severe system disturbances. The work also
considers the network expansions up to 2011. The initial conditions are considered
critically for better analysis. As one of the initial conditions to do the stability studies, all
system variables are within acceptable limits and the stability analysis is done at both off
peak and peak loads for static simulations and at peak loads only for transient simulations.
The assumptions considered, on the other hand on this study, are that the Zambian system
is connected via two 330 kV circuits to the Zimbabwe system to the south and to the 220
kV Congo DR system to the North but no power exchange between these two systems is
considered. Studies in steady-state and transient states have been carried out with an
expected peak load demand in 2011 amounting to 1670 MW (the losses on the
transmission system are not included). An additional study in stead state has been carried
out with an expected off-peak load demand in 2011 amounting to 1418 MW (the losses on
the transmission system are not included). In any case the generation is to match the load
demand values plus power system loses.
The methodology taken was to carry out Simulations in stead state to calculate the power
flows over the transmission system, the voltage profile and the active and reactive
generation of the generators. N-1 Contingency situations were examined. Whatever the
situation, the Zambian system must be able to satisfy the load demand and operate within
the acceptable limits. Simulations were also performed in transient state to verify that the
System was able to recover un acceptable situation without loss of synchronism of any
generator or sustained oscillations.The most severe faults being three phase faults near
generating stations and major substations on various system components and analyse the
results for a specific short period (10 seconds). The faults are cleared within 100 ms. Also
considered in the simulations is the taking out of some major loads and the analysis of the
effect.
The major findings are that in the stead studies the system is able to withstand any N-1
contingency without exceeding limits. And in the transient state studies the overall
behaviour of the system is not beyond limits. Oscillations are dumped within the expected
period of 4 to 10 seconds. All generators operate in synchronism.
Key words
Rotor angle stability, transient stability, inter-area oscillations, spinning or primary reserve.
iii
Acknowledgement.
Firstly I would like to give thanks to Dr. Tuan A. Le and the course coordinator, Ola
Carlson to give me the opportunity to do the thesis on our ZESCO power system.
My second gratitude goes to my classmate, Mr. Gustavo who guided me through the
process of learning the Power Factory soft ware by Dig Silent that I used on my stability
studies. There were no conditions attached, he was really helpful with his great knowledge
in Power Factory software.
Many thanks go to all my lecturers and classmates who shared the knowledge with me
during my Masters studies at Chalmers University of Technology. Class mates like Mr.
Thinley, Kalid T., Selamu T. to mention but a few, gave me un conditional guidance in
most of my Study work.
Not forgetting my workmates, from the department of Engineering Development, who
guided me in the simulations of various stability scenarios, Mr. Kennedy Mwanza, as my
supervisor who has great knowledge as well in Power Factory software, Mr. Julius
Kampamba, Mr. C. Nthala, Mr. G. Musonda and Mr. A. Sikombe. They gave me a
conducive working atmosphere. I worked freely with them.
The accomplishment of this project wouldnt have been made possible without the data
that I collected from various power stations and major substations. Therefore my sincere
gratitude goes to the ZESCO Engineers and Technicians who helped me gather all the
necessary data I needed.
iv
Contents
LIST OF FIGURES ............................................................................................................ viii
LIST OF TABLES ...............................................................................................................xii
Chapter 1: Introduction .......................................................................................................... 1
Chapter 2: Overview of the Zambian Power network ............................................................ 3
2.1
LIST OF FIGURES
Figure 1: The Zambian Power System ........................................................................................ 6
Figure 2: Classification of power system stability. ..................................................................... 8
Figure 3: Generator connected to infinite bus bar through two parallel lines. ............................ 9
Figure 4: Electrical representation. ........................................................................................... 10
Figure 5: Equal area criterion for the loss of one parallel line .................................................. 11
Figure 6: Short circuit at the end of the line .............................................................................. 13
Figure 7: Power angle relationship after a fault at either end of the parallel line ..................... 14
Figure 8: Fault in the middle of the line. ................................................................................... 15
Figure 9: Circuit model for the fault in the middle of the line .................................................. 15
Figure 10: Star delta transformation.......................................................................................... 15
Figure 11: Final circuit representation where only
is considered as the transfer
reactance .................................................................................................................................... 16
Figure 12: Equal Area criterion for the fault in the middle of the line...................................... 16
Figure 13: Critical clearing angle .............................................................................................. 17
Figure 14: Auto reclosing to either transient or persistent fault ................................................ 17
Figure 15: AVR Model IEEET1A ........................................................................................... 19
Figure 16: AVR Model SCRX/SEXS ...................................................................................... 19
Figure 17: Speed Governor Model IEEEG3 ............................................................................ 20
Figure 18: Power Factory general load model .......................................................................... 21
Figure 19: Load flow calculation window indicating the voltage dependence terms for load
flow calculations in Power Factory software. ........................................................................... 22
Figure 20: Diagram indicating the mixture of static and dynamic load model used for
stability studies. ......................................................................................................................... 22
Figure 21: Model used to approximate the behavior of the linear dynamic load. ..................... 23
Figure 22: Model used to approximate the behavior of the non-linear dynamic load. ............. 23
Figure 23: Low/High voltage approximations used in the non-linear dynamic load model. .... 24
Figure 24: Calculated load flow at peak period ....................................................................... 28
Figure 25: Copper belt load ...................................................................................................... 29
Figure 26: voltage profile ......................................................................................................... 30
Figure 27: Voltage profile ......................................................................................................... 31
Figure 28. Voltage profile with Kariba N-LHill line out .......................................................... 33
viii
Figure 52: Single line diagram of the Zambia Power System ................................................... 64
Figure 53: Model3 of SVC and its parameters .......................................................................... 66
Figure 54: Simulated fault on KFG-Lhill Line close to KFG HPP ........................................... 89
Figure 56: Voltage magnitude and rotor angle for a fault close to KFG HPP .......................... 90
Figure 57: Close-up fault to Kafue gorge bus bar on KFG-LHill line ..................................... 91
Figure 58: Close-up fault to Kafue Gorge bus bar on KFG-LHill line .................................... 92
Figure 59: Auto reclosing on KFG-LHill line ........................................................................... 93
Figure 60: Auto reclosing on KFG-Lhill line............................................................................ 94
Figure 61: Auto reclosing on KFG-LHill line ........................................................................... 95
Figure 62: Clearing time at 300ms for a close up fault to KFG HPP on KFG-LHILL Line (
Voltage magnitude and angle difference) ................................................................................. 96
Figure 63: Clearing time at 300ms (Rotor angle, Voltage angle) for a KFG HPP close up
fault............................................................................................................................................ 97
Figure 64: Clearing time at 300ms for a close up fault at KFG HPP ( Active power,Voltage
magnitude and frequency) ......................................................................................................... 98
Figure 65: Close-up fault to Kariba bus bar on KNB-LHIll line .............................................. 99
Figure 66: Close-up fault to Kariba bus bar on KNB-LHIll line ............................................ 100
Figure 67: Close-up fault to Kariba bus bar on KNB-LHIll line ............................................ 101
Figure 68: Auto reclosing at Kariba end then at LHill end ..................................................... 102
Figure 69: Auto reclosing at Kariba end then at LHill end ..................................................... 103
Figure 70: Auto reclosing Kariba LHill line ........................................................................... 104
Figure 71: Fault on LHill-Kabwe line ..................................................................................... 105
Figure 72: Fault on LHill Kabwe line ................................................................................... 106
Figure 73: Fault on LHill-Kabwe line ..................................................................................... 107
Figure 74: LHill-Kabwe fault 400ms clearing time. ............................................................... 108
Figure 75: LHill-Kabwe fault and auto reclosing ................................................................... 109
Figure 76: LHill Kabwe fault and auto reclosing .................................................................... 110
Figure 77: Kabwe Kitwe line fault ........................................................................................ 111
Figure 78: Kabwe-Kitwe line fault.......................................................................................... 112
Figure 79: Kabwe-Kitwe line fault.......................................................................................... 113
Figure 80: Kabwe-Kitwe auto reclosing ................................................................................. 114
Figure 81: Kabwe-kitwe auto reclosing .................................................................................. 115
Figure 82: Kabwe Kitwe line auto reclosing ......................................................................... 116
Figure 83: Fault on Kabwe pensulo line ................................................................................. 117
Figure 84: Kabwe-pensulo line fault ....................................................................................... 118
Figure 85: Kabwe-pensulo line fault ....................................................................................... 119
x
Figure 86: KFG-Kfue west fault (close to Kafue west) .......................................................... 120
Figure 87: KFG-Kfwest line fault ........................................................................................... 121
Figure 88: KFG-KFWest line fault ......................................................................................... 122
Figure 89: KFG-KFWest auto reclosing ................................................................................. 123
Figure 90: KFG-KFWEST line auto reclosing ....................................................................... 124
Figure 91: KFG-KFWest line auto reclosing .......................................................................... 125
Figure 92: Fault on Luano-Kansanshi line .............................................................................. 126
Figure 93: Fault on Luano-Kansahi line ................................................................................. 127
Figure 94: Fault on Luano Kansanshi line .............................................................................. 128
Figure 95: Reactive Power, Excitation Voltage and current of the Generating Machines for
the fault close to KNBC HPP .................................................................................................. 128
Figure 96: Reactive power, excitation voltage and current of the machines for a fault close
to KFG HHP ............................................................................................................................ 129
Figure 97: Power swing for a fault close to KFG HHP .......................................................... 129
Figure 98: Power Swing for a fault close to KNBC HPP ....................................................... 130
Figure 99: Excitation voltage after a fault close to Vic Falls .................................................. 130
Figure 100: Power swing for a fault close to Vic. falls on Kariba HPP Lhill Line and
KFG HPP - LHill Line ............................................................................................................ 131
xi
LIST OF TABLES
Table 1: Loss of supply in the past 20 years. .............................Error! Bookmark not defined.
Table 2: Unit commitment ........................................................................................................ 65
Table 3: Reactive power compensation and SVC Models ........................................................ 66
Table 4: Loading on the lines at peak load ................................................................................ 72
Table 5: Load flow with Kabwe-Kitwe line out at peak load ................................................... 72
Table 6: Load flow with Kariba north and LHill line out (Load reduced to account for
increased loses). ........................................................................................................................ 73
Table 7: Voltage profile with Kariba North- LHill line out. ..................................................... 75
Table 8: Load flow with KFG-LHil line out. ............................................................................ 76
Table 9: Voltage profile with KFG-LHil line out ..................................................................... 77
Table 10: Load flow with KFG-Kafue west line out. ............................................................... 78
Table 11: Load flow with Lhill-Kabwe line out (load reduced to 98% to account for
increased transmission loses). ................................................................................................... 80
Table 12: Load flow calculations with Kabwe- Kitwe line out (load reduced to 93% to
account for increased losses). .................................................................................................... 82
Table 13: Load flow calculation with Kabwe-Luano line out. ................................................. 84
Table 14: Detailed parameters of the AVRs ............................................................................. 87
Table 15: Detailed parameters of speed Governors. ................................................................ 88
xii
Chapter 1: Introduction
ZESCO power system has in the past twenty years under gone several of system
disturbances and the latest being early last year [1]. The most common disturbances are the
ones to do with rotor angle and voltage instability following a severe system fault near
generating stations or on lines to major load centres. It is in this regard that there is need to
do some system stability studies to find a better solution to such disturbances. Therefore
the stability studies should be based on 330 kV, 220 kV and 88 kV transmission system up
to 2011. The highest voltage level is 330 kV in Zambia.
The Power system stability studies on the Zambian Power network are based on the fact
that by 2011 the Power demand will have increased from 1500 MW to about 1670 [1].
Generation capacity also will have been up rated by 11%. Therefore the network studies
are performed with the view that there will be this kind of Generation and demand by 2011
and hence the need to perform stability studies to ascertain the stability of the system.
Some severe situations have been examined to ascertain the stability of the Zambian
network. The critical period for the study is the annual peak load demand. Some load flow
simulations have also been done on 80% of the full peak load demand of the Zambian
network to represent the off peak load demand. The unity commitment of the peak load is
characterised as follows; all the six generating units at Kafue Gorge operate at almost full
capacity seconded by the four units at Kariba North Bank Power station. The rest operate at
almost full capacity as well.
All power plants are modelled as Hydro power plants (HPP) in Dig Silent software. This
study reports the static and dynamic behavior of the Zambian power system with the view
of the increased generation and load demand by 2011. For the transient study, the
electromechanical transients are considered, few seconds after the disturbance occurrence,
in order to detect a potential loss of synchronism on groups.
The description of the power system is detailed enough to simulate the electromechanical
transients. The study is focused on the behavior of the generators in terms of rotor angle
without any power exchange with the Zimbabwe or Congo DR system.
Currently the Zambian network is operated with the spinning reserve of 70 MW since it is
always interconnected with ZESA to the south and SNEL of Congo to the North. But this
spinning reserve is not enough if the Zambian system were to stand on its own. The
recommended spinning reserve in this situation is 180 MW representing the capacity of one
of the largest machines [1].
This report has the following details;
A brief discussion on the Zambian network is highlighted to give a wide
understanding of the network.
The basic concepts on Power system stability is illustrated in chapter three where
Equal Area Criterion is explained on how it helps to give the critical clearing angle or
the critical clearing time and their importance.
The methodology used to perform the Power System Stability study
The different steps of the proposed work
2.1
ZESCO System
ZESCO owns and operates most of the power stations, transmission system, the
distribution system and the National Control Center.
ZESCO produces almost all of its electric power from hydropower stations which account
st
for 1668 MW, as at 31 May 2010 [1]. The remainder, about 1.6 MW is produced from
isolated diesel power stations.
2.1.1 Kafue Gorge Power Station
This is the largest Power Station in Zambia. It is located on the Kafue River and has been
in operation since 1971. The Station has an installed capacity of 990 MW with 6 generators
of 165MW each. Two generators feed one transformer consisting of three single-phase
generators. There are therefore ten single-phase generators, including a spare generator.
2.1.2
KNBC is the second largest power station after Kafue Gorge. It has a total capacity of 720
MW consisting of four generators of 180 MW each. Each generator feeds one three phase
transformer. The power station is located on the north bank of Kariba dam on the Zambezi
River. It has been in operation since 1977.Originary it had 4 by 150 generators but there
has been an uprating exercise on all the four generators to 180 MW. Currently there are
two more 180 MW generators being constructed to be completed in 2012. To the south of
this power station is another power station of 600 MW belonging to ZESA of Zimbabwe.
The two power stations are interconnected by two by 330 kV transmission lines of 1.5 km
long.
2.1.3 Victoria Falls Power Station
The station is a run-of-river station located on the Zambezi River at Victoria Falls. It has an
installed capacity of 108 MW and comprises three power stations namely stations A, B and
C. Station A was commissioned in 1936. It has an installed capacity of 8 MW consisting of
two generators of 1 MW each and another two of 3 MW each. Station B was commissioned
in 1968 and has an installed capacity of 60 MW consisting of 6 generators of 10 MW each.
in June 1996 and upgraded in 2005. The SCADA system covers 24 transmission stations,
which include four (4) Power Stations and twenty (20) Substations.
CEC operates a regional control center for its system on the Copper belt. ZESCO and
Lunsemfwa Hydro Power Company also operate control rooms at their stations.
System operation is the function of maintaining the power system in a stable operating
condition. This involves:
a. Monitoring changes in demand and scheduling and dispatch of generating plant in
accordance with expected requirements.
b. Monitoring and taking corrective action to maintain frequency and voltage in the system.
c. Monitoring transmission lines, to ensure that the electrical and thermal stability limits are
not exceeded.
d. Ensuring an acceptable level of system security.
e. Being prepared to take appropriate action in the event of a failure of any equipment that
may jeopardize the security position.
f. Having a contingency plan to recover the system in the event of a complete system
failure i.e. a black-start capability.
The traditional large disturbance stability problem is related to the short term or transient
period, which is usually limited to a few seconds following the disturbance. It is concerned
with the system response to a severe disturbance, such as a transmission system fault.
Much of the electric utility industry effort and interest related to system stability to date
have been concentrated on the short-term response, and as a result the system is designed
and operated so as to meet a set of reliability criteria concerning transient stability [3]. Well
established analytical techniques and computer programs exist for the analysis of transient
stability. In recent years, the need for studying the response of the system for longer
periods has been recognized, and the terms mid-term and long-term stability have been
introduced. Analytical tools for studying these aspects of system stability are evolving.
As power system have evolved through continuing growth in interconnections, use of new
technologies and controls, and the increased operation in highly stressed conditions,
different forms of system instability, frequency stability and inter-area oscillations have
become greater concerns than in the past [4]. Voltage stability, frequency stability and
inter-area oscillations have become greater concerns than in the past. Historically transient
angle instability has been the dominant stability problem on most systems, and has been the
focus of much of industrys attention concerning system stability.
A typical modern power system is a high-order multivariable process whose dynamic
response is influenced by a wide array of devices with different characteristics and
response rates. Depending on the network topology, system operating condition and the
form of disturbance different sets of opposing forces may experience sustained imbalance
leading to different forms of instability. Below, in
Figure 2, is the summary of the classification of the system stability, giving the overall
picture of the power system stability problem and identifying its categories and
subcategories [4].
The classification of power system stability is for convenience case to identify causes of
instability, applying suitable analysis tools, and developing corrective measures. In any
given situation, however, any one form of instability may not occur in its pure form. This is
particularly true in highly stressed systems and for cascading events; as systems fail one
form of stability may lead to another form. However, distinguishing between different
forms is important for understanding the underlying causes of the problem in order to
develop appropriate design and operating procedures.
While classification of power system stability is an effective and convenient means to deal
with the complexities of the problem, the overall stability of the system should always be
kept in mind. Solutions to stability problems of one category should not be at the expense
of another. It is essential to look at all aspects of the stability phenomena and at each aspect
from more than one view point.
Power System
Stability
Rotor Angle
Stability
Small
disturbanc
e Angle
Frequency
Stability
Voltage Stability
Transient
Stability
Short
Term
Large
Disturbance
Voltage
Stability
Short
Term
Long
Term
Short
Term (110sec)
Small
Disturbance
Voltage
Stability
Long
Term
(160min)
Figure 3: Generator connected to infinite bus bar through two parallel lines.
(3)
Basically the two equations, equation ( ) and ( ) give the power angle curves as shown
below in Figure 5 where Pmax1 and Pmax2 power curves are clearly shown.
10
Figure 5: Equal area criterion for the loss of one parallel line
When the system is perturbed, the magnitude of E remains constant at its pre-disturbance
value and changes as the generator rotor speed deviates from synchronous speed .
3.2.2 Equal Area Criterion;
The equation of motion or the swing equation may be written as
( 4)
Where Pm
time, in s
From the equation ( ) we have following relationship between the rotor angle and the
accelerating power [2];
=
( )
- )
Now Pe is a nonlinear function of , and therefore the above equation cannot be solved
directly. If both sides are multiplied by 2d/dt, then
(
11
Or
[
Integrating gives
[ ]
( )
The speed deviation d is initially zero. It will change as a result of the disturbance. For
stable operation, the deviation of angle must be bounded, reaching a maximum value (as
at
on the line2 out- power curve on Figure 5 above) and then changing direction. This
requires the speed deviation d/dt to become zero at some time after the disturbance.
Therefore, from the equation( ), as a criterion for stability we may write;
( )
Where
is the initial rotor angle and
is the maximum rotor angle. As illustrated in the
last figure above. Thus, the area under the function Pm-Pe plotted against must be zero if
the system is to be stable. In the last figure above this is satisfied when area
. Kinetic energy is gained by the rotor during acceleration when
changes from to . The energy gained is
= (
= area
to
is;
= area
( )
( )
Since the losses are not considered the energy gained is equal to the energy lost which
means that area
in equation ( ) equal to area in equation( ). And this forms the
basis of equal area criterion.
The criterion enable us to determine the maximum swing of and hence the stability of the
system without computing the time response through formal solution of the swing
equation.
We now consider the loss of one parallel line. The initial operating point of the system
would be at point a (from figure4) where the mechanical power Pm is equal to electrical
power Pe. When the line is opened the operating point suddenly changes to point b because
the transfer reactance has now changed. Because of the inertia angle cannot change
12
instantly. The mechanical power is greater than the electrical power at this point hence
there will be some accelerating power that will make the rotor angle shift from
to
at
point c. At this point the mechanical power is equal to electrical power but because of the
acceleration power which makes the speed of the rotor higher than the synchronous speed
and the rotor angle continues to rise until it reaches maximum value
where the rotor
speed is now equal to synchronous speed and where the kinetic energy gained during this
acceleration will have expended by transferring the energy to the system. That is area
is
equal to area
At this point the electrical power will be greater than mechanical power
and consequently there will be some deceleration power and the rotor speed will be seen to
be reducing. Eventually we see that there will be some oscillations about point c until these
oscillations are damped.
If we now suddenly increase the mechanical power from the initial operating point shown
in Figure 5, we see a situation where we need more decelerating power available because
area
has now increased. At this point we search for the critical point, a point at which
the two areas will just be equal so that we dont lose stability of the system.
3.2.3 Fault at Either end of the Line
Another interesting situation is when we have a fault on one of the parallel lines but close
to either end of that line. See the Figure 6 below.
13
Figure 7: Power angle relationship after a fault at either end of the parallel line
In this case when a fault occurs the operating point suddenly shifts from point a to point b.
Before the fault the power angle relationship is given by
Pelect = PmaxI Sin and during the fault the power transfer is zero and after the fault is
cleared by opening the faulted line the power transfer becomes; PmaxII Sin as shown in
Figure 7 above.
The rotor angle wont change immediately owing to the inertia and it will move along the
zero line to
when the fault is cleared. At this point the new operating point will be at c.
and because rotor speed is greater than the synchronous speed the rotor continues to
accelerate until point d where the rotor speed is equal to the synchronous speed. At this
point the Electrical power is higher than the mechanical power hence the deceleration in
the rotor speed which gives out some oscillations until the oscillations are dumped.
From the figure above we see that if we increase the clearing time the acceleration area
becomes larger and this limits the deceleration area available to a critical clearing angle .
Similary if we reduce the fault clearing angle the smaller is the accelerating area compared
to the deceleration area available and hence more chance of the system remaining stable.
And if the initial operating point is raised a similar situation occurs where the decelerating
area available becomes smaller compared to the acceleration area.
We therefore conclude that the stability of the system is dependent on two things in this
case, the initial operating angle and the fault clearing time.
3.2.4 Fault in the Middle of the Line
Now let us take another scenario where the fault occurs in the middle of the line. See
Figure 8 below;
14
Figure 9: Circuit model for the fault in the middle of the line
15
Figure 12: Equal Area criterion for the fault in the middle of the line
From the above figures, Figure 8, Figure 9, Figure 10, Figure 11 and Figure 12, we see that
the only difference between the previous case and this one is that in this case where the
fault is in the middle of the line the power transfer never goes to zero hence more chances
of the system remaining stable unless the fault clearing time is increased in such a way that
the accelerating area is larger than the decelerating area.
16
If we auto-reclose to a transient fault we see that the decelerating area becomes larger due
to the fact that the new operating point goes back to the initial operating point. But if we
auto reclose to a persistent fault the decelerating area reduces and we may go into a
runaway situation because now the accelerating power is larger than the decelerating power
available. This situation can be avoided if the auto-reclosing is only allowed once and more
time set for the initiation of the auto-reclosing, say 10 seconds and by then the system will
have been stabilized. Delayed auto reclosing only applies to three phase faults because this
is when we have critical situation for the rotor stability.
18
19
Additionally, the term load can be used for entire MV-feeders in case of an HV-system or
LV-feeders if an MV system is in the center of interest.
4.2.2 Load Modeling in Power Factory Software.
In Power Factory, most of the loads are modeled as General loads where they represents:
A complete feeder
A combination of dynamic and static loads
The general load model representation is shown in Figure 18 below;
21
Figure 19: Load flow calculation window indicating the voltage dependence terms for load
flow calculations in Power Factory software.
4.2.3 Three phase load modeling for transient Stability Simulations.
For transient simulations a three-phase load can be modeled as a percentage of static and
dynamic load. The static portion is modeled as constant impedance whereas the dynamic
load can be modeled as either a linear load or a non-linear load [13].
Z
%
Dynamic
Load %
Figure 20: Diagram indicating the mixture of static and dynamic load model used for
stability studies.
According to [13] the models used to approximate the behavior of linear and non-linear
dynamic loads are given in Figure 21 and Error! Reference source not found.
respectively.
22
Figure 21: Model used to approximate the behavior of the linear dynamic load.
Figure 22: Model used to approximate the behavior of the non-linear dynamic load.
23
Figure 21 and Figure 22 represent small signal model and are valid in limited voltage
range. This voltage range is defined as
and
and outside this range the power is
adjusted as shown in Figure 23 below [13].
Figure 23: Low/High voltage approximations used in the non-linear dynamic load model.
24
corresponding to loss of one large unit at Kariba North Bank or Kafue Gorge power
stations.
5.2 Methodology
The operation of the Zambian power system was simulated to analyze its behavior and its
ability to operate within its capacity in stead state and in transient state.
In permanent-state the electrical parameters that characterize the behavior of the system,
currents, voltages, generation, angles of the machine, position of the automatic on-load tapchange, are assumed to be constant. The load flow calculation is used to simulate the
behavior of the power system in permanent state and to calculate its electrical parameters.
The behavior of the power system is satisfactory if, and only if [14]:
All load flow calculations were carried out for the peak and the off-peak load demands.
In transient-state the system is affected by a fault, such as a short-circuit, a tripping of a
unit or a disconnection of a load, all these parameters evolve very quickly during a brief
period until the system recovers a new permanent state situation. If the system fails to do it,
a loss of synchronism between some units and other units of the system may occur [14].
The transient-state analysis determines if the up rating of the machines can improve the
control of the voltage and the frequency of the system. The electromechanical behavior of
the power system is analyzed versus time for few seconds. The generators and their control
system are represented in detail, taking into account their inertia, their turbine with the
speed governor, the electrical parameters of their alternator with their excitation system and
voltage regulator. Moreover, the voltage and frequency dependent characteristics of loads
are represented. A fault is applied on a line connected to Hydro Power Plant and then is
cleared by permanent tripping of the faulted element following a normal operation of the
protections. The dynamic behavior of the Machines connecting to the system is satisfactory
if [14]:
No loss of synchronism of units occurs;
No sustained voltage oscillations are detected on substations;
No sustained oscillations of the rotor angle appeared on the machines;
Voltage profile and currents remain within the acceptable limits.
Tripping of one of the two 330 kV circuits connecting Kariba North to the Zambian
system.
Tripping of one of the two 330 kV circuits between Kafue Gorge and LHill
substation.
Tripping of 330 kV Kafue Gorge-Kafue west line.
Tripping of 220 kV Vic.Falls-Muzuma line
Tripping of one of the three 330kV circuits between Leopards Hill and Kabwe.
Tripping of one of the two circuits between Kabwe and Luano and between Kabwe
and Kitwe.
Tripping of the 330 kV Luano-Kansanshi Mine.
Tripping of the 330 kV Kabwe-Pensulo Line.
The generation had been adjusted to the Zambian load in order to have no transit on the
two
circuits interconnecting the Zambian and the Zimbabwe systems, i.e. between Kariba North
Bank and Kariba South Bank substations. The power system must operate within the limits
defined by the Zambian grid code. If it does not, improvements (such as capacitor banks)
will be proposed to allow a satisfactory operation.
The load flow calculations were performed in normal and in N-1 conditions for the peak
and the off-peak.
5.4
Load flow gives us the analysis of the power system in terms of power flow, real and
reactive power, on various lines and the voltage magnitudes and respective angles at
various bus bars at a particular time instant for given condition of Generation and loads
[13].
The power system operation is considered as Quasi-static, the static analysis of power
network. The real power balance, reactive power balance, transmission flow limits and bus
voltage limits is studied.
In Power Factory software the following is specified: the generating bus bars as PV buses
simply because at these buses the voltage magnitude is maintained by the excitation of the
generators. The Kafue Gorge bus bar has been selected as slack bus bar. This is a reference
bus bar where voltage magnitude and angle are specified. This means that all loses are
assigned to this bus bar. The real and reactive power is allowed to vary at this bus bar.
5.4.1 Analysis in Normal Conditions
The simulation was performed in normal conditions; all the network elements were in
operation. The generation is located in the south of the transmission system and about 45%
of the total demand is located in the north of the system (Copper belt area).See Figure 24
and Figure 25 below. The North of the system is then supplied from the South through four
330 kV lines between Kabwe and Luano substations of which two are direct lines ,then
one goes via Kitwe substation to Luano the fourth one goes via Kitwe and Chambishi
substations. See Figure 1. Kariba North substation is linked to Kariba south substation
through two 330kV circuits. These two border systems are balanced in order to have no
27
load on these two circuits. The unit commitment of the Zambian network is displayed in
Table 2. Figure 24 below shows the Generated power, loses and the installed capacity
As can be seen Figure 24,the system is operating at almost full capacity hence the spinning
reserve cannot hold system stability in case of loss of one generator in Kafue Gorge or
Kariba unless the interconnections from other mentioned countries are considered as it is
shown in the N-1 analysis below.
In case of voltage profile, on the Copper belt area, the voltage can be controlled in a
satisfactory way with two Static Var compensator units, which have been implemented in
two main 330kV substations (i.e. one in Kitwe and one in Luano). To operate the system
within the voltage limits, the reactive compensation means were connected as shown in
Appendix7 Table 3. Despite heavy loads on the copper belt, which accounts for 45% of the
total load, the voltage profile is within the limits. The power factor is still ok with this
compensation despite the high inductive load on the copper belt.
28
29
30
Figure 27: Voltage profile for the calculated load flow under normal system condition
One of the three 330 kV circuits between Kariba North and Leopards Hill
One of the three 330 kV circuits between Leopards Hill and Kabwe
One of the two 330 kV circuits between Kabwe and Luano
One of the two 330 kV circuits between Kabwe and Kitwe
Pensulo line from Kabwe
After each tripping, the Zambian network impedance is increased and so the losses. Then,
the flow over the two circuits between Kariba North Bank substation and Kariba South
Bank substation will correspond to the additional losses.
5.5.1 Tripping of one of the two 330 kV circuits between Kariba North and Leopards Hill
Following the tripping of the circuit, the behavior of the system was satisfactory, no
overload
31
Occurred on the transmission system. The initial power flowing through the tripped circuit
Kariba North - Lhill 1A was the same as that of the other parallel circuit. See appendix8.
The tripped line was loaded to 27% of its capacity. Therefore the remaining line was
loaded to 54% after a tripping.
The voltage profile of the Copper belt area kept to almost its initial value thanks to the
SVC of Kitwe and Luano. The reactive power on Kitwe SVC bank was raised from 2 Mvar
to 18 Mvar and from 3 Mvar to 24 Mvar for Luano substation. See Table 3 in appendix 7.
The most significant voltage drop is at Leopards Hill substation with a dip of 1% (i.e. from
340 kV to 336.5 kV). See Figure 28 below.
32
The lowest voltage in the Copperbelt area reached 0.95p.u. at Michelo and in the south at
Kafue town. See Table 7 in Appendix 10. Kariba North units generated 30.7 MVAr, which
were within their reactive limits. Kafue Gorge units generated 53 MVAr, which were
within their reactive limits.
5.5.2 Tripping of one of the three 330 kV Circuits between Leopards Hill and Kabwe
Following the tripping of the circuit, the behavior of the system was satisfactory, no
overload occurred on the transmission system. The initial power flowing through the
tripped circuit Leopards Hill Kabwe was 34.6% for each line. After a tripping the power
for one line was equally dispatched between the two remaining circuits. See Table 5 in
Appendix 8.
The voltage profile of the Copper belt area kept to its initial value. Much of the reactive
power was supplied by the SVC of Kitwe and Luano to the north. The Generated reactive
power on all Machines at the big Generating stations in the south was within limits. The
most significant voltage drop is at Kafue 88 kV substation in the south (0.84 p.u.) and
Michelo 220 kV close to the lower limit (0.95 p.u.) in the north. After the tripping, the
voltage profile stayed within the acceptable limits
33
5.5.3 Tripping of one of the two 330 kV Circuits between Kabwe and Luano
Following the tripping of the circuit, the behavior of the system was satisfactory, no
overload occurred on the transmission system. The initial power flowing through the two
lines to Luano from Kabwe was 30% on each line. The power flow on the tripped circuit
Kabwe - Luano had been dispatched between the remaining circuit Kabwe - Luano and the
two circuits Kabwe - Kitwe which were currying 36% each initially. After the tripping, the
circuit Kabwe - Luano was loaded at 50% (350 MW) and the two circuits Kabwe Kitwe
were loaded at 55% each (382 MW). See Table 5 in Appendix 8.
The voltage profile of the Copper belt area was virtually kept to its initial again with the
help of the SVC of Kitwe and Luano
Kariba North units generated 50% of their reactive power limits and Kafue Gorge units
generated 66% of their reactive power limits. The results of the load flows calculations are
displayed in Appendix 8.
5.5.4 Tripping of one of the two 330 kV circuits between Kabwe and Kitwe
Following the tripping of the circuit, the behavior of the system was satisfactory, no
overload occurred on the transmission system. A similar situation to the previous scenario
prevailed
5.5.5 Tripping of Kabwe-Pensulo Line
After the tripping of this line the system was stable. No overloads on the lines and no major
under voltages recorded. The only problem was on the Generators on Lusiwasi s/s which
could trip on under frequency because the Northern part load is transferred to these
generators of limited capacity.
All critical N-1 contingency calculations are displayed in Table 6 to Table 13 in appendix
9.
5.6 Analysis at off peak for both normal and N-1 contingencies.
This operation was similar to the above analysis. This is made possible for the fact that the
generation was reduced according to the adjusted load and the system compensation
followed suit.
34
clearing angle at which the system would remain stable in any situation. This of course
depends on the fault clearing time.
All these scenarios are simulated and analyzed on the Zambian network. From chapter
three it is shown that the initial operating point is crucial for the stability of the system. The
higher the initial maximum operating power output of the generator the shorter is the
critical clearing time. This is the reason for basing the analysis on the peak period in the
system.
To summarize the analysis presented in chapter three, the following are the factors
influencing the transient stability of the generator;
35
The primary reserve of Zambian system amounts to 180 MW, representing one of the
biggest generating units. With the interconnections to the neighboring countries, SAAP in
particular, Zambia gives a power reserve of about 70 MW [14].
The effective primary reserve of the HPP units depends on the opening time of the valves
of the turbine.
5.7.3. Simulated Faults
Three phase faults were applied near generating stations to ascertain the stability of the
Zambian Network. Following cases were examined:
Three phase to ground fault eliminated by definitive tripping of the faulted line in 100
ms. That is both ends of the faulted line being isolated simultaneously.
Three phase to ground fault eliminated by definitive tripping of the faulted line in 100
ms then the faulted line is automatically reclosed after 10s from the generating side of
the line and the other end auto reclosing 5seconds thereafter. In all auto reclosing
cases there was no switch on to fault. The fault was first cleared before auto reclosing.
Three phase fault on the transmission line close to 330 kV Kafue Gorge HPP bus bar
Three phase fault on the transmission line close to 330 kV Kariba North HPP bus bar
Three phase fault on the transmission line close to 220 kV Vic. Falls HHP bus bar
Three phase fault on the transmission line close to Kafue Gorge HPP on KFG-Kafue
west line
Three phase fault on the 330 kV transmission line between LHill and Kabwe
substations
Three phase fault on the 330 kV transmission line between Kabwe and Luano
substations
Three phase fault on the 330 kV transmission line between Kabwe and Kitwe
substations
Three phase fault on the 330 kV transmission line between Kabwe and Pensulo
substations
Three phase fault on the 330 kV Kansanshi transmission line from Luano
36
The behavior of the system during and after the fault was satisfactory. The generators
operated above the reactive limit during the fault but eventually stabilized. See Figure 30
below.
All groups operated in synchronism. A voltage dip close to zero for 100ms (during the
fault) was recorded on Kafue Gorge 330 kV busbar. The maximum rotor angle on Kafue
Gorge HPP was 80 degrees peak to peak as can be seen from Figure 30. The oscillations
were damped within 10seconds see Figure 30.
Figure 30: From top to bottom: Excitation voltage, Excitation Current, Machine reactive
power, Voltage dip and Rotor angle variations before, during and after the fault close to
KFG HPP
The power oscillations on the remaining KFG-LHill line reached first high value of 600
MW from initial stead state value of 210 MW before stabilizing to a value of 425 MW. The
power oscillations were damped within 10seconds. No sustained oscillations were seen.
See Figure 31 below;
37
Figure 31: Power swings on the four lines from Main Generating stations to Lhill
Substation
Frequency deviations were not alarming on all Generators from all major hydro power
plants. They were within acceptable limits as can be seen from Figure 32.
38
Figure 33: Voltage dip on major Load centers on the Copper belt after a fault close to
KFG-HPP
Another interesting case was the increase of the clearance time to see if the line would still
be stable if the fault would be cleared in 400ms according the zone two settings of the lines
on the distance relay. Zone 2 is the backup protection to zone one. If the fault is not cleared
in zone one then zone two should clear it.
The best clearing time that was satisfactory was 200ms further than that the system was
very unstable. Oscillations were never damped. See
Figure 34 below for a 300ms fault. For more variables on this simulation see appendix 13.
Figure 34: Voltage and rotor angle oscillations for a 300ms fault on KFG-Lhill line
39
5.7.3.2 Close up fault to Kafue Gorge HPP on KFG-LHill Line at peak load with auto
reclosing
Another necessary simulation on the same line was auto reclosing to a transient and
permanent fault. For a transient fault, a three phase fault was applied 1 second from the
initiation of the simulation. After the fault was cleared, at t =1.1 seconds during simulation
time, the line auto-reclosed after 10 seconds according to the relay settings. The first end of
the line near, KFG HPP was reclosed at t = 11.1 then five seconds later the other end was
reclosed. This line is set to be synchronized at Lhill S/S.
The system operated satisfactory after this operation. There were no sustained oscillations.
See the results in Figure 35.
the reclosure the frequency deviation was seen to be lower than the nominal due to
increased power flow to the north. See Figure 36 below.
Figure 36: From top to bottom, power swings on main generating stations, Voltage dips on
main Load bus bars and Frequency deviations after auto reclosing the KFG-LHill line.
5.7.3.3 Auto reclosing on to a persistent fault on KFG-Lhill.
The operation of the system after auto reclosing to a fault 10 seconds after the line was
isolated was satisfactory. All oscillations were damped. The maximum rotor angle reached
upon auto reclosing was almost like at the first fault. This is because the system was almost
stable after 10 seconds. See Figure 37 and 38 below;
41
42
There were no major power swings on the copper belt loads. The voltage dip reached 27%
of the nominal value due to system losses. The frequency on the Kafue Gorge machines
went up higher than the rest of the machines on the other hydro power plants and was seen
to stabilize at a lower value due to increased load flow. See Figure 39.
Figure 39: Auto reclosing on persistent fault- power swing on the copper belt lines, voltage
profile and machine frequency on major generating stations.
The reactive power on the Kafue Gorge machines exceeded the limits but was stabilized.
See Figure 40. The increase of the reactive power on the machines is as a result of the fault
current flows through pure reactance to the fault hence only reactive power flows [2].
43
Figure 40: Excitation voltage, current and reactive power on all machines on major
generating stations-auto-reclosing on a persistent fault
The power swings on the four main lines from major generating stations were damped. See
Figure 41 .
Figure 41: Power swing on the four transmission lines to LHill substation from Kariba and
Kafue Gorge HPP after auto-reclosing on to a persistent fault.
44
Figure 42. Effect of high speed auto reclosing (Rotor angle, Voltage profile and rotor angle
difference)
45
Figure 43: Effect of high speed auto reclosing (Rotor angle difference, Voltage angle &
speed deviation)
46
Figure 44: Effect of high speed auto reclosing (Active Power, Voltage profile &
Frequency)
47
Figure 45: Effect of high speed auto reclosing (Excitation voltage, Excitation current,
reactive power and Active power flow)
48
5.7.3.5 Faults on the remaining lines close to the main Hydro power plants.
The behavior of the whole system after a fault close to the main hydro power plants on the
remaining circuits was satisfactory. The pattern of variable oscillations was similar to the
one analyzed here before. The rotor angle oscillations were damped within 10seconds. No
sustained oscillations of any kind were recorded for a fault cleared in 100 ms. See Figure
64 to Figure 99.
The voltage dips were recorded on the major substations on the copper belt but were not
sustained. The post fault voltages were close to the initial value which means the loses
were not all that high after the isolation of the faulted circuit.
5.7.3.6 Busbar faults
The only scenario on power system stability that was different from the one just analyzed
here before is that of a bus bar fault. A complete bus bar fault was simulated at Leopards
Hill substation. This is the focal point of all the power to the copper belt that accounts for
about 45% of total power from major Generating stations. The fault was applied 1 second
after the start of the simulation. The fault duration was 50 milliseconds. This fault duration
accounts for CT error, relay and breaker opening times.
The power system operation after the fault was not satisfactory. This was expected since
45% of the total load was suddenly interrupted that means more power input than the
power output.
The rotor angle and voltage oscillations for Kafue Gorge and Vic. Falls were not damped
except for the Kariba North Hydro power plant machines. See figure 40 below. The KNBC
machines were spared because of the interconnection to the Southern load that provided
some inertia. Infact the machines were lightly overloaded at this stage as can be seen from
the new operating angle. It dropped to 32 degrees from the initial 40 degrees.
Figure 46: From top to bottom: Rotor angle for KFG HPP machines, Voltage magnitude
and the rotor angle for KNBC HPP for a bus bar fault at LHill Substation.
49
The frequency deviation on the remaining machines was not satisfactory. The one for Vic
falls looks like it was about to stabilize because of the light load to the western part of the
country that are connected to the Vic falls Power Station machines. The Kariba North Bank
HPP machine frequency deviation was satisfactory. There was a bit of deviation because of
the light load after the fault. See Figure 48.
Figure 47: Rotor angle, voltage angle and speed deviation on all major HPP machines for a
bus bar fault at LHill substation
As can be seen from Figure 48 below, the power flow to the north was suddenly disrupted.
The voltage totally collapsed. The frequency on the KNBC HPP machines looks ok. It
slightly went up for the light load as already mentioned.
50
Figure 48: Active power on the transmission lines to the North, Voltage profile on the
Copper belt Major substations and the frequency on all HPP generators for a bus bar fault
at L.Hill substation
.
The solution to the above problem is to stager the circuits on the Leopards Hill substation
bus bars. At this substation there are two bus bars coupled by a bus coupler breaker. If a
fault occurs on one of them the only faulted bus bar will be Isolated and the other will
remain intact to save copper belt load. With this kind of simulation the results are shown in
Figure 49 and Figure 50 below. All oscillations were damped and the voltage profile on the
copper belt looks ok despite the added loses with the tripping of two lines connecting the
next substation, Kabwe. This also reduces the power flow to copper belt as can be seen
from Figure 50. With this power flow reduction the frequency value went up but it was
within limits, see Figure 50.
51
Figure 49: Rotor angle and voltage profile for the fault at Leopards hill with the staggered
circuits for a bus bar fault.
Only slight voltage drop was recorded on the copper belt due to the increased loses as can
be seen from Figure 50. There was some slight power swing on the northern power lines.
52
Figure 50: Active power flow to the north, voltage profile at the copper belt and the
generating frequency for a bus bar fault at LHill
53
6.2 Recommendations
The stability of the Zambian Power System can be further enhanced if more generating
plants are implemented as the load grows. As at now the spinning reserve when operating
at peak loads is very small, about 70 MW. Already two by 180 MW Hydro Power
Generators are being implemented at Kariba North Bank to be commissioned in 2012 but
this will be taken up by the ever increasing demand with the increase in the number of
mining industry.
A research to come up with the specifications to acquire and install SVCs on major
substations on the copper belt is recommended for the reason already given in the
conclusion remarks. There should, also, be a thought to come up with the Generating
stations in the North for System stability especially voltage stability. If Generation capacity
is up graded in Lusiwasi which is part of Northern part of Zambia then we cannot have
further instability problems that arise from the faulted Kabwe-Pensulo line.
55
REFERENCES
[1]
Energy regulation Board Report of Zambia, Power outage report 4th June, 2006
[2]
[3]
[4]
[5]
R.T. Byerly and E.w. Kimbark, Stability of Large Electric Power Systems, IEE
Press, 1974
[6]
P. Kundur, Power system stability and Control, A Volume in the EPRI Power
System Engineering series.
[7]
[8]
M.Sedighizadeh, A.Rezazadeh, Load modeling for power flow and transient stability
Computer studies at Bakhtar, Network World Academy of Science, Engineering and
Technology 36 2007.
[9]
[10]
L. Hajagos, Behnam, Danai, Laboratory measurement and models and their effects
on Voltage studies, IEEE Trans.On power system vol.13, No.2, PP.584-592, May
1998.
[11]
W.S. kao, Dynamic Load modeling in Power System Stability studies, IEEE Trans
56
W.S.Kao, comparison simulated power system dynamics applying various load with
actual recovered data , IEEE Trans.On power systems vol.9, No.1PP284-254,
February.
[13]
[14]
57
58
59
The set time for differential protection is instantaneous tripping and for distance protection
the time is graded in three zones. Zone 1 is instantaneous tripping, zone 2 we have 400
seconds and zone 3 is 1.5 s.
61
ITE
M
NO.
1.
INCIDE
NT
DATE
LOCATIO
N
DESCRIPTIO
N
OF
INCIDENT
INCIDENT
DURATION
&
LOAD
LOST
COMMENT
26/03/19
89
Kafue
Gorge
Power
Station
The
power
station
experienced
extensive
damage due to
fire
Recommission
1.ZESA
power
system was
affected
G12/12/1989
G2-2/12/1989
G3-24/2/1990
G4- 6/2/1990
G5-8/8/1991
2.
Import
support from
neighbors
Zimbabwe
and Congo
DR
G610/12/1991
2.
1994
Kariba
South
Power
station
N/A
3.
14/11/19
97
Kafue West
Leopards
Hill 330Kv
line
Collapsed
towers on the
Kafue WestL/Hill 330kV
line.
15:01
15:14hrs
Kafue Gorge
power station
and all lines
from
power
station tripped
following
attempted high
62
Tripping of
Kariba North
power
station
to
SAPP
frequency
dropped to
45.7Hz. Tie
lines
to
ZESA
tripped on
under
frequency.
speed
auto
reclose onto
faulty line
4.
5.
17/12/20
05
24/12/20
05
Kabwe Step
Down
Substation
Loss
Kafue
Gorge
Mudslide
20:52hrs
of
17:25
18:13hrs;
to
Loss
of
whole
Copper belt
and tie line
to DRC.
First
two
generators
restored
at
07:22hrs on
25/12/2005.
Third
generator on
29/12/2005.
Fourth
generator on
23/01/2006
No load loss.
Import
support from
SAPP
530 MW
63
at
64
65
Loadin
g
Active
Power
Total
Active
Power
Power
Factor
Active
Power
Reactive
Power
Terminal
i in MW
Terminal
i in MW
Terminal
i
Terminal
j in MW
Terminal
i
in
Mvar
ChambKitwe 330
8.8018
4
7.54172
6
7.54172
6
0.14700
49
7.57042
5
50.7451
8
ChambLuano 330
5.0636
4
12.6161
6
12.6161
6
0.36562
18
12.6222
32.1169
7
CosakKitwe 220
A1
3.8441
7
12.2688
5
12.2688
5
0.99306
3
12.2574
9
1.45269
3
CosakLuano 220
1A
11.347
9
37.9737
8
37.9737
8
0.99723
68
-37.9425
2.82882
3
Coventry
StreetLeopards
Hill 132
1A
112.72
2
100.829
6
100.829
6
0.85659
73
105.119
6
-60.7364
Coventry
StreetLusaka
West 132
1A
36.593
6
32.6993
9
32.6993
9
0.85571
93
32.8125
9
19.7728
2
KabweKitwe 330
1A
30.222
6
191.565
5
191.565
5
0.93433
34
194.555
4
73.0723
9
KabweKitwe 330
2A
30.222
6
194.555
4
194.555
4
0.99351
3
191.565
5
22.2690
7
KabweLeopards
Hill 330
1A
34.629
6
246.087
1
246.087
1
0.99915
24
248.085
9
10.1387
7
KabweLeopards
Hill 330
34.629
6
248.085
9
248.085
9
0.99926
47
246.087
1
9.51910
6
67
2A
KabweLeopards
Hill 330
3A
34.629
6
246.087
1
246.087
1
0.99915
24
248.085
9
10.1387
7
KabweLuano 330
1A
26.107
9
167.538
9
167.538
9
0.99996
06
165.001
6
1.48695
9
KabweLuano 330
2A
26.107
9
165.001
6
165.001
6
0.92593
54
167.538
9
-67.3029
KabweMulugushi
66 1A
60.024
4
28.5431
2
28.5431
2
0.99994
37
26.9979
7
0.30296
44
KabwePensulo
330 1A
11.268
3
15.4599
3
15.4599
3
0.40689
37
-15.303
-34.7075
Kafue
GorgeKafue
West 330
1A
33.925
5
229.260
1
229.260
1
0.95046
32
228.427
5
74.9766
9
Kafue
GorgeLeopards
Hill 330
1A
46.143
8
323.266
6
323.266
6
0.97695
74
324.969
5
70.6236
1
Kafue
GorgeLeopards
Hill 330
2A
46.143
8
324.969
5
324.969
5
0.97926
62
323.266
6
67.2254
3
Kafue
TownKafue
West 330
1A
10.316
6
48.1657
3
48.1657
3
0.65812
63
-48.1603
55.1024
1
Kafue
TownMapepe 88
1A
73.878
7
36.6559
8
36.6559
8
0.82585
29
38.8257
7
-25.0284
Kafue
TownMazabuka
88 1A
63.163
8
30.1838
3
30.1838
3
0.80452
65
27.6941
1
22.2822
7
68
Kafue
TownMuzuma
220 1A
16.075
8
37.2707
9
37.2707
9
0.96730
94
36.7168
1
9.77126
6
Kafue
TownNampund
we 88 1A
66.451
25.3492
6
25.3492
6
0.83825
46
23.2093
8
16.4895
2
Kafue
WestLeopards
Hill 330
1A
14.149
3
100.572
2
100.572
2
0.99820
39
100.752
3
6.03596
1
Kafwe
WestLusaka
West 330
1A
13.794
6
79.5095
5
79.5095
5
0.88209
55
79.3814
7
42.4609
5
Kansanshi
-Luano
330 1A
28.357
1
153.393
7
153.393
7
0.79251
87
151.151
3
118.037
3
Kansanshi
-Lumwana
330_1
12.363
4
59.9999
9
59.9999
9
0.84453
48
60.1513
3
38.0446
6
KansuswaKitwe 220
1A
21.065
8
62.0513
4
62.0513
4
0.90306
02
-61.8534
29.5128
9
KansuswaLuano 220
1A
18.355
2
53.5284
2
53.5284
2
0.87370
11
53.6963
5
29.8037
8
KansuswaMufulira
66 1A
39.658
4
31.4579
8
31.4579
8
0.89082
49
31.2724
1
16.0444
9
KaomaMongu 66
1A
5.6858
0.93826
67
0.93826
67
-0.94
0.96224
68
0.34054
54
Kapiri
MposhiMpongwe
88 1A
4.2614
7
2.81577
4
2.81577
4
0.99556
17
2.80367
2
0.26617
82
Kariba
NorthKariba
South 330
14.294
3
105.003
5
105.003
5
0.99999
36
-105
0.37676
28
69
1A
Kariba
NorthKariba
South 330
2A
14.294
3
105.003
5
105.003
5
0.99999
36
-105
0.37676
28
Kariba
NorthLeopards
Hill 1A
27.044
2
184.396
5
184.396
5
0.98853
98
182.951
1
28.1593
1
Kariba
NorthLeopards
Hill 2A
27.044
2
182.951
1
182.951
1
0.94338
42
184.396
5
64.3271
7
KasamaLubushi T
66 1A
8.4560
4
-2.64167
-2.64167
0.66085
41
2.69318
4
3.00007
5
KasamaMbala 66
1A
4.0368
1
1.59504
9
1.59504
9
0.71327
2
1.57561
9
1.56735
4
KasamaMpika 66
1A
6.1263
2.19033
5
2.19033
5
0.99722
92
2.24681
3
0.16339
24
Katima
MuliloSesheke
66 1A
13.518
2
5.33754
1
5.33754
1
0.92859
97
5.37388
9
2.13296
5
Kawambw
aMporokos
o 66 1A
3.9943
5
0.45299
75
0.45299
75
0.95830
56
0.46342
35
0.13507
36
KazungluVictoria
Falls
66
1A
11.393
5
6.04020
1
6.04020
1
0.94580
43
5.92034
6
2.07387
4
Kazungula
-Sesheke
66 1A
5.5309
2
1.89116
5
1.89116
5
0.93056
22
1.92200
4
0.74408
75
KitweLuangwa
66 1A
10.617
5.41154
9
5.41154
9
0.95466
33
5.39999
9
1.68745
6
KitweMaposa
220 1A
21.768
9
61.9711
5
61.9711
5
0.85670
64
61.8877
8
37.3115
70
KitweMaposa
220 2A
21.768
9
61.8877
8
61.8877
8
0.84722
92
61.9711
5
38.8047
3
KitweMill 66 1A
42.668
3
27.6958
2
27.6958
2
0.71102
07
27.4905
4
27.3900
6
Leopards
HillMapape 88
1A
88.765
2
51.7938
5
51.7938
5
0.80855
6
49.0371
9
37.6924
9
Leopards
Hill-Roma
132 1A
101.21
5
92.1358
2
92.1358
2
0.86446
69
95.5928
5
53.5772
3
Leopards
HillWaterwor
ks 88 1A
90.677
3
55.0707
3
55.0707
3
0.84001
22
-52.92
35.5704
2
Leopards
HillWaterwor
ks 88 2A
96.964
4
50.5431
1
50.5431
1
0.72158
14
48.0908
1
48.4941
8
LuanoMichelo-T
220 1A
43.869
5
109.745
8
109.745
8
0.75628
32
108.115
6
94.9387
8
MaambaMuzuma
88 1A
19.438
1
11.0174
6
11.0174
6
0.85532
36
10.7766
2
6.67359
4
MuzumaVictoria
Falls 220
1A
20.576
58.2286
2
58.2286
2
0.92521
46
59.1219
4
23.8804
2
PensuloSerenje 66
1A
2.1577
8
1.12669
1
1.12669
1
0.98691
69
1.12445
8
0.18406
42
SenangaSesheke
66 1A
15.632
6
3.67272
9
3.67272
9
0.77202
73
4.06520
7
3.02365
9
ShesekeVictoria
Falls
220_1
6.6872
5
11.9845
5
11.9845
5
0.63100
39
12.0530
5
14.7342
5
71
72
Table 6: Load flow with Kariba north and LHill line out (Load reduced to account for
increased loses).
73
74
75
76
77
See voltage profile below with the Kafue Gorge- Kafue West Line out
78
79
Table 11: Load flow with Lhill-Kabwe line out (load reduced to 98% to account for
increased transmission loses).
80
81
Table 12: Load flow calculations with Kabwe- Kitwe line out (load reduced to 93% to
account for increased losses).
See corresponding voltage profile below.
82
83
84
85
86
87
88
89
Figure 55: Voltage magnitude and rotor angle for a fault close to KFG HPP
90
Figure 56: Close-up fault to Kafue gorge bus bar on KFG-LHill line
91
Figure 57: Close-up fault to Kafue Gorge bus bar on KFG-LHill line
92
93
94
95
Figure 61: Clearing time at 300ms for a close up fault to KFG HPP on KFG-LHILL Line (
Voltage magnitude and angle difference)
96
Figure 62: Clearing time at 300ms (Rotor angle, Voltage angle) for a KFG HPP close up
fault.
97
Figure 63: Clearing time at 300ms for a close up fault at KFG HPP ( Active power,Voltage
magnitude and frequency)
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
Figure 94: Reactive Power, Excitation Voltage and current of the Generating Machines for
the fault close to KNBC HPP
128
Figure 95: Reactive power, excitation voltage and current of the machines for a fault close
to KFG HHP
129
Figure 99: Power swing for a fault close to Vic. falls on Kariba HPP Lhill Line and KFG
HPP - LHill Line
.
131