Installation Checklist Adhesive Bonding
Installation Checklist Adhesive Bonding
Installation Checklist Adhesive Bonding
Adhesive Bonding
Project Title
Sub-contractor Date
1 System
2 Pipe Diameter
3 Joint NO.
4 Jointer ID No.
5 Pipe Bell Cleaned
6 Pipe End Tapered
7 Angle of Taper
8 Shaving Length SA
9 OD at tip (S1)
10 Bell length up to stopper (BA)
11 Cemet kit Expiration date
12 Joint Cured With Heating Blanket
13 Force Curing Start Time
14 Force Curing Finish Time
15 Total Curing Time
16 Joint Marked for Identification
Remarks: