Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Cost Effectiveness of Different Canal Lining Materials: Mr. Amrut Sangale, Dr. S. S. Valunjkar

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

International Journal of Engineering and Technical Research (IJETR)

ISSN: 2321-0869, Volume-3, Issue-5, May 2015

Cost Effectiveness of Different Canal Lining


Materials
Mr. Amrut Sangale, Dr. S. S. Valunjkar

5. Cement concrete tile lining,


AbstractThe purpose of this study is to produce a
comparative study of irrigation canal lining by the use of 6. In situ cement /lime concrete lining,
existing materials. This study reveals why irrigation canal lining 7. Stone masonry lining,
and describes a number of various lining and there analysis.
There are variable materials which are adopting concrete lining, 8. Soil cement lining,
brick lining, stone masonry lining, and polyethylene film with
concrete cover and geo membranes lining. However in our 9. Shotcrete lining
country as per environmental condition mostly cement concrete
10. Ferrocement lining.
lining is popular. Cost of each lining is different than others
b) Geomembrane lining
Index Terms Reduce cost, cost comparison, saving in
water, lining materials, lining cost, canal lining. High Density Polyethylene (HDPE), Polyvinyl Chloride
(PVC), Low Density Polyethylene (LDPE) with cover
I. INTRODUCTION comprising layer of betonies with adequate earth/burnt clay
tile brick or pulverized fuel ash-lime brick or burnt clay fly
The irrigation has been from the time immemorial and so
ash building brick/precast cement concrete.
has been building of irrigation canals, but is not only since last
century that canals have been designed on more or less Functions of Lining
scientific substructure. A canal may be rigid boundary or a
The function of lining are:
mobile boundary canal .Irrigation system should be built in
such a way that they operate in maximum efficiency. The 1. Seepage control,
efficiency of the conveyance and distribution system, that is
2. Prevention of water logging,
convey of water at minimum cost and with minimum seepage
and evaporation loss, essentially affects the economy of an 3. Increased hydraulic efficiency,
irrigation project. Now many irrigation project constructed in
4. Increased resistance to erosion,
Maharashtra, especially in West Maharashtra including
Satara, Sangli, Kolhapupur, Pune. 5. Reduction in cross section area,
The many canal constructed in this area are unlined canal,
concrete canal, stone masonry canal. Design of canals are 6. Low operation and maintenance cost.
being carried out in accordance with Circular No MIS 1094/ Fig. 1 shows the various linings used in India so far.
(156/94) MP (A), dated 18-2-1995 by Irrigation Department,
Government of Maharashtra. For this paper case study of
concrete canal lining no-6 of Khatav canal, Urmodi Dam
Division, Satara. Regional Schedule of Rates of Pune Region
used for the estimation of canal lining.

II. DIFFERENT CANAL LINING


Lining Systems
As per IS 10430:2000 CRITERIA FOR DESIGN OF
LINED CANAKS AND GUIDANCE FOR CULL OF TYPE
OF LINING following are different lining systems.
a) Rigid Lining
1. Stone pitched lining,
2. Brick lining,
3. Pulverized fuel ash-lime bricks lining,
4. Precast cement concrete /stone slab lining, FIG. 1 LINING TYPES UTILIZED IN INDIA.

Mr. Amrut Namdev Sangale, M.E.II (Civil - CM) Dept. Of Civil III. DESIGN & MEASUREMENT OF CANAL LINING
Engineering, Government College of Engineering, Karad, Maharashtra,
India, 9595964194.
Dr. S. S. Valunjkar, Professor& Head of Dept. Of Civil Engineering, The basic parameter to design the canal is discharge, and as
Government College of Engineering, Karad, Maharashtra, India. per case study the discharge is 20 cumecs.

1 www.erpublication.org
Cost Effectiveness of Different Canal Lining Materials

As per Circular no. MIS 1094/ (156/94) Excavation of 4174.4 m3 (rate 51.45 Rs per m3) Cost =
214772 Rs.
Slope of ground is 1:5000
Dressing of side slope area 1874 m2 (rate 1.85 Rs per m2)
Side slope 1 V: 1.5 H
Cost = 3467 Rs.
B/d ratio 1.5 to 2
Cost of 15 mm thick 1:3 CM = 301343 Rs.
Assume that canal cross section is totally in cutting & strata
Cost of 230 mm thick UCR = 459388
is hard murum.
As per RSR Pune 2013-14,
A) Cement Concrete Lining
Total design cost per 100 m = 978970 Rs.
As per IS code3873:1993 design of C.C lining
Velocity = 0.9 m/s,
C)Brick /Burnt Clay Tiles Lining
Area req. = (20/0.9) =22.22 m2
Excavation of 3670 m3 (rate 51.45 Rs per m3) Cost =
Provide, B = 4m,
188841 Rs.
d =3.65 m (with 0.9 m extra free board)
Dressing of side slope area 1760.8 m2 (rate 1.85 Rs per m2)
As per design provide 10 cm thick concrete bed & 8 cm Cost = 3257 Rs.
side wall.
Cost of 10 mm CM (1:5) = 156348 Rs.
B) Stone Masonry Lining
Cost of two 50mm thick brick coat = 394394 Rs.
As per IS code 11809:1994 for Stone Masonry
Cost of plaster (1:3) = 391175 Rs.
Velocity = 0.8 m/s,
As per RSR Pune 2013-14,
Area raq. = 25 m2 ,
Total design cost per 100 m = 993298 Rs.
Provide B = 4.2 m,
d = 3.80 m (with 0.9 m extra free board) V. RESULT AND DISCUSSION OF CANAL LINING
Comparison of the three different comparing estimated
As per design provide 0.23 m thick stone masonry with 15
annual costs of types of lining cost show in the table 1.
mm CM on prepared sub-grade.
The following work illustrates calculate and compare
C)Brick/ Burnt Clay Tile Lining annual costs and additionally in graphical form show in fig 2.
As per IS code 9698:1995 design of C.C lining
Table.1 Comparing Estimated Annual Cost of Lining
Velocity = 0.9 m/s,
Sr. Type of work Cost of Lined canal Per 100 m
Area req. = (20/0.9) =22.22 m2 No
.
Provide, B = 4m, Cement Stone Burnt
Concrete Masonry Clay Tile
d =3.65 m (with 0.9 m extra free board) 1 Total cost 717579 978970 993298
As per design provide 10 mm thick CM on sub-grade, then 2 Life 50 50 30
provide two 50 mm thick coat of burnt clay tiles with 3 Salvage 179394 244742 148994
separated by 15 mm sandwich plaster & 5 mm thick mortar. value
4 T. D. D L. 538184 734227 844303
IV ESTIMATION OF CANAL LINING
5 10763 14684 28143
A. D. C.
Estimation is carried by using Regional Schedule of Rates
(RSR) Pune region 2013-14. 6 A. I. C. 22424 30592 28557
7 A. M. C. 4981 4843 8009
A) Cement Concrete Lining 8 Total Annual 38168 50119 64709
cost:5+6+7
Excavation of 3958.56 m3 (rate 51.45 Rs per m3) Cost =
200860.8
Nomenclature:
Dressing of side slope area 1835.14 m2 (rate 1.85 Rs per T. D. D. L. = Total depreciation during life,
2
m ) Cost = 3395 Rs. A. D. C. = Annual depreciating charge,
A. I. C. = Annual interest charge,
Cost Preparation of sub-grade = 40051.3 Rs.
A. M. C. = Annual maintenance charge.
Cost of M 15 concrete for bed & side lining =473272 Rs. B = Canal bed width.
D = Total height including free board.
As per RSR Pune 2013-14,
Total design cost per 100 m = 717579.12 Rs. In this study concrete lining, stone masonry lining & burnt
brick clay lining are commonly utilized in Maharashtra and
B) Stone Masonry Lining

2 www.erpublication.org
International Journal of Engineering and Technical Research (IJETR)
ISSN: 2321-0869, Volume-3, Issue-5, May 2015
discussed fairly and a compression with deference to Maharashtra, India. One paper published on the topic Cost Effectiveness of
Different Canal Lining Materials on IJERT.
durability and economically.

Dr. S. S. Valunjkar Professor& Head of Dept. Of Civil


Engineering, Government College of Engineering, Karad, Maharashtra,
India.

Fig. 2 Comparison of Annual Cost

VI. CONCLUSION

In this study mainly fixate on the detail of construction cost of


variant of lining and its durability. Compare cement concrete,
Stone masonry and Burnt clay tile lining. According to
analysis of this topic cement concrete lining is more felicitous
then other two types of lining. Cost analysis of the topic
cement concrete lining more cost efficacious then other types
of lining method.

ACKNOWLEDGEMENT
I would relish to express my deep and sincere gratitude to
my guide Dr. S. S. Valujkar Head of Department of Civil
Engineering, for guiding me to accomplish this paper work. I
am very thankful to Mr. Ruju Mulani, Asst. engineer at
Urmodi Dam Division, Satara (Krishna Irrigation Project) for
providing all the obligatory data to carry out my work.

REFERANCES
[1] M. El-Kady, h. Wahby, Lining of Egyptian Canals Techniques and
Economic Analysis,April1984.
[2] Pradeep Shau, The Use of Canal Lining Avilable Material And Its
Comparative Study e-ISSN: 2278,p-ISSN: 2320-334X, Volume 11,
Issue 3 Ver. . IV (May-June 2014).
[3] Government of Maharashtra Irrigation Department circular No. MIS
1094/(156/94) MP (A) Dated: 18-2-1995.
[4] IS 3873: 1993, Laying Cement Concrete/ Stone Slab Lining Of
Canal-Code Of Practice .
[5] IS 3872:2002, Lining Of Canals With Burnt Clay Tiles- Code of
Practice.
[6] IS 11809;1994, Lining For Canals By Stone Masonry- Code of
Practice.
[7] Regional Schedule of Rates Pune Region (Under The Juridiction
MKVDC) 2013-14.

Mr. Amrut Namdev Sangale M.E.II (Civil - CM)


Dept. Of Civil Engineering, Government College of Engineering, Karad,

3 www.erpublication.org

You might also like