Mr. Amrut Namdev Sangale, M.E.II (Civil - CM) Dept. Of Civil III. DESIGN & MEASUREMENT OF CANAL LINING
Engineering, Government College of Engineering, Karad, Maharashtra,
India, 9595964194.
Dr. S. S. Valunjkar, Professor& Head of Dept. Of Civil Engineering, The basic parameter to design the canal is discharge, and as
Government College of Engineering, Karad, Maharashtra, India. per case study the discharge is 20 cumecs.
1 www.erpublication.org
Cost Effectiveness of Different Canal Lining Materials
As per Circular no. MIS 1094/ (156/94) Excavation of 4174.4 m3 (rate 51.45 Rs per m3) Cost =
214772 Rs.
Slope of ground is 1:5000
Dressing of side slope area 1874 m2 (rate 1.85 Rs per m2)
Side slope 1 V: 1.5 H
Cost = 3467 Rs.
B/d ratio 1.5 to 2
Cost of 15 mm thick 1:3 CM = 301343 Rs.
Assume that canal cross section is totally in cutting & strata
Cost of 230 mm thick UCR = 459388
is hard murum.
As per RSR Pune 2013-14,
A) Cement Concrete Lining
Total design cost per 100 m = 978970 Rs.
As per IS code3873:1993 design of C.C lining
Velocity = 0.9 m/s,
C)Brick /Burnt Clay Tiles Lining
Area req. = (20/0.9) =22.22 m2
Excavation of 3670 m3 (rate 51.45 Rs per m3) Cost =
Provide, B = 4m,
188841 Rs.
d =3.65 m (with 0.9 m extra free board)
Dressing of side slope area 1760.8 m2 (rate 1.85 Rs per m2)
As per design provide 10 cm thick concrete bed & 8 cm Cost = 3257 Rs.
side wall.
Cost of 10 mm CM (1:5) = 156348 Rs.
B) Stone Masonry Lining
Cost of two 50mm thick brick coat = 394394 Rs.
As per IS code 11809:1994 for Stone Masonry
Cost of plaster (1:3) = 391175 Rs.
Velocity = 0.8 m/s,
As per RSR Pune 2013-14,
Area raq. = 25 m2 ,
Total design cost per 100 m = 993298 Rs.
Provide B = 4.2 m,
d = 3.80 m (with 0.9 m extra free board) V. RESULT AND DISCUSSION OF CANAL LINING
Comparison of the three different comparing estimated
As per design provide 0.23 m thick stone masonry with 15
annual costs of types of lining cost show in the table 1.
mm CM on prepared sub-grade.
The following work illustrates calculate and compare
C)Brick/ Burnt Clay Tile Lining annual costs and additionally in graphical form show in fig 2.
As per IS code 9698:1995 design of C.C lining
Table.1 Comparing Estimated Annual Cost of Lining
Velocity = 0.9 m/s,
Sr. Type of work Cost of Lined canal Per 100 m
Area req. = (20/0.9) =22.22 m2 No
.
Provide, B = 4m, Cement Stone Burnt
Concrete Masonry Clay Tile
d =3.65 m (with 0.9 m extra free board) 1 Total cost 717579 978970 993298
As per design provide 10 mm thick CM on sub-grade, then 2 Life 50 50 30
provide two 50 mm thick coat of burnt clay tiles with 3 Salvage 179394 244742 148994
separated by 15 mm sandwich plaster & 5 mm thick mortar. value
4 T. D. D L. 538184 734227 844303
IV ESTIMATION OF CANAL LINING
5 10763 14684 28143
A. D. C.
Estimation is carried by using Regional Schedule of Rates
(RSR) Pune region 2013-14. 6 A. I. C. 22424 30592 28557
7 A. M. C. 4981 4843 8009
A) Cement Concrete Lining 8 Total Annual 38168 50119 64709
cost:5+6+7
Excavation of 3958.56 m3 (rate 51.45 Rs per m3) Cost =
200860.8
Nomenclature:
Dressing of side slope area 1835.14 m2 (rate 1.85 Rs per T. D. D. L. = Total depreciation during life,
2
m ) Cost = 3395 Rs. A. D. C. = Annual depreciating charge,
A. I. C. = Annual interest charge,
Cost Preparation of sub-grade = 40051.3 Rs.
A. M. C. = Annual maintenance charge.
Cost of M 15 concrete for bed & side lining =473272 Rs. B = Canal bed width.
D = Total height including free board.
As per RSR Pune 2013-14,
Total design cost per 100 m = 717579.12 Rs. In this study concrete lining, stone masonry lining & burnt
brick clay lining are commonly utilized in Maharashtra and
B) Stone Masonry Lining
2 www.erpublication.org
International Journal of Engineering and Technical Research (IJETR)
ISSN: 2321-0869, Volume-3, Issue-5, May 2015
discussed fairly and a compression with deference to Maharashtra, India. One paper published on the topic Cost Effectiveness of
Different Canal Lining Materials on IJERT.
durability and economically.
VI. CONCLUSION
ACKNOWLEDGEMENT
I would relish to express my deep and sincere gratitude to
my guide Dr. S. S. Valujkar Head of Department of Civil
Engineering, for guiding me to accomplish this paper work. I
am very thankful to Mr. Ruju Mulani, Asst. engineer at
Urmodi Dam Division, Satara (Krishna Irrigation Project) for
providing all the obligatory data to carry out my work.
REFERANCES
[1] M. El-Kady, h. Wahby, Lining of Egyptian Canals Techniques and
Economic Analysis,April1984.
[2] Pradeep Shau, The Use of Canal Lining Avilable Material And Its
Comparative Study e-ISSN: 2278,p-ISSN: 2320-334X, Volume 11,
Issue 3 Ver. . IV (May-June 2014).
[3] Government of Maharashtra Irrigation Department circular No. MIS
1094/(156/94) MP (A) Dated: 18-2-1995.
[4] IS 3873: 1993, Laying Cement Concrete/ Stone Slab Lining Of
Canal-Code Of Practice .
[5] IS 3872:2002, Lining Of Canals With Burnt Clay Tiles- Code of
Practice.
[6] IS 11809;1994, Lining For Canals By Stone Masonry- Code of
Practice.
[7] Regional Schedule of Rates Pune Region (Under The Juridiction
MKVDC) 2013-14.
3 www.erpublication.org