Technical Specification PTB
Technical Specification PTB
Technical Specification PTB
SPECIFICATIONS
D. In case discrepancies exist between this Section and its corresponding elaborated
sections, notify the Procuring Entity immediately for clarification; their decision shall
be final.
E. The Contractor shall bear the responsibility of checking all the numbers and
units as indicated in the Bill of Quantities. It is understood that the Contractor shall
supply and install the required units in accordance with the Plans and the
Specifications.
A. The execution of this Specification, Plans and other related Contract Documents shall
be subjected to the rules and regulations as provided in the General Conditions of
the Contract. The Plans and specifications shall be interpreted by the Procuring Entity
and or his/her representative.
B. The Contractor shall consult the Procuring Entity on portion of the work not mentioned
in the Specification and not illustrated on the Plans. He shall not work without proper
instruction or detailed plans approved by the Procuring Entity, otherwise he shall be
responsible for the in acceptance of the work done without details. In such case, the
Contractor shall make good the work at his own expense.
D. TWO (2) SET of clean Plans and specification shall always be kept at the jobsite to be
available to the Procuring Entity or their representative upon his request during the
construction.
1
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
a) The Work to be done under this Project consists of furnishing all labor, materials, tools,
equipment and facilities, including supervision, for the proper completion of the work as
specified herein in strict accordance with accepted codes and standards. Provide
sufficient workmen and competent supervisors familiar with the requirements and
installations of the specified items in the execution of this portion of the Work.
a) Provide record progress photographs taken at a fixed point and angle as, when and
where directed by the Engineer at intervals of not more than ten (10) days. The
photographs shall be sufficient in number and location to record the exact progress of
works. Billing photographs shall be in 4R size with corresponding billboard indicating
the name of the project and location, bill number, item number, name of the person
taking the photograph, date taken and the on-going activity.
a) The Contractor shall furnish the Project Engineer monthly progress reports within
seven (7) days before the end of every month, indicating progress made, construction
activities, inventories of material used and stored on job site, number of laborers,
equipment available and hours utilized, number of working days, the summary of the
daily log of the month and all important events in relation to the Works.
a) The Contractor shall prepare and submit three (3) sets as-built drawings and a final
construction report.
b) Fire Protection
a) The Contractor shall provide all construction workers/ staff with safety gears (i.e.
helmets, shoes, belts, gloves, etc.) at Site.
2
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
a) The Contractor shall provide safety devices (i.e. barricades, warning signs and other
appropriate tools) as necessary for public protection.
9.0 ENVIRONMENTAL PROTECTION
a) Fires
1. Fires and burning of rubbish on the site are not permitted except when authorized
by the Engineer. Where fires or burning is permitted, the Contractor shall prevent
the structures, materials or vegetation which is to be preserved from staining
and/or smoke damage. When so happen, the Contractor shall restore, clean and
return stained or damaged work to fresh conditions.
b) Disposal of Waste
1. The Contractor shall not bury rubbish and solid waste materials on the Site unless
approved by the Engineer. The Contractor shall not dispose of dredging spoils,
waste or volatile materials, such as mineral spirits, oil or paint thinner into the sea,
waterways, storm water drainage or sanitary sewers.
a) GENERAL
1. Work under this Contract shall be in accordance with the terms and conditions
stipulated in the Conditions of Contract and Section 1 "General Requirements"
of these Specifications and shall apply to this Section whether herein referred
to or not.
b) SCOPE OF WORK
c) MOBILIZATION
1. The Contractor shall mobilize and put into operation all equipment and plants
required to undertake the Contract.
3. Sufficient supply of spares for the equipment and plants shall be carried on-
board the towing/carrying vessels. Equipment/plants encountering breakdowns
must be repaired on site by the most expeditious method possible at no cost to
the Procuring Entity. In the event that the equipment/plants call for major repair
works that cannot be undertaken at the site, the Contractor shall replace such
equipment/plants with equal or better performance capacity at no additional
mobilization costs to the Procuring Entity and the Contractor shall not be
entitled to any time extension.
d) DEMOBILIZATION
3
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
a) The dismantling, preparation and loading for removal and shipment of all
Contractors plant, equipment and personnel at each site after completion of
the works.
a) DESCRIPTION
b) GENERAL PROVISIONS
1. The Contractor shall be deemed to have satisfied himself of the site conditions, and
to have included in his unit prices provision for all risks that may arise during or in
connection with the work.
2. The demolition work shall be carried out by approved methods and equipment such
as concrete breakers, gas-cutters, hydraulic jacks, compressed air disintegrators.
etc., however, no blasting shall be used unless approved in writing by the Engineer
and after obtaining the written permission of the concerned Authorities.
3. The Contractor shall provide suitable equipment, skilled labor and appropriate
temporary works such as scaffoldings to ensure safety in his demolition works as
well as in the adjacent area.
4. The Contractor shall demolish all the structural members above the level on which
the subsequent and permanent works under this Contract will begin. To this end,
the temporary construction works such as excavation shall be conducted by the
Contractor.
5. Materials coming from the demolition works, except general earth, shall remain the
property of the Procuring Entity, the designated part of which shall be stored by the
Contractor at places specified by the Engineer's authorized Representative
c) PARTICULAR REQUIREMENTS
1. Steel Members
a) Demolished materials shall be removed from the site and dumped at the
disposal areas approved by the Engineer.
1. Prior to the commencement of the demolition work, the Engineer shall submit to
the Contractor a list in which all the materials to be salvaged and overhauled, as
property of the Procuring Entity and the location of their storage shall be
described. Materials embedded in concrete units shall not be salvaged.
4
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
3. Debris, if it does not contain any pollutant in the opinion of the Contractor may be
dumped at the offshore area.
4. The Contractor may dump debris on land areas but out of the site, which areas
shall be procured and prepared at his own expense. In this case, safety measures
shall be undertaken in the transporting, unloading, covering and others as
requested by the Engineer.
a) SCOPE OF WORK
b) EXECUTION
1. The pesticide company should have a valid license from Fertilizer and
Pesticide Authority of the Department of Agriculture. All pesticide shall be
applied by or under the direct supervision of a certified pesticide applicator.
c) APPLICATION
b) CONTRACTORS GUARANTEE
1. Upon completion of work, and on a condition for final acceptance, the
Contractor shall submit to PPA a written guarantee from the pesticide company
which shall provide that:
2. The soil poisoning treatment shall prevent subterranean termites from attacking
the building on its contents for a period of not less than one (1) year.
3. The Contractor shall thereby warrant all works in pest control that all materials
and workmanship applied under the contract are of good quality in every
respect and will remain as such for not less than one (1) year.
5
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
3.1 GENERAL
a) All works falling under this category shall include reinforced concrete for all kinds and
parts of any reinforced concrete structure.
b) MATERIALS
2. Concrete aggregates shall conform to ASTM C33 except the aggregates failing
to meet these specifications but which have produced concrete of adequate
strength and durability may be used to the approval of the Structural Engineer.
3. Water used in mixing concrete shall be clean and free from injurious amounts of
oil, acids, alkalis, salts, organic material or other substances deleterious to
concrete or steel. In addition, the mixing water for pre stressed concrete shall
not contain deleterious amounts of chloride iron.
c) Mixing of Concrete
1. All concrete shall be mixed until there is a uniform distribution of the materials
and shall be discharged completely before the mixer is recharged.
d) Conveying of concrete
1. Concrete shall be conveyed from the mixer to the place of final deposit by
methods that will prevent the separation or loss of materials.
e) Depositing of Concrete
f) Curing
a) Unless otherwise specified, the vertical and horizontal reinforcements for CHB shall be
10 mm at 400-mm o.c. for all wall thickness. Lap splices shall be 300 mm long
(minimum)
b) Lintel beams to be used shall be (t x 0.20m) reinforced by 4-12 mm bars with 10mm at
300 mm o.c. ties where "t" is the CHB wall thickness.
c) Lintel beam shall be provided at top of CHB wall openings. It shall extend at least 200
mm beyond the openings.
6
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
The following minimum concrete cover shall be provided for reinforcing bars.
a) Cast-in-place concrete
c) Not exposed to weather or in contact with ground, slabs, walls and joints.
No 14 and No 18 38mm
b) Unless otherwise noted in the plans the minimum yield strength of the reinforcing bars
to be used corresponding to the structural member shall be as enumerated below :
1) A semicircular turn plus an extension of at least 4 bar diameter but not less than
62 mm at the free end of the bar
2) A 90-degree turn plus an extension of at least 12 bars diameter at the free end
of the bar.
10 mm to 25 mm - 6 bar diameter
28 mm to 36 mm - 8 bar diameter
No 14 to No 18 - 10 bar diameter
a) All forms and false work to be used in the work must be designed, and constructed by
the Contractor for rigidity and adequacy for carrying the loads of the fresh concrete
and/or additional superimposed construction loads. The Authority may from time to time
verify the adequacy and safety of such temporary works and may require the Contractor
to submit detailed designed drawings of forms and falseworks proposed to be used.
Approval of such drawings or design of forms, however, shall not relieve the Contractor
of his liability on resulting imperfections or damages to the finished concrete, or other
7
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
b) Forms may be re-used but shall be scrapped by a wire brush of all clinging mortar.
Bulges should be planed and realigned prior to its use.
c) Prior to placing concrete form surfaces should be oiled for easy form removal. However,
the oil coating should not be so thick as to stain and soften the concrete surface. Oil
coatings should be applied before rebars are placed.
a) Concrete surfaces shall conform accurately to the form, alignment, grades and sections
shown in the drawings or as prescribed by the Engineer. It shall be free from bulges,
ridges, honeycombing or roughness of any kind and shall be of a reasonably smooth
wood float finish.
DIVISION 4 MASONRY
4.1 MATERIALS
a) Concrete Hollow Blocks shall have a minimum face shall thickness of 1 (.025)
Nominal size shall be 6x 8x 16 and 4x 8x 16 minimum compressive
strength shall be as follows:
Class A - 900 psi
b) All units shall be stored for a period of not less than 28 days (including curing period)
and shall not be delivered to the job site prior to that time unless the strengths equal
or exceed those mentioned in these specifications.
d) Sand shall be river sand, well screened, clean, hard, sharp siliceous, free from loam,
silt or other impurities, composed of grains of varying sizes within the following limits:
9 Passing 100
16 Retained 5
100 Retained 97
8
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
4.2 ERECTION
a) All masonry shall be laid plumb, true to line, with level and accurately spaced
courses, and with each course breaking joints with the source below. Bond shall be
kept plumb throughout; corners and reveals shall be plumb and true. Units with
greater than 12 percent absorption shall be wet before laying. Work required to be
built in with masonry, including anchors, wall plugs and accessories, shall be built
as the erection progresses.
b) Masonry Units. Each course shall be solidly bedded in Portland cement mortar. All
units shall be damp when laid units shall be showed into place not laid, in a full bed
of unfurrowed mortar. All horizontal and vertical points shall be completely filled
with mortar when and as laid. Each course shall be bonded at corners and
intersections. No cells shall be left open in face surfaces. All cells shall be filled up
with mortar for exterior walls. Units terminating against beam or slab soffits shall be
wedged tight with mortar. Do not lay cracked, broken or detached block.
a) PLASTERING: Clean and evenly wet surfaces. Apply scratch coat with sufficient
force to form good keys. Cross scratch coat upon attaining its initial set; keep
damp. Apply brown coat after scratch coat has set at least 24 hours after scratch
coat application. Lightly scratch brown coat; keep moist for 2 days; allow drying
out. Do not apply finish until brown coat has seasoned for 7 days. Just before
applying coat, wet brown coat again. Float finish coat to true even surface; trowel
in manner that will force sand particles down into plaster, with final troweling, leave
surfaces varnished smooth, free from rough areas, trowel marks, checks, other
blemishes. Keep finish coat moist for at least 2 days; thereafter protect against
rapid drying until properly, thoroughly cured.
b) SCAFFOLDING
b) Provide all scaffolding required for masonry work, including cleaning
down on completion removes.
a) Do not start floor tiling occurring in space requiring both and wall tile
setting has been completed.
b) Before spreading setting bed, establish border lines center wires in
both directions to permit laying pattern with minimum of cut tiles. Lay
floors without borders from center line outward. Make adjustment at
walls.
c) Clean concrete sub floor and moisten it without soaking. Sprinkle dry
cement over surface. Spread setting bed mortar on concrete and tamp
to assure good bond over the entire area then screed to smooth, level
bed. Set average setting bed thickness at but never less than .
d) WALL TILE INSTALLATIONS
9
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
4. Set wall tile by troweling neat tile adhesive skim coat on float
coat or apply skim coat to back of each tile unit. Immediately float
tile in place. Make joints straight, level and perpendicular.
Maintain vertical joints plumb.
5. Grouting: Grout joints in wall tile with neat white cement
immediately after suitable area of tile has been set. Tool joints
slightly concave, cut off excess mortar ad wipe from face tile.
Roughen interstices of depressions. In mortar joints after gout
has been cleaned from surface. Fill to line of cushion tile bases
or covers with mortar. Make joints between wall tile, plumbing
and other built in fixtures with light colored caulking. Immediately
after grout has had its initial set, give tile wall surfaces protective
coat of non-corrosive soap.
DIVISION 5 METALS
a) WROUGHT IRON: Shall be free from any cracks. Blisters, flaws and comply other
defects and comply with BS 15, Grade A.
b) GALVANIZED STEEL: Shall be entirely and evenly coated with zinc and free from
stains, bare spots and other defects, such as blisters, pits, unplated areas, cloudy
patches, cracks and stains.
d) STAINLESS STEEL: Shall be of high chromium, high nickel steel. It shall comply
generally with the requirements of BS 970 EN and shall be the type established for
welding (58B).
f) HANDRAILS AND RAILING HANDRAIL: Stainless steel of high chromium, high nickel
steel. 45mm diameter handrail, hairline finish.
6.1 CARPENTRY
e) MATERIALS
2. WOOD GLUE: Use appropriate type of wood glue for joints in wood.
3. ROUGH HARDWARE: Provide all items of rough hardware necessary for the
installation of specified work. It shall be suitable type and of sufficient size and length
to draw the work firmly together
10
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
a) MATERIALS
1. DOOR & JAMBS: Use Ipil kiln dried. Jamb shall be finished according to door
finish. Refer to drawings for areas of application.
a) MATERIALS
b) INSTALLATION WORKMANSHIP:
7.2 WATERPROOFING
b) MATERIALS
1. Two component flexible cementitious waterproofing system with an elongation
break at 50%.
c) APPLICATION
8.1 GENERAL
a) Provide all door frames, doors and related items required for anticipated work. Provide
manufacturers guarantee that doors will have ample strength from ordinary use and will
11
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
be free from warping and checking for 5 years. Provide testing certification for
internationally accredited testing laboratory for all fire rated doors.
4.) FABRICATION
5.) INSTALLATION
6.) ADJUSTMENTS
12
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
DIVISION 9 SPECIALTIES
a) SCOPE
1.) To supply and install aluminum clip-in ceiling system as indicated in the
Drawings.
1.) Clip-in system shall be made of hot-dipped aluminum structure. Clip-in system
shall be standard perforated and the surface is finished with post coating or
pre-coated, the color is global white.
2.) 600mmx1200mm, 0.70mm thickness
Metal ceiling shall be stored in a dry interior location and shall remain in cartons prior to
installation to avoid damage. The cartons shall be stored in a horizontal position. Proper
care should be taken when handling to avoid damage or soiling.
e) INSTALLATION
1.) General
After opening the product carton, and before installation, be sure to locate,
remove and set aside the hardware kit before proceeding. Metal ceiling must
not be used to support any other materials and are also not approved for
exterior application.
a.) According to the ceiling floor plans, draw the line for location of the grid
b.) Determine the hanging point location
c.) Install the hanger wire, hanger wires spacing between 1200mm
d.) Installing, leveling, straightening grids: C-channel spacing between
1200mm. DP-12 main carrier (cross tee) spacing based on metal ceilings
width, clip-in ceiling panel installed by DP12 main carrier. Clip-in metal
ceilings installed system of grid has upper and lower layers, upper is for C-
channel and lower is for DP12 main carrier, their spacing is between
1200mm. Lower is DP12 main carrier, spacing determined by clip-in
panels installed side width. C-channel (upper) and DP12 main carrier
13
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
The installers need to wear gloves to avoid damage and pollute the ceiling
panels; before installing, cleaning surfaces of the metal ceilings. Use a
clean, soft white cloth and mild detergent and water to wipe off any dirt or
fingerprints. The dust in the back side of metal ceiling is normal
a) SCOPE
2.) To supply and install toilet partition/cubicles and ledges as indicated in the
Drawings.
a) MATERIALS
b) INSTALLATION
1.) All pilasters shall rest on NSS adjustable foot and anchored to the division wall by
satin anodized U-channel.
2.) The pilasters shall be finished with satin anodized heavy duty channel at the top rail.
3.) All edges of doors and pilasters are chamfered and finished without any metal
framing.
4.) Fixing of pilaster to the wall shall be done with satin anodized heavy duty channel
Furnish materials and equipment and perform labor required to complete all sanitary
fixtures. See drawings and details for sizes and locations of work required.
a) FIXTURES
14
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
cover, stain resistant, and low maintenance with ICC (Import Commodity
Clearance) or PS (Philippine Standard) markings.
2.) Urinal
a. Wall-hung rectangular base and U-shaped urinal for lever type flush
valve, including accessories, color white, with anti-bacterial protection,
stain resistant, and low maintenance with ICC (Import Commodity
Clearance) or PS (Philippine Standard) markings.
3.) Lavatory
a. Under counter oval lavatory, including accessories, color white with anti-
bacterial protection, stain resistant, and low maintenance, with ICC
(Import Commodity Clearance) or PS (Philippine Standard) markings.
b. Minimum fixture dimension: 500mm (length) and 400mm (width)
a. Single Hole, single lever lavatory type faucet including plastic pop-up
drain and other accessories, minimum flow rate 2.0 liters per minute,
minimum flow pressure 8.0 psi, with water-saving mechanism, in
chrome-plated color, with ICC (Import Commodity Clearance) or PS
(Philippine Standard) markings.
a) GENERAL SCOPE
1.) Furnish materials and equipment and perform labor required to complete all toilet
accessories. See drawings and details for sizes and locations of work required.
b) MATERIALS
c) EXECUTION
1.) Furnish and install all toilet accessories true to line, plane and level, in accordance
to manufacturer's specifications.
10.3 SIGNAGES
a) SCOPE
b) MATERIALS
1.) Shall be made of durable and weather-resistant cast acrylic, 3mm thk.
c) EXECUTION
1.) Coordinate with the Supervising Engineer before the final printing of signage.
2.) Install signage true to line, plane and level, in accordance with Drawings.
DIVISION 11 FINISHES
11.1 WALL
a) PLASTERING
1. Cement Plaster
a) Base Coat Proportion: Mix scratch coat in the proportion of one part by
volume of cement to not less than 2 nor more than 4 parts by volume of
damp loose sand. Mix brown coat in the proportion of one part by volume of
cement to not less than 3 nor more than 5 parts by volume of damp loose
sand.
f) Finish Coat Proportion: Mix finish coat in the proportion of one part by
volume of cement to not less than 2 nor more than 3 parts by volume of
damp loose sand.
b) CONCRETE FINISHES
1. SCHEDULE OF FINISHES
16
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
b) Off Form Finish: For Use plywood form to prepare surface for designated finish.
c) Steel Trowelled Finish: For floors intended as walking surfaces or for reception of
floor coverings.
3. PAINTING
A. SCOPE OF WORK
B. MATERIALS:
C. SCHEDULE
Surface Preparation: Remove all loose, scaling, flaking, and peeling off paint by wire
brushing, scraping, or rough sanding
Surface Preparation: Remove all loose, scaling, flaking, and peeling off paint by wire
brushing, scraping, or rough sanding
17
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
4. NEW METAL SURFACES Structural Steel trusses, purlins, G.I. pipes and angular bars
Finish: Flat
11.2 FLOORS
1. MATERIALS
b) Mortar - All mortar setting bed for use on floors shall be tile adhesive.
d) COLOR: Color shall be selected by the ESD Manager from the range currently
available from the manufacturer.
18
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
e) ACCESSORIES: Ceramic floor tiles shall have the sizes indicated on the plans and
all accessory tiles shall be in matching sizes; all accessory tiles shall be as required
for conventional mortar installation.
g) OTHER MATERIALS: All other materials, not specifically described but required for
a complete and proper tile installation, shall be as selected by the Contractor subject
to the approval of the Supervising Engineer.
11.3 CEILING
a. MATERIAL : 0.40mm thk base metal thickness, 0.20m nominal width, pre painted,
white
DIVISION 16 ELECTRICAL
16.1 GENERAL
a.) The work under this Division specification consists of Electrical Systems and other
related works, such as but not limited to fabrication, supply, delivery, coordination
and installation, shall be complete in all aspects for a proper completion and
turnover of the project except to those portion clearly stated to be done by others.
b.) All works to be done shall be in accordance with the latest edition of Philippine
Electrical Code (PEC), National Building Code, Regulation of locality, Utility
provider, Manufacturer standard, other Governing applicable codes and this
Specification.
c.) This Specification provide a broad outline, understanding of the required system
and other associated equipment requirements for the project, but not includes all
detail in the design and construction.
a. Under this Division of specification and as shown in plans, provide all materials,
equipment including all necessary accessories and perform all the work needed
to complete execution of electrical system but not limited to the following main
items:
19
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
p. .Perform complete testing and commissioning of all electrical power and lighting
systems.
20
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
s. Application, securing approval and preparation for all necessary plans, shop
drawings, payment, forms other related documents and coordination with
electrical utility provider and/or building administration personnel involved for
permanent power connection.
t. If anything has been omitted for any items of materials or work that are
necessary for the completion of this project, such item is deemed included in
this division of work.
a. All Materials to be use shall be brand new, in good conditions, free from any
defects, damage and corrosion.
b. All Materials shall conform and certified or listed to a reputable 3rd party
certifying body, such as UL, IEEE, NEMA, IPCEA and ASTM, on where such
standard has been established for particular types of materials.
d. All Materials shall be approved from both location and purposed intended.
16.4 EXECUTION
1.) All the legal fees and permit for the installation and finishing of
electrical works required by the rules and regulations of Puerto
Princesa City and the requirements of the local power provider shall
be obtained by and at the expense of the Contractor.
2.) After finishing the electrical works, the Contractor shall furnish
PPA final certificate of inspection and approval from the
government authorities. The Contractor shall prepare as-built
plans including all necessary documents required by PPA.
21
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
3.)The plans do not show all the necessary accessories, fittings etc.
The contractor shall be responsible in completing this required
necessary item in finishing the project.
c. Services
d. Installation Requirements
3.) Protection from work. The contractor shall protect his work
from damage during and after until it was properly turn over to
the owner.
e. Contract Drawings
f. Workmanship
3.) After all the electrical works are done the contractor shall
have set of files ready for access and reference indicating
all works that are installed and incorporating any changes
during the installation period. A set of this file shall be turn
over to the engineer.
23
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
j. Testing
24
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
3. Punch-list
3. The contractor shall record all the changes in the drawing and
submit copy of As-Built drawings to the PPA.
1. The work consist of furnishing of all materials and labor, tools and equipment
and all necessary services to complete the mechanical work ready for
operation as shown in the drawings and specified as follows:
2. Relocation of two (2) units existing split type ACU's (please refer to AR--2)
including installation of refrigerant lines, drain pipes and electrical supply on
all relocated ACUs
3. Supply and installation of six (6) units 3T Ceiling Mounted Cassette Type Air
Condition
4. Supply and installation of one (1) unit Window Type Air Condition
The mechanical work shall be done in accordance with all the requirements
of the latest Mechanical Code and regulations and Ordinance of the local
enforcing authorities.
25
Extension of Passenger Terminal Building,
Port of Puerto Princesa, Palawan
All materials to be supplied shall be new and of high quality suitable for the
location and purpose. Materials shall be standard products of reputable
manufacturers.