10/01/04 W42.2
up the pipe joint with the preceding section of
pipe. A shallow bell hole must be made at the
joints to facilitate installation of the
polyethylene tube.
10/01/04 W42.3
polyethylene sheet, or with a tube cut open, wrapped around
the pipe to cover the damaged area, and secured in place.
MEASUREMENT AND PAYMENT (Sec. 44.08) The price for this item
shall be included in prices for other items and shall include
all material, labor, tools and appliances to accomplish this
work. No separate payment for this item will be made.