Proposal Schedule For Remedial Works of Retension Pond at Taman Puteri Subang, Section U5, Shah Alam For Majlis Bandaraya Shah Alam

The document outlines a 9 task proposal schedule from July 20 to August 20 for remedial works of a retention pond in Taman Puteri Subang, Shah Alam. The first tasks include installing scupper drains and earth works from July 20-27. Anti-climb fencing will then be purchased and installed from July 27 to August 2. A walkway with curb and TNB brick wall will be constructed from August 2-10 followed by road pavement from August 11-12. The project then allows time for a final survey, cleaning, and completion of survey drawings by August 20.

Uploaded by

syafiqabang
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
60 views

Proposal Schedule For Remedial Works of Retension Pond at Taman Puteri Subang, Section U5, Shah Alam For Majlis Bandaraya Shah Alam

The document outlines a 9 task proposal schedule from July 20 to August 20 for remedial works of a retention pond in Taman Puteri Subang, Shah Alam. The first tasks include installing scupper drains and earth works from July 20-27. Anti-climb fencing will then be purchased and installed from July 27 to August 2. A walkway with curb and TNB brick wall will be constructed from August 2-10 followed by road pavement from August 11-12. The project then allows time for a final survey, cleaning, and completion of survey drawings by August 20.

Uploaded by

syafiqabang
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROPOSAL SCHEDULE FOR REMEDIAL WORKS OF RETENSION POND AT TAMAN PUTERI SUBANG, SECTION U5, SHAH ALAM FOR

MAJLIS BANDARAYA SHAH ALAM

July August
ID Task name Duration Start Finish
20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1.0 Install Scupper Drain 5 days 20-Jul 24-Jul
1.1 Housing area 5 days 20-Jul 24-Jul
2.0 Earth Work 8 days 20-Jul 27-Jul
2.1 Housing Area 6 days 20-Jul 25-Jul
2.2 TNB Area 3 days 25-Jul 27-Jul
3.0 Anti Climb Fencing 7 days 27-Jul 2-Aug
3.1 Purchasing & Delivery 1 day 27-Jul 27-Jul
3.2 Installation 7 days 2-Aug 2-Aug
4.0 Walkway with Curb 6 days 2-Aug 7-Aug
5.0 Construct TNB Brick Wall 4 days 7-Aug 10-Aug
6.0 Road Pavement 2 days 11-Aug 12-Aug
7.0 Final Survey 1 day 13-Aug 13-Aug
8.0 Cleaning 2 days 13-Aug 13-Aug
9.0 Survey Drawing 1 day 20-Aug 20-Aug