CONSTRUCTION WORK

RATES
Contractor : Dil Bahadur Rai : 9804036194, 9843876318
S.No. Description Unit Rate Remark
1 Earth Digging (below 20 ft) Cu.ft 12
2 Earth Filling Work (below 20 ft) Cu.ft 10
3 Flat Brick Soling Sq.ft 8
4 P.C.C (up to 3 inch) Sq.ft 18
5 R.C.C (Raft dhalan) Cu.ft 32
6 Shear Wall Dhalan Cu.ft 40
7 Column Dhalan Cu.ft 40
8 Slab Dhalan Cu.ft 35
9 Sill Dhalan 4 R.ft 60
10 Sill Dhalan 9 (Single) R.ft 80
11 Koping Dhalan R.ft 80
12 Brick Wall 4 Sq.ft 25
13 Brick Wall 9 Sq.ft 30
14 Internal Plaster Sq.ft 15
15 External Plaster (Simple) Sq.ft 25
16 Ceiling Plaster Sq.ft 15
17 Chaukas Fitting No. 500
18 Kora masino Sq.ft 25
19 Floor Cheeping Sq.ft 6
20 Pning Sq.ft 8
21 Skirting R.ft 40
22 Pani Patti R.ft 50
23 Double Patti R.ft 50
24 Spring R.ft 70
25 Mason Per.Person 1000
26 Labour Per.person 600
Height Factor : 5%