033 InstGde Aeon 4000 PRSystem PDF
033 InstGde Aeon 4000 PRSystem PDF
033 InstGde Aeon 4000 PRSystem PDF
Aeon Gold
Control Unit
SMPS 4000
Rectifier
356940.033
Issue 2, 2006 June
Table of contents
Table of contents
2(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
Table of Contents
1.1 Warnings
If you are uncertain about any of the safety precautions or the safety risks involved with
installing and running the AEON 4000 system, the safety notes in the General Information
section in the System Overview (Art. No 356940.013) MUST be consulted.
1.2 Introduction
The following chapters will guide you step-by-step through:
Mechanical Installation
All cable connections
Battery Installation
Installation of SMPS modules
A level surface is recommended for floor cabinets and the adjustable legs on floor cabinets
can absorb an unevenness of approx. 2 cm (0.8).
Fans are located inside the units which blow the air from the back of the cabinet to the front,
to cool the SMPS 4000 rectifiers. To achieve an adequate amount of air for the ventilation
process, it is generally not recommended to install AEON 4000 cabinets against walls.
Exceptions can be made for installations with air conditioning systems and elevated floors
where the tiles underneath the cabinets are removed.
The recommended distance from the wall will depend on the room temperature. Our
recommendations are given below for full power operation at 40C.
4(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
1 Installation of the Rectifier Systems
Pozidrive bits
Torx bits
1.4 Unpacking
5 Some cabinets may weigh more than 250 kg (550lb). Appropriate lifting
equipment should thus be used and care must be taken while handling
Procedure 1 Unpacking
Eltek Energy DOES NOT consider a compression gland connection to a steel wired armoured
cable (SWA) as satisfactory for this important safety function.
2) In cases where a Clean Earth is available, connect a DC PE cable from the system's
positive bus-bar to a Clean Earth. This cable must be capable of withstanding the
system's short-circuit current for at least the time taken for the battery fuse to rupture and
must be sized accordingly.
Eltek Energy strongly recommend to establish a Clean Earth connection on each site
If an external Clean system Earth is not available the mains PE terminal may be the source
of earth reference for the equipment. In this case, the common rail must be connected to the
PE terminal.
Mains safety
protective earth
(PE)connection
6(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
1 Installation of the Rectifier Systems
The Customer may in this situation (clean earth unavailable) remove the default yellow/green
wire from the PE terminal to the cabinet earth bolt.
In general the positive load pole should be connected either to the small copper connection
points if the MCBs are used, and the large connection point on the copper bar if the blade
fuses are used. Drawing 1 in chapter 4 gives a general overview of the system.
Large
connection
points
Small
connnetion
points on
positive
pole
Load
MCBs
Figure 3 Example of large and small connection points with load MCBs
On the negative side the cables are either connected to the top of the large blade fuses, or to
the top of the MCBs. The number of MCBs and blade fuses vary from system to system, and
so does the contactor configuration.
NH00 (BLADE 8 mm
FUSE)
70 mm2 (2/0 AWG)
NH01 (BLADE 8 mm
FUSE)
150 mm2 (300 MCM)
NH02 (BLADE 10 mm
FUSE)
240 mm2 (470 MCM)
NH03 (BLADE 12 mm
FUSE)
400 mm2 (600 MCM)
8(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
1 Installation of the Rectifier Systems
L1
L2
L3
Eltek recommends the following fuse rating for AC input when you have 24 VDC, 48 VDC
and 60VDC output:
10(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
1 Installation of the Rectifier Systems
terminal
Table 3 Recommended fuses for 24 VDC, 48 VDC and 60VDC output
The blade fuse positions Fbx (NH0x) are reserved for battery connection. The batteries
should be installed as recommended by the battery manufacturer. You will find the
following color coding on the battery cables, depending on the type of load distribution
used in your system:
2. CONNECT POSITIVE
BATTERY CABLES
In case of positive load distribution connect
(USUALLY BLACK) TO THE
COMMON BUSBAR ON
negative battery cables to common bus bar
TOP OF THE CABINET
3. CONNECT NEGATIVE
BATTERY CABLE In case of positive load distribution connect
(USUALLY BLUE) TO THE positive battery cables to the battery fuses.
BATTERY FUSES
AEON Gold has four additional inputs for voltage monitoring which are normally used to
check the symmetry voltages in one or several battery strings (See chapter 2.3 for details).
There are two optional ways of performing symmetry voltage monitoring:
The symmetry monitoring connections depend on whether the system has positive earth,
which is most common in 48Vdc and 60Vdc systems or negative earth, which is most
common in 24Vdc systems. In systems with negative distribution and positive earth all
symmetry connections should be connected to Agnd reference on TB3 pin 18, which is
connected to battery minus. In systems with positive distribution and negative earth all
symmetry+ connections are to be connected to Agnd reference, which again is connected to
battery plus. In this case the negative symmetry connections are connected to the battery
string(s).
For centre point monitoring in a positive earth system the symmetry + connections are to be
connected to the battery centre point. One connection for each battery string. If only one
string is installed only symmetry 1+ should be used and the other three connections should
not be used.
For centre point monitoring in a negative earth system the symmetry - connections are to be
connected to the battery centre point.
For block monitoring the connections are shown in Figure 7 both for positive and negative
earth systems.
12(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
1 Installation of the Rectifier Systems
+
Negative Distribution Positive Distribution
12V
Symmetry 3+ Symmetry 1-
12V
Symmetry 2+ Symmetry 2-
12V
Symmetry 1+ Symmetry 3-
12V
3. FASTEN THE MODULE WITH A Located behind the handle in front of the module,
FRONT PANEL SCREW see Figure 8.
Green Power
LED
Communication
LED (Yellow)
Handle
14(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
1 Installation of the Rectifier Systems
DC -
Pin no. Description
1 PE
2 PE DC +
3 Mains L
4 Mains L
PIN 10
5 Mains N
6 Mains N
7 PE
9 A/CANH (5V)
10 A/CANH (0V)
16(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
2 Connections to AEON Gold Control Unit
Relay 10 can be assigned as AEON Gold failure alarm output by setting a dipswitch under
Config Relay 10, in ON position. Any software setting of this relay will then be disabled.
Relay 8-10 are the default driving contactor relays for LVLD 2-4, but all of the relays in the
table can be configured for this purpose in WinPower.
18(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
2 Connections to AEON Gold Control Unit
Relay 3 C TB5 9
Relay 4 NO Fuse Alarm Relay TB5 10
Relay 4 NC TB5 11
Relay 4 C TB5 12
Relay 5 NO Common Rectifier Alarm Relay TB5 13
Relay 5 NC TB5 14
Relay 5 C TB5 15
Relay 6 NO Common Alarm TB5 16
Relay 6 NC TB5 17
Relay 6 C TB5 18
Relay 7 NO TB6 1
Relay 7 NC TB6 2
Relay 7 C TB6 3
Relay 8 NO TB6 4
Relay 8 NC TB6 5
Relay 8 C TB6 6
Relay 9 NO TB6 7
Relay 9 NC TB6 8
Relay 9 C TB6 9
Relay 10 NO TB6 10
Relay 10 NC TB6 11
Relay 10 C TB6 12
Table 9 Alarm relay outputs
1 1
1 1
2 2
2 2
3 3
3 3
4 4
4 4
5 5
5 5
6 6 6 6
7 7 7 7
8 8 8 8
9 9 9 9
3000 mm 3000 mm
Cable Screend twisted 6 core 0.22 Square mm Cable Screend twisted 6 core 0.22 Square mm
20(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
2 Connections to AEON Gold Control Unit
1 1
2 2
3 3
4 4
5 5
6 6
7 7
8 8
9 9
1 1
22(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
2 Connections to AEON Gold Control Unit
2.9.1Control Unit
The AEON Gold control unit or central processor unit (CPU) is located either on the hinged
door behind the front panel or inside the cabinet. On this board you will find all necessary
terminals for internal or external connections. Information LEDs, service switch,
configuration switch and reset button are also located on this board. The Aeon Gold
241241.100 has control unit with part number 240278.185.
CAN bus
DC Fuse, 1A
Figure 1 AEON Gold control unit part number 240278.185
The CPU has a heartbeat LED. The heartbeat LED will pulse during normal operation. If the
alarm module looses its connection to the system, the LED will stop pulsating and the reset
button can be used to restart the alarm module. The parameters are stored in the CPU, so use
of this button will not affect the system.
On the control unit there is a service switch with an indicator LED that is lit when the service
switch is in ON position. Relay 10 can be configured for different purposes. Configure relay
10 enables the user to do this. For details, see chapter 2.5.
Note: For 60 V systems, the new Aeon Gold HW, Art. 241241.100 is required.
2.9.2Front panel
The AEON Gold front panel comprises a keypad, a LCD display, a green LED (indicating
that the system is ON) and a red LED (indicating that the system is in alarm mode). This
module is located on the hinged door or above it, mounted in a 19 rack. It is connected via an
interface cable to a 26 pin D-sub connector on the side of the control unit.
24(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
2 Connections to AEON Gold Control Unit
10 Numerical keys
Red LED - 3 Keys for menu scroll
Alarm 1 key for scroll back
2.9.3Power Supply
The Alarm module can be fed with AC and/or DC voltages. Default power for AEON Gold is
DC power from rectifiers or batteries. If using 230VAC input, an optional external
transformer is require. An extra fuse on the transformers secondary side is also optional. This
AC voltage will be transformed to DC voltage inside the AEON Gold, since the input
contains rectifiers and filters to handle the low voltage AC from the external transformer. The
default DC input is made for voltages between 20VDC to 90VDC.
Transformer External
fuse (AC) transformer
2.9.4Inputs
2.9.4.1Analogue inputs
The main board is designed for monitoring up to 4 battery strings, with one shunt input and
one symmetry measurement for each string. In addition there is one system voltage input and
two temperature measurement inputs. The resulting input allocation is as follows:
DC voltage inputs for system voltages 24VDC, 48VDC and 60VDC, used for DC
voltage measurements and symmetry supervision. This covers, typically, 1 battery
voltage reference input, and 4 symmetry inputs for centre measurements of 4 strings or
1 string of 4 *12Volt inputs.
Voltage range: 75VDC for new Aeon Gold 241241.100.
DC voltage inputs with 60mV range for shunt (current) measurements.
Temperature measurement input, 2 inputs using a A/K sensor (current generator).
2.9.4.2Digital inputs
The main board is equipped with 10 different inputs, 3 for fuse supervision and 7 as generic
inputs.
Battery Fuse alarm is powered internally and activated by a dry contact.
Load Fuse alarm 1 and 2 need external power to activate.
7 generic inputs are powered internally and activated by a dry contact.
Type: 2 Voltage input and 8 dry contact inputs
Isolation: Optocoupler isolated
2.9.5Digital outputs
The main board is equipped with 12 relay outputs. These are mainly used as alarm relays or as
driver output to optional contactors. They are configurable as Normally Open or Normally
Closed operation (NO/NC).
Type: dry contact
Isolation Voltage range: 250VAC
Max Contact Current: 1A
2.9.6Communication ports
The CPU board is equipped with 3 communication ports:
1 RS232 port (com0) based on the internal CPU comm port, configured as a ITU
V24. DCE device.
1 RS232 port (com 1) based on an external uart chip, configured as a ITU V24. DTE
device.
1 CAN bus interface. A full CAN B. Interface, optically isolated and based on the
CPUs internal port.
The DTE port marked COM1 is used for communication with PC (Winpower Gold), modem
or SNMP adapter. The DCE port marked COM0 is used for software upgrade or service, but
can also be configured to be a Winpower connection point. This is done in the service menu
on the AEON Gold front panel. See System Operation for AEON 4000 (Art. No 355204.013)
for details.
26(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
2 Connections to AEON Gold Control Unit
Both the COM0 and the COM1 port can be configured to be a Webpower connection port.
For further description of Webpower, see The Webpower Operation Guide, part. No
356943.013.
For further description of the SNMP communication solution, see User Manual SNMP
Adapter, part. No. 356942.013.
Figure 15SNMP adapter with fuse and External transformer with fuse
28(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
3 Start-Up And Commissioning Instructions
9 Please note that system start-up and configuration require the use of
WinPower Gold and a PC
3.2.2System Start-Up
CHECK THE FOLLOWING: OK
1. Verify that AEON Gold is connected to a power supply. Normally there is a
AC transformer installed that is feeding the control unit. Turn the 2-pole AC
MCB to AEON Gold ON. If no AC supply is available to the AEON Gold, then
connect a battery string temporarily to the DC bus bars (in order to power up
the AEON Gold ).
30(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
3 Start-Up And Commissioning Instructions
3.2.3Alarm Levels
Alarm levels are verified in WinPower, under general configuration, in the Define Triggers
menu and Set Levels menu.
3.2.3.1Default Values
Factory set Default values Customer Unit
specified values
System Voltages 24V 48V 60V
High Battery Voltage: 28,5V 57V 71,25V V
Low Battery Voltage: 24,5V 49V 61,25V V
Battery standby Voltage: 20V 40V 50V V
Battery Voltage: 26.8V 53.5V 66,8V V
Disconnect Voltage 21.5V 43.0V 53,75V V
(LVBD):
Rectifier trip voltage 29,75V 59,5V 74,38V V
(OVP)
Disconnect Delay Time 0 min min
Power limitation 100% (common)
Procedure 10 Commissioning Default Values
The relays can be configured to different detector classes, so that many different detectors can
trigger one relay. Each trigger has three possible alarm classes, alarm, warning and info. The
alarm response on AEON Gold differs between the alarm classes. For more details see System
Operation for AEON 4000 (Art. No.355204.013).
32(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
3 Start-Up And Commissioning Instructions
Set the maximum value for high battery voltage alarm lower than the actual output
voltage. Exit by pressing OK button
Observe that high battery voltage alarm and corresponding alarm relay are triggered
Set the maximum value back to original number.
Test Load Fuse Alarm (on MCB's )
Turn OFF one of the load fuses (NB: there must be a fuse connected to a load).
Observe that the load fuse alarm appears in the Alarm Display and the corresponding
alarm relay (if configured) are activated.
Test Load Fuse Alarm (on blade fuses)
Remove a blade fuse, which is connected to an output with a load already connected,
and observe that the load fuse alarm and corresponding alarm relay (if configured) are
activated.
Test Battery Fuse Alarm (on blade fuses)
Operate one of the micro switches located on top of the blade-fuses, and observe that
the battery fuse alarm appears in the Alarm Display and corresponding alarm relay (if
configured) are activated.
Test Rectifier Communication Alarm
Turn off the mains breaker
Remove rectifier no.1 from its position in the rack shortly after turning off the mains
breaker.
Observe that a rectifier communication alarm is activated in AEON Gold
Return rectifier no.1 back into position and turn on the mains breaker
Test Rectifier Common Alarm
Switch of the mains breaker to rectifier no.1.
Observe that a rectifier common alarm is activated in AEON Gold
Turn on the mains breaker again
Test LVBD NOT APPLICABLE
Select the General Configuration Menu in WinPower.
Select Relay Test, and then select LVBD Relay.
Observe that the LVBD is deactivated (you will hear a distinct click as the contactor
operates)
Operate the Service Switch and observe that the LVBD is activated again. Return the
Service Switch to the normal position.
Select the LVBD Relay again, in order to reset the LVBD Relay.
Test LVLD NOT APPLICABLE
Select General Configuration menu in WinPower Gold
Select Relay Test tab, then select LVLD Relay
Observe that LVLD is activated (only when LVLD is NC)
Observe that the LVLD is deactivated when exiting the Relay Test Menu
Normal Operation
Check that the system is operating without any faults.
Select the General Configuration Menu in Winpower
Select Event Log and erase all events stored in the log.
Comments:
APPROVAL
Engineer, sign.: Date: Approved by Customer, sign.:
34(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
3 Start-Up And Commissioning Instructions
Calibration of battery current measurement is normally done during FAT (factory acceptance
test). However, re-calibration may be necessary after installing the system. This recalibration
is not easily performed because it requires a certain amount of available load current,
preferably more than 30 % of the current rating of the shunt. To ease recalibration AEON
Gold has a 60 mV precision output called Cal output 60 mV. High calibration point will
then be the current that corresponds to 60 mV on the shunt, and be equal to the shunt rating.
In other words, if the shunt gives 60 mV at for example 2000 A the high calibration point is
2000. To recalibrate in this way, remove the current sensing on TB2, pin 6(+) and pin 7(-).
Calibrate the low calibration point at 0 A when the cables are short-circuited, then connect the
60 mV outputs left pin to TB2 pin 6 and the right one to TB2 pin 7. Calibrate the high
calibration point at the corresponding current. Remember to reconnect the wires from the
shunt after calibration.
3.3.1System data
Supplier's Order no.: System model AEON Gold Measured Mains
Voltage:
Serial no.: No. of Power Racks: Software version of No. of Modules:
AEON Gold:
Mains configuration
Verify that the system is correctly configured:
400V, 3P and N 400VAC, 3P and N, dual input
230VAC, 3 phase 230VAC, 3 phase, dual input
LVBD LVLD Symmetry Modem Temp. Compensation
Alarm
YES YES YES YES YES
NO NO NO NO NO
Other configurations, specify:
3.3.2Batteries
Battery Manufacturer:
Recommended Float Charge Voltage, at Battery Type: Cell Slope Voltage
20C(68F) (mV/C): (systems with
Measured Float Charge At_____C temperature
Voltage compensation only)
36(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
4 Drawings
4 Drawings
The following example drawings are enclosed:
38(44) Installation & commissioning, AEON 4000, Art. No. 356940.033, v2,2006-06
4 Drawings
Phone: +4732203200
Telefax: +47 32203210
Internet: http://www.eltekenergy.com
e-mail: eltek@eltekenergy.com