References
References
Brief Notes
Introduction
Production Planning is a managerial function which is mainly concerned with the following
important issues:
What production facilities are required?
How these production facilities should be laid down in the space available for
production? and
How they should be used to produce the desired products at the desired rate of
production?
Important functions covered by production planning and control (PPC) function in any
manufacturing system are shown in Table1along with the issues to be covered.
Table 1: Production Planning and control Functions
Job Production
In this system products are made to satisfy a specific order. However that order may be
produced-
only once
or at irregular time intervals as and when new order arrives
or at regular time intervals to satisfy a continuous demand
The following are the important characteristics of job shop type production system:
Machines and methods employed should be general purpose as product changes are quite
frequent.
Planning and control system should be flexible enough to deal with the frequent changes in
product requirements.
Man power should be skilled enough to deal with changing work conditions.
Schedules are actually nonexistent in this system as no definite data is available on the
product.
In process inventory will usually be high as accurate plans and schedules do not exist.
Product cost is normally high because of high material and labor costs.
Grouping of machines is done on functional basis (i.e. as lathe section, milling section etc.)
This system is very flexible as management has to manufacture varying product types.
Material handling systems are also flexible to meet changing product requirements.
Batch Production
Batch production is the manufacture of a number of identical articles either to meet a specific
order or to meet a continuous demand. Batch can be manufactured either-
only once
or repeatedly at irregular time intervals as and when demand arise
or repeatedly at regular time intervals to satisfy a continuous demand
The following are the important characteristics of batch type production system:
As final product is somewhat standard and manufactured in batches, economy of scale can
be availed to some extent.
Machines are grouped on functional basis similar to the job shop manufacturing.
Semi-automatic, special purpose automatic machines are generally used to take advantage of
the similarity among the products.
Labor should be skilled enough to work upon different product batches.
In process inventory is usually high owing to the type of layout and material handling
policies adopted.
Semi-automatic material handling systems are most appropriate in conjunction with the
semi-automatic machines.
Normally production planning and control is difficult due to the odd size and non repetitive
nature of order.
Mass Production
In mass production, same type of product is manufactured to meet the continuous demand of the
product. Usually demand of the product is very high and market is going to sustain same demand
for sufficiently long time.
The following are the important characteristics of mass production system:
As same product is manufactured for sufficiently long time, machines can be laid down in
order of processing sequence. Product type layout is most appropriate for mass production
system.
Standard methods and machines are used during part manufacture.
Most of the Equipments are semi-automatic or automatic in nature.
Material handling is also automatic (such as conveyors).
Semi-skilled workers are normally employed as most of the facilities are automatic.
As product flows along a pre-defined line, planning and control of the system is much
easier.
Cost of production is low owing to the high rate of production.
In process inventories are low as production scheduling is simple and can be implemented
with ease.
PRODUCT DESIGN
Product design is a strategic decision as the image and profit earning capacity of a small
firm depends largely on product design. Once the product to be produced is decided by the
entrepreneur the next step is to prepare its design. Product design consists of form and function.
The form designing includes decisions regarding its shape, size, color and appearance of the
product. The functional design involves the working conditions of the product. Once a product is
designed, it prevails for a long time therefore various factors are to be considered before
designing it. These
Factors are listed below: -
(a) Standardization
(b) Reliability
(c) Maintainability
(d) Servicing
(e) Reproducibility
(f) Sustainability
(g) Product simplification
(h) Quality Commensuration with cost
(i) Product value
(j) Consumer quality
(k) Needs and tastes of consumers.
Above all, the product design should be dictated by the market demand. It is an important
decision and therefore the entrepreneur should pay due effort, time, energy and attention in order
to get the best results.
TYPES OF PRODUCTION SYSTEM
Broadly one can think of three types of production systems which are mentioned here under: -
(a) Continuous production
(b) Job or unit production
(c) Intermittent production
(a) Continuous production: - It refers to the production of standardized products with a
standard set of process and operation sequence in anticipation of demand. It is also known as
mass flow production or assembly line production This system ensures less work in process
inventory and high product quality but involves large investment in machinery and equipment.
The system is suitable in 117plants involving large volume and small variety of output e.g. oil
refineries reform cement manufacturing etc.
(b) Job or Unit production: - It involves production as per customer's specification each batch
or order consists of a small lot of identical products and is different from other batches. The
system requires comparatively smaller investment in machines and equipment. It is flexible and
can be adapted to changes in product design and order size without much inconvenience. This
system is most suitable where heterogeneous products are produced against specific orders.
(c) Intermittent Production: Under this system the goods are produced partly for inventory and
partly for customer's orders. E.g. components are made for inventory but they are combined
differently for different customers. . Automobile plants, printing presses, electrical goods plant
are examples of this type of manufacturing.
Several different terms are used such as:
Operations management, production and operation management, production planning and
control, manufacturing system and management, etc. Originally applied primarily in
manufacturing companies focus on production management. These approaches and tool later
applied to service organizations focus on managing an organizations operation.
Break-Even Analysis
The objective is to maximize profit. On economic basis only revenues and cost need to be
considered for comparing various locations.
The steps for locational break-even analysis are :
Determine all relevant costs for each location.
Classify the location for each location in to annual fixed cost and variable cost per unit.
Plot the total costs associated with each location on a single chart of annual cost versus
annual volume.
Selwct the location with the lowest total annual cost(TC) at the expected production
volume.
Question:
Potential locations A, B and C have the cost structures shown below for manufacturing a product
expected to sell for Rs 2700 per unit. Find the most economical location for an expected volume
of 2000 units per year.
Solution:
For each plant find the total cost using the formula
TC=Fixed cost+ Variable cost/unit (volume)
= FC+VC(v)
From the graph, the different ranges of production volumes over which the best location to be
selected are summarized.
The same details can be worked out using a graph. From the graph one can visualize that the site
c is desirable for lower volume of production. For higher volume production site B is desirable
for a moderate volume of production site A is desirable. In the increasing order of production
volume the switch over from one site to another takes place as per the order below
Site C to site A to site B
Let Q be the volume at which we switch the site C to site A
Total cost of site C Total cost site A
5000000+4000Q 6000000+1500*Q
2500Q 1000000
Q 400 Units
Similarly the switch from site A to site B
Total cost of site A total cost of site B
6000000+1500Q 7000000+500Q
1000Q 1000000
Q 1000 Units
The cutoff production volume for different ranges of production may be obtained by using
similar procedure.
WORK STUDY
o First technique applied for increasing productivity.
o Considered as a valuable tool in increasing productivity.
Definition: Work study is a generic term for the techniques of method study and work
measurement. These techniques are used in the examination of human work in all its
contexts. They lead systematically to the investigation of all the factors which affect the
efficiency and economy at the work place in order to affect improvement.
METHOD STUDY
Method study is the technique of systematic recording and critical examination
of existing and proposed ways of doing work and developing an easier and economical
method.
For example, assume that observed time for an operation is 0.7 mts. The rating of the
Operator is found to be 120.
ALLOWANCES
Various types of allowance are
1. Rest and personal allowance.
2. Process allowance.
3. Contingency allowance.
4. Special allowance.
5. Policy allowance.
CALCULATION OF STANDARD TIME
Standard time or allowed time is the total time in which a job should be completed at
standard performance. It is the sum of normal time (basic time) and allowances. Policy
allowance is not included.
Standard time is worked out in a stop watch time study in the following manner.
PRODUCTION STUDY
Production study is a technique of work measurement to check accuracy of the original
time study. This study is done to find the time delay due to occasional elements. These
elements may occur at irregular intervals. Example: Tool grinding, setting tools etc. There
are chances of missing these elements in the stop watch time study. Production study is
conducted for a longer periodat least for half a day or one shift.
RATIO DELAY STUDY
This study is also known as work sampling or activity sampling. Here the ratio of
the delay time and working time to the total time of an activity is found out. This is done
by random (irregular) observations. This study is applied to
1. Long cycle operations.
2. Activities where time study is not possible.
SYNTHESIS FROM STANDARD DATA
Synthesis is a work measurement technique to work out standard time for a job by
totaling the elemental times already obtained from previous time studies. Many operators
in an industry have several common elements. Example: starting the machine, stopping the
machine etc. Whenever these activities occur, they take the same duration of time. These
elements are called constant elements. Time for some elements vary proportionately with
the speed, feed, and length of cut etc. in machining operation. These elements are known as
variable elements. Time for all these constant elements and variable elements are collected
from the time studies previously made. These are stored in a file. This is called time
standard data bank. Data bank contains data in the form of
1. Tabulated standard time for constant elements.
2. Charts and graphs.
3. Formulae etc.
ANALYTICAL ESTIMATING
Setting the time standards for long and non-repetitive operations by stop watch
method are uneconomical. Analytical estimating technique determines the time values for
such jobs either by using the synthetic data or on the basic of the past experience of the
estimator when no synthetic or standard data is available. In order to produce accurate
results the estimator must have sufficient experience of estimating, motion study, time
study and the use of synthesized time standards.
PREDETERMINED MOTION TIME SYSTEM (PMTS)
Definition: PMTS is a work measurement technique where by times, established
for basic human motions (classified according to the nature of the motion and the
conditions under which it is made) are used to build up the time for a job at a defined level
of performance. Few well-known systems using this concept are
1. M.T.M. : Method Time Measurement.
2. W.F.S. : Work Factor System.
3. M.T.A. : Motion Time Analysis.
4. D.M.T. : Dimensional Motion Times.
5. B.M.T. : Basic Motion Times.
ERGONOMICS
Ergons means work and Nomos means Natural laws. Ergonomics or its
American equivalent Human Engineering may be defined as the scientific study of the
relationship between man and his working environments. Ergonomics implies Fitting the
job to the worker. Ergonomics combines the knowledge of a psychologist, physiologist,
anatomist, engineer, anthropologist and a biometrician.
PROCESS PLANNING
PROCESS PLANNING
Process planning is a detailed specification which lists the operation, tools, and
facilities
Usually accomplished in manufacturing department
Also known as operations planning
Systematic determination of the engineering processes and systems to manufacture
a product competitively and economically
DEFINITION
Process planning can be defined as an act of preparing a detailed processing
documentation for the manufacture of a piece part or assembly
APPROACHES TO PROCESS PLANNING
1. Manual Process planning
2. Computer Aided Process planning (CAPP)
a. Retrieval CAPP system
b. Generative CAPP system
Disadvantages
Very complex
Time consuming
Requires large amount of data
Requires skilled process planner
More possibilities for human error
Increases paper work
Inconsistent process plans results in reduced productivity.
19. List the commonly used methods to reduces the cycle time to a minimum.
i) Reduce/eliminate idle time in the bottleneck activity
ii) Reduce the independent activity time
iii) Reduce the concurrent activity time.
PRODUCTION SYSTEM
Introduction
A Production System is a system whose function is to transform an input into a desired
output by means of a process (the production process) and of resources. The definition of a
production system is thus based on four main elements: the input, the resources, the production
process and the output. Most of the organizations (including non-profit organization) can be
described as production systems.
Facility Planning
4.1 Definition of Facilities Planning
4.2 Disciplines involved in Facilities Planning (FP)
4.3 Applications of Facilities Planning (FP)
4.4 Factors affecting Facility Layout
Time study
It was proposed by Frederick Taylor and later modified to include a performance rating
(PR) adjustment.
Once the method is established, the next objective is to set the standard time for the work.
This aspect of work study is called Time study (or Work measurement).
The main objectives of time study are:
1) To determine the standard time for various operations which helps in fixing wage rates
and incentives.
2) To estimate the cost of product accurately.
3) To predict accurately the duration for a particular work and customer is promised
accordingly.
4) To determine the number of machines an operator can run.
5) To determine the optimum number of men and machine.
6) To provide information for planning and scheduling.
7) To balance the work of all workers working in a group.
8) To compare the work efficiency of different workers/operators.
Work measurement techniques
1. Time study using stop watch.
2. Predetermined motion time system (PMTS).
3. Work sampling.
4. Analytical estimating.
Selection of Worker for Time Study
The worker on which time study should be conducted must
Have necessary skill for the job.
Have sufficient experience with the given method on the job (that is, he should have
crossed the learning stage).
Be an average' worker as regards the speed of working.
Be temperamentally suited to the study (those who can't work in normal fashion when
watched, are not suitable for the study).
Have knowledge about the purpose of study.
Line balancing
Plants having continuous flow process and producing large volume of standardized
components prefer conveyor assembly line. Here the work centres are sequenced in such a way
that at each stage a certain amount of total work is carried out so that at the end of conveyor line,
the final product comes out. This requires careful preplanning to balance the timing between
each work centres so that idle/waiting time is minimized. This process of internal balancing is
called Assembly line balancing.
Line balancing is defined as the procedure for creating work stations and assigning tasks
to them according to a predetermined technological sequence such that the idle time at each work
station is minimized.
Some terminologies used in line balancing:
1. Work station: It is a location on the assembly line where specified work is performed.
2. Cycle time: It is the amount of average time a product spends at one work station
3. Task : The smallest grouping of work that can be assigned to a work station.
4. Task time: Standard time to perform task.
5. Station time: Total standard time at a particular work station.
Flow control
Flow control applies to the control of continuous production as found in oil refineries,
bottling works, cigarette making factories, paper making mills and other mass manufacturing
plants.
(a) Operation time: It amounts the time required to manufacture each part, to make one
subassembly and to execute one assembly. This information is available from the operation
sheet.
(b) Line balancing: the assembly line should be balanced. Each work station should have the
more or less same operating time and the various operations should be sequenced properly.
(c) Routing and scheduling: A combination route and schedule chart showing the fabrication of
parts, subassemblies and final assembly is shown below.
(d) Control of parts subassemblies and Assembly: A supervisory function coupled with an
appropriate information feedback system keeps a check whether the small parts arriving in lots
and big parts coming continuously are available at right time, in proper quantities for making
subassemblies as per scheduled plan.
(e) Dispatching: Dispatching is nothing but issuing orders and instructions to start a particular
work which has already been planned under routing and scheduling.
Functions of Dispatching
(i) Assignment of work to individual man, m/c or work place.
(ii) Release necessary order and production firm.
(iii) Authorize for issue of materials, tools, jigs, fixtures, gauges, dies for various jobs.
(iv) Required materials are authorized to move from stores or from operation to
operation.
(v) Issue m/c loading and schedule chart, route sheet, etc.
(vi) To fix up the responsibilities of guiding and controlling the materials and operation
processes.
(vii) To issue inspection order.
(viii) Issue of time tickets, drawing, and instruction cards.
Dispatch procedure
The various steps of dispatch procedure for each operation are listed below:
(a) Store issue order: Authorise store department to deliver required material.
(b) Tool order: Authorise tool store to release the necessary tools. The tools can be
collected by the tool room attendant.
(c) Job order: Instruct the worker to proceed with operation.
(d) Time tickets: It records the beginning and ending time of the operation and forms the
basis for workers pay.
(e) Inspection order: Notify the inspectors to carry out necessary inspections and report
the quality of the component.
(f) Move order: Authorise the movement of materials and components for one facility to
another for further operation.
In addition, there are certain dispatch aspects such as:
(1) All production information should be available beforehand.
(2) Various order cards and drawing with specification should be ready.
(3) Equipment should be ready for use.
(4) Progress of various orders should be recorded.
(5) All production records should be on Gantt chart.
(a) Centralized Dispatching:
In centralized dispatching system, a central dispatching department orders directly to the
work stations. It maintains a full record of the characteristics and capacity of each equipment and
work load against each m/c.
(b) Decentralized Dispatching:
In decentralized dispatching system, the shop supervisor performs the dispatch function.
He/she decides the sequence of handling different orders.
A centralized dispatching system has the following advantages:
(i) Much of red tape (excessive adherence to official rules) is minimized.
(ii) Shop supervisor knows the best about his shop.
(iii) Communication gap is reduced.
(iv) It is easy to solve day to day problem.
Line of balance (LOB)
LOB is a graphical technique used to find out the state of completion of various processes
at a given time for a product. This technique is economical when the production volume is
limited and applied to the production of aircrafts, missiles, heavy machines, etc.
For drawing the LOB, the following information are required:
Contracted schedule of delivery
Key operations in making the product.
The sequence of key events.
The expected/observed lead time w.r.t. delivery of final product.
Based on above information, a diagram is drawn which compares pictorially the planned verses
actual progress. This is called line of balance (LOB).
2 Marks Questions with Answers
PRODUCTION SCHEDULING
INVENTORY
Introduction
The amount of material, a company has in stock at a specific time is known as inventory or in
terms of money it can be defined as the total capital investment over all the materials stocked in
the company at any specific time. Inventory may be in the form of,
Raw material inventory
In process inventory
Finished goods inventory
Spare parts inventory
Office stationary etc.
Why Inventories?
Inventories are needed because demand and supply cannot be matched for physical and
economic reasons. There are several other reasons for carrying inventories in any organization.
To safe guard against the uncertainties in price fluctuations, supply conditions, demand
conditions, lead times, transport contingencies etc.
To reduce machine idle times by providing enough in-process inventories at appropriate
locations.
To take advantages of quantity discounts, economy of scale in transportation etc.
To decouple operations i.e. to make one operation's supply independent of another's
supply. This helps in minimizing the impact of break downs, shortages etc. on the
performance of the downstream operations. Moreover operations can be scheduled
independent of each other if operations are decoupled.
To reduce the material handling cost of semi-finished products by moving them in large
quantities between operations.
To reduce clerical cost associated with order preparation, order procurement etc.
Inventory Costs
In order to control inventories appropriately, one has to consider all cost elements that are
associated with the inventories. There are four such cost elements, which do affect cost of
inventory.
Unit cost: it is usually the purchase price of the item under consideration. If unit cost is
related with the purchase quantity, it is called as discount price.
Procurement costs: This includes the cost of order preparation, tender placement, cost of
postages, telephone costs, receiving costs, set up cost etc.
Carrying costs: This represents the cost of maintaining inventories in the plant. It
includes the cost of insurance, security, warehouse rent, taxes, interest on capital
engaged, spoilage, breakage etc.
Stockout costs: This represents the cost of loss of demand due to shortage in supplies.
This includes cost of loss of profit, loss of customer, loss of goodwill, penalty etc.
If one year planning horizon is used, the total annual cost of inventory can be expressed as:
Total annual inventory cost = Cost of items + Annual procurement cost + Annual carrying
cost + Stockout cost
Variables in Inventory Models
D = Total annual demand (in units)
Q = Quantity ordered (in units)
Q* = Optimal order quantity (in units)
R = Reorder point (in units)
R* = Optimal reorder point (in units)
L = Lead time
S = Procurement cost (per order)
C = Cost of the individual item (cost per unit)
I = Carrying cost per unit carried (as a percentage of unit cost C)
K = Stockout cost per unit out of stock
P = Production rate or delivery rate
dl = Demand per unit time during lead time
Dl = Total demand during lead time
TC = Total annual inventory costs
TC* = Minimum total annual inventory costs
The total annual cost of the inventory (TC) is given by the following equation in EOQ model.
The graphical representation of the EOQ model is shown in Figure 2 .
ABC manufacturers produces 1, 25,000 oil seals each year to satisfy the requirement of
their client. They order the metal for the bushing in lot of 30,000 units. It cost them $40 to place
the order. The unit cost of bushing is $0.12 and the estimated carrying cost is 25% unit cost. Find
out the economic order quantity? What percentage of increases or decrease in order quantity is
required so that the ordered quantity is Economic order quantity?
Economic Production Quantity (EPQ) Model
In EOQ model supply was instantaneous, which may not be the case in all industrial
applications. If supply of items is gradual to satisfy a continuous demand, then supply line will
be depicted by a slanted line (Figure 3 ). Figure 3 : Economic Production Quantity Model
(EPQ Model)
In this situation, when the order is placed, the supplier begins producing the units and supplies
them continuously. While new units are added to inventory, other units are being used. Thus, if
delivery rate (P) > demand rate (D), the net result will be a net increase in the inventory level.
The slope of replenishment line will thus be (P-D). Similarly the slope of demand line will be (-
D). The average inventory carried per year is
A numeric illustration of the EPQ model is given in
MRP
Introduction
It was discussed in demand forecasting that in the dependent demand situation, if the
demand for an item is known, the demand for other related items can be deduced. For example, if
the demand of an automobile is known, the demand of its sub-assemblies and sub components
can easily be deduced. For dependent demand situations, normal reactive inventory control
systems (i.e. EOQ etc.) are not suitable because they result in high inventory costs and unreliable
delivery schedules. More recently, managers have realized that inventory planning systems (such
as materials requirements planning) are better suited for dependent demand items. MRP is a
simple system of calculating arithmetically the requirements of the input materials at different
points of time based on actual production plan. MRP can also be defined as a planning and
scheduling system to meet time-phased materials requirements for production operations. MRP
always tries to meet the delivery schedule of end products as specified in the master production
schedule.
MRP Objectives
MRP has several objectives, such as:
Reduction in Inventory Cost: By providing the right quantity of material at right time to
meet master production schedule, MRP tries to avoid the cost of excessive inventory.
A simple sketch of an MRP system is shown in figure 1. It can be seen from the figure that an
MRP system has three major input components:
Master Production Schedule (MPS): MPS is designed to meet the market demand (both the
firm orders and forecasted demand) in future in the taken planning horizon. MPS mainly depicts
the detailed delivery schedule of the end products. However, orders for replacement components
can also be included in it to make it more comprehensive.
Bill of Materials (BOM) File: BOM represents the product structure. It encompasses
information about all sub components needed, their quantity, and their sequence of
buildup in the end product. Information about the work centers performing buildup
operations is also included in it.
Inventory Status File: Inventory status file keeps an up-to-date record of each item in
the inventory. Information such as, item identification number, quantity on hand, safety
stock level, quantity already allocated and the procurement lead time of each item is
recorded in this file.
After getting input from these sources, MRP logic processes the available information and gives
information about the following:
Planned Orders Receipts: This is the order quantity of an item that is planned to be
ordered so that it is received at the beginning of the period under consideration to meet
the net requirements of that period. This order has not yet been placed and will be placed
in future.
Planned Order Release: This is the order quantity of an item that is planned to be
ordered in the planned time period for this order that will ensure that the item is received
when needed. Planned order release is determined by offsetting the planned order receipt
by procurement lead time of that item.
Order Rescheduling: This highlight the need of any expediting, de-expediting, and
cancellation of open orders etc. in case of unexpected situations.