Kitchen Expansion 2018
Kitchen Expansion 2018
Kitchen Expansion 2018
SUBSTRUCTURE
1 SETTING OUT
Item(1) Lump Item 200
ITEM 2 6861.50
SUPERSTRUCTURE
6 Masonry works
125mm hollow block 55 m2 65 3575
8 Reinforcement works
R12 ɸ rod for column & lintel 210 Kg 4 840
R6 ɸ rod stirrups 26 Kg 4 104
Binding wire 0.5 Roll 50 25
969
9 Formwork
Formwork for slab, columns, lintel 18 m2 120 2160
10 Roofing
Roof structure & Roofing sheets 57 m2 90 5130
ITEM 3 5155
11 Finishes
Plastering & dressing(1:5) 110 m2 18 1980
Tiling( floors & walls) 70 m2 55 3850
2
Ceiling wrks (T & G) 65 m 35 2275
ITEM 4 16025
13 Electrical wrks
Materials(excludes A/C) Lump Item 3000 3000
Labour Lump Item 500 500
3500
14 Plumbing wrks
Materials Lump Item 2000 2000
Labour Lump Item 600 600
2600
ITEM 5 6100
CONTIGENCY(3%) 1030.245