PAS 8810 2016 Tunnel Design Code of Practice
PAS 8810 2016 Tunnel Design Code of Practice
Publication history
First published April 2016
PAS 8810:2016
Contents
Foreword ..................................................................................................... iii
Introduction ................................................................................................. v
1 Scope ......................................................................................................... 1
2 Normative references............................................................................... 2
4 Functional requirements.......................................................................... 9
Annexes
Annex A (normative) Design management ............................................... 73
Annex B (informative) Closed-form solutions for static analysis of tunnel
lining in soft ground.................................................................................... 77
Annex C (informative) Convergence-confinement method (CCM) in
segment lining design.................................................................................. 78
Annex D (informative) Six-stage Gate process........................................... 80
Bibliography................................................................................................. 81
List of figures
Figure 1 – Typical fire curves for tunnel design.......................................... 12
Figure 2 – Typical geometry of precast concrete segment lining.............. 45
Figure 3 – Calculation of taper.................................................................... 47
Figure 4 – Schematic diagram of strain and stress block for reinforced
concrete and fibre reinforced section for the development of the M-N
envelope....................................................................................................... 49
Figure 5 – Joint contact width and stress distribution change with joint
rotation for flat joint................................................................................... 52
Figure 6 – Joint contact width and stress distribution change with joint
rotation for convex-convex joint................................................................. 52
Figure 7 – Simplification of non-uniform load with eccentricity for
bursting check on flat joint ........................................................................ 53
Figure 8 – Edge spalling schematic............................................................. 54
Figure 9 – Example of EPDM Gaskets gap pressure curve......................... 54
Figure 10 – Example of a 3D model of a segmental lining with contact
elements used at the joints......................................................................... 60
Figure 11 – State of tensile stress of radial and circumferential joints
of a segmental lining................................................................................... 61
Figure 12 – Analysis methods for design of tunnels in soft ground ........ 62
Figure 13 – Typical continuum model......................................................... 63
Figure 14 – Bedded beam spring model..................................................... 64
Figure 15 – Coefficient of earth pressure change prior (i.e. at rest) and
following tunnel construction (variation of horizontal stresses in kPa)... 66
Figure 16 – Typical FE model of a segmentally lined tunnel..................... 67
Figure 17 – Example of a bedded shell model for an opening in a
segmental lining with internal temporary support................................... 69
Figure 18 – Example of 3D FE model for junction...................................... 70
Figure C.1 – Convergence-confinement method – Longitudinal
displacement profile (LDP) and ground response curve (GRC) with support
characteristic curve....................................................................................... 78
Figure C.2 – Stress reduction method, conceptual sketch ........................ 79
List of tables
Table 1 – Typical elements differentiated from the type of tunnel and
associated design issues .............................................................................. 9
Table 2 – Tunnel construction methodology and associated typical lining
types in soft ground tunnelling ................................................................. 15
Table 3 – Recommendations for durability against chemical attack for
the external and internal surface of precast segmental linings where
protective lining is not necessary ............................................................... 27
Table 4 – Limiting values of composition and properties for concrete
where a DC-class is specified....................................................................... 28
Table 5 – Additional protective measures (APMs) ..................................... 29
Table 6 – Recommendations for circumstances in which internal lining is
necessary for precast concrete segmental linings for tunnels and shafts
used for water and sewer services, storage and transportation .............. 29
Table 7 – Typical design situations for precast concrete segmental
tunnel lining ................................................................................................ 34
Table 8 – Typical actions for tunnels in transient design situations ......... 36
Table 9 – Typical actions for tunnels in persistent design situations ....... 38
Table 10 – Typical STR/GEO failure modes of tunnel linings .................... 40
Table 11 – ULS Partial factors on actions ................................................... 41
Table 12 – ULS Partial factors for materials ............................................... 42
Table A.1 – Suggested categories for tunnel lining design checking ...... 74
Table B.1 – Closed-form solutions for static analysis of tunnel lining
in soft ground .............................................................................................. 77
Table D.1 – Suggested six-stage Gate process for tunnel lining design ... 80
Foreword
This PAS was sponsored by High Speed Two (HS2) Limited and the British Tunnelling
Society (BTS). Its development was facilitated by BSI Standards Limited and it was
published under licence from The British Standards Institution. It came into effect on
30 April 2016.
Acknowledgement is given to Hyuk-Il Jung, Chris The British Standards Institution retains ownership
Peaston, Bryan Marsh, Michael Devriendt, Michele and copyright of this PAS. BSI Standards Limited as the
Mangione, Eden Almog and Rob Harding of Arup as publisher of this PAS reserves the right to withdraw or
the technical authors, and the following organizations amend this PAS on receipt of authoritative advice that
that were involved in the development of this PAS as it is appropriate to do so. This PAS will be reviewed at
members of the steering group: intervals not exceeding two years, and any amendments
• Arup arising from the review will be published as an amended
PAS and publicized in Update Standards.
• Atkins
• Balfour Beatty This PAS is not to be regarded as a British Standard. It
• British Tunnelling Society (BTS) will be withdrawn upon publication of its content in, or
• CH2M Hill as, a British Standard.
• Costain
The PAS process enables a code of practice to be
• Crossrail rapidly developed in order to fulfil an immediate
• Donaldson Associates need in industry. A PAS can be considered for further
• Dragados development as a British Standard, or constitute part
of the UK input into the development of a European or
• Health and Safety Executive (HSE)
International Standard.
• Highways England
• High Speed Two (HS2) Limited
• INECO Relationship with other publications
• London Underground This PAS is expected to be used in conjunction with
• Mott MacDonald BS 6164, which makes recommendations for and gives
• Network Rail guidance on health and safety practices in tunnel
design and construction.
• OTB Concrete
• Skanska
• Thames Tideway Use of this document
• University College London, Department of Civil It has been assumed in the preparation of this PAS
Engineering that the execution of its provisions will be entrusted
• UnPS to appropriately qualified and experienced people, for
• VINCI whose use it has been produced.
• Co-opted members
Copyright is claimed on Figure 12. Copyright holder is
The British Tunnelling Society, 5 Churchill Place, Canary
Acknowledgement is also given to the members of
Wharf, London, E14 5HU.
a wider review panel who were consulted in the
development of this PAS.
Presentational conventions
The provisions of this PAS are presented in roman
(i.e. upright) type. Its recommendations are expressed
in sentences in which the principal auxiliary verb
is “should”. The word “may” is used to express
permissibility and the word “can” is used to express
possibility, e.g. a consequence of an action or an event.
Commentary, explanation and general informative Particular attention is drawn to the following specific
material is presented in italic type, and does not regulations:
constitute a normative element. • Construction (Design and Management) Regulations
2015 [1];
Spelling conforms to The Shorter Oxford English
• Construction Products Regulations 2013 [2]; and
Dictionary. If a word has more than one spelling,
the first spelling in the dictionary is used (e.g. • Health and Safety at Work etc. Act 1974 [3].
“organization” rather than “organisation”).
Introduction
HS2 and BSI engaged with a number of construction As tunnel construction technology is fast changing,
industry stakeholders to identify areas in which it some of the recommendations set out in this PAS
was felt that the industry could benefit from further might not be fully applicable to a newly-introduced
standardization. technology that does not exist at the time of this
PAS publication.
PAS 8810 was developed specifically to cover the design
of segmental tunnel linings, which was identified as an This PAS is not intended to limit the design flexibility
area in which additional standardization was required. or the adoption of new technology, and, as such, is
Segmental tunnel linings are currently designed with not intended to be used as a barrier that prevents the
reference to a large number of published general building adoption of innovative designs.
standards and industry documents, together with several
Eurocodes. However, there is no codified or standardized A number of other areas were identified as benefitting
design document that applies specifically to precast from standardization. A wider programme of work is
concrete segmental tunnel linings, and the volume of underway to develop a further three PASs:
relevant standards, guidance and documentation has • PAS 8811, Temporary works – Client procedures
led to both conflicting guidance and requirements, and – Code of practice (in preparation), which gives
the misinterpretation and misapplication of standards. recommendations for UK infrastructure client
PAS 8810 therefore aims to bring together existing procedures with respect to temporary works
standards and industry documents into a single, usable construction projects, from planning through
standardization document while simultaneously reducing to removal.
unnecessary administration and delay by streamlining,
• PAS 8812, Temporary works – Application of European
clarifying and standardizing the design process for
Standards in design – Guide, which gives guidance on
segmental lining design.
the application of European Standards in the design
of temporary works in the UK for practitioners in
Clauses 4 to 8 cover the more general aspects of tunnel
the fields of structural and geotechnical temporary
design and do not restrict the designer to a single
works design.
construction methodology at the conceptual design
stage, as a designer would not limit their study only to • PAS 8820, Construction materials – Alkali-activated
segmental tunnel lining design. Clauses 9 to 12 provide cementitious material and concrete – Specification,
specific, technical information on precast concrete which specifies requirements for alkali-activated
lining elements for segmental tunnel linings. cementitious binders for suppliers of alkali-activated
binders, ready mixed concrete, engineers and
At the time of publication, the intention is to architects, contractors, asset owners and end users.
standardize further areas of tunnel lining design in the
near future including sprayed concrete linings and cast-
in-situ linings.
1 Scope
This PAS makes recommendations for the design of This PAS covers:
concrete segmental tunnel linings. It covers design 1) functional requirements;
considerations from project inception through to the
2) conceptual design;
end of the service life of the tunnel. At the early stage
of the design (e.g. conceptual design stage), the study 3) characterization of ground;
of the options for the selection of the tunnel lining 4) materials design and specification;
is not limited to concrete segmental tunnel linings. 5) material characterization and testing;
Thus Clauses 4 to 8 in the PAS are applicable to tunnels
6) limit state design;
with all types of linings. Clauses 9 to 12 give specific
recommendations on the design of concrete segmental 7) concrete segmental lining design;
tunnel linings. 8) concrete segment lining modelling;
9) instrumentation and monitoring; and
This PAS is for use by design engineers (usually directly
10) design management.
employed by the client but this could sometimes be the
contractor’s designer, for example, in a design and build This PAS does not cover:
project) and clients (usually the owner of the tunnel
a) sprayed concrete lined tunnels;
who is responsible for the design and construction of
concrete tunnel linings) and contractors. b) cast-in-situ concrete lined tunnels;
c) any tunnel lining using material other than
The PAS sets out detailed design recommendations by concrete, such as spheroidal graphite iron or steel;
referencing existing national standards (BS, BS EN) or d) cut and cover tunnels;
internationally-recognized industry standards. Technical
e) drill and blast excavations;
requirements from existing standards are referenced,
rather than repeated. Specific design recommendations f) hard rock tunnelling;
are included only for the design items that are not g) pipe jacking; and
available from existing standards. h) project planning and management.
NOTE 1 Recommendations for health and safety
practices in tunnel construction are given in BS 6164.
NOTE 2 Requirements for handling ground support
elements are given in BS EN 16191.
2 Normative references
BS 6164, Code of practice for health and safety in BS EN 14651, Test method for metallic fibre concrete
tunnelling in the construction industry – Measuring the flexural tensile strength (limit of
proportionality (LOP), residual)
BS 6744, Stainless steel bars for the reinforcement of
and use in concrete – Requirements and test methods BS EN 14889-1, Fibres for concrete – Part 1: Steel fibres –
Definitions, specifications and conformity
BS 7979, Specification for limestone fines for use with
Portland cement BS EN 14889-2, Fibres for concrete – Part 2: Polymer
fibres – Definitions, specifications and conformity
BS 8500-1, Concrete – Complementary British Standard
to BS EN 206 – Part 1: Method of specifying and BS EN 15167-1, Ground granulated blastfurnace slag for
guidance for the specifier use in concrete, mortar and grout – Part 1: Definitions,
specifications and conformity criteria
BS 8500-2, Concrete – Complementary British Standard
to BS EN 206 – Specification for constituent materials BS EN 16191, Tunnelling machinery – Safety requirements
and concrete
BS EN ISO 14688-1, Geotechnical investigation and
BS EN 206:2013, Concrete – Specification, performance, testing – Part 1: Identification and classification of soil –
production and conformity Identification and description
BS EN 450-1, Fly ash for concrete – Part 1: Definition, BS EN ISO 14688-2, Geotechnical investigation and
specifications and conformity criteria testing – Part 2: Identification and classification of soil –
Principles for a classification
BS EN 934-2, Admixtures for concrete, mortar and
grout – Part 2: Concrete admixtures – Definitions, BS EN ISO 14689-1, Geotechnical investigation and
requirements, conformity, marking and labelling testing – Part 1: Identification and classification of rock
– Identification and description
BS EN 1008, Mixing water for concrete – Specification
for sampling, testing and assessing the suitability of BS ISO 13270, Steel fibres for concrete – Definitions and
water, including water recovered from processes in the specifications
concrete industry, as mixing water for concrete
NA to BS EN 1992-1-1, UK National Annex to Eurocode
BS EN 1990, Eurocode – Basis of structural design 2: Design of concrete structures – Part 1-1: General rules
and rules for buildings
BS EN 1992-1-1, Eurocode 2: Design of concrete
structures – Part 1-1: General rules and rules for buildings PAS 1192-2, Specification for information management
for the capital/delivery phase of construction projects
BS EN 1997-1, Eurocode 7: Geotechnical design – Part 1: using Building Information Modelling
General rules
concrete specified by reference to a product name for design situation involving exceptional conditions of
a particular concrete offered by a particular producer the structure or its exposure, including fire, explosion,
to meet specific claimed performance impact or local failure
4 Functional requirements
4.1 General 4.1.3 The designer should assess the typical elements
set out in Table 1 and, where relevant, document their
4.1.1 The designer should design and size the tunnel impact on the tunnel’s sizing and lining design.
lining to meet the functional requirements of the
specific project.
Table 1 – Typical elements differentiated from the type of tunnel and associated design issues
Tunnel types Elements differentiated from the type of tunnel Design issues
Transportation • Rail and track form (for rail tunnel), • Sizing, operational train or vehicle load
tunnels pavement form (for road tunnel) to lining
Water/sewerage • Water head loss – surface roughness • Joint design, secondary lining design (sizing)
tunnels
• Internal pressure maintenance • Joint design, water tightness design –
leakage and external water pressures
4.2 Health and safety requirements 4.3.2.3 As a minimum, the client should include in their
operational requirements document, the project’s:
4.2.1 The client should provide the designer with the
a) operational requirements (see 4.3.2.1 and 4.3.2.2);
health and safety requirements for the project. Such
requirements should satisfy the safety requirements during b) security requirements (see 4.3.3);
construction, operation and maintenance of the tunnels. c) durability requirements (see 4.3.4);
NOTE 1 Attention is drawn to the Construction (Design d) repair and maintenance requirements (see 4.3.5);
and Management) Regulations 2015 (CDM) [1] which e) fire safety requirements (see 4.3.6);
impose statutory duties on designers to consider health
f) water tightness requirements;
and safety.
g) contractual requirements (not covered in this
NOTE 2 The designer of the tunnel lining may be
PAS); and
different from the “Principal Designer” and the “Principal
Contractor” defined in the CDM Regulations 2015. h) legal requirements (not covered in this PAS).
NOTE The client might also provide information
4.2.2 The designer should design and size the tunnels to relating to project-specific tolerances, deformation
fulfil the client’s health and safety requirements. limits, and design-checking specifications.
4.2.3 The designer should apply health and safety 4.3.3 Security requirements
practices relating to tunnel design and construction in
4.3.3.1 The client should identify whether the tunnel
accordance with BS 6164.
structure forms part of the UK’s critical national
NOTE BS 6164:2011, 6.1 highlights the importance infrastructure and inform the designer of their findings.
of the integral nature of design and construction for
NOTE Specific security-related design requirements can
tunnelling projects. Recommendations for the design of
be applied either by the client or by the government,
tunnel lining with consideration of Health and Safety
particularly for major infrastructure assets which might
requirements are given in BS 6164:2011, Clause 8.
form part of the UK’s critical national infrastructure.
1)
www.cpni.gov.uk
4.3.4.2 The designer should design the tunnel lining to structural redesign in the later stages of design. This
meet the target design working life specified by the client. can introduce significant cost and programme impacts
to the design and construction stages. For example, for
4.3.4.3 Tunnels need to be designed, where practicable, a pressurized water tunnel, the client might require
to minimize the requirement for maintenance regular inspection of the tunnel by draining the tunnel,
interventions other than visual inspections. To support which means a critical load case for the tunnel lining
this requirement, the designer should provide a structural design might occur when the tunnel is
statement of potential degradation modes identified drained for its maintenance period, rather than during
during the design of the tunnel lining and a schedule normal operating conditions.
of the expected interventions during the design
working life. 4.3.6 Fire safety requirements
NOTE To prepare the schedule of the expected NOTE 1 The ITA document Guidelines for structural
interventions required under 4.3.4.3, the designer fire resistance for road tunnels [4] is focused on road
needs to consider all components, including structural tunnels which are exposed to severe hydrocarbon fire
elements, gaskets and sealing materials and also the scenarios induced by vehicles’ fuel. Further fire safety
ability of all materials to resist degradation by ground, requirements for road tunnels can be found from World
groundwater and the environment throughout the Road Association (PIARC) Road Tunnels Manual [5].
design working life.
NOTE 2 Railway tunnels (freight, passenger or
other) can also be exposed to severe fire events such
4.3.4.4 The designer should design the durability of
as the Channel Tunnel fires 1996, 2008 and 2015.
tunnel lining in accordance with 7.9; and the BTS,
The fire resistance of railway tunnels captured by
Tunnel Lining Design Guide, Section 4 [NR1].
the interoperability regulations are described in
COMMISSION REGULATION (EU) No 1303/2014 of
4.3.4.5 The design needs to cover the durability of
18 November 2014 [6], Technical Specification for
all materials used in the tunnel lining as permanent
Interoperability relating to ‘safety in railway tunnels’ of
components. Where temporary components are left in
the rail system of the European Union.
place, the designer should assess and document their
impact on the durability of the permanent components. NOTE 3 The extent of the fire damage and the
repair required has an impact on the finance of the
NOTE Permanent components include concrete,
infrastructure due to the combination of costs for
reinforcement and waterproofing systems and all
repairing the tunnel and loss of revenue resulting from
exposure conditions, both internal and external, and on
extended closure of the tunnel.
both primary and secondary linings.
4.3.5.2 The designer should identify repair and NOTE 3 The fire curve defines the design fire event for
maintenance requirements for the tunnel (including the lining design. Further information can be found
internal operational components such as rail, in EFNARC Specification and guidelines for testing of
pavement, and cable) with reference to the client’s passive fire protection for concrete tunnels linings [7].
project-specific repair and maintenance regime. NOTE 4 The selection of the fire curve is dependent on
the tunnel use and local conditions. Typical examples
4.3.5.3 The designer should provide adequate space are included in Figure 1.
and structural capacity in the tunnel lining design, NOTE 5 The tunnel lining may be exposed to a fire
so as to fulfil the identified repair and maintenance during construction. The designer is expected to verify
requirements. the suitability of the lining for the construction fire case.
NOTE Failing to identify repair and maintenance
requirements can lead to changes in the tunnel size and
4.3.6.2 The client should set out the criteria that the 4.3.6.4 The designer should design the tunnel lining in
designer should follow for the structural fire design of accordance with the fire and life safety requirements
the tunnel lining under the selected fire load and curve for the project and assess and document the need for
(see 4.3.6.1). additional active fire-protection measures, including a
fire sprinkler system, cross passages, refuges, ventilation
4.3.6.3 The designer should assess and document the and emergency escape.
properties and performance of the concrete using the
appropriate test procedure.
NOTE 1 The required fire resistance can be obtained by 4.4 Requirements relating to external
the addition of monofilament synthetic fibres to the impacts
concrete mix.
NOTE It is important that the tunnel lining is designed
NOTE 2 There have been a significant number of to limit any external impacts on the environment
tests (e.g. CTRL 2003) undertaken on concrete mixes around the tunnel.
containing monofilament polypropylene fibres with a
diameter of <32 microns. These tests have demonstrated 4.4.1 The designer should carry out a detailed review
acceptable control of explosive spalling where a suitable of the external impacts on the environment around the
quantity of monofilament polypropylene fibres has tunnel that can affect the sizing of the tunnel, selection
been added to the concrete mix. of tunnel lining type, tunnel construction methodology,
NOTE 3 The quantity of synthetic fibres per cubic construction sequence and/or dimensions of staged
metre of concrete can be verified by fire tests as it is a excavation details.
function of the concrete mix. NOTE Examples of the external impacts on the
NOTE 4 An appropriate test method needs to account environment around the tunnel include impact to
for the expected in-service loading on the lining as well existing structures/residences and infrastructures,
as the relevant thermal stresses induced by the design changes to groundwater level and groundwater
fire curve. pollution.
NOTE 5 The required fire resistance can also be
obtained by the application of protective layers.
5 Conceptual design
5.1.2 The designer should carry out the conceptual 5.1.6 The designer should assess and, where relevant,
design of the tunnel lining upon the request from the document the following factors to determine the
client in accordance with the accepted schedule of optimal alignment for the project requirements
deliverables (see A.5). and constraints:
NOTE It is advisable that this takes place at the Gate 2 a) the geology or geological features;
stage of the project shown in Annex D or an equivalent b) the length of tunnel, necessity of intermediate
stage where a modified process is adopted. shafts and access locations;
c) horizontal and vertical constraints including;
5.1.3 The designer should identify options for the
tunnel construction methodology and document these 1) availability and desirability of sites for portals,
in the conceptual design output. shafts and stations;
2) operational constraints such as gradient and
5.1.4 The designer and the client should discuss and curvature minimum radii;
select a single option from the options identified in 3) potential obstructions such as existing piles,
5.1.3, and the option selected should be agreed in tunnels, sewers, services and utilities and
writing between the designer and the client in order to wells; and
proceed to the next design stage.
4) connections to existing infrastructure
NOTE 1 The client can accept multiple options when
d) existing foundations and buildings including listed
further study is considered necessary. In this case, the
buildings and heritages; and
introduction of an intermediate design stage(s) might
be required for the selection of a single option. e) the legal, environmental, social and political impact.
NOTE 2 It is advisable that the client and designer
5.1.7 The designer should undertake a sufficient level
document the reasons for discarding an option to avoid
of design detail at the conceptual design stage to allow
repeating the same option study in the next stage design.
a robust project cost and programme to be determined.
5.1.5 The designer should carry out conceptual design NOTE 1 The project cost and programme are
with consideration given to the following key elements: determined by either the client or the contractor.
a) space-proofing of the tunnel to meet the client’s NOTE 2 Target tolerances can be set by the client, the
functional requirements; planning process or funding requirements.
b) review of the tunnel construction methodology and NOTE 3 At the conceptual design stage, it is not
type of lining structure with consideration given advisable to carry out a large amount of detailed
to interactions between multiple drifts, adjacent structural designs. There might be a project-specific
excavations, geotechnical and hydrogeological critical design element that requires more design effort
conditions (including hazardous substances such as to demonstrate an option’s feasibility. However, it is
gases), third party and environmental impact; not usually possible to carry out a detailed review due
to the lack of information at the conceptual design
c) estimation of the tunnel lining structural types and
stage, such as ground strength parameters and loading
thickness with consideration given to concrete grade
conditions from buildings. In this scenario, the designer
and reinforcement type (bar, steel or steel fibres);
can make a feasibility conclusion based on a reasonably
d) feasibility study of the tunnel lining’s structural conservative assumption, but assumptions need to be
integrity under the expected critical loading registered in the risk register document.
conditions (e.g. under high internal pressure for
water tunnel);
Table 2 – Tunnel construction methodology and associated typical lining types in soft ground
tunnelling
SGI
SGI or steel
NOTE 1 Only precast concrete segment lining design is covered in this PAS.
NOTE 2 This PAS uses the terms “TBM” and “mined” in place of ‘mechanized’ and “conventional” respectively.
While “mechanized” and “conventional” are widely used and internationally-recognized terms in the
tunnelling industry, this PAS elects to use “TBM” and “mined” which are considered to be more appropriate,
given the scope of the PAS.
NOTE 3 TBM tunnelling is one of a number of methods of mechanized tunnelling (for the definition of
mechanized tunnelling, see the ITA’s website (https://www.ita-aites.org/en/) or BS 6164:2011, 7.1). The term
“TBM” is used throughout this PAS to denote that the design of the segment lining is directly linked to the
TBM rather than other mechanized tunnelling methods.
NOTE 4 Mined tunnelling is one of a number of methods of conventional tunnelling (for the definition of
conventional tunnelling, see ITA Working Group 19 publication “General Report on Conventional Tunnelling
Method” or BS 6164:2011, 7.1). As the scope of this PAS is limited to tunnelling in soft ground, the specific term
“mined” is considered to be more appropriate than the use of the term “conventional”.
A)
Not a common type under the specified construction method.
B)
Limited to small diameter tunnels only. Design details not covered in this PAS.
5.2 Selection of tunnel construction 5.2.1 The designer’s selection of the tunnel construction
methodology methodology should conform to BTS, Specification for
Tunnelling, Section 301 [NR2].
NOTE Selection of tunnel construction methodology in
soft ground conditions has a direct link to the selection 5.2.2 The designer should take account of the
of tunnel lining types. Table 2 provides the general functional requirements of any secondary lining,
relationship between the tunnel construction methods where required.
and the types of lining structure.
5.2.3 The designer should select the junction b) space requirements for safe construction and
construction method to conform to BTS Specification maintenance;
for Tunnelling, Section 311 [NR2] with consideration c) construction tolerance based on the assumed
given to the: tunnel construction methodology;
a) main tunnel construction methodology and d) survey tolerance;
lining type;
e) end throw and centre throw when a curved tunnel
b) branch tunnel construction and lining type; is constructed using rigid straight sections of lining;
c) available access space for construction plant and f) long-term deformation of the tunnel lining
tunnelling operations; (ovalization – see Note to 5.3.2); and
d) escape and refuge during construction; g) any project-specific space requirements.
e) ground and groundwater conditions at the junction; NOTE 1 BTS, Tunnel Lining Design Guide [NR1], Figure
f) lining break-out method from the main tunnel; and 2.1 provides major spatial considerations for tunnel
g) water tightness at the junctions. linings for rail, road and utility tunnels.
NOTE 1 Junctions such as sumps, niches, cross passages NOTE 2 The construction tolerance of a tunnel can be
and intersections require breaking out of the lining affected by various independent elements. For example
which is considered to be a high-risk activity. in TBM tunnelling, the TBM’s driving tolerance links to
the lining ring’s positional tolerance, and the segment’s
NOTE 2 The junction construction method can differ
erection tolerance can be independent from the TBM’s
from the main tunnel’s construction methodology, for
driving tolerance.
example, a main tunnel constructed using a TBM with
precast concrete segment lining, and a cross passage
5.3.2 Where no project-specific tolerance for space
constructed using a mining technique mechanically
proofing is specified by the client, the designer should
performed by means of picks or teeth.
determine the space-proofing tolerances in accordance
with BTS, Specification for Tunnelling, Section 328 [NR2].
5.3.3 Where there are no deformation limits specified NOTE 4 The feasibility options report can save time and
by the client, the designer should determine the costs when something changes in the next design stage.
deformation limit in accordance with BTS, Tunnel The designer and/or client can go back to the feasibility
Lining Design Guide, Section 5.8.4 [NR1]. options report and find out why one option had been
dismissed, minimising the risk of repetition.
5.3.4 The designer should discuss and agree in writing NOTE 5 It is advisable that the feasibility options report
with the client the overall size of the tunnel, having is reviewed and signed off by the client during the
considered all factors listed in 5.3.1. conceptual design stage.
NOTE The sizing of the tunnel section is one of the most NOTE 6 Some clients have a combined documentation
critical design input parameters that directly affects the process in which the feasibility options report forms
project’s construction cost and programme, e.g. tunnel part of other documents, such as the approval in
size influences lining thickness, TBM size, excavation principle (AIP).
volume and ground movement/settlement, ventilation
and aerodynamics/hydraulics. Tunnel size determined
using unrealistic assumptions and/or uncertain space 5.5 Approval In Principle (AIP)
requirement information is considered to be a critical
project risk which could cause significant impact to the 5.5.1 The necessity of an AIP document should be
project’s design programme and cost. The consequences agreed in writing between the client and the designer
of changing the tunnel size at a subsequent stage in the at the beginning of conceptual design stage (see A.5.1
project increase as the project progresses. It is important and A.5.3).
to fix the size of the tunnel at the concept stage to
minimize programme delay and cost risk. 5.5.2 Where an AIP is deemed necessary, the designer
should produce an AIP for the selected tunnel options
that provides the design concept, basis, criteria and
5.4 Feasibility options report assumptions to be used for the detailed design of the
tunnel lining. The AIP should include:
5.4.1 The necessity of a feasibility options report should
a) tunnel lining structural design logic and procedure;
be discussed and agreed between the client and the
designer at the beginning of conceptual design stage b) design assumptions;
(see A.5.1 and A.5.3). c) ground model to be used (this might be preliminary
depending on the status of the site investigation
5.4.2 Where a feasibility options report is required, the and testing information available);
designer should compile a feasibility options report d) tunnel lining structural analysis methods to be used;
that includes the options development background and
e) design code/standard to be used for the design;
associated decision-making history in the tunnel lining
design, and reflects the project requirements. f) load combinations to be used;
NOTE 1 The feasibility options report for tunnel lining g) section profile of the tunnel;
design can be produced as part of the overall project h) tunnel alignment; and
options report, which provides information on elements i) lining materials, grade and type, including
such as the alignment options and stations layout reinforcements.
options reports.
NOTE The term concept design statement (CDS) is
NOTE 2 It is advisable to include the following subjects sometimes used instead of AIP. The purpose and
in the feasibility options report: contents of CDS are the same as the AIP.
• expected tunnel excavation methods, e.g. mined
or TBM; 5.5.3 The AIP should be reviewed and approved in
• suggested tunnel lining types, e.g. SCL, cast-in-situ or writing by the client.
precast concrete segment;
5.5.4 The designer should use the AIP as a basis of
• conceptual conclusion about meeting the ultimate design in the detailed design stage of the tunnel lining.
and serviceability limit states under critical load
NOTE The AIP can be used as part of the information to
conditions of the project;
assist the transfer of design information from one stage
• feasibility of construction methods; and to the other (or from one designer to the other at the
• any project-specific challenges that affect the same design stage). Information on managing the risk
conceptual decisions of the tunnel lining design. associated with the transfer of information between
NOTE 3 It is advisable to use a decision tree or flow designers is given in BTS, Joint Code of Practice for Risk
diagram in the feasibility options report for the Management of Tunnel Works in the UK [8].
development of a preferred option.
6 Characterization of ground
6.3.6 Ground stiffness 6.4.2.2 The designer should base the design of the
In-situ ground investigations and laboratory testing tunnel lining on the GIR.
should be carried out to measure ground stiffness
either directly or indirectly. 6.4.3 Geotechnical design report (GDR)
NOTE For both direct and indirect methods, the 6.4.3.1 A GDR should be produced and provided to the
measured stiffness can be influenced by the ground client by the designer. The GDR should include:
disturbance that has occurred prior to testing. For indirect a) the assumptions, data, methods of calculation
measures it is important to understand the basis of the and results of the verification of safety and
correlation being used and to check that it is appropriate serviceability;
for the ground strain level, ground stress and direction b) a description of the site and surroundings;
of loading likely to be experienced when forming the
c) a description of the ground conditions and ground-
tunnel. The testing can also be designed to inform
borne risks;
strength and stiffness calibration for constitutive models.
6.6.2 Characteristic value 6.6.2.5 Where statistical methods are employed in the
NOTE 1 The zone of ground governing the behaviour selection of characteristic values for ground properties,
of a tunnel structure at a limit state is much larger than the designer should select a method that:
a test sample or the zone of ground affected in an a) differentiates between local and regional
in-situ test. Consequently the value of the governing sampling; and
parameter often requires careful consideration of a b) accommodates the use of experience of comparable
range of values covering a large surface or volume of ground properties.
the ground.
NOTE For instance, statistical studies might have
NOTE 2 Geotechnical test results can exhibit already been carried out to consider the variability of a
considerable scatter compared with the manufactured material such as London clay that could be relevant to a
materials. This is caused by a number of factors particular tunnel project.
including the ground macro- and micro-fabric and
disturbance of the ground in sampling or carrying out 6.6.2.6 Where statistical methods are used, the designer
the in-situ ground investigations. should derive the characteristic values such that the
NOTE 3 Examples of selecting characteristic ground calculated probability of a worse value governing the
are provided in Simpson and Driscoll, Eurocode 7 – A occurrence of the limit state under consideration is not
commentary [18]. greater than 5%.
6.6.2.1 The designer should select the ground and 6.6.2.7 When undertaking a back analysis of observed
groundwater parameters in accordance with BS EN behaviour, the designer should initially use best
1997-1:2004+A1:2013, 3.3. estimate, rather than characteristic parameters, to back
NOTE BS EN 1997-1:2004+A1:2013, 2.4.5.2 provides calculate observed behaviour.
the principles for selecting characteristic values of
geotechnical parameters for use in design. 6.6.3 Observational methods
The designer should determine alternative ground and
6.6.2.2 The designer should select characteristic values groundwater parameters from characteristic ones if an
for geotechnical parameters based on results and observational approach to design is adopted. Where an
derived values from laboratory tests and in-situ ground observational approach is adopted, the designer should
investigations (see 6.3) conform to the principles set out in CIRIA 185 [NR3].
NOTE 1 The formation of tunnels using sprayed
6.6.2.3 The designer should select characteristic values
concrete lining methods is sometimes carried out in an
of a geotechnical parameter as a cautious estimate of
observational manner. While the sprayed concrete lined
the value affecting the occurrence of the limit state.
tunnel support system might be fully designed to cater
for a range of ground conditions, the use of a range of
6.6.2.4 With respect to the macro structure of the
toolbox measures can be introduced based on observed
ground, the designer should consider scale effects when
behaviour. Under such circumstances, the design of the
selecting parameters for tunnel lining design.
tunnel lining can accommodate parameters other than
NOTE 1 Examples of the macro structure of the ground characteristic parameters, provided there is a robust
are jointing, lamination and fissuring. system and toolbox measures in place to introduce
NOTE 2 These might not be identified from laboratory mitigations in a rapid manner to avoid displacements of
or in-situ ground investigations and might only be the ground and lining exceeding pre-defined tolerable
properly appraised by acquiring sufficiently high-quality limits. BS EN 1997-1:2004+A1:2013, 2.7 identifies the
samples and carrying out appropriate geotechnical precautions that need to be in place if executing works
logging of these. using the observational method.
NOTE 2 These methods are not commonly used in
combination with precast tunnel lining segments.
7.2 Cements and combinations 7.3.4.1 The use of silica fume as a type II addition
should conform to BS EN 206:2013, 5.2.5.2.3.
NOTE 1 A list of cement and combination types is given
NOTE Fly ash, ground granulated blastfurnace slag and
in BS 8500-1:2015, Table A.6.
limestone fines can be taken fully into account in the
NOTE 2 Not all the cements or all the combinations concrete composition in respect of cement content and
in BS 8500-1:2015, Table A.6 are suitable for use in water-to-cement ratio. See BS 8500-2: 2015, 4.4.
tunnel linings in all exposure conditions. Cements or
combination types other than those in BS 8500-1:2015,
Table A.6 might be suitable for use in tunnel linings in 7.4 Aggregates
particular exposure conditions.
7.4.1 Aggregates should conform to BS EN 12620 and
When selecting cement or combination type, the BS 8500-2:2015, 4.3.
designer should review durability recommendations NOTE Guidance on the use of BS EN 12620 is given in
and select the most appropriate cement or combination BS PD 6682-1.
type for the project (see 7.9).
7.4.2 Lightweight aggregates should conform to
BS EN 13055-1 and BS 8500-2:2015, 4.3.
NOTE Guidance on the use of BS EN 13055-1 is given in
BS PD 6682-4.
7.5 Water 7.8.4 The designer should assess the following factors
when determining the exposure conditions:
Mixing water and water used for curing should
a) concrete in tunnel linings might be exposed to
conform to BS EN 1008.
more than one type of exposure condition;
NOTE The exposure conditions to which the
7.6 Admixtures concrete is subjected can be expressed as a
combination of the exposure classes given in
Admixtures should conform to BS EN 934-2. BS 8500-1:2015, Table A.1 and Table A.2.
b) different surfaces of tunnel linings are likely to be
subject to different exposure conditions;
7.7 Reinforcement
c) different parts of a tunnel might be subject to
7.7.1 Bar different exposure conditions or severity
7.7.1.1 Carbon steel reinforcement should conform of exposure;
to BS 4449. NOTE For example, near portals the temperature
variation, moisture conditions and carbon dioxide
7.7.1.2 Stainless steel reinforcement should conform concentration might be different from those
to BS 6744. deeper within the tunnel.
d) tunnel linings where one surface is in contact with
7.7.2 Fibre water containing chloride and another is exposed
7.7.2.1 Steel fibres should conform to BS EN 14889-1, to air are potentially in a more severe exposure
BS ISO 13270 or a European Technical Approval. condition than described by exposure class XD2 or
XS2 in BS 8500-1:2015, Table A.1, see 7.9.2; and
7.7.2.2 Polymer fibres should conform to with e) exposure conditions can change over the design
BS EN 14889-2 or a European Technical Approval. working life of the tunnel linings.
NOTE Guidance on fibre properties is given in BTS,
Specification for Tunnelling 2010, 203.3 [NR2]. 7.8.5 Where relevant, the designer should document
the findings of the assessments undertaken in 7.8.1
to 7.8.4.
7.8 Exposure classes related to
environmental actions
7.9 Durability
7.8.1 The designer should assess the applicability of
general exposure classes given in BS 8500-1:2015, 7.9.1 General
Table A.1 and Table A.2 to specific exposure conditions 7.9.1.1 The designer should design the tunnel lining in
existing in tunnels. accordance with BS EN 1990:2002+A1:2005, 2.4, such
NOTE Specific exposure conditions include elevated that deterioration over the design working life does
carbon dioxide and temperature levels in highly- not impair the performance of the structure below that
trafficked road tunnels. required.
NOTE Specialist advice might be required.
7.8.2 Where the general exposure classes given in
BS 8500-1:2015, Table A.1 and Table A.2 as not 7.9.1.2 The designer should assess and document the:
applicable to the specific exposure conditions, the
a) intended or foreseeable use of the structure;
designer should assess the applicability of the durability
guidance in BS 8500-1 (see 7.9.1.4). b) required design criteria;
c) expected exposure conditions;
7.8.3 Where the durability guidance in BS 8500-1 is d) composition, properties and performance of the
assessed as not applicable to the specific exposure materials and products;
conditions, the designer should assess the need for
e) properties of the ground;
alternative measures.
f) choice of the structural system;
g) shape of members and the structural detailing;
h) quality of workmanship, and the level of control;
i) particular protective measures; and
j) intended maintenance during the design
working life.
7.9.1.3 The designer should assess and document or due to ingress of chloride in a similar way to
the anticipated level of maintenance (see 4.3.4 and normal reinforcement as described in 7.9.2.2 and
4.3.5) and exposure conditions (see 7.8) based on the 7.9.2.3. Predictive models can be used to determine
document produced in 7.9.1.2. the required properties of concrete, or the need for
additional methods of protection, to restrict the extent
7.9.1.4 The designer should assess and document of corrosion of fibres such that it does not adversely
whether the recommendations given in BS 8500-1:2015, affect the performance of the lining over the design
Table A.4 and Table A.5 need to be enhanced for the working life.
particular conditions of the tunnel under design. Corrosion of carbon steel fibres close to the surface can
cause rust stains.
7.9.2 Resisting corrosion of reinforcement in concrete
7.9.2.1 General 7.9.2.2 Carbonation-induced corrosion of reinforcement
The designer should design the tunnel lining so as to The designer should select a combination of cover
prevent unacceptable levels of deterioration due to to reinforcement and limiting values of concrete
corrosion of reinforcement over the design working life. composition and properties, such that damaging
carbonation-induced corrosion of reinforcement does
COMMENTARY ON 7.9.2.1 not occur during the design working life. Additional
protection should be included, if required.
Corrosion of carbon steel reinforcement can result from
carbonation of the concrete cover or from ingress of
COMMENTARY ON 7.9.2.2
chloride from the surroundings.
The reaction of atmospheric carbon dioxide with
Durability recommendations to resist corrosion of
concrete results in a reduction in the alkalinity of the
reinforcement in concrete are given in BS 8500-1:2015,
concrete. If the carbonation reaches the reinforcement
Table A.4 and Table A.5. For a given quality of concrete,
it can break down the passive oxide layer on carbon
increasing concrete cover can result in increased
steel and result in corrosion if moisture is present. The
protection against corrosion. Increased concrete cover
carbonation process is progressive, but normally slow.
can, however, result in increased thickness of the lining
and a larger excavation. Guidance on combinations of concrete quality
and cover to reinforcement to resist carbonation-
Durability recommendations to resist corrosion of
induced corrosion of reinforcement is given in BS EN
reinforcement in concrete in BS 8500-1:2015 do not
13369:2013, Annex A and BS 8500-1:2015, Table A.4 and
make any distinction between in-situ and precast
Table A.5. The recommendations in BS 8500-1:2015 are
concrete elements. BS EN 13369:2013, Annex A gives
generally more rigorous.
recommendations for concrete cover to resist corrosion
of reinforcement for precast concrete elements made in Levels of carbon dioxide in tunnels, especially heavily-
accordance with that standard. The recommendations trafficked road tunnels, can be higher than normal
in BS EN 13369:2013 and BS 8500-1:2015 differ atmospheric concentrations and can result in higher
significantly in some circumstances with BS 8500-1:2015 rates of carbonation of concrete than in normal
recommendations generally being more rigorous. atmospheric exposure, especially at higher than normal
ambient temperatures. Durability recommendations
The recommendations in BS 8500-1:2015, Table A.4
given in BS 8500-1:2015, Table A.4 and Table A.5 for
and Table A.5 can result in cover to reinforcement
carbonation-induced corrosion exposure conditions
that is too large for some tunnel lining applications.
are based on normal UK atmospheric carbon dioxide
Additional methods of protection, such as corrosion-
concentration and temperature.
resistant reinforcement, surface protection, special
admixtures or cathodic protection, might reduce the NOTE Guidance on additional methods of protection
cover required for protection of reinforcement which might allow reduction in the required cover to
against corrosion. provide protection against corrosion of reinforcement
is given in Enhancing reinforced concrete durability,
Recommended crack width limits for reinforced
Concrete Society Technical Report 61 [19].
concrete in different exposure classes are given in
BS EN 1992-1-1:2004+A1:2014, 7.3.1.
7.9.2.3 Chloride-induced corrosion of reinforcement
For steel fibre reinforced concrete (SFRC), minimum
concrete cover recommendations only apply to the The designer should select a combination of cover
embedded bar reinforcement, not to the steel fibres. to reinforcement and limiting values of concrete
Carbon steel fibres can corrode when passivity is composition and properties of concrete, such that
lost due to carbonation of the surrounding concrete damaging chloride-induced corrosion of reinforcement
does not occur during the design working life. Footnote C to BS 8500-1:2015, Table A.1 identifies
Additional protection should be included, if required. where one surface is immersed in water containing
chloride and another is exposed to air, elements are
COMMENTARY ON 7.9.2.3 potentially in a more severe exposure condition than
Additional protection might be required if the described by exposure class XD2 or XS2 in BS 8500-
combination of concrete and cover are unable to 1:2015, Table A.1, especially where the dry side is at a
provide the required performance high ambient temperature. Evaporation of chloride-
containing water on the dry side can result in high
Water-borne chloride (e.g. saline groundwater or run-
concentration of chloride within the concrete even
off containing de-icing salts) coming into contact with
where the level of chloride in the water is low.
a concrete surface can result in build-up of chloride at
the reinforcement to a level where corrosion of steel Guidance on additional methods of protection which
reinforcement is initiated. might allow reduction in the required cover to provide
protection against corrosion of reinforcement is given
Guidance on combinations of concrete quality and
in Enhancing reinforced concrete durability, Concrete
cover to reinforcement to resist chloride-induced
Society Technical Report 61 [19].
corrosion of reinforcement is given in BS EN
13369:2013, Annex A and BS 8500-1:2015, Table A.4 and
Table A.5. The recommendations in BS 8500-1:2015 are 7.9.3 Resisting chemical attack
generally more rigorous. 7.9.3.1 The designer should assess and document the
risk of potential chemical attack from groundwater,
including seepage, and other possible sources such as
effluent and road drainage, including fluids conveyed
within the tunnel.
COMMENTARY ON 7.9.3.2
External surfaces of tunnel linings can be subject to
high hydrostatic pressure which can result in increased
rates of penetration of aggressive chemicals.
Recommendations for concrete properties, limiting
values of composition and additional protective
measures (APM) for in-situ concrete elements to resist
chemical attack are given in BS 8500-1:2015, A.4.5.
Guidance on resisting attack from some aggressive
chemicals not included within BS 8500-1:2015, A.4.5
can be found in BRE Special Digest 1 [20], Concrete in
aggressive ground.
Recommendations for durability for external surfaces
of precast segmental linings for water and sewer
services, storage and transportation, and for internal
surfaces where protective lining is not necessary, are
given in Table 3. Table 4 gives details of the limiting
values associated with the specification of the DC-
class. Recommendations for where protective lining is
necessary for durability of internal surfaces of precast
segmental linings for water and sewer services, storage
and transportation, are given in Table 6. Where a
protective lining with adequate chemical resistance
is provided on the internal surface it is not necessary
to consider the recommendations in Table 3 for the
internal surface.
Table 3 – Recommendations for durability against chemical attack for the external and
internal surface of precast segmental linings where protective lining is not necessary A)
A)
Applicable to both natural and brownfield sites, and for internally carried water and effluent not
requiring protective lining in accordance with recommendations in Table 6.
B)
Aggressive Chemical Environment for Concrete exposure class, in accordance with BS 8500-1:2015,
Table A.2.
C)
A DC (Design Chemical) Class one step lower or reduction of one APM can be applied by the designer to this
indicated category if surface carbonation is assured (10 days minimum time to be allowed by the manufacturer
before dispatch). No reduction is permitted for categories where this indication is not present.
D)
APM, see Table 5.
Table 4 – Limiting values of composition and properties for concrete where a DC-class is specified
Design Max. w/c Minimum cement or combination content Cement or combination types
Chemical ratio (kg/m3) for maximum aggregate size of:
Class
20 mm 14 mm 10 mm
DC-2 0.55 300 340 360 II/B-V+SR A), IIIA+SR B), IV/B-V, III/
B+SR B)
0.40 380 380 380 II/B-V+SR A), IIIA+SR B), CEM I-SR0,
CEM I-SR3
0.35 380 380 380 II/B-V+SR A), IIIA+SR B), CEM I-SR0,
CEM I-SR3
A)
25-35% fly ash
B)
Where the alumina content of the slag is not greater than 14% and/or the C3A content of the Portland
cement (CEM I) fraction is not greater than 10%
C)
21-24% fly ash
D)
Where the alumina content of the slag is greater than 14% and the C3A content of the Portland cement
(CEM I) fraction is greater than 10%
A)
Further details of APMs are given in BRE Special Digest 1 [20], Concrete in aggressive ground.
B)
This APM might not be possible in many tunnel situations.
Table 6 – Recommendations for circumstances in which internal lining is necessary for precast
concrete segmental linings for tunnels and shafts used for water and sewer A) services,
storage and transportation
Industrial, including > 5.0 Lining not needed unless sulfate level
contaminated groundwater of water or effluent is more than 1
and run-off from vehicles 400 mg/l SO4
A)
Under certain conditions, sulfuric acid can be generated by bacterial action on sewage and protective lining
could be needed. In this case, it is advisable that a project-specific durability assessment is undertaken and
specialist advice is sought.
8.1 General principles 8.1.1 The designer should design concrete tunnel
linings to conform with the requirements of BS EN
COMMENTARY ON 8.1 1990, BS EN 1992-1-1 and the NA to BS EN 1992-1-1,
The use of fibre reinforcement has become prevalent and conformance testing should be consistent with
in all types of concrete tunnel lining, although fibre these principles.
reinforced concrete (FRC) is not covered by either BS EN NOTE BS EN 1990 establishes the principles of limit
1990:2002+A1:2005 or BS EN 1992-1-1:2004+A1:2014. state design.
A complementary methodology to BS EN 1992-1-1
is available from RILEM [NR4] and more recently fib 8.1.2 Where FRC is employed for concrete segmental
(Fédération internationale du béton) has published its lining, the designer should base the design on either
fib Model Code for Concrete Structures 2010 [NR5], the RILEM σ-ε methodology [NR4], or the fib Model
which includes limit state design methodologies for FRC. Code for Concrete Structures 2010 [NR5], or design
The structural design of FRC elements is based on assisted by testing (see BS EN 1990). The chosen
the post-cracking residual strength provided by methodology should be documented, and where none
fibre reinforcement. Bending tests are carried out to of these procedures is adopted, the reasons for this
determine the load-deflection relationship and from choice should also be recorded.
which the necessary tensile stress-crack width relationship
can be derived. Both the RILEM and fib design 8.1.3 The designer should base the determination
methodologies are based on a three-point bending test of the material parameters necessary for the design
on a notched beam conforming to BS EN 14651. on characteristic values. The material parameter
The RILEM and fib design methodologies were characterization should be consistent with the
respectively developed exclusively for SFRC and methodology selected in 8.1.2 and be in a manner
“based most of all on experience with SFRC”. BS EN which is consistent with the adopted limit state design
14651 is based on the complementary test method approach.
developed by RILEM for metallic FRCs, although
the principles of the test method can also be used 8.1.4 Conformance with the relevant plain concrete
to characterize the residual strength performance material parameters should be in accordance with
of macro-synthetic (MS)FRC. Nonetheless, the fib BS 8500-1 and BS 8500-2.
methodology does not cover “fibre materials with NOTE The specification of the relevant plain concrete is
a Young’s modulus which is significantly affected by covered in Clause 7.
time and/or thermo-hygrometrical phenomena”, and
the design methodologies are therefore limited with 8.1.5 Conformance requirements for FRC should be in
respect to (MS)FRC. Concrete Society Technical Report accordance with the principles of limit state design, and
63, Guidance for the design of steel-fibre-reinforced should use test methods that are consistent with those
concrete, [21] provides outline guidance with respect to which underpin the design methodology.
the extension of the RILEM methodology to the design NOTE Conformity testing of FRC is not covered by the
of precast concrete segmental linings and Concrete RILEM or fib methodologies.
Society Technical Report 65 [22], Guidance on the use
of macro-synthetic-fibre-reinforced concrete, further
extends this guidance to MSFRC.
8.1.6 When determining FRC material parameter 8.2.2 Where “additional requirements” are specified
values for use in conceptual or preliminary design, the by the designer, these should include appropriate
designer should make reference to data available from performance requirements, test methods and
fibre manufacturers in the first instance, and where conformance criteria.
held, to historic data relating to concrete with similar
material parameters to those of the proposed design. 8.2.3 The designer should assess and document the
NOTE 1 The key characteristic values of FRC material likely long-term concrete strength and its effect on the
parameters might have to be assumed during properties of the FRC. Where the long-term concrete
conceptual or preliminary design stages. FRC residual strength is likely to exceed the specified 28-day
strength parameters are dependent on the type and strength, the designer should ensure that the values
dosage of fibre in combination with both the strength of the FRC material parameters used in the design are
grade and other properties of the base concrete. achieved in practice.
NOTE 2 An estimation of flexural tensile parameters NOTE 1 The RILEM design methodology is applicable
of SFRC for different fibre dosages is given in Post- to SFRC with strength grades up to C50/60. The fib
cracking behaviour of steel fibre reinforced concrete methodology does not state a strength grade limit
[23]. This can be useful where no prior data exists. but does state that for ultra-high performance FRC
additional rules can apply. It is likely that the 28-day
8.1.7 When specifying conformance testing, the strength in some applications exceeds that required for
designer should cover both the preconstruction trial adequate structural performance.
conformance and production conformance of those NOTE 2 Segmental linings might require significant
material parameter values assumed in the design. early age strength development to suit the logistics
of the production processes. These requirements can
8.1.8 When compiling the specification (see 8.1.7), the have a significant effect on the long-term strength
designer should identify, in principle, the actions to be of the concrete such that the strength required
taken in the event of non-conformance. to demonstrate 28-day compliance might not be
representative of the long-term strength.
8.1.9 Where the assumed characteristic values for
FRC material parameters cannot be confirmed by 8.2.4 The post-crack performance of FRCs may reduce
preconstruction testing, the designer should review the with aging. The designer should therefore assess and
design, and any changes should be documented and document the likely effect of this on the lining’s long-
the preconstruction testing repeated. term performance.
8.3 Preconstruction and production 8.3.4 The methodology developed by the contractor
testing of concrete materials in 8.3.3 should be documented in the form of quality
procedures which assure that the conformance
8.3.1 The designer should specify the testing required achieved in the preconstruction trials can also be
to demonstrate that the concrete conforms to the achieved in the works.
requirements of the design
8.3.5 The production of all FRCs should conform to
8.3.2 Where segmental tunnel linings incorporate fibre the quality assurance procedures developed by the
reinforcement of any type, the designer should specify contractor during the preconstruction trials.
preconstruction trials to demonstrate that the FRC
performance parameters used in the design are realized 8.3.6 The contractor should undertake production
in practice when using the concrete, fibre type and testing of FRC beams in a manner that is consistent with
dosage proposed for the works. the standard test methods that underpin the relevant
design methodology.
8.3.3 When undertaking preconstruction trials for
NOTE If the quality assurance procedures developed
all FRCs, the contractor should develop a production
during the preconstruction trials are sufficient to
methodology that can be demonstrated to achieve
ensure that the in-situ fibre content and concrete
conformity with all the requirements of the project-
strength grade are compliant, it might not be necessary
specific specification.
to conduct beam tests.
Table 7 – Typical design situations for precast concrete segmental tunnel lining
Typical transient design • Demoulding, storage/stacking and handling of the segmental lining
situation • Transportation of the segmental lining
• Installation of the segmental lining
• Propulsion of the TBM
• Grouting of the segmental lining
• Initial ground and water conditions
• Operation of construction equipment within the tunnel
• Additional temporary works within the tunnel (i.e. temporary fixings, specific
temporary works associated with openings, compressed air)
• Ground treatment, including compensation grouting
Self-weight A) ●
Thermal effects ●
Shrinkage ●
Grouting B) ●
Construction equipment E) ●
Temporary fixings F) ● ●
Testing loads G) ●
For the purposes of this PAS, these typical actions for tunnels are defined as follows:
Self weight: The self-weight of a tunnel lining can be defined as a vertical gravity load. The density of typical
A)
materials used in the construction of the tunnel lining is defined in BS EN 1991-1-1:2002, Annex A, Table A.1 to A.5.
B)
Grouting: The grouting operations are required to inject grout material in the annulus between the tunnel
lining and the surrounding ground or voids in the tunnel lining to ensure full contact is established. Grout loads
might be required to be greater than the external hydrostatic pressure in order to displace any water-filled
voids.
C)
TBM hydraulic ram loads: The ram loading due to TBM excavation, where used, is defined as the load re-
quired to propel the tunnel boring machine forward against ground and water pressure and friction of the
component parts of the machine. This load is applied to the tunnel lining as a compression force acting on the
leading joint face of the tunnel lining.
D)
Initial water and ground loads: The loading due to ground and acting vertically and laterally on the tun-
nel. This load is influenced by seepage of water into the tunnel excavation and ground-structural interaction
around the tunnel lining causing redistribution of the ground loads around the excavated void. These loads are
calculated in accordance with the characterization of the ground defined in Clause 6 and the ground structural
interaction model defined in Clause 11.
Construction equipment loads are project specific. Loads include, but are not limited to, normal operation of
E)
gantry cranes, temporary construction railways, excavators and rubber-tyred vehicles within the tunnel.
F)
Loads from temporary fixings are typically indirect loads required to support temporary services. These include,
but are not limited to, spoil conveyors, temporary ventilation ducts, water and mechanical and electrical services.
G)
Testing loads are project specific. Loads include, but are not limited to pressure testing in water and sewage
tunnels, railway loading and road traffic loading depending on the tunnel type. In many cases these loads are
equivalent to those expected during the working life of the tunnel lining.
9.3.2 Loads associated with persistent design situations 9.3.3 Loads associated with seismic design situations
9.3.2.1 Loads associated with persistent design Seismic design situations are characterized by the
situations consist of permanent and variable actions. probability of seismic events in the specific project
The designer should derive loads from, but not limited location. The designer should assess and document the
to, the actions listed in Table 9. frequency, magnitude and loads associated with seismic
NOTE Table 9 lists typical loads and actions for tunnels design situations with reference to ITA, Seismic design
in the persistent design situation. This table represents and analysis of underground structures [NR7].
a basic outline of potential design situations which can
differ on a project-specific basis. 9.3.4 Loads associated with accidental design situations
The designer should define the loads associated with an
9.3.2.2 The designer should clearly state in the drawings accidental design situation on a project-specific basis.
and the tunnel lining design report any future
NOTE 1 Accidental design situations are characterized
development loading allowance considered in tunnel
as exceptional events during the design working life of
lining design.
the tunnel structure.
NOTE 2 Loads resulting from these exceptional events
include fire, explosions, derailment impact from trains
and vehicle collisions within the tunnel.
Self-weight ●
Ground A) ●
Water B) ●
Unloading/dewatering E) ●
Internal loads F) ● ●
For the purposes of this PAS, these typical actions for tunnels are defined as follows:
A)
Ground loads: The loading due to ground acting vertically and laterally on the tunnel. This load is influenced
by the geological history of the material and ground structural interaction with the tunnel excavation (see
Clause 11). Allowance can be made for long-term effects, such as deterioration or weathering of the ground
mass, swelling, creep and squeezing.
B)
Water loads: This load represents the water pressure acting on the tunnel structure. This load is dependent on
the performance requirement of the tunnel lining and fluctuations with the water table over time. Initial maxi-
mum and minimum water levels are defined by the designer and calculation of the water load needs to take
into account the specific gravity of the groundwater which can vary due to salinity, for instance. If the structure
is considered watertight, then these initial water levels can be applied to the structure as hydrostatic loads.
However, if the structure is considered drained, then the water load is reduced to a resultant seepage load on
the tunnel. The seepage load is calculated based on the efficiency of the drainage system.
C)
Existing imposed loads can be defined with reference to existing infrastructure (imposed loads at surface
include road traffic loads, railway traffic loads, weights of existing buildings acting through ground bearing
foundations or imposed loads at sub-surface include piled building foundations, load transferred around/from
existing tunnels). Imposed loads at surface are likely to become critical when tunnels are situated at shallow
depths and at sub-surface are likely to become critical when tunnels are situated in close proximity to existing
structures.
D)
Future imposed loads are defined with reference to potential infrastructure (future imposed loads at surface:
future roads, railways or ground bearing buildings, or at sub-surface such as future pile foundations). Allow-
ance for future development loading in the design of tunnel linings might be defined by client requirements.
If the proposal of a future developer is already in existence or in planning, dialogue with the developer can
take place. In the absence of any guidance, the designer can apply past industry practice consisting of a surface
surcharge representing a potential future development.
E)
Unloading/dewatering is defined as a variety of loads associated with deformation of the tunnel lining struc-
ture which can act on the lining from future development proposals for surface or sub-surface excavations (at
the surface, examples include the construction of basements or cuttings for road or rail infrastructure and at
sub-surface or below-surface level, examples include the excavation of tunnels). Unloading/dewatering is likely
to become critical when tunnels are situated at shallow depths or the excavation is in close proximity to the
tunnel lining. The designer might consider an appropriate separation or magnitude of the unloading/dewater-
ing which is insignificant to the design of the tunnel lining.
F)
Internal loadings can be defined with reference to the tunnel use (loads include self-weight of internal
structures, concentrated loads from permanent fixings, loads from rail, road or water and temperature
increases in the tunnel). Where permanent fixing loads are beneficial in the persistent design situation they are
not considered, as services might be removed for replacement or maintenance.
9.4 Ultimate limit state (ULS) and 9.4.1.1.1 Of the ULSs defined in BS EN
serviceability limit state (SLS) 1990:2002+A1:2005, the designer should, as a
minimum, verify STR, GEO, and UPL for the design of
NOTE ULS and SLS are relevant to each of the four the tunnel lining.
design situations (see Note to 9.2). This PAS focuses on
the ULSs and SLSs commonly used for transient and 9.4.1.1.2 The designer should identify and document
persistent design situations. For further information on the ultimate limits states for the determined design
seismic design situations refer to BS EN 1998-1 and for situations and actions. Failure modes of the tunnel
accidental design situations see BS EN 1990. lining members should be identified and documented
for each case.
9.4.1 ULS
9.4.1.1.3 The designer should verify the selected
9.4.1.1 General
ultimate limit state by ensuring that the design effect
NOTE 1 The principles of ULSs can be found in BS EN of actions is not greater than the design resistance
1990:2002+A1:2005, 3.3 and 6.4, and BS EN 1997- obtained with consideration of the partial factors on
1:2004+A1:2013, 2.4.7. the actions, materials and resistances.
NOTE 2 Of relevance to tunnel lining design, the
definitions of ULSs are as follows: 9.4.1.2 Failure or excessive deformation of structural
• EQU – static equilibrium; members or ground (STR and GEO)
• STR – internal failure or excessive deformation of the 9.4.1.2.1 The designer should verify STR/GEO in
structure or structural members; accordance with Design Approach 1 identified in BS EN
• GEO – failure or excessive deformation of the ground, 1997-1.
where the strengths of ground are significant in NOTE BS EN 1997-1 requires ULS verifications for
providing resistance; persistent and transient design situations using two
• UPL – loss of equilibrium of the structure or ground separate “combinations” of partial factors. The
due to uplift by water pressure (buoyancy); and rationale behind this sub-division is to cover uncertainty
relating to applied loading or actions (Combination 1,
• HYD – hydraulic failure, internal erosion and piping
DA 1-1) and uncertainty relating to ground strength
by hydraulic gradient.
(Combination 2, DA 1-2).
NOTE 3 As tunnel linings are normally considered to be
confined by the surrounding medium (i.e. the ground), 9.4.1.2.2 Where numerical analyses are used for
EQU and HYD are not normally considered critical for Design Approach 1, Combination 1 (DA1-1) in tunnel
lining ULS verification and are therefore not covered lining design, the designer should adopt BS EN 1997-
in this PAS. Exceptions to this rule exist, for example 1:2004+A1:2013, 2.4.7.3.2 (2), requiring load factors
during construction, and would be considered based on to be applied to action effects (structural forces and
the defined design situation for the individual project. bending moments) rather than to actions.
HYD needs to be considered if flow of water is allowed
through the ground and into the tunnel.
9.4.1.2.3 Design Approach 1, Combination 2 (DA1-2) 9.4.1.3 Loss of equilibrium of the structure or ground
can be applied to tunnel lining analysis, however DA1-2 due to uplift (UPL)
requires decreasing of ground strength parameters, 9.4.1.3.1 For shallow tunnels, the designer should assess
which can lead to an unrealistic ground behaviour. The and document the potential for ultimate limit state
designer should undertake a system of robust checking failure due to flotation from the action of differential
where this design approach is selected. water pressure.
NOTE 1 Examples of these ULSs and typical failure
modes of tunnel linings are described in Table 10. 9.4.1.3.2 The designer should carry out UPL verification
NOTE 2 Occasionally, the client’s design standard for both transient and persistent design situations in
requires the tunnel lining not to collapse up to a certain accordance with BS EN 1997-1:2004 +A1:2013.
level of deformation. This is understood to consider a NOTE UPL verification can relate to buoyancy of the
long-term deformation that can be induced by poor tunnel structure or differential heave at junctions with
build and/or unknown future activity (either natural shafts and station boxes.
or human induced) around the tunnel. This is usually
specified as a form of ovalization (ratio between the 9.4.2 SLS
deformation in diameter change and the un-deformed The designer should define SLS on a project-specific
tunnel diameter). This ovalization limit is normally basis.
interpreted into an equivalent bending moment that
NOTE 1 SLS can refer to water tightness, displacement
is required to deform the lining, and the tunnel lining
and crack width limit.
is designed to have enough structural capacity to resist
this bending moment. Thus, the ovalization limit is NOTE 2 SLS is defined during consideration of the
considered as an ultimate limit state requirement functional requirements of the tunnel (see 4.1 to 4.5).
(see 10.2.1.2).
Direct shear (structure) Any location on the segmental lining (for example,
through segment body or assembly systems for
segment tunnel linings)
Punching shear (structure) Any location where there is a concentrated point load
Bearing capacity (ground) Any location, but typically due to a concentrated load
point being transferred to the surrounding ground
(for example, a temporary prop used during the
construction of a tunnel opening)
Heave of the invert of excavation (ground) Inadequate shear strength at side wall
Excessive ovalization and collapse via loss of equilib- Inadequate passive resistance of the ground
rium (ground) supporting the lining
NOTE 1 Partial safety factors for fibre reinforced concrete can be taken from fib Model Code for Concrete
Structures 2010 [NR5], Section 5.6.6. Table 12 refers to a partial factor for FRC in flexural tension (residual
strength) only.
NOTE 2 Modification to partial factors for concrete and steel bar reinforcement materials can be made and
details are given in BS EN 1992-1-1:2004+A1:2014, Annex A.
9.6 Load combinations 9.6.1 The designer should identify a critical load case
or cases for each design situation based on the project-
NOTE BS EN 1990:2002+A1:2005, 6.4.3 defines the specific conditions.
principles of combination of actions (with the exception
of fatigue verifications). For persistent or transient 9.6.2 For ULS the designer should apply
design situations, the general format is based on a load combinations in accordance with BS EN
design value of the leading variable action and design 1990:2002+A1:2005, Section 6.4 and Table A1.2, Table B
combination values of accompanying variable actions. and Table C.
This combination introduces o, factor for combination
value of a variable action that can be used to reduce 9.6.3 For SLS, the designer should apply load
accompanying variable actions. combinations in accordance with
BS EN 1990:2002+A1:2005, Section 6.5.
9.7 Structural fire design spalling can then be specified as an allowable spalling
limit in concrete material specification verified by
NOTE 1 For road tunnels, the structural fire resistance subsequent preconstruction testing of the concrete mix
can be carried out with reference to the research that is used in the works.
developed by the ITA Working Group No. 6, Guidelines
for Structural Fire Resistance for Road Tunnels [4]. 9.7.1 The designer should review the following two
This ITA guideline is focused on road tunnels which design situations as a minimum when undertaking
are exposed to severe fire scenarios induced by structural fire design of a tunnel lining:
vehicles’ fuel.
a) design situation 1 – resistance of the tunnel
NOTE 2 BS EN 1992-1-2:2004 provides guidelines lining to withstand actions during the fire event.
for the structural design of concrete structures at The critical load case is typically induced at the
high temperatures and sets limitations in strength maximum fire temperature considering the loss
parameters for concrete and steel reinforcement as a of section due to spalling and loss of structural
function of the temperature. In addition, it provides resistance due to high temperatures;
simplified methods of analysis for the resistance of
b) design situation 2 – resistance of the tunnel lining
a section, such as the 500°C isotherm method. As
to withstand actions post-fire event, prior to repair.
the range of heating rates assumed in BS EN 1992-1-
2:2004 may not be consistent with those that could be
9.7.2 To account for a fire event in design, the designer
experienced by the tunnel lining, the approach may
should assess and document the following change of
require further justification via testing, in particular
material characteristics:
with fire curves that are more onerous than the
standard curve. a) loss of section induced by explosive spalling;
NOTE 3 Where a fire curve of higher intensity than the b) loss of stiffness of the concrete due to increase in
standard ISO 834 curve is being applied to the design temperature;
and/or where high strength/low permeability concrete c) loss of strength of concrete and reinforcement
is used in the lining (as is typical for segmental precast (including fibres) due to increase of temperature; and
linings) then consideration needs to be given to the d) expansion of the lining and partial restraint
inclusion of a nominal allowance for spalling in the provided by the surrounding ground with resulting
structural calculations. This nominal allowance for fire induced stresses.
NOTE 1 A number of existing guides discuss the design NOTE 3 The American Concrete Institute’s (ACI)
of segmental tunnel linings in significant detail. Further Committee 544 Fiber-Reinforced Concrete publication
information on segmental lining design is given in BTS, 544.7R-16 ‘Report on Design and Construction of
Tunnel Lining Design Guide [NR1]; and Association Fiber-Reinforced Precast Concrete Tunnel Segments’
Française des Tunnels et de l’espace Souterrain [28] provides detailed design guidance for steel fibre
(AFTES), Recommendations for the design, sizing and reinforced concrete segment linings so the designer
construction of precast concrete segments installed at may find this report useful for the design of segment
the rear of a tunnel boring machine (TBM) [27]. lining, especially when steel fibre is used. However,
NOTE 2 Clause 10 is drafted mainly for the bolted particular attention needs to be given to the fact that
precast concrete segment lining, thus subclauses that ACI 544.7R-16 is written based on the American design
deal with the connections (10.1.3 and 10.2.4), grooves codes rather than the Eurocodes.
(10.2.2.4), gaskets (10.2.3), and annulus grouting
(10.3.3) are not applicable to expanded precast 10.1.1 Segment geometry
concrete segment lining. 10.1.1.1 The designer should determine the thickness
of a precast concrete segmental tunnel lining based on
the relevant transient, persistent, accidental and seismic
10.1 Geometrical properties design situations.
NOTE 1 A precast concrete segmental tunnel lining
10.1.1.2 Where possible, the selection of the ring
consists of a pre-manufactured lining. The circular
configuration should be discussed and agreed in
cross-sectional profile of the tunnel is sub-divided into a
writing between designer and contractor.
number of segments; the cross-sectional joints between
these segments are called radial joints. The tunnel is NOTE 1 This might not be possible where the contractor
also sub-divided in the longitudinal direction, due to has not been appointed at the time of tunnel lining
the practicalities of placing pre-manufactured elements design.
in the tunnel environment; these joints between NOTE 2 A number of different rings types exist that
segments in the longitudinal direction are called impact construction means and methods. Examples
circumferential joints. A ring is defined as a series of of the different ring types of the rings can be found
segments that, when placed together, form a complete in the BTS, Tunnel Lining Design Guide [NR1]; and
circle. An exception to this is a hexagonal segment AFTES, Recommendations for the design, sizing and
that can never form a complete ring due to the half- construction of precast concrete segments installed at
staggered arrangement of segment assembly in the the rear of a tunnel boring machine (TBM) [27]. See
longitudinal direction of the tunnel. Figure 2 for a typical rectangular ring.
NOTE 2 Details on the general geometrical design NOTE 3 The ring is formed with a number of initial
of the precast concrete segment lining are given in segments and a key segment. The initial segments
AFTES, Recommendations for the design, sizing and can be a variety of shapes – rectangular, trapezoidal
construction of precast concrete segments installed at or rhomboidal. The key segment is angled in a wedge
the rear of a tunnel boring machine (TBM) [27]. shape to allow insertion longitudinally into the ring.
10.1.1.3 The designer should assess and document the 10.1.1.9 The designer should examine the alignment
key draw based on the anticipated dimensions of the and groundwater conditions and determine whether
TBM when designing the ring. a tapered ring is required. Where a tapered ring is
required, the designer should taper the ring width
10.1.1.4 The designer should select the number of to allow the lining to be built on curves or to correct
segments in a ring based on: misalignments without the need for inserting packing
a) the ring diameter; at the circumferential joint.
b) the size constraints for handling segments with the NOTE 1 A parallel-sided ring has limited capability in
anticipated TBM; the correction of the build alignment.
c) structural performance; and NOTE 2 The taper, especially on a long ring, needs to
be optimized to limit the risk of damage to the tailskin
d) contractor’s preference.
seals and the segments if the segments are not aligned
10.1.1.5 The designer should select the number and size within the tolerances.
of the segments within a ring to accommodate clocking
10.1.1.10 Where a tapered ring is required, the designer
positions.
should add the taper to the leading and/or trailing
10.1.1.6 The designer should set the clocking positions circumferential joint faces.
on each segment so that the TBM thrust ram shoe is not NOTE Historically, the use of a left/right tapered ring
applied over any radial joint. has allowed the key segment to be installed above
the axis level to eliminate perceived difficulties of
10.1.1.7 Where possible, the designer should select the inserting a key segment at the invert, or to avoid high
number and size of the segments within a ring so that concentrated load on a key, for example from floating
each segment, including the key segment, can always track slab pads. However, a modern TBM segment
be supported by at least one TBM thrust ram during erection system is considered capable of placing the key
assembly of the tunnel lining. segment at the invert with little difficulty.
NOTE 1 This provision means that each segment
(including the key segment) needs to have at least two 10.1.1.11 Where a tapered ring is required, the designer
bolt/dowel positions on the circumferential joint. should calculate the ring’s taper using the following
equation (see Figure 3):
NOTE 2 This provision limits the risk of key segment
slippage which has occurred on tunnels with high T = D × B / Rmin
external ground and water pressures.
where: T is the taper
10.1.1.8 The designer should define the longitudinal D is the external diameter of ring
length of the ring based on the: B is the mean width of ring
a) ease of construction; Rmin is the minimum radius of design curve
b) junction/opening size;
c) structural performance;
d) contractor’s preference; and
e) health and safety considerations during
construction.
NOTE Longer rings result in improved water tightness
as the total length and number of circumferential joints
in the tunnel overall is reduced. However, a long ring
increases difficulties in installing the segment both in
terms of its length (when the segment is turned in the
build area) and in terms of the stroke of the hydraulic
rams on the TBM (which need to retract and extend the
length of the segment ring and, typically, the length
of any key draw). The use of longer rings can increase
the risk of damage and cracking during handling and
transportation.
10.1.3.3 Where applicable, the designer should design 10.2.1.1.1 When developing the M-N envelope, the
the size and number of bolt pockets to provide designer should ignore the flexural tensile strength of
sufficient surface area for the use of a vacuum plain concrete.
segment erector.
NOTE In TBM construction, vacuum erectors are widely 10.2.1.1.2 When FRC is used, the designer should
used and the lifting capacity of the vacuum erector is use the αcc specified for reinforced concrete rather
highly dependent on the available suction area that is than plain concrete to determine the lining design’s
affected by the number and size of bolt pocket. compressive strength, provided the dosage of fibre is
enough to make the lining fail in ductile mode (see
10.1.3.4 The designer should assess the risk of segment Figure 4). Where the dosage of fibre is not enough to
damage against the need to remove the bolts once the make the lining fail in ductile mode, the factor for plain
ring is complete and grouted into place and advise the concrete should be used.
client of any identified risks.
COMMENTARY ON 10.2.1.1.2
10.1.4 Manufacturing tolerances αcc is a coefficient that takes account of long-
term effects on the compressive strength and of
10.1.4.1 The designer should define manufacturing
unfavourable effects resulting from the way the load
tolerances of segments and rings in accordance with
is applied for determining the design compressive/
BTS, Specification for Tunnelling, Section 204 [NR2].
tensile strength value. NA+A2:2014 to BS EN 1992-1-
1+A1:2014 requires reducing of αcc 0.85 to 0.6 for the
10.1.4.2 The designer should determine the appropriate
plain concrete which is considered not applicable for
manufacturing tolerances when designing convex or
fibre reinforced concrete lining structure. αcc directly
concave radial joints.
affects the size of compression block which governs the
10.1.4.3 The designer should document the defined size of M-N envelope.
manufacturing tolerances in a project‘s materials and When determining the shape and size of tensile stress
workmanship specification. block in an FRC lining, it is advisable to use the fib
NOTE A full ring mock-up section to test the Model Code for Concrete Structures 2010 [NR5].
geometrical tolerance of the ring is essential for the Various recommendations on the structural design
precast concrete segment lining. It is advisable to build of FRC are available in the industry and those
at least three test rings to confirm fully-integrated ring- recommendations are being improved/updated as a
to-ring connection geometry. result of continuous academic research and industry
feedback. This PAS does not specify a prescriptive
design process for FRC but sets out external design
10.2 Design recommendations for precast recommendations that are considered suitable for the
concrete segment lining tunnel lining design guide.
Figure 4 – Schematic diagram of strain and stress block for reinforced concrete and fibre
reinforced section for the development of the M-N envelope
Key
Ac area of compression in the design l 0.8 for fck≤50MPa
section 0.8 - (fck-50)/400 for 50<fck≤90MPa
As area of tension reinforcement cu3 ultimate limit strain for bi-linear stress-strain relationship (see
BS EN 1992-1-1:2004+A1:2014, Figure 3.4 and Table 3.1)
Fc compressive force s strain of reinforcement steel (varies with neutral axis position)
Fs tension force in reinforcement f strain of fibre reinforced concrete respectively (varies with
neutral axis position). The strain limit is considered with the
maximum allowed crack width in steel fibre concrete section
for ULS (see fib Model Code for Concrete Structures 2010,
Section 5.6 [NR5])
Ff tension force in the tension section fcd design compressive strength of concrete
of fibre reinforced concrete section
fck characteristic compressive strength αc partial material factor of concrete (equally applies to both
of concrete (see BS EN 1992-1- reinforced and fibre reinforced concrete)
1:2004+A1:2014, Table 3.1)
1.0 for fck≤50MPa cc 0.85 (both reinforced and fibre reinforced concrete)
The designer can ignore the reduction of ring stiffness 10.2.2.2 Bursting
and use I for the design of the segment when the radial 10.2.2.2.1 Bursting failure verification is considered to
joint of the lining is designed to transfer full bending be a ULS verification. When verifying bursting failure at
moment through the joint. the joint, the designer should assess and document:
The designer can estimate Ij to suit the geometry of the a) construction tolerance at the joint – so-called lips
joint and the anticipated behaviour of the joint when and steps: this reduces the joint contact width, and
the lining is being deformed. also influences the centre line of the stress line;
For the verification of the long-term deformation limit b) when there is no clear project-specific guidance
check, it is advisable that the designer demonstrates on the construction tolerance, the designer should
that the calculated Mmax combined with the factored act in accordance with the BTS, Specification for
hoop thrust estimated from the most onerous long- Tunnelling, Section 328 [NR2];
term permanent load case is plotted within the M-N
c) the shape of the joint and the actual contact areas
envelope of the segment. Both the highest and lowest
between the two segments;
hoop thrust are usually considered to determine which
case is the most onerous. Mmax is usually not combined d) the contact area between the ram loading and the
with any accidental load case. segment, including all tolerances; and
Although Mmax is obtained from the deformation limit, e) rotation at the joint (birdsmouthing): this affects
a suitable load factor can be considered for the Mmax. the shape of the compressive stress block at the
joint – when the birdsmouthing is significant,
See Morgan, A contribution to the analysis of stresses
the joint contact width decreases, increasing the
in a circular tunnel [31] for the origination of
bursting stress.
equation (10.1).
NOTE The level of joint rotation is linked to the
See Muir Wood, The circular tunnel in elastic ground
sectional distortion of the lining. The angle of
[32] for the origination of equation (10.2).
birdsmouthing can be estimated using geometrical
10.2.1.3 Shear failure check relationship with consideration of the determined
The designer should design the tunnel lining against hoop thrust and bending moment level at the
shear failure in accordance with BS EN 1992-1- radial joint.
1:2004+A1:2014, 6.2.
10.2.2.2.2 The designer should carry out joint bursting
NOTE BS EN 1992-1-1:2004+A1:2014 does not consider
stress checks, taking account of the joint-facing
the contribution of fibres in the increase of shear
geometry.
resistance. fib Model Code for Concrete Structures
2010, Section 7.7.3.2 [NR5] considers the contribution NOTE 1 Joint bursting stress checking is sensitive to
of fibres to the shear resistance when fibres are used the joint contact width. A schematic comparison of the
with bar reinforcement, but no design guidance is stress distribution at the joint between the flat joint
provided for the fibre only reinforced concrete. For and the convex-convex joint is demonstrated in Figure
fibre only reinforced concrete lining, BS EN 1992-1- 5 and Figure 6. Further information on the types of
1:2004+A1:2014, 12.6.3 can be used for the ULS shear joint geometry is given in AFTES, Recommendations for
resistance verification. the design, sizing and construction of precast concrete
segments installed at the rear of a tunnel boring
machine (TBM) [27], Section 3.5.3.
10.2.2 Joint design
NOTE 2 The load on the segment joint is normally
10.2.2.1 General not uniformly distributed and can be applied with an
10.2.2.1.1 The designer should verify the segment eccentricity. The simplification shown in Figure 7 can be
lining’s joint for both bearing and bursting failure. used for the hand calculation of the joint bursting force
unless a finite element (FE) model is used with the use
10.2.2.1.2 When verifying the segment lining’s joint of actual load distribution on the joint.
design, the designer should assess and document the
TBM ram loading (circumferential joint) and hoop
thrust (radial joint).
Figure 5 – Joint contact width and stress distribution change with joint rotation for flat joint
Figure 6 – Joint contact width and stress distribution change with joint rotation for convex-
convex joint
Figure 7 – Simplification of non-uniform load with eccentricity for bursting check on flat joint
10.2.2.2.3 The designer should determine the bursting 10.2.2.4 Groove and edge design
force at the joint of the tunnel lining in accordance 10.2.2.4.1 The designer should document the geometry
with BS EN 1992-1-1:2004+A1:2014, 6.5.3 (3). of the joint with consideration to:
NOTE Alternatively, some designers elect to use a) the dimension of the gasket groove;
Leonhardt’s empirical equation to obtain the
b) the necessity of caulking groove at intrados edge of
distribution of bursting tensile force along the depth
segment; and
of the joint. The FE analysis method can also be used
to determine bursting stress at the lining joint. For c) recesses or chamfers to prevent corner edge damage.
Leonhardt’s equation, see Leonhardt, Prestressed NOTE Further information on the types of
Concrete Design and Construction [33], Chapter 9. waterproofing gaskets, and guidance on their selection,
is given in AFTES, Recommendations for the design,
10.2.2.2.4 The design tensile strength of concrete sizing and construction of precast concrete segments
should be in accordance with BS EN 1992-1- installed at the rear of a tunnel boring machine (TBM)
1:2004+A1:2014, 3.1.6 (2) for plain concrete and FRC. [27], Section 3.5.4.
10.2.2.2.5 The designer should assess and document the 10.2.2.4.2 The designer should document the
necessity of full-scale testing to justify the capacity of a dimensions of the gasket groove to suit the
segment under large loads at the joints in accordance manufacturer’s selected product detail.
with BS EN 1990:2002+A1:2005, 5.2 and Annex D.
NOTE Design assisted by testing can provide a more 10.2.2.4.3 The designer should design the gasket
detailed behaviour of an FRC segment prior to and location to have enough distance from the outer edge
after cracking. It can be beneficial for determining the of the segment to avoid edge spalling near the joint,
bursting capacity of the FRC segment. taking account of construction tolerances (see Figure 8).
NOTE The edge spalling is not considered to be an
10.2.2.2.6 If the design tensile strength of the concrete ultimate limit failure of the segment ring, but affects
is less than the bursting stress, the designer should the durability and serviceability (water tightness) design.
design the joint to be reinforced to have sufficient
tensile resistance to prevent bursting. 10.2.3 Gasket design
10.2.3.1 The designer should select the gasket to meet
10.2.2.3 Bearing water tightness requirements under the design water
For the precast concrete segment lining, the designer pressure for the design working life with consideration
should verify bearing failure at the radial joints in of the chemical composition of the groundwater.
accordance with BS EN 1992-1-1 :2004+A1:2014, 10.9.4.3
(6) and 6.7.
Dimensions in mm
10.2.3.2 The designer should verify the gasket design NOTE 1 The gasket’s water tightness capacity varies
for all possible combinations of pressure, offset with the gap and offset (construction tolerance). When
induced by the construction tolerance (lips and steps) the lining deforms, the lining’s radial joints tend to
and maximum gap due to birdsmouthing at the joint rotate and make the joints open. The birdsmouthing
associated with ring diametrical deformations induced increases the gap between the joint face, meaning the
by construction tolerances and loading conditions. gasket’s water tightness capacity is decreased.
NOTE 2 Figure 9 illustrates the typical relationship
between the water tightness capacity defined in water
pressure bar and the gap distance with and without offset.
NOTE 3 The gasket can be either glued to the lining
following manufacture of the segment or can be cast in
the lining during the manufacture of the segment.
NOTE 4 A double gasket system, i.e. two rows of 10.3 Design recommendations for
gaskets, one at extrados and the other at intrados, can transient design situations
be considered to provide a secondary water tightness
line within the segment joints. Care needs to be given 10.3.1 Transport, storage and handling
to the fact that the water tightness capacity (i.e. bars) 10.3.1.1 The designer should determine a lifting
of the double gasket system is defined by the higher method for the segments for key stages including
capacity of the two gaskets, not by the sum of both demoulding, rotation, stacking, transport and erection
gaskets’ capacity. in the TBM, including segment connections, taking due
account of health and safety considerations.
10.2.4 Bolt and dowel socket/pocket design NOTE 1 Safety factor requirements for segment
10.2.4.1 The designer should design the bolt socket to erection by TBM are given in BS EN 16191:2014, 5.2.5.2.
avoid a block shear failure along the weakest section Further information on health and safety requirements
at the bottom of the bolt pocket against the pre- is given in BS 6164:2011, 7.8.2.5.
tensioning force of the bolt. NOTE 2 Typical lifting methods of a segment include
NOTE Where a block shear failure occurs, this is the use of a vacuum erector, single-point lifting,
considered to be a ULS verification. clamping or the use of a forklift.
10.2.4.2 The designer should design the bolt and dowel 10.3.1.2 The designer should design the segment
socket to provide enough pull-out resistance against the to account for the loads resulting from lifting and
pre-tension force of the bolt and the pull-out force of handling, from the initial casting to the erection inside
the dowels (coming from the gasket’s push-away action). of the TBM. While these transient actions vary from one
NOTE 1 When the use of packers is expected, the project to another, the designer should check operations
packer compression and unload characteristics need to against the following list for the segment design:
be considered together with the gasket parameters. a) segment lifting and turning during curing and
NOTE 2 Particular attention needs to be paid to the mould stripping;
push-fit type dowel’s engagement tolerance because b) handling stages from precast plant to storage areas;
inadequate engagement tolerance can cause the risk of c) segment stacking and insertion of timber spacer
segment slipping back during erection of the next ring. between units;
10.2.4.3 When designing the segment, the designer d) removal from storage and unloading on site;
should assess the interaction between the bolt pockets, e) transportation along the tunnel;
grout holes and dowels to ensure they do not lead to a f) segment erection in the TBM;
plane of weakness and cracking on the segment. g) TBM gantries’ wheels rolling over the last
segmental rings installed.
10.3.1.3 The designer should carry out design checks 10.3.3 Annulus grouting
to assess the impact of the stresses induced on the 10.3.3.1 The designer should define annulus grouting
segments at each design stage. The design checks for primary and secondary grouting in a TBM-driven
should consider: segment-lined tunnel.
a) the possible dynamic effects of handling (e.g. NOTE Primary grouting is commonly carried out before
placing a segment on a stack during lifting or the ground load is fully transferred to the segment
storage stages); lining, unless the ground is very soft (e.g. very young
b) implementation tolerances (e.g. accuracy of marine clay). The primary grout load is therefore
intersegment block positioning at the storage considered to be hydrostatically applied to the lining.
area); and
c) the true age of the concrete and its characteristic 10.3.3.2 The designer should specify grout injection
strength, when carrying out each relevant operation. pressure in the segment lining design with reference to
the hydrogeological condition of the ground.
NOTE Certain cases can become dimensionally critical
and might require either the short-term improvement NOTE For primary grouting, BTS, Specification for
of concrete properties or the increased reinforcement Tunnelling [NR2] requires sufficient pressure to place
of sectional areas. It is advisable to consider re- the grout properly but not greater than 1 bar above
designing the handling and stacking process with the prevailing hydrostatic pressure at the location
modifications to the equipment rather than re- of grouting.
designing the segment to satisfy handling and stacking
requirements. 10.3.3.3 The designer should estimate and document
the tunnel lining’s hoop thrust due to the maximum
10.3.1.4 The designer should document the size, grout injection pressure using one of the analysis
number and geometry of sockets in accordance with methods described in Clause 11. The designer should
the TBM erector’s details to limit the risk of damage then verify the segment lining’s stability using the
(also see 10.3.1.1 in relation to the provision of a M-N envelope.
shear pin). The designer should ensure the segment is NOTE 1 It is unlikely that primary grout pressure is a
compatible with an erector conforming to BS EN 16191. critical load case for the segment design unless the
NOTE Further information on shear pins is given in BS hydrostatic groundwater pressure is very high.
16191:2014, 5.2.5.2. NOTE 2 Secondary grouting is carried out for a specific
ring or segment only when primary grouting proves
10.3.1.5 Where two sockets are required, the designer insufficient. Secondary grouting is normally performed
should position them to avoid causing a plane of through the grout hole by the drilling of the segment.
weakness within the segment. As the secondary grout area is localized, it is unlikely
NOTE Sockets can be equipped with the cast-in grout/ that the secondary grout is going to deform the
lift plug with non-return valve for grouting. entire ring in a symmetric shape. The potential failure
mode is punching shear failure along the perimeter
of the grout area but this is rare. It is difficult to verify
10.3.2 Hydraulic ram loads
the structural stability of the segment against the
10.3.2.1 The designer should estimate and document secondary grouting without knowing the size of the
the design ram loads based on the specific geotechnical area that secondary grouting is likely to be applied to.
conditions for the project, taking account of any project- It is therefore advised that the designer check punching
specific requirements. The maximum ram loads should be shear failure with a reasonable assumption for the
confirmed by the contractor prior to segment manufacture. grout area. Unless specific guidance is provided by the
NOTE Ram loads are applied to the precast concrete client’s design standard, a 1 m × 1 m section can be
segmental lining to propel the TBM forward against used for the punching shear checking.
friction caused by the dead load of the machine and
the ground and water pressures. The force imparted by 10.3.4 Other loads
the hydraulic ram provides a concentrated variable load
The designer should assess and document the impact of
onto the circumferential joint face of the lining.
other bespoke loads such as construction vehicle loads
on the precast concrete segmental lining (see Table 8).
10.3.2.2 Designers should assume a plane face for
adjacent rings and ensure any cracking induced by NOTE An example of a construction vehicle load is
the ram loads is within a width limit (specified in the the self-weight of the back-up train behind the TBM.
durability report) that does not affect the serviceability Construction vehicles impart a concentrated variable
of the lining. load case onto the precast concrete segmental lining.
NOTE Packers can be used for the correction of plane.
11.1 General NOTE 6 The BTS, Tunnel Lining Design Guide [NR1] and
the ITA, Guidelines for the Design of Tunnels [NR6] are
The designer should model the behaviour of the tunnel among various references available that describe the
in the geological setting where it is to be constructed, methods for the analysis of tunnels with or without
in order to obtain information for: an explicit inclusion of the ground and structure
a) the design of the geotechnical and structural interaction.
components of the tunnel; NOTE 7 The basic theoretical framework for ground-
b) the selection of necessary control measures to structure interaction analysis of tunnel linings is
monitor and safeguard the tunnel construction and -
given in Szechy, The Art of Tunnelling [34]. It includes
adjacent affected assets; and mathematical derivation from the first principles of
c) a better understanding of the possible mechanisms closed-form solutions for various design cases, which
of failure, including an assessment of risks and form the basis of most modern methods of analysis.
potential mitigations.
NOTE 1 The creation of models for the design of the
tunnel lining requires the simplification of a complicated 11.2 Selection of modelling approach
real problem to a simplified theoretical model. The 11.2.1 In order to achieve a robust tunnel lining design
selection of the modelling approach for the ground model, the designer should:
behaviour, the tunnel behaviour and their interaction is
a) select a suitable ground behaviour model
a key aspect in the design of the tunnel lining.
and associated criteria for geotechnical and
NOTE 2 The ultimate output from the modelling of a hydrological parameters;
tunnel structure, whether it is with simplified closed-
b) select a suitable method to model the structural
form solutions or advanced numerical modelling, is
behaviour of the tunnel;
the parameters required for the design of the tunnel
lining. These include the internal forces of the lining’s c) select a suitable method to simulate the interaction
structural members (axial forces, bending moments and between the ground model and the tunnel lining
shear forces) which form the basis for the sizing and model to obtain the effects of such interaction.
structural checks of the tunnel lining and any associated
11.2.2 The designer should use the ground behaviour
detail such as assembly systems and waterproofing.
models in 11.3 to estimate the loading and restraints
NOTE 3 The modelling can also indicate the state of provided by the ground within the geotechnical
stress and behaviour of the ground which can be an environment extrapolated from the ground model
important aspect of the design, especially at junctions as defined in Clause 6. The designer should decide
and other changes of profile. whether analytical methods based on closed-form
NOTE 4 In addition, some modelling approaches solutions or more advanced methods via numerical
can provide resulting deformation of the tunnelled modelling are appropriate for the stage of the design
structure and the ground above or adjacent to it. under consideration.
These outputs are required to meet performance
requirements for the new tunnel and justify that the 11.2.3 The designer should define the tunnel lining
effects of the tunnel construction to adjacent above parameters in accordance with 11.4 to obtain the
and below ground structures are suitably managed. required structural input parameters for modelling the
NOTE 5 Clause 11 focuses on modelling approaches correct behaviour of the tunnel lining.
with particular reference to segmental lining design. NOTE These parameters are selected with reference
While some of the recommendations are applicable to to the geometrical and material characteristics for the
mined tunnel design and permanent cast-in-situ design, structural design based on the recommendations given
it is advisable that reference for the modelling of these in Clauses 6 to 10.
structures is sought in other guidelines such as those
provided by the BTS and ITA.
11.2.4 The designer should select the ground and 11.3 Selection of the ground
structure interaction model from those set out in 11.5. behaviour model
NOTE 1 These methods include analytical models
(closed-form solutions), bedded spring models and full 11.3.1 Ground pressures
numerical modelling. The designer should select a ground behaviour model
NOTE 2 Due to their relative simplicity and limited to estimate the ground loading acting on the tunnel.
amount of input parameters, analytical models NOTE The selection of a ground behaviour model
and bedded spring methods are a useful tool for depends on the ground conditions as well as on the
preliminary analysis and validation of results from more stage of the design. The most common methods include
complex methods of analysis, as well as back analysis of the following:
monitoring data. • Full overburden – Full ground vertical stress is
NOTE 3 Numerical analyses offer the ability to model assumed to act at the tunnel axis level. This is used to
explicitly complex structures and uneven ground obtain ground loads for tunnels in softer ground or
loading and behaviour, including adjacent above and loose soils where arching effect is unlikely over the
below ground structures, different geological strata, design working life of the structure.
detailed constitutive behaviour and construction • Ground arching – Terzaghi, Theoretical Soil Mechanics
sequences. This provides an unparalleled capability for [35] proposed the arching effect defined as a
simulating ground behaviour, structural behaviour and “transfer of pressure from a yielding mass of soil
ground and structure interaction. However, due to the onto adjoining stationary parts”. The arching effect
complexity of some numerical modelling, more time is facilitated and maintained solely by the shear
and effort is required to produce a robust model. strength of the ground. The arching effect can be
NOTE 4 The selection of the overall approach used to carry out an analytical calculation of the
depends on the complexity of the analysis in terms of ground loads on tunnels of various geometries. The
geotechnical and geometrical conditions and could vary mathematical framework for arching in shallow and
depending on the stage of the design. -
deep tunnels in soft ground is given in Szechy, The
Art of Tunnelling [34].
11.2.5 The designer should verify any selected approach • Convergence-confinement method – Effective ground
with an alternative method and undertake sufficient loading on the tunnel lining can be obtained from
sensitivity studies to assess the variability in results due the principles of the convergence-confinement
to the consideration of a range of values to account for method. An estimate of the ground forces before
the variability in input. installation of the lining can be obtained through
the definition of the ground reaction curve described
in Annex C. When estimating ground loads using
this method, ground parameters and in-situ stress
are assessed in drained or undrained conditions
depending on the hydrological conditions. Water
pressures cannot be relaxed and can be superimposed
to obtain the total pressure on the tunnel lining.
• Numerical analysis – 3D or 2D axisymmetric numerical
models can model, explicitly, the behaviour of the
ground around a tunnel structure and provide the
most realistic estimate of ground loading for tunnels
in soft ground, accounting also for the method of
construction. Further details on numerical analysis are
included in 11.7.
The designer should select one of the following NOTE Analysis of segmental linings using 3D solid
methods to account for the segmented nature of the elements allows the modelling of the full behaviour
lining in terms of the rotational stiffness of the full ring. of radial and circumferential joints using contact (or
a) The second moment of area of the full ring is interface) elements. This methodology is therefore
reduced to consider the influence of the radial generally more refined when compared to the
joints; this reduction is a function of the number modelling of the lining using beam or shell elements
of joints and the geometry of the joint contact if the behaviour of the joints is governing the design.
face. This method is the only method applicable An example of a 3D model of a segmental lining with
to closed-form solutions assuming linear-elastic contact elements used at the joints is given in Figure 10.
behaviour of the ring and a single value of the
moment of area is an input of such formulations 11.4.3.3 Where required in 3D numerical models, the
(see 10.2.1.2.2). designer should model the circumferential stiffness to
account for the relative stiffness produced by the joint
NOTE The contact face for a flat joint is nominally
assembly system and any contact resistance through
the full joint contact width as set out in 10.2.2.
friction between segments, when friction can develop
The contact face for a convex-convex joint is
at the joints.
traditionally assumed to be zero for the purpose
of the calculation of the second moment of area of
the ring. 11.4.4 Modelling of local effects on segmental lining
b) In 2D bedded beam spring and numerical models, The designer should carry out explicit modelling of
the lining is represented by beam elements. While the segment to check local effects at the joints coming
the approach set out in 11.4.2 a) is commonly used from ram forces or bursting forces. Where necessary,
in these methods, the designer should consider the designer should include the non-linear material
the benefit of modelling the joints explicitly. The behaviour of the concrete (in particular if FRC segments
joints can be explicitly modelled introducing a are employed). A constitutive model with elasto-plastic
local discontinuity in second moment of area at properties should be defined as a stress-strain non-
all joint locations while maintaining full sectional linear curve.
rotational stiffness properties for the rest of the NOTE 1 RILEM σ-ε methodology [NR4], TR63, or the fib
ring. When flat joints are used, an upper value Model Code for Concrete Structures 2010 [NR5] define
for the rotational stiffness should be chosen in a possible constitutive model to use in the FE analysis.
order to obtain conservative results for the lining NOTE 2 Shell elements or solid elements can be used
design. Lower bounds should be chosen to assess to provide a better understanding of the stress-
the deformation limits of the lining. When convex- strain behaviour of the concrete segments under
convex joints are used, the rotation stiffness should concentrated loads to assess maximum tensile stresses,
be set equal to zero. strains, crack location and expected width. Figure 11
shows the state of tensile stress (highlighted in red) in
11.4.3 3D Modelling of tunnel linings segments loaded with concentrated forces at the radial
11.4.3.1 In 3D numerical models, including 3D spring and the circumferential joint.
models, the designer should model the lining using
plate or shell elements.
NOTE 1 3D solid elements can be used, but these need
11.5 Methods of analysis of ground
to be selected to allow an easy derivation of resolved structure interaction
forces and moments. The designer should select the approach to model the
NOTE 2 The constitutive behaviour of both radial and interaction between the ground and the lining from
circumferential joints is of great importance in 3D FE the list of methods set out in Figure 12.
models to determine the expected joint behaviour as NOTE These methods are divided into several main
the tunnel deforms. categories, which are described in 11.6 and 11.7.
Figure 10 – Example of a 3D model of a segmental lining with contact elements used at the
joints
Figure 11 – State of tensile stress of radial and circumferential joints of a segmental lining
Key
H Tunnel depth R Tunnel diameter
Total unit weight of elastic medium (ground) t Lining thickness
K0 Coefficient of earth pressure at rest v’ Effective vertical stress
NOTE 2 Analytical methods for the design of tunnel NOTE 2 Guidance on analysis of tunnel lining in soft
support requirements are generally defined as 2D ground using continuum analytical solutions is given
or 3D, closed-form theoretical solutions that assume in BTS, Tunnel Lining Design Guide [NR1]. Additional
a circular tunnel in an elastic or elastic-plastic details are given in ITA, Guidelines for the Design of
homogenous continuum under static equilibrium. Tunnels [NR6].
11.6.4 Bedded beam spring models 11.6.4.3 The designer should assess and document the
11.6.4.1 The designer should carry out the analysis need for more advanced modelling methods when the
of tunnel linings in soft ground using bedded spring use of spring models results in convergence difficulties
models in accordance with ITA, Guidelines for of the numerical solution.
the Design of Shield Tunnel Lining [NR9] and ITA, NOTE Convergence difficulties can occur due to the
Guidelines for the Design of Tunnels [NR6]. assumption of very soft ground stiffness or in the case
NOTE 1 As illustrated in Figure 14, bedded beam of very high stress conditions.
spring models are action-reaction models that enable
a simple analysis of a tunnel lining. Loads (e.g. ground
and water pressures) are applied to the tunnel lining 11.7 Numerical methods
represented by a series of beam or shell elements, so NOTE 1 Numerical analysis methods attempt to satisfy
a non-circular tunnel can be modelled and analysed. all theoretical requirements, include realistic ground
As the tunnel deforms under the applied load, only and lining constitutive models and incorporate
the springs in compression (representing the ground boundary conditions that more accurately simulate
reaction) provide a passive reaction resulting in force field conditions.
equilibrium. No tension is permitted in the radial spring
NOTE 2 Approaches based on finite difference (FD)
by introducing compression-only, non-linear springs.
and FE methods are most widely used for tunnel lining
NOTE 2 Bedded beam spring models are useful in design. These methods involve a computer simulation
all stages of design. However, it is advised that care of the full stress path from green field conditions,
be taken when used in detailed design as the beam through to construction, and in the long term. Other
spring model provides a rudimentary representation methods such as the discrete element method (DEM)
of ground-structure interaction. It is advisable to carry and boundary element method (BEM) are also available
out a comparison analysis via the use of a continuum and can be superior to FE/FD methods in certain
analytical solution (for circular tunnels) or full instances such as analysis of small-scale features or
numerical analysis models (see 11.6.1 d)). extremely complex geometries.
NOTE 3 The applicability of these methods is defined in
11.6.4.2 The designer should perform the analysis of the
the BTS, Tunnel Lining Design Guide [NR1].
tunnel lining in accordance with the recommendations
for limit state design in Clause 9 for the identified
design situations and load combinations, including
distributed or localized internal loads.
h) apply adjacent underground and above-ground The designer should initialize the effective in-situ
structures (existing and under construction); ground stress around the tunnel location using the
coefficient of earth pressure at rest, K0.
i) model the excavation;
NOTE 1 As a consequence of the tunnel being formed,
j) model the installation of lining and selection of the
the horizontal effective stress falls such that the
most appropriate lining modelling methodology
coefficient of earth pressure changes (often referred to
and structural constitutive model;
as Km, with m denoting ‘mobilized’). The lining needs to
k) apply load variations and combinations in accommodate this initial stress regime, and over time,
accordance with Clause 9, with particular attention a number of factors could influence how the stress
to the effects of high-imposed internal loads from a regime might change. These include:
pressured water tunnel;
• horizontal stresses around the tunnel with time
l) carry out an initial run and model validation using increasing towards at rest K0 conditions; and
independent simplified calculations and case
• change in groundwater pressure, either caused by
history data;
pore pressure equalization following the formation
m) apply where applicable any intrusive mitigation of the tunnel or from the tunnel acting as a drain
works such as ground improvement/compensation
NOTE 2 Figure 15 shows an image taken from a FE
grouting;
model of the K0 or Km conditions prior and following
n) consider impacts from concurrent adjacent excavation of a tunnel in London Clay. Following
excavation and construction activities; formation of the tunnel, the coefficient of earth
o) consider the effect of loads from/on existing pressure can be seen to have dropped significantly at
structures and foundations; the tunnel axis level, while at the crown and invert
p) consider the time-dependent behaviour of the it has significantly increased. This emphasizes the
ground and material parameters; relaxation of horizontal stresses at axis level and effect
of arching of stresses above and below the tunnel.
q) consider the effect of an applied surcharge load if
required, at the appropriate stage; and
r) carry out independent reviews of the model and
final validation using independent simplified
calculations and calibration models.
Figure 15 – Coefficient of earth pressure change prior (i.e. at rest) and following tunnel
construction (variation of horizontal stresses in kPa)
11.7.2.4 Stress reduction 11.7.3 Finite element (FE) and finite difference (FD)
The designer should determine the stress reduction mesh geometry
parameters when a numerical analysis method is For FE and FD models, the designer should select the
adopted for the design of the tunnel lining. appropriate mesh geometry to achieve:
NOTE 1 The most popular method to simulate the a) an accurate geometrical representation of the
tunnel construction procedures is the “stress reduction structure and the ground;
method”, often referred to as the l-method, that b) the recognition that the mesh sizing at points of
allows simulation of the 3D tunnelling process with 2D isolated loads or stress-concentrations might need
models by reducing the initial stress around the tunnel to be finer to achieve accurate output;
perimeter. The approach to be used in conjunction
c) the recognition that a coarser mesh might be
with the convergence-confinement method is given in
appropriate at zones where construction is unlikely
Annex C.
to change the pre-existing stress conditions;
NOTE 2 The stress reduction calculation is often
d) the required level of numerical accuracy (e.g. the
erroneously linked to volume loss. Volume loss is
fineness of the mesh);
normally used for ground movement and building
damage assessment, with the aim of generating the e) a realistic representation of stress/deformation
maximum expected ground movement. However, for changes during sequential stages;
lining design, the higher the ground convergence f) a correct modelling of boundary condition (e.g.
assumed (i.e. volume loss) the higher the stress the use of infinite elements along the border or
reduction and, therefore, the less the load imposes suitably large mesh such that the influence of the
on the lining. An approach that only assumes a high boundary is negligible).
estimate of volume loss may not be conservative for NOTE 1 Additional guidance of meshing requirements
lining design. is given in the BTS, Tunnel Lining Design Guide [NR1]
and NAFEMS publications available online at www.
nafems.org.
NOTE 2 A typical FE model of a segmentally lined
tunnel is shown in Figure 16.
11.7.4 Special considerations for numerical modelling 11.7.4.3 Ground creep and shrinkage/swelling
11.7.4.1 Model calibration NOTE Ground creep and shrinkage/swelling behaviour
is a complex phenomenon typical, but not exclusive, to
The designer should calibrate any numerical model
ground with a high content of clay minerals. Certain
against independent information or calculations using:
clay minerals swell or shrink significantly (up to 65% in
a) simplified hand calculations using engineering volume) when subject to changes in water content.
first principles;
b) design calculations using analytical or empirical 11.7.4.4 When undertaking analysis of the segmental
methods; lining in swelling or creeping ground the designer
c) simplified numerical model (other than the actual should assess and document long-term creep
model) that can be calibrated against other deformations of the lining, as well as additional
methods; and swelling pressures as measured in laboratory tests.
d) back analysis of case history data from publications
11.7.4.5 When considering ground creep, the designer
and conference proceedings of actual movements/
should use creep laboratory tests to calibrate advanced
measurements in similar ground conditions, with
constitutive models.
similar structures and construction.
NOTE Consideration of the swelling and creep
mechanisms for tunnel structures is covered in the
11.7.4.2 Parameters to calibrate
US Department of Transportation Technical Manual
During the calibration process of the numerical for Design and Construction of Road Tunnels – Civil
model the designer should investigate and document, Elements [38].
as a minimum:
a) constitutive ground model;
b) drainage and groundwater flow;
c) ground stresses and ground reactions;
d) lining average hoop force; and
e) lining deformation profile and maximum
distortions.
11.8 Junctions and interface with 11.8.1.3 When designing junctions in weak water-bearing
existing assets ground, the designer should specify ground improvement
techniques as possible measures to allow the safe
11.8.1 Analysis principles for junctions construction of the junction and provide additional
NOTE 1 The design of junctions is considered to be one restraint to the segmental lining close to a junction.
of the most challenging tasks in tunnel lining design
in soft ground. This is due to the complex construction 11.8.1.4 When designing the ground improvement
sequence and high proportion of ground-structure techniques, the designer should carry out iterations and
interaction, as well as the interaction between various sensitivity checks. The designer should specify on-site
structures often built using different construction verification of in-situ improved ground parameters. This
methodologies and at different times. should be carried out with sufficient time in advance of
the construction to modify the design, if necessary.
NOTE 2 For segmental lining design, the most common
case is the design of a junction between a segmental 11.8.1.5 When designing the junctions, the designer
lining and a cross passage, which includes analysis should allow flexibility in the design to cater for
of the stability of the segments next to the opening, potential contingency measures to be applied.
temporary works for the cross passage excavation and
the collar structure linking the segmental lining to the 11.8.1.6 When designing the junctions, the designer
secondary lining of the cross passage. should optimize the geometry and size of the excavation
and keep the opening size as small as possible for both
11.8.1.1 Due to the relatively high deformations and operational and construction requirements.
loads experienced by both the ground and lining, the
designer should assess and document the non-linear, 11.8.1.7 The designer should take account of the
elasto-plastic behaviour of the ground and structure, excavations required during construction of the
and model the junction according to the findings. openings in the design of the segments.
NOTE 2D analytical methods such as the ‘hole-in-plate’ 11.8.3.2 When modelling openings, the designer should
Kirsch [39], Timoshenko [40], Roark [41] solutions or take into account the joints between the concrete
strut-and-tie models as well as 2D numerical solutions, segments or any temporary support that is provided to
provide a means for estimating the flow of stresses support the opening.
around a junction by reducing the geometry to a NOTE 1 An example of a bedded spring shell model
2D plane stress projected solution. The 2D analytical for an opening in a segmental lining with internal
method can be used to check feasibility of the junction temporary support is given in Figure 17.
design when reasonably conservative assumptions are
NOTE 2 For a drained excavation, seepage forces act
set for the analysis. However, the 2D analytical method
on the perimeter of the excavation while the water
can have limited capability in considering complex
pressure is reduced providing less overall confinement.
stress flow and can be unable to provide integrated
Seepage analyses are usually carried out with simplified
behaviour around the junction. The selection of a 2D
analytical methods or full numerical modelling and
or 3D approach is dependent on the complexity of the
provide a key input to address the behaviour around
problem and is to be assessed by the designer on a
the junction excavation.
project-specific basis.
NOTE 3 The interaction of the excavations can result
However, the 2D analytical method can have limited
in an extensive plastic zone. This plastic zone can
capability in considering complex stress flow and might
result in significant non-linear behaviour and stiffness
be unable to provide integrated behaviour around
degradation, which can only be fully captured by 3D
the junction. The selection of a 2D or 3D approach is
numerical modelling using advanced constitutive models.
dependent on the complexity of the problem and is to
be assessed by the designer on a project-specific basis.
Figure 17 – Example of a bedded shell model
for an opening in a segmental lining with
11.8.3 3D bedded spring shell models internal temporary support
11.8.3.1 Where the results of the 2D analyses are not
conclusive, the designer should carry out 3D analyses
for the detailed design of a junction.
NOTE 1 The use of 3D bedded spring shell models
can be advantageous in the event of localized load
discontinuities such as piled foundations close to the
segmental lining.
NOTE 2 The use of 3D bedded spring shell models for
junction design offers a significant benefit over 2D
analytical and numerical solutions. Although limited in
their ability to model ground-structure interaction, they
are able to capture the full 3D load path in the lining,
as well as estimate tunnel deformations and determine
ground reactions. 3D bedded spring shell models can
also be convenient to use in certain situations such
as when full-slip is assumed at the ground-structure
interface. They are much simpler and quicker to
construct than full numerical analyses, and allow
modelling of the structure in detail.
Annex A (normative)
Design management
Category 1 Designs can be checked in the same • Simple structures, designed using standard
group as that which prepared the design, methods of analysis, or consisting of standard
but by a person other than the designer. elements where the design of the elements has
been previously checked.
• Checking against design calculations and
assumptions, and critically considering whether
the base assumptions are valid.
Category 2 Designs can be checked in the designer’s • All works not included in Category 1, except
office by a separate group which has not those of a complex nature which are included in
been involved in the original design or by Category 3.
an independent organization.
Category 3 Designs can be checked by an indepen- • Complex or unusual designs, and designs
dent organization with the competence involving the following features:
and resources to perform the check and –– high degree of redundancy;
to the acceptance of the project manager.
–– high financial risks;
–– high health and safety risk;
–– high environmental pollution risks;
–– significant risk to third-parties; and
–– where required by a third party.
A.4 Design responsibilities for A.5.3 At the beginning of a project, the client, the
segmental tunnels designer and/or the contractor should determine and
agree in writing the types and number of deliverables
The client should meet, discuss with the designer and/ required at each stage to suit the project characteristics,
or contractor, and allocate and document design the complexity of the project, the interfaces with
responsibilities for the segmentally-lined tunnel, based external stakeholders and their individual requirements.
on the project’s contractual arrangements.
NOTE 1 The design responsibilities can rest either with A.5.4 At the beginning of a project, the client and the
the design and build contractor or the employer’s designer should develop and agree in writing a hierarchy
designer. of documents such that the general requirements that
NOTE 2 When segmentally-lined tunnel lining design is are common to many design submissions are captured
undertaken by the employer’s designer, the contractor’s in one document and subsequent submissions reference
early engagement to refine the design to suit the the common documents.
individual contractor’s particular requirements can be NOTE This avoids repetition of contents (i.e. cut and
considered. This approach was used for High Speed 1 paste) in deliverables.
(Channel Tunnel Rail Link) and Crossrail1 projects.
A.5.5 The designer should submit the design in the
optimum number of deliverables possible taking
A.5 Design deliverables account of design approval/acceptance delay risk.
NOTE 1 The client might ask for additional submissions
A.5.1 The designer should submit deliverables to the
from the designer before signing off the design.
client in line with the agreed approval/acceptance
process (see A.2.2). NOTE 2 The complexity of managing the acceptance
process tends to increases in proportion to the number
A.5.2 The client should select a competent individual of deliverables.
(see A.1) from within their organization, or secure
the services of professionals to review the design for
conformance to the project requirements. A.6 Health and safety
Design management of tunnel lining design in health
and safety aspects should be in accordance with:
a) BS 6164;
b) BS EN 16191; and
c) BS EN 12110.
NOTE Attention is also drawn to the CDM Regulations
2015 [1].
Annex B (informative)
Closed-form solutions for static analysis of tunnel lining
in soft ground
Table B.1 contains a summary of the closed-form
solutions suggested for the static analysis of a tunnel
lining in soft ground with associated advantages and
disadvantages. See 11.5 and 11.6 for further details.
Table B.1 – Closed-form solutions for static analysis of tunnel lining in soft ground
Einstein and Schwartz • Accounts for lining/joint flexibility • Circular cross-section assumed
(1979) [48] • Considers the relative stiffness • Need to derive distortional loads
between the ground and lining from effective stresses, then add
• Can model either external loading or water
excavation unloading conditions • Elastic
• Well suited to preliminary design • Support wished-inplace
and design adaptation during • Contradiction with the assumption of
construction plane strain
NOTE The original equations of the closed form solutions set out in Table B.1 are presented for coefficient of
earth pressure at rest K0≤1.0. It is advised that care be taken when K0>1.0, as the original equation needs to be
modified to suit the ground loading condition.
Annex C (informative)
Convergence-confinement method (CCM) in segment
lining design
C.1 General When equilibrium is reached between the two curves as
shown in Figure C.1, the pressure acting on the tunnel
The convergence-confinement method provides a lining can be calculated as the pressure at equilibrium.
relationship between the state of stress around an This value is lower than the in-situ stress and the so
excavated profile as a function of the radial convergence. called critical support pressure, pcr (which is the state of
stress of the ground when the tunnel is installed and is
This information is collected in the ground reaction
equal to (1-l) multiplied by the in-situ stresses).
or GRC. Longitudinal displacement profile and GRC
as illustrated in Figure C.1 are required to relate Further details on the use of the convergence-
deformations of the excavated tunnel wall at successive confinement method for tunnel lining design are given
stages in the analysis to the actual physical location in AFTES, Recommendations on the convergence-
along the tunnel axis. This provides a percentage of confinement method [50].
the in-situ load that is acting on the lining at any point
from the face and in particular at the distance where Due to the theoretical formulation of the convergence-
the lining is installed (point with radial deformation uso). confinement method, the ground-lining interface is
This percentage at a predefined distance from the face, not explicitly accounted for and full-bond is implicitly
such as the point of installation of the lining for a TBM assumed.
tunnel, is defined as the ground relaxation factor (l).
A significant disadvantage of the convergence-
The ground reaction curve can be used in conjunction confinement method as formulated using analytical
with the support characteristic curve. The latter solutions is the inherent assumption that K0 =1. The
provides the internal support pressure that can be designer needs to consider this limitation during design.
carried by the lining when the lining is installed. The
use of the closed-form solutions provide a simplified
method to obtain an estimate of ground loads with the
convergence-confinement method approach.
C.2 Applicability of the convergence- High l-factor occurs with large round lengths and/or
confinement method in numerical late installation of tunnel lining.
Annex D (informative)
Six-stage Gate process
Table D.1 – Suggested six-stage Gate process for tunnel lining design
Gate 4 Detailed design This includes full sets of calculations, and design and check
certificates. It includes or references all the information
required for construction. Some documents such as
specifications can only be submitted at a Gate 4 stage. An
SDR and an IDR are also appropriate at this stage
Gate 5 Construction stage Address any issues raised on the Gate 4 submission
Bibliography
[11] HUDSON, J. A. and HARRISON, J. P. Engineering [25] HIGHWAYS ENGLAND. Design Manual for Roads
Rock Mechanics – An introduction to the Principles. and Bridges, Volume 2, Highway Structures Design
Oxford: Elsevier, 1997 (Substructures and Special Structures) Materials, Section
2 Special Structures, Part 9, BD 78-99 Design of Road
[12] PERRY, J. and WEST, G. Sources of Information Tunnels. UK: Highways Agency, Stationery Office, 1999
for Site Investigations in Britain, Report 192 (Revision
of TRL Report LR 403). Crowthorne, UK: Transport [26] INSTITUTION of CIVIL ENGINEERS. Sprayed concrete
Research Laboratory, 1996 linings (NATM) for tunnels in soft ground, ICE design
and practice guides. London: ICE, 1996
[13] MUIR WOOD, A. Tunnelling: Management by
Design. E & F N Spon, London and New York, 2000 [27] ASSOCIATION FRANCAISE DES TUNNELS ET DE
L’ESPACE SOUTERRAIN (AFTES). Recommendations for
[14] CLAYTON, C. R. I., SIMONS, N. E. and MATTHEWS, the design, sizing and construction of precast concrete
M. Site Investigations, Granada Technical Books, segments installed at the rear of a tunnel boring
Manchester, 1982 machine (TBM). Paris, France: AFTES, 1997 (translated to
English in 1999)
[15] MAYNE, P.W. and KULHAWY, F.H. Ko-OCR
Relationships in Soil. In: Journal of the Geotechnical [28] ACI COMMITTEE 544. Report on Design and
Engineering Division. VA, USA: American Society of Civil Construction of Fiber-Reinforced Precast Concrete
Engineers, 1982, Vol. 108, GT6, pp. 851-872 Tunnel Segments, 544.7R-16. Farmington Hills, MI:
ACI, 2016.
[16] SIMPSON, B. Retaining Structures: Displacement
and design. 32nd Rankine Lecture. In: Geotechnique, [29] JAPANESE SOCIETY OF CIVIL ENGINEERS (JSCE).
1992, pp 541-576 The design and construction of underground structures
(in Japanese), Japan Society of Civil Engineers, Tokyo,
[17] ESSEX, R. J. Geotechnical Baseline Reports for Japan, 1977
Underground Construction, Guidelines and Practices.
Reston, Virginia: American Society of Civil Engineers, 1997 [30] BLOM, C.B.M. Design Philosophy of Concrete
Linings for Tunnels in Soft Soils, Ph.D. thesis, Technical
[18] SIMPSON, B. and DRISCOLL, R. Eurocode 7 – A Univ. of Delft, DUP Science, Delft, Netherlands, 2000
commentary. Watford, UK: Construction Research
Communications Ltd, 1998 [31] MORGAN, H. D. A contribution to the analysis of
stress in a circular tunnel. In: Geotechnique 11, 1961,
[19] BAMFORTH, P.B, Enhancing reinforced concrete No.3, pp. 37-46
durability, Technical Report No.61. Camberley, UK:
Concrete Society, 2004 [32] MUIR WOOD, A. The circular tunnel in elastic
ground. In: Geotechnique 25 (1), 1975, 115-127
[20] BRE Construction Division. Concrete in aggressive
ground. Bracknell, UK: BRE, 2005 [33] LEONHARDT, F. Prestressed concrete design and
construction, Chapter 9, Berlin: Wilhelm Ernst & Shon,
[21] CONCRETE SOCIETY (CS). Technical Report No.63, 1964
Guidance for the design of steel-fibre-reinforced
concrete. Camberley, UK: CS, 2007 [34] SZECHY, K. The Art of Tunnelling. Budapest,
Hungary: Akadémiai Kiado, 1970
[22] CONCRETE SOCIETY (CS). Guidance on the use of
macro-synthetic-fibre-reinforced concrete, Technical [35] TERZAGHI, K. Theoretical Soil Mechanics. London: J
Report No.65. Camberley, UK: CS, 2007 Wiley and Sons, 1943
[23] BARROS, J.A.O., CUNHA, V.M.C.F., RIBEIRO, A.F., [36] POTTS, M., ZDRAVKOVIC, L. Finite Element Analysis
ANTUNES, J.A.B. Post-cracking behaviour of steel fibre in Geotechnical Engineering, Thomas Telford, 1999
reinforced concrete. RILEM, In: Materials and Structures
38, 2005, pp. 47-56 [37] ZDRAVKOVIC, L., CARTER, J, Contributions to
Geotechnique 1948-2008: Constitutive and numerical
[24] LONDON UNDERGROUND. Standard 1055, modelling. In: Geotechnique, Vol: 58, 2008, pp. 405-412
Civil Engineering – Deep Tube Tunnels and Shafts.
London: London Underground, 2011
[39] KIRSCH, G. Die theorie der elastizitat und die Further reading
bedurfnisse der festigkeitslehre. In: Verein Deutsche
ANAGNOSTOU, G. and KOVARI, K. Face Stability
Ingenieure, Vol. 42, 1898, pp. 797-807
Conditions with Earth-Pressure-Balanced Shields. In:
[40] TIMOSHENKO, S.P. and WOINOWSKI-KRIEGER, S. Tunnelling and Underground Space Technology, 1996,
Theory of Plates and Shells, 2nd ed., McGraw-Hill, New Volume 11, No. 2.: 165-173.
York, 1959
ASSOCIATION OF GEOTECHNICAL AND
[41] ROARK, R. J. and YOUNG, W. C. Formulas for Stress GEOENVIRONMENTAL SPECIALISTS. Electronic Transfer
and Strain, 5th ed. New York, USA: McGraw-Hill, 1975 of Geotechnical and GeoEnvironmental. Data Version,
Fourth Edition. Kent: AGS, 2011.
[42] BRITISH TUNNELLING SOCIETY. Closed-face
tunnelling machines and ground stability, Thomas BLOCKLEY, D. I. The New Penguin Dictionary of Civil
Telford Books, London, 2005 Engineering. London: Penguin Books, 2005.
[43] BRITISH TUNNELLING SOCIETY. Monitoring BS 6100-3:2007, Building and civil engineering –
Underground Construction – A best practice guide, ICE Vocabulary – Part 3: Civil engineering – General
Publishing, London, 2011
BS EN 12715:2000, Execution of special geotechnical
[44] ROYAL INSTITUE OF BRITISH ARCHITECTS. RIBA work – Grouting
Plan of Work 2013 Overview, RIBA, London, 2013
BS EN 12716:2001, Execution of special geotechnical
[45] ROYAL INSTITUE OF BRITISH ARCHITECTS. Guide work – Jet grouting
to Using the RIBA Plan of Work 2013, RIBA Publishing,
BS EN 14487-1:2005, Sprayed concrete – Part 1:
London, 2013
Definitions, specifications and conformity
[46] HIGHWAYS ENGLAND. Design Manual for roads
BS EN 14487-2:2006, Sprayed concrete – Part 2:
and bridges – Part 1 BD 2/12 Technical Approval of
Execution
Highway Structures UK: Highways Agency, Stationery
Office, 2012
BS EN 14488-3:2006, Testing sprayed concrete – Part 3:
Flexural strengths (first peak, ultimate and residual) of
[47] DUDDECK, H. and ERDMANN, J. On structural
fibre reinforced beam specimens
design models for tunnels in soft soil. In: Underground
Space, Vol.9, 1985, Pergamon Journals Ltd, USA,
BS EN 14488-5:2006, Testing sprayed concrete – Part 5:
pp. 246-259
Determination of energy absorption capacity of fibre
reinforced slab specimens
[48] EINSTEIN, H.H., and SCHWARTZ, C.W. Simplified
analysis for tunnel supports. In: Journal of the
BS EN 1991-1-2:2002, Eurocode 1: Actions on structures
geotechnical engineering division. New York: American
– Part 1-2: General actions – Actions on structures
Society of Civil Engineers, Vol. 105, 1979, GT4,
exposed to fire
pp. 499-518
BS EN 1992-3:2006, Eurocode 2: Design of concrete
[49] MUIR-WOOD and CURTIS, D.J. Discussion on the
structures – Part 3: Liquid retaining and containment
circular tunnel in elastic ground. In: Geotechnique,
structures
Vol. 26, 1976, No. 1, pp. 231-237
BS EN 1994-1-1:2004, Eurocode 4: Design of composite
steel and concrete structures – Part 1-1: General rules
and rules for buildings
BS EN 934-5:2007, Admixtures for concrete, mortar HOEK, E., CARRANZA-TORRES, C., DIEDERICHS, M.S.,
and grout – Part 5: Admixtures for sprayed concrete and CORKUM, B. Integration of geotechnical and
– Definitions, requirements, conformity, marking and structural design in tunnelling. Proceedings University
labelling of Minnesota 56th Annual Geotechnical Engineering
Conference. Minneapolis, 2008, 1-53.
CHANG, Y. and STILLE, H. Influence of early age
properties of shotcrete on tunnel construction INTERNATIONAL TUNNELLING ASSOCIATION. General
sequences, Shotcrete for Underground Support report on conventional tunnelling, ITA Working Group
VI, Proceedings of the Engineering Foundation on Conventional Tunnelling. ITA Report No.002, 2009.
Conference, Niagara-on-the-Lake, Canada. New York:
American Society of Civil Engineers, 1993. INTERNATIONAL TUNNELLING ASSOCIATION. ITA Report
– Shotcrete for Underground Support: a State-of-the-
CHEUNG, K., WEST, K., YEOW, H.C. and SIMPSON, B. Do art Report with Focus on Steel-fibre Reinforcement. In:
Eurocodes make a difference? In: Geomechanics and Tunnelling and Underground Space Technology, 1992,
Tunnelling, 2010, Vol. 3, No. 1: 35-47. Volume 7, No. 4: 388-391.
CUR. Recommendation 111 Steel fibre reinforced INTERNATIONAL TUNNELLING ASSOCIATION. ITAtech
concrete industrial floors on pile foundations – Design Design Guidance for Sprayed Applied Waterproofing
and construction. Netherlands, 2010. Membranes. ITAtech Activity Group – Lining and
Waterproofing, ITAtech Report No.2, 2013.
DAUB. Recommendations for the Design, Production
and installation of Segmental Rings. DAUB: Cologne, INTERNATIONAL TUNNELLING ASSOCIATION. ITAtech
2013. Design Guidance for Precast Fibre Reinforced Concrete
Segments. ITAtech Activity Group Support, ITAtech
DAVIS, E.H., GUNN, M.J., MAIR, R.J. and SENEVIRATNE, Report No.7, 2015.
H.N. The stability of shallow tunnels and underground
openings in cohesive material. In: Geotechnique, 30, JOHN, M., and MATTLE, B. Design of tube umbrellas. In:
1980, No. 4: 397-416. Magazine of the Czech Tunnelling Committee and the
Slovak Tunnelling Association, 2002, Volume 11, No. 3.
DEUTSCHER AUSSCHUSS FÜR STAHLBETON. Technical
Rule on Steel Fibre Reinforced Concrete Draft. Berlin: KLAPPERS, C., GRÜBL, F. OSTERMEIER, B. Structural
DafStb, 2012. analyses of segmental lining - coupled beam and spring
analyses versus 3D-FEM calculations with shell elements.
EUROPEAN FEDARATION OF NATIONAL ASSOCIATIONS In: Tunnelling and Underground Space Technology,
REPRESENTING FOR CONCRETE. European Specification 2006, Volume 21: 254-255.
for Sprayed Concrete. EFNARC, 1996.
LAWRENCE, C., TAYLOR, J. Design of tunnel cross-
FANG, Y.S., LIN C.T., LIU, C., CHENG, K.H., SU, C.S., passages. RETC, 2011: 119-136.
CHEN, T.J. Construction of a Cross Passage between Two
MRT Tunnels. Proceedings of the 18th International LECA, E., and DORMIEUX, L. Upper and lower bound
Conference on Soil Mechanics and Geotechnical solutions for the face stability of shallow circular
Engineering. Paris, 2013. tunnels in frictional material. In: Geotechnique, 48,
1990, No 4: 581-606.
GABA, A.R., SIMPSON, B., POWRIE, W., and BEADMAN,
D.R. Embedded retaining walls – guidance for economic LUNARDI, P. The design and construction of tunnel
design. C580. London: CIRIA, 2003. using the approach based on the analysis of controlled
deformation in rocks and soils. Tunnel and Tunnelling
HARDING, A., CHAPPELL, M., BURDICK, M., KRULC, International special supplement, ADECO-RS approach,
M. Opening supports to segmental linings: A novel May 2000.
shotcrete support solution. In: Mining Engineering,
2014, Volume 66, No. 6: 102-102. OWEN, G.N. SCHOLL, R.E. Earthquake engineering of
large underground structures, Report no. FHWA/RD-
80/195. Federal Highway Administration and National
Science Foundation, 1981.