Tunnelling and Underground Space Technology: Zili Li, Kenichi Soga, Peter Wright
Tunnelling and Underground Space Technology: Zili Li, Kenichi Soga, Peter Wright
Tunnelling and Underground Space Technology: Zili Li, Kenichi Soga, Peter Wright
a r t i c l e i n f o a b s t r a c t
Article history: A series of 3D soil–fluid coupled finite element analyses was conducted to examine the long-term tunnel
Received 18 January 2015 behaviour of an old cast-iron cross passage in stiff London clay. In the proposed geotechnical FE model, an
Received in revised form 27 May 2015 advanced critical state constitutive model was employed to simulate complex soil behaviour, whereas
Accepted 10 July 2015
the details of the tunnel linings was simplified using shell elements. The computed time-dependent soil
Available online xxxx
load derived from the geotechnical model was then applied to a structural finite element model where
the details of the cross passage structure such as bolted-joints and tunnel segments were explicitly mod-
Keywords:
elled. This proposed semi-coupled soil-structure model shows agreement against field observations and
Cast-iron cross passage
Tunnel opening
it was found in this particular case that the structural condition evaluated from the FE model is more crit-
Long-term ground response ical than that of the conventional bedded ring method. Results show that the surface ground settlement is
3D soil arching governed mainly by the twin tunnel construction and the presence of the cross passage does not increase
Semi-coupled soil-structure model the settlement. On the other hand, the construction of a cross passage affects the structural performance
of the adjacent running tunnel in both short term (undrained) and long term (soil consolidation). In par-
ticular, the critical location is identified to be the tunnel segment adjacent to the opening at the axis level
and its stresses and deformation increase with consolidation time.
Ó 2015 Elsevier Ltd. All rights reserved.
1. Introduction tunnel structures. In this approach, the soil loading applied to tun-
nel lining is estimated using a set of reaction springs that considers
London has one of the most extensive networks and oldest sec- the interaction between the soil and the tunnel (i.e. the conven-
tions of railway tunnels in the world (Wolmar, 2004). The tional bedded ring method) (Klappers et al., 2006; Li et al., 2014,
long-term performance of old tunnels, which is associated with submitted for publication). However, such springs are not capable
the change in earth pressure during soil consolidation due to seep- of simulating the complexities of soil behaviour such as soil stress
age into the tunnel, is of great concern (e.g. Mair, 2008). In partic- history, anisotropy and the changes in soil stiffness and earth pres-
ular, the engineering conditions of old cross passages between sures due to seepage induced consolidation around the tunnel in
adjacent cast-iron tunnels are found to be critical by recent assess- the long-term.
ment (Wright, 2010). The long-term behaviour of a tunnel in London clay was inves-
To assess the conditions of a tunnel, analytical equations tigated by Wongsaroj et al. (2007) using soil–fluid coupled finite
derived from 2D plane-strain models are widely adopted element analysis, which allowed the influence of soil strata and rel-
(Murakami and Koizumi, 1980; Duddeck and Erdmann, 1985; ative soil-lining permeability to be considered (Wongsaroj et al.,
RTRI, 1997). Such conventional 2D methods allow engineers to 2013). Later Laver (2010) conducted a further study to account
examine the general behaviour of a full tunnel ring, but they fail for the effect of twin tunnels interaction on long-term behaviour
to investigate the performance of some special structural features and identified that the interaction effect depends on the spacing
such as cross passage openings. To overcome this problem, finite between the two tunnels and cover depth. Many of the past
element analysis is often used to account for the details of such researches (e.g. Addenbrooke, 1996; ITA, 2000; Laver, 2010) pri-
marily focused on ground response induced by tunnel excavation
rather than investigating the tunnel lining behaviour subjected to
⇑ Corresponding author.
long-term changes in earth pressures. In particular, less attention
E-mail addresses: tongjilzl@gmail.com (Z. Li), ks207@cam.ac.uk (K. Soga), Peter.
Wright@ch2m.com (P. Wright).
has been paid on the long-term tunnel behaviour of cross passage
1
Formerly Tube Lines Ltd, 15 Westferry Circus, Canary Wharf, London E14 4HD, section, which is often more structurally critical than the other
UK. non-cross passage running tunnel sections.
http://dx.doi.org/10.1016/j.tust.2015.07.005
0886-7798/Ó 2015 Elsevier Ltd. All rights reserved.
Z. Li et al. / Tunnelling and Underground Space Technology 50 (2015) 152–170 153
Nomenclature
The proposed model takes account of many critical mechanical fea- manner similar to the soil elements, each ring near the cross pas-
tures, such as elastic and plastic anisotropy, small strain stiffness sage was modelled individually, whereas a number of rings were
as well as stiffness degradation. Due to lack of site investigation, modelled together using fewer elements in the remaining area.
the soil properties in each strata were assumed to be typical values To take account of segmental joints, Li et al. (2014) conducted 3D
according to Laver (2010) and Tube Lines (2007) as shown in FE structural analysis, which considered some critical structural
Table 2. Further details of the constitutive model can be found in features explicitly (e.g. tunnel segment, bolted joint) and validated
Wongsaroj (2005) and Laver (2010). against past experimental data (Thomas, 1977), and the results
In the geotechnical model, the tunnel linings were modelled were compared to those computed from the 2D plane strain
using 8-node, double curved thick shell elements. The elements method (LUL, 2003). It was found that the bending stiffness of
were numbered along the tunnel rail direction consecutively. In a bolted cast iron lining can be generally considered as a continuous
Z. Li et al. / Tunnelling and Underground Space Technology 50 (2015) 152–170 155
Table 1
Assumed soil properties (Wongsaroj, 2005; Laver, 2010).
Stratum Bulk density, c (kN/m3) Critical angle of shearing resistance, /cv0 (°) Coefficient of earth pressure at rest, K0 Permeability, k (m/s)
Made Ground 20 25.0 0.6 1 107
London Clay 20 21.0 1.5 2 1011
Lambeth Group 20 27.0 1.5 2 1011
Table 2
Summary of material properties for all soil units (Wongsaroj, 2005; Laver, 2010).
ring with a reduction factor based upon Muir Wood’s formula Table 4
(Muir Wood, 1975), which equals to 0.44 for the case considered Construction stages assumed in FE simulation.
in this study. Construction Description
The lintel and trackbed at the opening section are also struc- stage
turally critical since they transfer the hoop load from the incom- 1 Geostatic
plete rings to the adjacent full rings. In this study, the lintel was 2 Remove the soil inside the running tunnel and reduce 50% of
modelled using 3-node quadratic beam elements, while 20-node the initial stress around the tunnel boundary (undrained)
quadratic solid elements were employed for the trackbed along 3 Place the lining and further reduce the initial stress to be 0%
(undrained)
the tunnel rail direction. The tunnel linings, lintel and trackbed
4 Remove the soil inside the cross passage tunnel and reduce
were modelled as linear elastic-perfectly plastic material and their 50% of the initial stress around the cross passage boundary
properties are summarised in Table 3. The tunnel shell elements (undrained)
and the adjacent soil elements shared the same nodes at the tunnel 5 Place the lining on the cross passage and further reduce the
initial stress to be 0% (undrained)
boundary; the interface was not modelled. This was considered to
6 Soil consolidation (drained)
be acceptable since the tunnel is unlikely to detach or slip away
from the surrounding ground during soil consolidation
(Wongsaroj et al., 2007). The 3D soil–tunnel–fluid coupled model
closely-space twin tunnels. The ground surface settlement builds
consists of 4648 elements and 9368 nodes. The model boundaries
up with the unloading of initial soil stress. When the soil load
were set to minimise the effects on ground response and tunnel
was decreased to 50% of the original overburden pressure, a
behaviour (Wongsaroj, 2005; Laver, 2010).
volume loss was 1.09%. This is in line with the typically measured
volume loss in London clay (Addenbrooke, 1996; Mair, 2008). In
2.2. Tunnel construction and long-term consolidation this study, an empirical reduction ratio of 50% ground pressure
was adopted for deep tunnels in stiff ground as suggested by
The construction of old cast-iron cross passages in London Muir Wood (1975) and Duddeck and Erdmann (1985).
Underground tunnel were carried out many decades ago and the After the twin tunnel construction, a cross passage was con-
detailed knowledge of tunnelling construction is not available structed in the model. All the construction stages in this study
owing to the absence of historical records. For brevity, a simplified were assumed to be in undrained conditions. Compared to the
construction stage was assumed in the FE modelling and sum- twin-tunnel construction stage, the effect of cross passage con-
marised in Table 4. It was thought that the twin tunnels were likely struction on ground deformation is very small as shown in Fig. 3b.
to be constructed first before the excavation of the cross passage. Tunnel drainage was then allowed in the post-construction
To consider the soil load redistribution induced by excavation, stage. Recent studies (e.g. Wongsaroj et al., 2013) identified the
the elements of excavated soil were removed and the initial nodal importance of soil–tunnel drainage condition on the long-term
loads around the tunnel boundary was reduced to a certain per- ground response due to tunnelling. That is, the magnitude of tun-
centage (e.g. 50%). Then the lining ‘shell’ elements were attached nelling induced consolidation depends on tunnel lining permeabil-
to the tunnel boundary. ity in relation to soil permeability and drainage distance. To
Fig. 3a shows the ground surface settlement immediately after quantify the consolidation effect, Laver (2010) proposed a radial
tunnel construction at the symmetrical plane of the cross-passage. flow model as shown in Fig. 4 and defined the following relative
The maximum ground settlement appears at the centre of the cross soil-lining permeability RP.
passage, where significant soil strain occurs between the two
DT kl 2C clay
RP ¼ ln þ1 ð1Þ
2t l ks DT
Table 3 kl
Summary of material properties for tunnel structures (after Thomas (1977), Gilbert KT ¼ ð2Þ
(1977) and Tube Lines (2005b)). t l cw
Specification Cast iron Steel Concrete where DT is the tunnel diameter, kl is the lining permeability, tl is
lining lintel trackbed the lining thickness, kS is the soil permeability, Cclay is the clay cover,
Young’s modulus (GPa) 100 200 24 KT is the lining seepage coefficient, and cw is the bulk unit weight of
Poisson’s ratio 0.26 0.28 0.2 water.
Tensile strength (MPa) 180 235 2.5
By increasing the lining seepage coefficient KT, the tunnel
Compressive strength (MPa) 600 235 25
becomes more permeable in comparison to the surrounding
156 Z. Li et al. / Tunnelling and Underground Space Technology 50 (2015) 152–170
(a) Ground surface settlement due to the unloading of initial soil stress
in the soil flow into the tunnel. But when the pore pressure is neg-
ative, it cuts off the flow since no water is supplied from inside the
tunnel to the soil. Such modelling allows the soil-lining drainage
condition to be modelled more realistically. The parameter RP will
be used in the later section to show the effect of soil consolidation
on the long-term behaviour of a cross passage in stiff London clay.
3. Ground response
pressure becomes zero at the edge of the tunnel lining in the long accompanied by greater volume loss. The volume loss can be as
term. The effective stresses of the soil near the tunnel increase and much as 2.64% for the fully permeable case (i.e. 2.4 times the short
thus the soil consolidates, which leads to long-term ground settle- term volume loss), indicating the significance of the long-term
ment until a steady-state flow condition is reached. ground settlement. Wongsaroj et al. (2013) normalised the com-
To compare the ground response of twin tunnels with and with- puted maximum surface settlement against the impermeable and
out a cross passage, Fig. 6 plots the ground surface settlements at fully permeable cases using the following equation:
the long-term steady state for the two cases. There is little differ-
ence in the surface settlement profiles of the two cases. Also, the Sc maxðssÞ Sc maxðssiÞ
DS ¼ ð3Þ
differential settlement along the longitudinal direction is small as Sc maxðsspÞ Sc maxðssiÞ
shown in Fig. 6b. This indicates, for closely-spaced twin tunnels,
the effect of cross passage on surface settlement may not be signif- where DS is dimensionless settlement, Sc max(ss) is the consolidation
icant from the engineering assessment point of view. Hence, for component of the maximum surface settlement at steady-state,
brevity, only the surface settlement directly above the cross pas- Sc max(ssi) = Sc max(ss) for an impermeable lining case, whilst
sage is examined in the follow sections. Sc max(ssp) = Sc max(ss) for a fully permeable lining case.
In this study, the permeability of the lining was varied so that Fig. 7b indicates the tunnel is impermeable (i.e. DS = 0, maxi-
the relative soil-lining permeability RP ranged between 105 and mum ground heave) if RP is smaller than 101. As the lining
106. Fig. 7a shows how the ground surface consolidation becomes more permeable, the DS increases and finally levels off
settlement changes with different lining permeability. The more when RP is bigger than 103 (i.e. fully permeable). Based on the
permeable the lining is, the more settlement builds up, which is results of a series of numerical analysis of the long-term ground
158 Z. Li et al. / Tunnelling and Underground Space Technology 50 (2015) 152–170
(i) Cross passage (ii) Big tunnel (D=9.8m) (iii) Small tunnel (D=3.8m)
(d) Pore water pressure profile due to seepage into the tunnel
Fig. 7. Ground surface settlement at different relative soil-lining permeability.
on the two soil columns at the sides of the tunnel. As the soil col-
umns shorten with time during consolidation, the soil columns
retract support, which results in more load transferred through
the lining.
For the closely-spaced twin tunnels in Northern Line, there are
three soil columns along the cross-section; one between the two
tunnels and two at the other two sides. The middle soil column
(see Column I in Fig. 10c) consolidates more rapidly between the
twin tunnels than the soil columns at the outer sides (Column II)
(i.e. an equivalent shorter drainage path). This differential consoli-
dation condition may cause soil loading along the lining to be
asymmetric.
Fig. 11a gives an illustration of the segmental lining in detail.
Fig. 8. Change in tunnel diameter at the full ring section during soil consolidation Along the lining, six tunnel elements were numbered
(Day 0 is the end of the cross passage tunnel construction). anti-clockwise starting from crown Segment A, invert Segment C
& D, and then finally back to crown Segment F. In the geotechnical
consolidation on tunnel lining as shown in Fig. 10b. In his mecha- model, each tunnel segment was modelled by two shell elements
nism, the overburden above the lining is sustained by the interac- named using subscript r and l, respectively; for example, shell ele-
tion between three load columns; one on either side of the tunnel ments A.r and A.l represent Segment A (see Fig. 11b). At tunnel axis
(i.e. soil column I & II) and one through the tunnel lining itself. level, Segment B is adjacent to the middle soil column I, whilst
During tunnel excavation in clayed soil, the overburden first relies Segment E is next to the outside soil column II.
160 Z. Li et al. / Tunnelling and Underground Space Technology 50 (2015) 152–170
(a) Long-term increase of hoop thrust (Day 0 is the end of the cross
passage tunnel construction)
Fig. 14. Soil load on different rings in short term and long term.
164 Z. Li et al. / Tunnelling and Underground Space Technology 50 (2015) 152–170
Table 5
Soil load applied on tunnel lining near the cross passage.
(c) (d)
Fig. 17. Structural model of a cast-iron joint: (a) Bolt in a joint, (b) Illustration of nine springs model at X–X cross section, (c) Spring model in rotational load, and (d) Spring
model in shear load (Li et al., 2014).
pressure applied to the lining. In this study, the external earth little tensile stress is found at most area of the segment. In partic-
pressure was considered to be 60% full overburden in both vertical ular, significant stress concentration occurs at the top radial flange
and horizontal direction based upon typical tunnel measurements (i.e. the arrowed area) due to the contact pressure transferred from
summarised by Addenbrooke (1996) and Tube Lines (2008). The the lintel. This computed tunnel behaviour is also noted in the field
applied external earth pressure will be sustained by the soil– observation as indicated by the dotted white circle in
tunnel interaction: usually, majority of the pressure (e.g. 90% Fig. 20a and b, where the segment under the lintel develops a local
according to the force factor n = 0.9) is carried by the tunnel lining distortion. In this figure, it is also found that the web of the lintel
(Duddeck and Erdmann, 1985; Li et al., submitted for publication), moves away from the soil side towards the tunnel side (see the
whilst the rest is by the soil springs. In this study, the soil spring red circle), which is illustrated in Fig. 20c. Likewise, the FE model
stiffness is 120 MPa/m for Stage 3 immediately after construction predicted a similar structural deformation mode of the lintel (see
and decreases to 60 MPa/m for Stage 4 during long-term consolida- Fig. 20d). In addition, large bending deformation occurs at the
tion, based upon relative soil–tunnel stiffness (Duddeck and end of the lintel as shown in Figs. 20 and 21, which is caused by
Erdmann, 1985; USACE, 1997; Tube Lines, 2007). the lintel-segment contact pressure; 7.9 mm bending deformation
In the first two stages (i.e. self-weight loading stage and soil occurs at left end (Fig. 21a), while 5.6 mm is at the right end
loading stage), all the linings consisted of full rings and the two (Fig. 21b). The computed tunnel model predicts a bending
approaches resulted in similar stress states. In the last two stages deformation of 6.9 mm generally in agreement against field obser-
(i.e. tunnel opening stage and long-term reloading stage), several vations (see Fig. 21c).
tunnel segments were removed to model cross passage opening Fig. 22 shows the observed dislocation of the segments above
and the soil subsequently consolidated. The soil spring-structure the opening modelled in this study. The inclination of the glass
model predicted a stress state within the permissible range both (see Fig. 22a and b) indicates that the segments above the lintel
in compression and tension. On the other hand, the semi-coupled moves inward to the tunnel about 2 mm over many decades after
soil-structure model gave greater stresses than the soil construction. The observed segment movement is also noted in the
spring-structure model because more soil load was applied to FE model (see as circled in Fig. 22c and d).2 At the full ring section,
Ring 3 due to the longitudinal soil arching effect described in the the rings squat by having positive horizontal displacement (red
previous section. This was also noted in the internal forces. The colour) at the right side of the tunnel and negative horizontal dis-
bending moments and hoop thrusts in Ring 3 for the two cases placement on the opposite side. At the cross passage section, more
are shown as shown in Fig. 18b and c, respectively. Again the horizontal movement builds up (light blue to dark blue colour) at
semi-coupled soil-structure model predicted greater moment and the opening side due to its weaker structural integrity after the
hoop thrust than the soil spring-structure model when the cross removal of tunnel segments. At the opposite of the opening side
passage was constructed. (the right side), the positive horizontal displacement reduces
Fig. 19 shows the compressive and tensile stress contours in the slightly. This shows that the tunnel at the cross passage section
critical Segment B of Ring 3 predicted by the semi-coupled
soil-structure model. Large compressive stress appears at the cir-
cumferential flange (see the black circle in Fig. 19b) and build 2
For interpretation of color in Fig. 22, the reader is referred to the web version of
ups in the long term due to the earth pressure reloading, whereas this article.
166 Z. Li et al. / Tunnelling and Underground Space Technology 50 (2015) 152–170
shifts towards the opening as shown schematically in the plan view The soil load then transfers through the end of the lintel to the seg-
given in Fig. 22e. Further detailed discussion on the cast-iron tunnel ment underneath. The significant lintel-segment contact pressure
behaviour can be found in Li et al. (2014, submitted for publication). results in local deformation and stress concentration at the contact
In summary, the soil pressure at the tunnel opening section area. In the segment, the transferred overburden load causes sig-
overloads the lintel and bends its web away from the soil side. nificant compressive stress at the circumferential flange. When
Z. Li et al. / Tunnelling and Underground Space Technology 50 (2015) 152–170 167
the soil consolidates (Stage 4), the soil load applied to the lining long term in stiff London clay. The computed ground response is
increases, which leads to further stresses and movement of the in line with the findings of previous efforts (Wongsaroj, 2005;
structure. Laver, 2010; Wongsaroj et al., 2013), while the calculated tunnel
Ideally, more sophisticated quantitative assessment of the com- behaviour shows agreement with field measurement (e.g. Tube
puted tunnel behaviour should be made against the field measure- Lines, 2005b). Results provide new insights into the mechanism
ment. However, most of the cast-iron cross passages in London of the long-term behaviour of a cross passage and the main conclu-
Underground were constructed more than 100 years, whereas the sions can be drawn as follows:
field monitoring data or construction records, if they were docu-
mented in the past, are now not available. The critical cast-iron (1) For closely-spaced twin tunnels, the effect of a cross passage
cross passage in Northern Line investigated in this study provided on the long-term surface ground settlement is limited. That
an opportunity to assess the potential long-term performance of is, the soil consolidation due to drainage into twin tunnels is
cross passage tunnels, whereas similar critical cross passage site much greater than the additional drainage effect by the cross
or relevant case study, to the authors’ best knowledge, is very rare. passage. The hydraulic field of the twin tunnels behaves
more like a large circular tunnel case circumscribing the
6. Conclusions whole cross passage area.
(2) After tunnel construction, the tunnel lining develops a fur-
A series of three dimensional soil-pore fluid coupled FE analyses ther squatting as the surrounding soil consolidates. The
was conducted to investigate the long-term behaviour of a cast magnitude of ovalisation at the cross passage section is less
iron tunnel cross passage in London Underground Tunnels. The than that of the full ring section. When segments are
computed soil load acting on the tunnel lining was applied to a removed, the flexible horizontal stiffness allows soil pres-
structural model that included the structural details such as sure to push it back to the original circular shape. The extent
flanges, pans and bolts. This allowed to examine the complex of influence of cross passage construction is generally
soil-structure interaction of the cross passage in both short and localised within five times of the opening size.
Z. Li et al. / Tunnelling and Underground Space Technology 50 (2015) 152–170 169
Fig. 22. The inward movement of the opening: (a) the left end of the opening, (b) the right end of the opening, (c) the overview of the inward movement in the FE model, (d)
the local inward movement (the distortion is magnified to 10 times), and (e) Illustration of the tunnel distortion (plan view).
170 Z. Li et al. / Tunnelling and Underground Space Technology 50 (2015) 152–170
(3) After cross passage construction, a 3D soil arching mecha- Dimmock, P.S., 2003. Tunnelling-Induced Ground and Building Movement on the
Jubilee Line Extension. Ph.D. Thesis, University of Cambridge.
nism develops and the soil adjacent to the cross passage sec-
Duddeck, H., Erdmann, J., 1985. On structural design models for tunnels in soft soil.
tion carries the additional overburden load and positive Underground Space 9, 246–259.
excess pore pressure develops. However, as the soil consoli- Gilbert, G.N.J., 1977. Engineering data on grey cast irons – SI units. BCIRA
dates, the overburden load gradually transfers back to the Alvechurch, Birmingham.
I.T.A. Working Group No. 2. (ITA), 2000. Guidelines for the design of shield tunnel
crown section of the tunnel opening, which is then trans- lining. Tunnelling Underground Space Technology, vol.15, pp. 303–331.
ferred to the ring next to the opening section via the lintel. Klappers, C., Grubl, F., Ostermeier, B., 2006. Structural analyses of segmental lining-
A tunnel load-analogy of a ‘‘table’’ with four load columns coupled beam and spring analyses versus 3D-FEM calculations with shell
elements. Tunn. Undergr. Space Technol. 21, 254–255.
was proposed to account for the 3D soil arching mechanism Laver, R., 2010. Long-Term Behaviour of Twin Tunnels in London Clay. Ph.D. Thesis,
observed in the geotechnical model. The University of Cambridge, Cambridge, UK, 2010.
(4) The tunnel segment adjacent to the opening at the axis level Lee, K.M., Hou, X.Y., Ge, X.W., Tang, Y., 2001. An analytical solution for a jointed
shield driven tunnel lining. Int. J. Numer. Anal. Meth. Geomech. 25 (4), 365–390.
is the most critical structural section. To better simulate the Li, Z., Soga, K., Wang, F., Wright, P., Tsuno, K., 2014. Behaviour of cast-iron tunnel
soil–tunnel interaction, a semi-coupled soil-structure model segmental joint from the 3D FE analyses and development of a new bolt-spring
that applied the soil load computed in the geotechnical model. Tunn. Undergr. Space Technol. 41, 176–192.
Li, Z., Soga, K., Wright, P. 2014b, Behaviour of Cast-Iron Bolted Tunnels and their
model directly to the detailed structural model was used. Modelling. Tunn. Undergr. Space Technol. (submitted for publication).
The computed tunnel behaviour derived from the proposed L.U.L. London Underground Ltd. (LUL), 2003. Review of Engineering Standard E3322
model shows agreement against the field observation and A2 Deep tunnels and shaft – assessment. LUL Report 4058-PMN, London.
Mair, R.J., 2008. Tunnelling and geotechnics: new horizons. Geotechnique 58 (9),
predicts a more critical stress state against the conventional
695–736.
bedded ring method. Results show that the lintel, which is Muir Wood, A.M., 1975. The circular tunnel in elastic ground. Geotechnique 25 (1),
overloaded by the soil pressure at the tunnel opening sec- 115–127.
tion, develops large bending deformation at the web section Murakami, H., Koizumi, A., 1980. On the behaviour of the transverse joints of a
segment. In: The 35th Annual Conference of the JSCE, pp. 73–86. (in Japanese).
as well as the contact area with the segment underneath. Railway Technical Research Institute. (RTRI), 1997. Design Standard for Railway
The lintel-segment contact pressure results in local defor- Structures (Shield-Driven Tunnel). Tokyo. (in Japanese).
mation and stress concentration at the radial flange of the Terzaghi, K., 1943. Theoretical Soil Mechanics. John Wiley and Sons, New York, pp.
66–76.
segment, whilst it transfers the overburden load to the cir- Thomas, H., 1977. Measuring the Structural Performance of Cast Iron Tunnel Linings
cumferential flange, where significant compressive stress in the Laboratory. Geotechnics Division, Building Research Station, Building
occurs. The deformation of the lining increases with time Research Establishment, Department of the Environment. pp. 29–36.
Tube Lines, 2005a. Tunnel Assessment Project Annual Works Plan 2: Historical
as the soil pressure and hoop load increases due to soil con- Study Report, TLL-L001-N416-DTAAWP2-TUN-RPT-00013, London, UK.
solidation. Hence it is important to evaluate the evolution of Tube Lines, 2005b. Deep Tube Tunnel Knowledge & Inspection Programme Annual
the distress in the segments of the ring next to the opening. Works Plan 2, Validation Report Elastic Continuum Analysis, Finite Element
Modelling Ultrasonic Testing, Strain Measurement, BEM Testing, ACSM Testing,
TLL-L001-N416-DTAAWP2-TUN-RPT-00006, London, UK.
In this study, the properties of tunnel structure was assumed Tube Lines, 2006. Projects Directorate Permanent Way Delivery Team AWP4:
not to change with time. By adopting a reasonable structural dete- Conceptual Design Statement, TLL-N098-P100-TUN-CDS-00001, London, UK.
Tube Lines, 2007. Deep tube tunnel knowledge & inspection programme Soil
rioration relationship, further investigation can be performed to
Parameters Report, TLL-L001-N416-DTAAWP2-TUN-RPT-00001, London, UK.
consider the effect of ageing process on the time-dependant lining Tube Lines, 2008. Deep tube tunnel knowledge & inspection programme annual
behaviour. work plan 2: Cast iron Openings report. TLL-L001-N416-DTAAWP2-TUN-RPT-
00003. London.
United States Army Corps of Engineers (USACE), 1997. Engineering and Design
Acknowledgements Tunnels and Shafts in Rock EM 1110-2-2901, Department of the Army,
Washington, DC, USA.
This work was supported by the Major State Basic Research Wolmar, C., 2004. The Subterranean Railway: How the London Underground was
Built and How it Changed the City for Ever. Atlantic.
Development Program of China (973 Program) (No. Wongsaroj, J., 2005. Three-Dimensional Finite Element Analysis of Short and Long-
2011CB013803) and the Cambridge Trust scholarship. Term Ground Response to Open-Face Tunnelling in Stiff Clay, PhD Thesis.
University of Cambridge.
Wongsaroj, J., Soga, K., Mair, R.J., 2007. Modelling of long term ground response to
References tunnelling under St James’ Park London. Geotechnique 57, 75–90.
Wongsaroj, J., Soga, K., Mair, R.J., 2013. Tunnelling-induced consolidation
ABAQUS Inc., 2012. ABAQUS User’s Manual, Version 6.12. SIMULIA. <www. settlements in London Clay. Geotechnique 63, 1103–1115.
simulia.com>. Wright, P., 2010. Assessment of London Underground tube tunnels – investigation,
Addenbrooke, T.I., 1996. Numerical Analysis of Tunnelling in Stiff Clay. PhD Thesis, monitoring and analysis. Smart Struct. Syst. 6, 239–262.
Imperial College of Science Technology and Medicine, University of London.