DATE OF COMMISIONING 14-Mar-17

FO
DRIVE FACEPLATE NAME FACEPLATE FUNCTIONS

FWD PP 1 KKS OK OK

FWD PP 2 KKS OK OK

FWD PP 3 KKS OK OK

TANKLEVEL 1 KKS OK OK

TANK LEVEL 2 KKS OK OK

AUTO GROUP NOT CHECKED AS THE LOGIC FOR AUTO GROUP DERIVES COMMAND FROM GAS TURBINES

ALARMS RELATED TO TANK LEVEL CHECKED BY FORCING DIFFERENT LEVEL VALUES.

LOW LEVEL <1600 MM


HIGH LEVEL >8000 MM
HI HI LEVEL >8500 MM

ALARM FOR LOW SUCTION PRESSURE IS NOT APPEARING IN CCR WHEN PICKED UP FROM LOCAL. HOWEV
FUEL OIL PRESSURE LOW ALARM IS ALSO NOT AVAILABLE AS THE TRANSMITTER FOR MEASURING PRESSUR

FILTER DP HIGH ALARM IS TO BE CHECKED WITH C&I


FOPH
OPERATION

CHECKED FROM REMOTE/ LOCAL, OK

CHECKED FROM REMOTE/ LOCAL, OK

CHECKED FROM REMOTE/ LOCAL, OK

TANK LEVEL COMING IN MM, READING MISMATCH


7.128 FROM DIP, 6.59 FROM SCADA
TANK LEVEL COMING IN MM, READING MISMATCH
7.154 FROM DIP, 6.59 FROM SCADA
OUP DERIVES COMMAND FROM GAS TURBINES(NOT COMMISSIONED YET)

FFERENT LEVEL VALUES.

CCR WHEN PICKED UP FROM LOCAL. HOWEVER IT IS IN ELECTRICAL LOGIC FOR TRIPPING THE PUMP. -- CHECKED
THE TRANSMITTER FOR MEASURING PRESSURE IS TO BE COMMISSIONED WITH GT#4.
REMARK

TRIPPED FROM EPB, SUCTION SWITCH

TRIPPED FROM EPB, SUCTION SWITCH

TRIPPED FROM EPB, SUCTION SWITCH, NOTIFICATION RAISED FOR DC FUSE FAIL

TANK LEVEL IN KL(MULTIPLYING FACTOR OF 0.198*LEVEL)

TANK LEVEL IN KL(MULTIPLYING FACTOR OF 0.198*LEVEL)

MMISSIONED YET)

N ELECTRICAL LOGIC FOR TRIPPING THE PUMP. -- CHECKED


BE COMMISSIONED WITH GT#4.
DATE OF COMMISIONING 20-Mar-17
DIVE
DRIVE CUT IN CUT OUT

OIL PUMP 1 155 KSC 175KSC

OIL PUMP 2 155 KSC 175KSC

SAF 1 OK OK

SAF 2 OK OK

AIR BARRIER
TO OPEN

AIR BARRIER
TO CLOSE

DIVERTER
DAMPER

LOW LEVEL
VERY LOW
V V LOW
C
DIVERTER DAMPER
RUN TIME

2mins
(CHANGED FROM 11min TO 2min)

2mins
(CHANGED FROM 11min TO 2min)

C/O TIMER : 2MIN : OK


MPER
OPERATION

CHECKED @ LOCAL, OK
TIME DELAY TO GENERATE PUMP FAILURE CMD: 5SEC

CHECKED @ LOCAL, OK

CYCLE TIME FOR P/P CHANGEOVER CHANGED FOR CHECKING FROM 7 DAYS TO 5MIN: OK

SAF TIMER FOR OPEN/CLOSE: 20 SEC