Professional Documents
Culture Documents
E39 Ahsop 06
E39 Ahsop 06
Purpose
The purpose of the SOP “hammer mill & Clinker Grinder” Operation is to train and guide operating personnel for
safe, right & correct procedures & optimum performance of the system.
2. Scope
This SOP defines the lineup, pre checks, permissive, operation procedure, Post startup checks, interlocks &
protections for hammer mill & Clinker Grinder.
3. Responsibility matrix
Sl
n Jobs Responsibility Competency Desired output / efficiency
o
1 Distribution Head- Operation
2 Compliance Station in charge/ Shift in To ensure that Bottom de-
charge/desk engineers ashing is done in the shift
Ensure Evacuation of bottom
Ash Plant (O) Supervisor Complete knowledge of ash hopper to avoid any
Bottom de-Ashing Furnace disturbance.
Field operators Field knowledge for
Bottom de-Ashing
procedure.
No. & Capacity: 2 Nos Clinker Grinders above Agitated Retention Tank
STARTING PERMISSIVE:
8. Startup sequence
1. Ensure stage#1 level should be down then close the manual gate v/v.
2. Stop the hammer mill from plc.
3. Stop the air lock tank sequence after should be air lock tank empty.
4. Stop the selected compressor after flushing conveying line.
1. Check the stage#2 level should be down then close the manual gate v/v.
2. Stop the air lock tank sequence after air lock tank empty.
3. Stop the selected compressor after flushing the conveying line.
14.Performance KPIs
At 150 MW:
o Stage1 empty : 180min
o Operating current : 95Amps
o Power consumption : 160KW
15. Abbreviation
6. O & M parameters
It is also applicable in B#1,3 & 4
Clinker Grinder Details
Sl No. DESCRIPTION Clinker Grinder
1 Make M/S Melco
2 Size 610 x 610
3 Capacity 60 TPH
4 Speed 45 RPM
MOTOR
1 Make Crompton Grieves
2 Motor Type 3-phase Induction Motor
3 Power Capacity (HP) 10
4 Voltage (V) 415
7 Motor speed (RPM) 1460 RPM
8 Full Load current (AMPS) 18
8. Operating procedure
1. Switch ON the Electrical power to the control panel.
2. Open sealing water.
3. Start HP Ash Pump.
4. Open HP Ash Pump Discharge valve.
5. Flush the Bottom ash discharge line to Ash Pond approx. 10 min.
6. Open Clinker Grinder Feed Gate.
7. Start LP Ash Pump for flushing the hopper with nozzles.
8. Open both side nozzles one by one for flushing the clinkers.
9. Open side nozzles one by one for proper flushing.
9. Operation Monitoring &control
10. Shutdown Procedure
1. When furnace flame started looking from Clinker grinder looking glass then Feed gate closed.
2. Stop the Clinker Grinder.
3. Close the Sealing water line valve.
4. Fill the Bottom Ash Hopper through LP ash pump water.
5. Flush the Bottom Ash discharge line for approx. 10 min to clear the discharge line.
6. Stop the HP Ash Pump.
7. When Bottom Ash Hopper started overflowing LP Ash Pump stops.
8. Stop the LP Ash Pump.
11. Best Practices followed (if any): Proper flushing of Clinkers from Both side nozzles & side nozzles.
15. Abbreviation
6. Technical specification
No. & Capacity: 1 per unit, each with 100% Unit Load
Pump Details
Sl No. DESCRIPTION H.P.Pump Clinker grinder
1 Pump Type VERTICAL GREAVES LTD U -
600
2 Liquid Pumped Water Slurry
3 Suction Temperature (oC) 30 100
4 Flow Rate (M3/Hr) 300 300
5 Specific Weight of Feed Water (Kg/M3) 916.0 916.0
6 Suction Pressure (Kg/M3) 5.43 14.40
3
7 Discharge Pressure (Kg/M ) 9.0 3.0
Operating Speed (RPM) 1440 1450
MOTOR 415 415
1 Power, KW 110 9.3
2 Voltage 415 415
3 Current, Amp 185 18.8
4 Speed, RPM 1480 1450
5 Insulation Class F F
8. Start up sequence
1 Inform the control room for bottom ash de ashing.
2 Open hydro ejector water I/L valve (> 6.0 kg/cm2).
3 Open clinker grinder gland sealing water valve.
4 Start the clinker grinder.
5 Open the feed gate & as a consequence bottom ash de ashing starts.
6 Open the water valve for inspection window.
7 When all the ash from hopper is evacuated, HP water nozzles should be opened sequentially for complete
flushing of bottom ash hopper.
8 Inspect the hopper to be empty & inform the same to the control engineer.
9. Operation Monitoring & control
1. Check grinder chamber evacuate in time.
2. Ensure bottom ash sampling.
3. Check for noise & vibration.
4. Check for oil & ash leakages, if any.
15. Abbreviation:
Technical specification
No. & Capacity: 2 Nos. Clinker Grinders for each unit(Below Bottom Ash Hopper)
No. & Capacity: 2 Nos Clinker Grinders above Agitated Retention Tank
8. Operating procedure
10. Switch ON the Electrical power to the control panel.
11. Open sealing water.
12. Start HP Ash Pump.
13. Open HP Ash Pump Discharge valve.
14. Flush the Bottom ash discharge line to Ash Pond approx. 10 min.
15. Open Clinker Grinder Feed Gate.
16. Start LP Ash Pump for flushing the hopper with nozzles.
17. Open both side nozzles one by one for flushing the clinkers.
18. Open side nozzles one by one for proper flushing.
9. Operation Monitoring &control
10. Shutdown Procedure
1. When furnace flame started looking from Clinker grinder looking glass then Feed gate closed.
2. Stop the Clinker Grinder.
3. Close the Sealing water line valve.
4. Fill the Bottom Ash Hopper through LP ash pump water.
5. Flush the Bottom Ash discharge line for approx. 10 min to clear the discharge line.
6. Stop the HP Ash Pump.
7. When Bottom Ash Hopper started overflowing LP Ash Pump stops.
8. Stop the LP Ash Pump.
11. Best Practices followed (if any): Proper flushing of Clinkers from Both side nozzles & side nozzles.
15. Abbreviation