7 Compressor
7 Compressor
7 Compressor
COMPRESSOR
1. Equipment Technical Details:Transport Air Compressor is required for ASH conveying
system. Total we have 12 PTAC and 9 STAC.PTAC is used for conveying ASH from buffer
hopper D-pump to 6000T RCC Silos. STAC is used for conveying 6000T RCC Silos to
5000T RCC Silo. Instrument air compressor is used for the instrument operation. There are 3
instrument air compressors for ESP, Compressor Cum Pump House, and Bottom Ash areas
instruments operation and 2 instrument air compressors for silo area instrument operations.
2. Technical Details
4. Operating Procedure:
Release local push button switch of Compressor.
Check Cooling water SOV has to be open.
Check cooling water line pressure is 6kg/cm2.
Start the selected Compressor.
Prepared by (PMPL): Reviewed by (PMPL): Reviewed by (PPGCL): Approved by (PPGCL):
Signature: Signature: Signature: Signature:
Check cooling water temperature (difference in inlet and out let is 5℃).
Check the discharge pressure as to be ok (for IAC 6.69kg/cm2, TAC 2.3 to2.5 kg/cm2).
Check the running parameters after start.
For any abnormalities record logbook and inform shift in-charge/ operation in charge.
5. Shut down procedure:
Stop the compressor from the PLC.
Isolate the cooling water inlet valve..
6. POINTS TO BE CHECKED BY OPERATOR IN EVERY SHIFT
EQUIPMENT CLEANING
PHYSICALLY VIBRATION CHECKING
PHYSICALLY TEMPRATURE CHECKING
OIL LEVEL AND GREASE CHECKING
7. CHECKING OF SYSTEM AFTER SHUT DOWN
PHYSICALLY CHECK BOTTOM ASH HOPPER AFTER OPENING THE MAN
HOLE DOOR AS LIKE FOREIGN MATERIAL AFTER THAT CHECK THE
ROTATION OF CLINKER GRINDER IN FORWARD AND REVERSE DIRECTION.
CHECK THE OIL LEVEL FREENESS.
PHYSICALLY ALL VALVE CHECKING MANUALLY OPERATION THROUGH
PLC AS WELL.
FIRST ENSURE SLURRY AND ASH WATER SUMP CLEANING AND THEN FILL
THE SUMP.
CHECK THE SEAL PRESSURE OF ALL DOME VALVE PHYSICALLY.
CHECK THE LINE VACUUM AND SHUT OFF VACUUM OF ALL PASSES.
CHECK FLUIDIZING BLOWER AIR OF INDIVIDUAL HOPPER.
CHECK THE PURZING OF BUFFER HOPPER AND SILO BAG FILTER.
IF ANY PROBLEM OBSERVED IN EQUIPMENT THEN INFORM TO SHIFT IN
CHARGE/ OPERATION IN CHARGE IMMEDIATLY