SWOT Analysis
SWOT Analysis
SWOT Analysis
Application of
SWOT Analysis in
the Management of
a Construction
Project
IGOR N. MILOSEVIC
RESEARCH PROCESS
A
n analysis of strengths, weaknesses,
opportunities, and threats 共SWOT兲 Information about the project environment, together with
implies an analysis of the internal possi- knowledge of the project’s possibilities, enable a team to de-
bilities 共strengths and weaknesses兲 of a termine the critical success factors that will satisfy the de-
project and its external environment mands of end product buyers. The analysis, as a rule, in-
共opportunities and threats that might cludes the team 共firm兲 managing the construction. Using
be faced during project management兲. Since risk is present in the analysis, the so-called strategic holes should be discov-
all aspects of our lives, risk analysis and consideration, as well as ered, and a clear plan for filling them in should be adopted
risk management, is a universal activity based on common 共Fig. 1; Hepworth 1998兲.
It is important to continually evaluate the factors that
sense, relevant cognition, experience, and application of appro-
influence the project’s goals—for example, construction time
priate procedures. We can understand risk management as a limits, prearranged costs, and quality standards—so they can
needtorecognizeandeliminate共oratleastreduce兲uncertainty be addressed by the contractor or by the project manager.
usingcontrolactivities. After defining the goals, internal and external possibilities for
APRIL 2010 䊏
78 Leadership and Management in Engineering
Figure 1. Research method framework
realizing the goals need to be identified, as well as obstacles accelerating the schedule to meet deadlines兲. This difference
to realizing those goals. To do this, we identify and then is subjectively evaluated by the team, adopting, first of all, a
analyze strengths, weaknesses, opportunities, and threats, measuring scale. When it comes to weaknesses and threats,
and if needed, we respond to them. We also extract those it is obvious that they need to be eliminated to the greatest
critical success factors that have an impact on achieving the possible extent. Noticing these differences between current
goals. Critical success factors can be complex and can include and ideal levels of critical success factors helps the other
organization, management, and synchronization of construc- people responsible for the project—for example, the investor
tion. The external domain for critical success factors can be and the suppliers on whom the elimination of the weak-
found in the interrelation of the physical environment and nesses partly depends.
building site conditions, and the investor, supplier, customs After determining the differences—that is, the deviation
agents, government, local government, or local community. from optimal critical success factor levels—there are three
It is noteworthy that external critical success factors represent options: 共1兲 accept the difference, 共2兲 reduce the difference
a large challenge because they are difficult to control. Using somewhat, or 共3兲 reduce the difference significantly. If the
the brainstorming method, a team should be able to identify elimination of a small difference would take too much of the
10 internal and external domains for critical success factors team’s time, or if there is a doubt that in spite of the invested
and then extract several of the most important and stick to labor, the difference will remain, leaving the difference at the
them. Finally, we analyze strengths, weaknesses, opportuni- current level is reasonable. The strategies for reducing and
ties, and threats and identify ways to eliminate the weak- eliminating the differences can be immediate concrete steps
nesses and threats 共Eccles and Pyburn 1992兲. and activities, or they can be long-term activities that could
During project management, new strengths, weaknesses, last the whole project. The need for those activities can be
opportunities, and threats can crystallize, and the team must addressed in further planning 共Bourne et al. 2000兲.
continually recognize them and enter them into the SWOT
analysis. The team also evaluates which of the new elements
are critical success factors. Then we begin to determine the The Construction Project and Investment
differences between the current and ideal critical success fac- The project we examine is a business situated in Belgrade,
tor level. For strengths and opportunities, it is possible to fall the capital of Serbia, referred to as “Azzaro.” It is situated
short of the ideal conditions because that difference will rep- parallel to Yuri Gagarin Street, so it continues a row of busi-
resent a potential for improvement in meeting the goal 共e.g., nesses with modern architecture that for the past several
years has fronted this busy street. The architecture is modern ation are given in the article “Application of the risk analysis
by domestic standards and uses glass and Alucobond facade software package Pertmaster when managing a construction
plate. 共Alucobond is a lightweight composite material con- project” 共Milosevic in press兲.
sisting of two prefinished 0.5-mm-thick aluminum cover The risk analysis for each of the registered contractors can
sheets laminated to a core of polyethylene plastic. Alucobond be based on the purchaser’s risk analysis, if it is included in
panels also maintain an extremely flat surface due to the the documentation. The better the analysis, the lower the
laminated construction of the material, thus reducing or contractor’s price, because there are fewer unknowns. In this
eliminating oil canning.兲 The gross area of the building is case, the risk analysis had to determine whether the contrac-
5,800 m2. The building’s construction consists of an ar- tor could meet the demand, but it also had to give the right
mored concrete shaft of raster walls 共7.2 ⫻ 5.4兲 and two balance: whether the contractor’s quote would be accepted
armored concrete cores, each with two lift shafts. The build- and the risk if the money was accepted and the contractor
ing is situated on an armored concrete ground plate. The happened to have a loss 共Fig. 2兲.
mezzanine ceiling is an armored concrete plate 22 cm thick
on the floor and 24 cm thick on the gallery; the plates above Strengths from the Contractor’s Point of View
the ground floor are also 24 cm thick, with an armored
concrete girder 40 cm thick. The total value of the invest- Advanced Project Management
ment is US$5 million. While working on this project, we used an advanced system
of project management with direct communication between
SWOT ANALYSIS FROM THE the construction site and the head office of the contractor’s
CONTRACTOR’S POINT OF VIEW firm. On this project, the contractor had the opportunity to
Examples provided for the SWOT analysis are from the Az- hire experienced engineers and foremen and made excellent
zaro construction project. Using the software package Pert- use of all employees on the project.
master 共an application for risk assessment and analysis兲, in-
fluence and risk factors on the Azzaro project were measured Workforce Stimulation
during the entire lifespan of the project. Factors that influ- On this project, workers’ wages were increased and equalized
enced project costs were subjectively evaluated. A detailed with respect to earlier projects. The wages of the high-
mathematical analysis of the risk and the results of the evalu- ranking workers 共craftsmen and specialized workers兲 were
APRIL 2010 䊏
80 Leadership and Management in Engineering
370 dinars per hour 共US$ 1 = 70 Serbian dinars兲, and the Resistance to New Methods of Working
wages of the low-ranking workers were about 300 dinars per Some senior and more experienced workers may find it dif-
hour. During the hard summer months, the contractor of- ficult to adopt new techniques and strategies. To help the
fered a bonus to the best craftsmen and all participants in the workforce accept modern technology, offer training and, if
project who had higher-level responsibilities. possible, monetary bonuses for meeting deadlines. Supervi-
sors should demonstrate patience and respect during the
Knowledge of the Subcontractor learning period.
On previous projects, the contractor had done business with
many subcontracting firms and had established good rela- Lack of Coordination
tions with them. When the contractor knows what to expect This weakness means that a problem related to coordinating
of the subcontractors, it makes project planning go much the workers can arise within the organization. The use of a
easier. modern formwork system and new materials positively in-
fluences coordination among workers.
Modern Technology
Modern materials and work automation have contributed to
rapid advancements in construction. This is a strength of the Possibility of Injury at Work
contractor and was reflected in the effective and efficient or- Because the workers are not accustomed to working with
ganization on the Azzaro project. new construction technology, there is an increased possibility
of injury at work.
Use of Modern Machinery
The contractor rented modern machinery for use while man- Undeveloped Relationship with the Subcontractor
aging the construction of the building. Unlike the concrete manufacturer, the contractor worked
with new vendors for both the locksmith and plastic work.
Use of PERI Trio Prefabricated Formwork Signed contracts should stipulate high penalties for missed
Trio formwork enables rapid progress during construction. deadlines.
Apart from that, the reasons to choose the Trio system were
exploitation load, minimal working time on a site, and
minimal labor expenses. The principal considerations were Opportunities from the Contractor’s Point of View
the agreed-upon quality of work and the schedule.
Favorable Contract Terms
Skillful Work Team Contract terms should realistically allow the contractor to
This was an additional contractor strength. It was specified finish the project within the anticipated time limit. It is very
that workers who had already worked on the construction of important for the contractor to study the contract and care-
residential and business projects of similar size and similar fully examine his responsibilities, as well as the investor’s
heights would participate in the construction of this build- rights and responsibilities. Only with the knowledge of these
ing. rights and responsibilities, as well as the risk he is undertak-
ing, can the contractor set prices and schedules. The contrac-
Good Relationship with Material Suppliers tor produces the budget for the specific project when he gets
This contractor had been cooperating with the same material a formal inquiry from the investor. Replying to inquiries
suppliers and the same concrete factory for a long time, so he entails considerable expense, which only the investor bears
was familiar with their working methods, and the risk fac- the risk for. A thorough evaluation of expenses should result
tors regarding shipment delays and other problems were sig- in a competitive price 共estimated expenses plus profit兲,
nificantly reduced. which is usually an excellent criterion for obtaining the job
and for the contractor’s success on the project. Underesti-
mated expenses always result in business losses, while over-
Weaknesses from the Contractor’s Point of View estimated expenses can be a cause for losing the business 共Lee
and Ko 2000兲.
Inexperienced Workers
The workers may need some time to adopt a method for
working with the PERI Trio formwork. This, in turn, could Reliable Investor
influence the scheduled deadlines. The workers need to be Former cooperative and positive experiences with a specific
trained at the beginning of the project and then supervised investor represent another very favorable circumstance and an
and assisted as needed. opportunity to respect any deadlines for the estimate.
Small Area for Storage and Manipulation on the Strengths from the Investor’s Point of View
Construction Site
The large gross area of the buildings coupled with tenants’ Good Selection of Contractor
moving into the buildings brings the possibility of problems The investor found a contractor who satisfied the criteria.
related to lack of space. The problem can be solved by using This is an important strength that allows future projects
a neighboring parcel of land without any reimbursement of with the investor and creates confidence in the contractor’s
expenses. ability to direct the suppliers. If the purchaser selects a bad
contractor or vice versa, or if both sides accept bad contract
Supervisory Board with an Interest in the Project terms, both can have serious problems, which can require
A supervisory board 共a group of individuals chosen by the more resources to solve than the risk analysis itself. Selection
stockholders of a company to promote their interests of the contractor who offered the lowest bid does not guar-
through the governance of the company and to hire and antee the lowest final expenses. A contractor will always be
supervise the executive directors and CEO兲 for the construc- tempted to lower the prices and profit in order to beat the
tion cannot be objective, because it has a conflict of interest competition and get the job. Taking into account the diffi-
in the project. This often happens among the participants of culties they have in realizing a profit, these contractors will
a project in Serbia. try to find other ways to make a profit, such as working with
poor quality materials or constantly setting new
Repeated Changes in Allocation of Space conditions—a frequent practice in the construction industry.
The investor’s repeated changes in the allocation of space An irresponsible contractor can cause construction delays and
inside the building present difficulties for the contractor, substituting cheap and poor quality materials can affect
who must deal with frequent improvisation and changes to building quality, which, together with constant new de-
the plan. mands, increase construction expenses.
SWOT ANALYSIS FROM THE INVESTOR’S
POINT OF VIEW Successful Acquisition of Project Documentation
From the moment he decides to undertake construction, the and Building Permits
investor is in suspense regarding the final outcome. A con- This is a strength the investor has because of good business
struction project lasts for a specific period of time; however, contacts.
APRIL 2010 䊏
82 Leadership and Management in Engineering
Figure 3. SWOT analysis from the investor’s point of view using the Azzaro project in New Belgrade as an example
Market Demand Related to Building in New Lack of Protection of the Investor’s Interests by
Belgrade the Supervisory Board
Although the investor conducted an evaluation before invest- This is a consequence regarding the supervisory board; the
ing, real estate prices increased during the construction. engineer attempted to justify some positions by protecting
his work and made an objective report to the investor im-
possible.
Contractor and Subcontractor Willingness to
Agree with Frequent Project Changes Inability to Use the Desired Materials
In many cases, the contractor and subcontractors have been During the project, the investor wanted to use some mate-
willing to oblige the investor and carry out changes in the rials with good aesthetics but weaker fire-fighting character-
project without any specific compensation. istics, which was against safety regulations.
APRIL 2010 䊏
84 Leadership and Management in Engineering
Figure 4. SWOT analysis from Parsons Brinckerhoff. 共Source: 具http://www.datamonitor.com/store/Product/
parsons_brinckerhoff_inc?productid⫽D45F7560-E705-4BA4-A98B-B33085B9A96E典 .兲
THE APPLICATION OF SWOT ANALYSIS business dealings, as well as the risks of further development.
BY THE CONSTRUCTION COMPANIES All well-known construction companies in Europe 共e.g.,
Construction is an industry in which uncertainty is more DPR Construction, Inc., Hensel Phelps Construction Co.,
common than in most others. Uncertainty includes situa- Ames Construction, Inc., Parsons Brinckerhoff兲 make their
tions in which there are no historical records or references SWOT analyses available through the Internet and use them
describing the situation that is being analyzed. Completely as a marketing tool. In our domestic market, no company,
certain situations in construction are rare. Aside from the except for the firm Komgrap, has tried to promote itself in
possible bad influences of the environment on construction, this way. Using SWOT analyses, construction firms can de-
the uniqueness of each project explains such uncertainty. termine their goals for further development, predict the fu-
With the conditions of market economy, and when private ture of the company, recognize the risks of their business
financiers significantly participate in project financing, keep- dealings, and recognize their strengths over the competition.
ing construction on schedule and within budget is very im- SWOT analysis is also suitable for the planning and con-
portant. In the western European countries, it takes a lot of tracting phases. Sometimes, an experienced contractor can,
time to plan and little time to construct a project. In Serbia, before signing the contract, influence its form and content,
we do it the other way around. This phenomenon is charac- especially if he has properly investigated the market and has
teristic of a long period of socialism and making “dictatorial” done a large number of favors for the investor during the
decisions, very often without a rational reason. Project failure concept phase of the project. Taking into account that the
often relates to not paying enough attention to problems one who finances the project is the one who decides, the
that occur on the majority of projects. If we could predict the investor still has the greatest influence on the text of the
problems and thus avoid them, managing expenses, sched- contract, and potential investors need to become familiar
ule, and quality would be easier. For very large, complex, or with contracts as much as possible 共Fig. 4兲.
new projects, there is a great possibility that they will be
submitted to high risk levels. It may seem that the risk price CONCLUSIONS
is high, but the price for not handling the risk is even higher. Mutual risk identification and SWOT analyses by both in-
SWOT analysis should first be carried out at the com- vestor and contractor are desirable so that both sides can be
pany level. Every construction company in Serbia can do a informed about the risks. The investor has to be ready to
SWOT analysis and use it to define its position with respect make a distinction between good and bad quality and hon-
to competitive companies and to recognize its strengths in esty. Bad quality and dishonesty can displace good quality
APRIL 2010 䊏
86 Leadership and Management in Engineering
Copyright of Leadership & Management in Engineering is the property of American Society of Civil Engineers
and its content may not be copied or emailed to multiple sites or posted to a listserv without the copyright
holder's express written permission. However, users may print, download, or email articles for individual use.