Tata Consulting Engineers Design Guide For Auxiliary Steam Header
Tata Consulting Engineers Design Guide For Auxiliary Steam Header
Tata Consulting Engineers Design Guide For Auxiliary Steam Header
DESIGN GUIDE
FOR
FLOPPY NO :
FILE NAME : M6590416.DOC
REV.NO R0 R1 ISSUE
PPD.BY RS Sd/- VS
CONTENTS
SL.NO. TITLE SH.NO.
1.0 INTRODUCTION 1
FIGURES
ISSUE
R1
REVISION STATUS
R0 86-06-24 -
ISSUE
R1
1.0 INTRODUCTION
The header should be sized for the maximum flow to be handled by it. In a
power plant, the design flow of the header is either the capacity of the
auxiliary PRDS connected to it or the maximum flow that can be imported into
the unit from another unit or package boiler through the interconnecting line,
whichever is greater. Generally, headers are designed for lower velocities
than pipelines in order to permit future expansion and / or effect trapping of
moisture / condensate entrained in steam.
3.1 The header with its nozzles can be fabricated in one of the following ways :
3.2 The first method is to have auxiliary steam header using standard wrought
steel tees with spool pieces.
3.3 The second method employs intersection of joints. The openings in the
header weaken it and additional wall thickness has to be provided on the
header by way of reinforcement. The need for additional wall thickness for the
branch lines should also be examined. In short, reinforcement calculations
have to be carried out for the header. Refer BS : 806 / ASME B 31.1 / IBR for
performing reinforcement calculations.
3.4 In the third method, weldolet type fittings are used alongwith openings made
in the header. These provide full strength joints without the need for
additional reinforcement. It is suggested that preference is given to the use of
weldolets as the amount of welding on the header is substantially reduced.
ISSUE
R1
4.1 The header being at floor level is a receptacle for condensate formed in the
branch lines. A drain pot should be provided on the header near one end with
a size as per guidelines given in Note-1 of Fig-1. The header should be
sloped towards the drain pot. All branch lines should be sloped towards the
header. The condensate collected in the drain pot is drained either through a
trap or though a motor operated valve, actuated by level switch. Refer Figs.
2A and 2B. The scheme depends on system requirements, operating
pressure and temperature and the quantity of drain to be handled. Traps are
adequate to handle small drain quantities at relatively low pressure and
temperature.
4.2 Motor operated valve actuated with level switch is recommended when the
operating temperature is greater than 400oC or at places where spray water is
introduced into steam piping (e.g. downstream of desuperheater, downstream
of HP Bypass valves).
The spacing between the branch pipes on the header is governed by the
following two requirements.
ISSUE
R1
The header should be supported from the floor through bottom pipe supports.
As the steam piping is hot and calls for thermal analysis, the header at one of
the support points should be anchored so as to split the piping connected in
to individual systems for purpose of stress analysis and to minimise the effect
of one branch on the other. Individual systems stress analysis shall be
carried out with header anchor as the anchor. Figures 3 to 6 indicate typical
arrangement for support of anchor and restraints.
ISSUE
R1
STEAM TO DEAERATOR
STEAM TO EJECTORS
OIL SYSTEM & SCAPH
SPARE CONNECTION
STEAM TO TURBINE
GLAND SEALS
STEAM FROM
AUX. PRDS.
SPARE
TI SAFETY PI
RELIEF VALVE
1300 TO 1500 mm
STEAM HEADER
SLOPE
FLOOR LEVEL
ELEVATION
TI PI
.
IN
M )
0 P
15 TY
(
PLAN
FIGURE.-1
STEAM HEADER
ISSUE
R1
SLOPE C OF HEADER
L
NB 25
T TO FLASH TANK OR WASTE
AS SHOWN IN FLOW DIAGRAM
DRAIN PLUG
(THREADED / WELDED
HALF COUPLING WITH PLUG)
FIGURE-2A
DRAIN POT WITH TRAP STATION
SLOPE C OF HEADER
L
LEGEND
HHLVL
HHLVL HIGH HIGH LEVEL PROBE TYPE
HLVL HIGH LEVEL LEVEL SWITCH
HLVL
M
DRAIN POT
(REF. NOTE-1) NB50
TO FLASH
TANK
(REF. NOTE-2)
DRAIN PLUG
(THREADED / WELDED
HALF COUPLING WITH PLUG)
FIGURE-2B
DRAIN POT WITH M.O VALVE
NOTES:
1. DRAIN POT SIZE SHALL BE AS FOLLOWS
HEADER < 150 mm SAME AS HEADER SIZE
HEADER > 200 mm HALF THE HEADER SIZE
OR 150 mm WHICH EVER IS GREATER.
2. WITH HIGH HIGH LEVEL THE MOTOR OPERATED VALVE WILL OPEN AND
CLOSE AT HIGH LEVEL
ISSUE
R1
25mm(TYP)
OR 100 mm
STUB
D
A A
(MIN)
2 mm PLATE 10THK.
VENT HOLE
PF
LEGEND
CC
25 GROUT(MIN.)
PF : PIPE FABRICATOR
CC : CIVIL CONTRACTOR
POCKET SIZE
50 S.Q. x 300 LONG
100 FOR b < 300
125 FOR b = 301 TO 400
STUB SIZE DIM. IN mm.
ELEVATION
NB OD(D) a b
b
50 60.3 75 120
a
65 73.0 90 140
ERECTION NOTES:
1. THE GROUTING SHOULD BE DONE AFTER SETTING THE PIPE LINE FOR SLOPE
2. HEIGHT OF FOUNDATION SHOULD BE CALCULATED CONSIDERING THE ACTUAL PIPE
ELEVATION AFTER SLOPE AT THE POINT OF SUPPORT
3. PIPE STUB IS NORMALLY ONE OR TWO SIZES SMALLER THAN HEADER SIZE
4. PIPE STUB WALL THICKNESS SHOULD BE CHECKED FOR WORST POSSIBLE COMBINED
PIPE REACTIONS AT ANCHOR. THE REACTIONS FORCES MUST BE INDICATED ON THE
PIPING DRAWING TO ENABLE THE PIPING FABRICATOR TO DESIGN WELD JOINTS.
ISSUE
R1
25mm(TYP)
OR 100 mm
A D
2 mm STUB A
(MIN)
PLATE 10THK.
VENT HOLE
PF
25 GROUT(MIN.)
CC
2 mm
(TYP)
POCKET SIZE
50 S.Q. x 300 LONG
100 FOR b < 300
125 FOR b = 301 TO 400
ELEVATION
PIPE MVT.
b = a + PIPE MOVEMENT IN
THE DIRECTION + 100mm.
a c = a + 200mm.
d = b + 100mm
a = SAME AS IN FIG. 3
b
d
LEGEND
100 FOR b < 300 PF : PIPE FABRICATOR
125 FOR b > 301 TO 400 CC : CIVIL CONTRACTOR
c
SECTION A-A
FIGURE-4
SLIDING SUPPORTS ON CONCRETE PEDASTALS
ERECTION NOTES:
SAME AS NOTES 1 & 3 OF FIGURE - 3
ISSUE
R1