Construction of Decentralised Waste Water Treatment Plant Pilot Project For Koye Fetche Condominium Site Weekly Progress Report

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 40

Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium

WEEKLY PROGRESS REPORT


LOT-II WWTP2 Date: 10 January 2017

1 Weather: Sunny
Sunny
2 Health and Safety: No accident,Meeting was conducted in previouse week
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: Last Week progress
- Hollow Block work for chemical building is under progress.
- Backfill work for areated mixing sludge tank is under progress.

Overall progress

-Excavation,lean concrete and concrete for base slab and wall ( fir
completed.
- Backfill work,lean concrete and outer face formwork fixing has be
6 E-M Installation Activities NA
- Bacfill work around foundation column and under equipment sea
7 Testing and Commissioning: NAand concrete work of grade beam of PTU completed. 80% concre
- Excavation , masonary work and concrete for footing pad,foundati
8 Other Activities: NA
control building.Formwork fixing for roof slab of control building
9 Measurement & Payment: - C30has
IPC-3 concrete for half section
been submitted by theofContractor.
BT unit base
It isslab
undercompleted .
evaluation.
10 Variations: - NA
Masonary work for dewatering building and PTU completed.
- Masonary workbuildings etc. building completed. Also,concrete w
for chemical
11 beam,elevation column ,intermediate beam and top tie beam of
12 Any Other Remarks: The quality
- -ofExcavation
concrete work for chlorination
for areated tank tank
mixing sludge wall completed.
is not satisfac
the cubes for BT base slab fall below the required strength and some

Signature __________________________________
oye Fetche Condominium Site
S REPORT
Prepared By: Eyob T.

previouse week

ding is under progress.


ge tank is under progress.

e for base slab and wall ( first lift ) of chlorination tank and parshal low meters
face formwork fixing has been completed for for both PSTs' central part(Diam.=5.2m)
n and under equipment seat of PTU completed.Also, lean concrete
PTU completed. 80% concrete for elavation column completed.
rete for footing pad,foundation column,grade beam and elevaton column completed for
oof slab of control building is under progress.
nit base
ctor. It isslab
undercompleted .
evaluation.
ng and PTU completed.
completed. Also,concrete work for footing pad,foundation column, grade
e beam and top tie beam of chemical building completed .
tion tank tank
g sludge wall completed.
is not satisfactory (form work dismantled this week). The strengh of most of
required strength and some are marginal.Failed rebar has been removed and replaced with
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium
WEEKLY PROGRESS REPORT
LOT-II WWTP2 Date: 16 January 2017

1 Weather: Sunny
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: Last Week progress
- Block work for chemical building is under progress.
- Backfill work for areated mixing sludge tank completed.
- The Contractor started to deliver rebar to the project site.

Overall progress

-Excavation,lean concrete and concrete for base slab and wall ( fir
completed.
- Backfill work,lean concrete and outer face formwork fixing has be
- Bacfill work around foundation column and under equipment sea
and concrete work of grade beam of PTU completed. 80% concre
seat of PTU completed.
- Excavation , masonary work and concrete for footing pad,foundati
control building.Formwork fixing for roof slab of control building
- C30 concrete for half section of BT unit base slab completed .
- Masonary work for dewatering building and PTU completed.
- Masonary work for chemical building completed. Also,concrete w
beam,elevation column ,intermediate beam and top tie beam of
- - Excavation for areated mixing sludge tank completed.

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: IPC-3 was submitted by the Contractor. It is responded back to the C
10 Variations: NA
11
Overall progress: Very slow ; Material shortage at site such as rebar and pipes to be e
for concrete due to rebar shortage. This will affect p
buildings etc.The Contractor has now started delive

12 Any Other Remarks: The quality of concrete work for chlorination tank wall is not satisfac
below the required strength and some are marginal. The Contractor h
employee at site.

Signature __________________________________
oye Fetche Condominium Site
S REPORT
Prepared By: Eyob T.

under progress.
ge tank completed.
ar to the project site.

e for base slab and wall ( first lift ) of chlorination tank and parshal low meters

face formwork fixing has been completed for for both PSTs' central part(Diam.=5.2m)
n and under equipment seat of PTU completed.Also, lean concrete
PTU completed. 80% concrete for elavation column completed.Concrete for equipment

rete for footing pad,foundation column,grade beam and elevaton column completed for
oof slab of control building completed waiting for rebar fixing.
nit base slab completed .
ng and PTU completed.
completed. Also,concrete work for footing pad,foundation column, grade
e beam and top tie beam of chemical building completed .
g sludge tank completed.

t is responded back to the Contractor as it is less than the minimum amount sepicified.
h as rebar and pipes to be embeded.The contractor could not make ready work sections
ar shortage. This will affect project progress especially for units suchas BT,PST,control
actor has now started delivering rebar to the project site.

tion tank wall is not satisfactory . The strengh of most of the cubes for BT base slab fall
e marginal. The Contractor has moblized special formwork and training was given to his
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium
WEEKLY PROGRESS REPORT
LOT-II WWTP2 Date: 22 January 2017

1 Weather: Sunny
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities:
- Block work for chemical building completed.
- Excavation work for final clarification tank is under progress.
- Backfill work for areated mixing sludge tank completed and layo
- Form work prepartion for intermediate beam concrete (C30) of

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA

11
Overall progress: Very slow ; Material shortage at site such as rebar and pipes to be e
for concrete due to rebar shortage. This will affect p
buildings etc.The Contractor has now started delive

12 Any Other Remarks: The Contractor has submitted proposal to change the size of rebar to
ø16 instead of ø12 rebars. As per the discussion at the meeting, we
only one step larger size to replace if smaller rebar size can be replace
going to reject their proposal and if you have different idea let me kn

Signature __________________________________
oye Fetche Condominium Site
S REPORT
Prepared By: Eyob T.

mpleted.
tank is under progress.
ge tank completed and layout for lean concreting is under prepation.
ate beam concrete (C30) of Pre-treatment unit.

h as rebar and pipes to be embeded.The contractor could not make ready work sections
ar shortage. This will affect project progress especially for units suchas BT,PST,control
actor has now started delivering rebar to the project site but small quantities.

o change the size of rebar to use available rebar sizes at stock. The Contractor wants to use
cussion at the meeting, we advised them to used to replace rebars with lesser bar size. And
ller rebar size can be replaced in view of crack control than the strength paratmeter. I am
ave different idea let me know.
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium
WEEKLY PROGRESS REPORT
LOT-II WWTP2 Date: 29 January 2018

1 Weather: Sunny
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities:
- Excavation work for final clarification tank is under progress.
- Lean concreting for sludge stablization tank completed.
- Lean concreting for biological sludge gravity thickener completed
- Rebar and formwork fixing for chlorination tank wall completed
- Concrete work for intermediate beam concrete of Pre-treatmen
- Rebar fixing for control building top slab is under progress.
- Rebar fixing for biological treatment unit base slab and starter ba
- Concrete work for dewatering building elevation column comple

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11
Overall progress: Slow ; Material shortage at site such as rebar and pipes to be embed
for concrete due to rebar shortage. This will affect p
buildings etc. The Contractor has improved its activ
on cutting and shaping of rebars to make other sec

12 Any Other Remarks: The Contractor has delivered reinforcement bars of different sizes to

Signature __________________________________
oye Fetche Condominium Site
S REPORT
Prepared By: Eyob T.

tank is under progress.


on tank completed.
gravity thickener completed.
nation tank wall completed (2 nd lift) and ready for concrete work.
m concrete of Pre-treatment unit completed.
lab is under progress.
unit base slab and starter bar is under progress.
g elevation column completed.

ebar and pipes to be embeded.The contractor could not make ready work sections
ar shortage. This will affect project progress especially for units suchas BT,PST,control
ractor has improved its activity for last week in comparison to previous weeks and now doing
of rebars to make other sections/units ready for conrete

ent bars of different sizes to project site.


Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium
WEEKLY PROGRESS REPORT
LOT-II WWTP2 Date: 5 Febraury 2018

1 Weather: Sunny
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities:
- Excavation work for final clarification tank is under progress (tan
- Concrete for chlorination tank wall completed.
- Concrete work for elevation column concrete of Pre-treatment u
- Rebar fixing for control building top slab is under progress.
- Rebar fixing for biological treatment unit base slab is under prog
- Block work for chemical building completed and plastering work

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11
Overall progress: Slow ; Material shortage at site such as rebar and pipes to be emb
for concrete due to rebar shortage. This will affect p
buildings etc. The Contractor has improved its activ
on cutting and shaping of rebars to make some sec

12 Any Other Remarks: The Contractor has delivered reinforcement bars of different sizes
could not supply embedded pipes to the project site to contiue subsq

Signature __________________________________
oye Fetche Condominium Site
S REPORT
Prepared By: Eyob T.

tank is under progress (tank-1).


ompleted.
concrete of Pre-treatment unit completed.
slab is under progress.
unit base slab is under progress.
pleted and plastering work is under progress.

s rebar and pipes to be embeded.The contractor could not make ready work sections
ar shortage. This will affect project progress especially for units suchas BT,PST,control
ractor has improved its activity for last week in comparison to previous weeks and now doing
of rebars to make some sections/units ready for conrete.

ment bars of different sizes to project site. But, still not in sufficient quantity.The Contractor
project site to contiue subsquent activities for primary clarification tanks.
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium
WEEKLY PROGRESS REPORT
LOT-II WWTP2 Date: 12 Febraury 2018

1 Weather: Sunny
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Excavation work for final clarification tank completed (tank-1) an
- Formwork and rebar fixing for intermediate beam of Pre-treatme
- Rebar fixing for control building top slab is under progress.
- Rebar fixing for biological treatment unit base slab is under prog
- Backfill work under base slab of primary gravity thickener is und

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA

11
Overall progress: Slow ; Material shortage at site such as rebar , expansion joint fill
The contractor could not make ready work sections for concret
will affect project progress especially for units suchas BT & PST.

12 Any Other Remarks: The Contractor couldn't supply expansion joint filler material fo BT un
continued.The Contractor could not supply embedded pipes to the p
clarification tanks.

Signature __________________________________
oye Fetche Condominium Site
S REPORT
Prepared By: Eyob T.

n tank completed (tank-1) and the other is under progress.


mediate beam of Pre-treatment unit is under progress.
slab is under progress.
unit base slab is under progress.
mary gravity thickener is under progress

s rebar , expansion joint filler material, pipes to be embeded.


y work sections for concrete due to rebar shortage and expansion joint filler material. This
ly for units suchas BT & PST.

n joint filler material fo BT unit and concrete casting for the other hald section couldn't be
ply embedded pipes to the project site to contiue subsquent activities for primary
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium
WEEKLY PROGRESS REPORT
LOT-II WWTP2 Date: 20 Febraury 2018

1 Weather: Sunny
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Excavation & backfill work for final clarification tank completed (
- Concrete for intermediate beam of Pre-treatment unit complete
- Rebar fixing for control building top slab is under progress.
- Rebar fixing for biological treatment unit base slab completed an
progress.
- Lean concreting under base slab of primary gravity thickener com

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA

11
Overall progress: Slow ; Material shortage at site such as rebar and pipes to be em
The contractor could not make ready work sections for concret
will affect project progress especially for units suchas BT, PST,FC

12 Any Other Remarks: The Contractor has now supplied expansion joint filler material at site
continued.The Contractor could not supply embedded pipes to the p
and final clarification tanks.

Signature __________________________________
oye Fetche Condominium Site
S REPORT
Prepared By: Eyob T.

arification tank completed (tank-1).


re-treatment unit completed.
slab is under progress.
unit base slab completed and installation of expansion joint filler material is under

rimary gravity thickener completed.

s rebar and pipes to be embeded.


y work sections for concrete due to rebar shortage and embedded pipes. This
ly for units suchas BT, PST,FCT, SST,BSGT & PSGT.

on joint filler material at site and and concrete casting for the other hald section can be
ply embedded pipes to the project site to contiue subsquent activities for primary clarification
Construction of Decentralised Waste Water Treatment Plant Pilot Project for Koye Fetche Condominium
WEEKLY PROGRESS REPORT
LOT-II WWTP2 Date: 26 Febraury 2018

1 Weather: Cloudy
Sunny with light rain
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Concrete for biological treatment unit base slab (second part) co
- Backfill work and lean concreting for final clarification tank comp
- Rebar fixing for control building top slab is under progress.
- Rebar and formwork fixing for wall section of biological treatmen

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA

11
Overall progress: Slow ; Material shortage at site such as rebar and pipes to be em
The contractor could not make ready work sections for concret
will affect project progress especially for units suchas BT, PST,FC

12 Any Other Remarks: Concrete for biological treatment unit base slab has been poured (se
there is still shortage of rebar to continue wall sections. in additiona,t
to contiue subsquent activities for primary clarification and final clari

Signature __________________________________
oye Fetche Condominium Site
S REPORT
Prepared By: Eyob T.

t base slab (second part) completed


final clarification tank completed (tank-1).
slab is under progress.
ection of biological treatment unit base slab (first half) is under progress

s rebar and pipes to be embeded.


y work sections for concrete due to rebar shortage and embedded pipes. This
ly for units suchas BT, PST,FCT, SST,BSGT & PSGT.

se slab has been poured (second part) yesterday and this is good progress for this week but
wall sections. in additiona,the Contractor could not supply embedded pipes to the project site
y clarification and final clarification tanks.
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 5 March 2018

1 Weather: Cloudy
Sunny with light rain
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Rebar and formwork fixing for wall section of biological treatmen
- Rebar fixing for control building top slab is under progress.
- Rebar fixing for dewatering building first floor slab is under progr
- Backfill work under base slab of primary clarification tank-1

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA

11
Overall progress: Slow ; Material shortage at site such as rebar and pipes to be embe
The contractor could not make ready work sections for concrete d
This will affect project progress especially for units such as BT, PST

12 Any Other Remarks: Rebar shortage stopped the Contractor to continue major structures.
project site to contiue subsquent activities for primary clarification an
Tadewose provided list of strucutures that should be pended and ad
due to the integration of civil with E-M works . However, the Contract

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
March 2018 Prepared By: Eyob T.

ection of biological treatment unit base slab (first half) is under progress
slab is under progress.
first floor slab is under progress.
ary clarification tank-1

ebar and pipes to be embeded.


work sections for concrete due to rebar shortage and embedded pipes.
ally for units such as BT, PST,FCT, SST,BSGT & PSGT.

o continue major structures.Also the Contractor could not supply embedded pipes to the
s for primary clarification and final clarification tanks.
at should be pended and addressed to the Contractor as there is a need for supplier's review
orks . However, the Contractor has resisted to continue at some sections.
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 12 March 2018

1 Weather: Sunny
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Rebar and formwork fixing for wall section of biological treatmen
- Excavation for FCT-2 and trench for embedded pipes is under pro
- Backfill work under base slab of primary clarification tank-1 is un
- Plastering work for pre-treatment unit is under progress
- Core samples were taken from biological treatment unit base slab

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: IPC-3 was requested and comments are given.
10 Variations: The Contractor has been requested for pricing and proposal of roa

11
Overall progress: Slow ; Material shortage at site such as rebar and pipes to be embe
The contractor could not make ready work sections for concrete d
This will affect project progress especially for units such as BT, PST

12 Any Other Remarks: Rebar shortage stopped the Contractor to continue major structures.
project site to contiue subsquent activities for primary clarification an
Tadewose provided list of strucutures that should be pended and ad
due to the integration of civil with E-M works . However, the Contract

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
March 2018 Prepared By: Eyob T.

ection of biological treatment unit base slab (first half) is under progress
mbedded pipes is under progress
ary clarification tank-1 is under progress
t is under progress
cal treatment unit base slab failed sections.

given.
r pricing and proposal of road,drainage and fence works.

ebar and pipes to be embeded.


work sections for concrete due to rebar shortage and embedded pipes.
ally for units such as BT, PST,FCT, SST,BSGT & PSGT.

o continue major structures.Also the Contractor could not supply embedded pipes to the
s for primary clarification and final clarification tanks.
at should be pended and addressed to the Contractor as there is a need for supplier's review
orks . However, the Contractor has resisted to continue at some sections.
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 27 March 2018

1 Weather: Sunny
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Rebar and formwork fixing for wall section of biological treatmen
available rebar at site.
- Lean cocrete for FCT (tank-1) completed.
- Lean concrete for PCT completed ( both tanks)
- Excavation work for primary sludge pumping station and distributi

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment:
10 Variations: The Contractor has been requested for pricing and proposal of roa

11
Overall progress: Slow ; Material shortage at site such as rebar and pipes to be embe
The contractor could not make ready work sections for concrete d
This will affect project progress especially for units such as BT, PST

12 Any Other Remarks: Rebar shortage stopped the Contractor to continue major structures.
project site to contiue subsquent activities for primary clarification an
The Contractor has not started removal of surplus material as said be
/Employer for distance greater than 2.5km before he start. But, we re
as possible.

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
March 2018 Prepared By: Eyob T.

ection of biological treatment unit base slab is under progress (both parts), with the only

ted.
oth tanks)
umping station and distribution chamber started.

r pricing and proposal of road,drainage and fence works.

ebar and pipes to be embeded.


work sections for concrete due to rebar shortage and embedded pipes.
ally for units such as BT, PST,FCT, SST,BSGT & PSGT.

o continue major structures.Also the Contractor could not supply embedded pipes to the
s for primary clarification and final clarification tanks.
f surplus material as said before.Rather , he requested for approval letter from our office
m before he start. But, we reminded him of your previuouse letter and start the remaval as soon
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 02 April 2018

1 Weather: Sunny
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Rebar and formwork fixing for wall section of biological treatmen
available rebar at site.
- Excavation,lean concrete under footing pad and C30 concrete for
- Masonary retaining wall and backfilling work for primary distribu
- Lean concrete for primary sludge pumping station completed.

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: The Contractor has submitted IPC-3
10 Variations: NA

11 Overall progress: Slow ; Material shortage at site such as rebar and pipes to be embe
The contractor could not make ready work sections for concrete d
This will affect project progress especially for units such as BT, PST

12 Any Other Remarks: Rebar shortage stopped the Contractor to continue major structures
project site to contiue subsquent activities for primary clarification a
The Contractor has started disposal of spoil with only two trucks as o

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
April 2018 Prepared By: Eyob T.

ction of biological treatment unit base slab is under progress (both parts), with the only

g pad and C30 concrete for footing pad completed for energy and blower buildings
g work for primary distribution champer is under progress
mping station completed.

ebar and pipes to be embeded.


work sections for concrete due to rebar shortage and embedded pipes.
ally for units such as BT, PST,FCT, SST,BSGT & PSGT.

o continue major structures.Also the Contractor could not supply embedded pipes to the
s for primary clarification and final clarification tanks.
oil with only two trucks as of saturday.
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 10 April 2018

1 Weather: Sunny
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Rebar and formwork fixing for wall section of biological treatmen
available rebar at site.
- C30 concrete for footing column completed for energy and blow
- Lean concrete for primary sludge pumping station completed.

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: The Contractor has submitted IPC-3
10 Variations: NA

11 Overall progress: Slow ; Material shortage at site such as rebar and pipes to be embe
The contractor could not make ready work sections for concrete d
This will affect project progress especially for units such as BT, PST

12 Any Other Remarks: Rebar shortage stopped the Contractor to continue major structures
project site to contiue subsquent activities for primary clarification a
The Contractor is carrying out disposal of surpless material.

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
April 2018 Prepared By: Eyob T.

ction of biological treatment unit base slab is under progress (both parts), with the only

pleted for energy and blower buildings


mping station completed.

ebar and pipes to be embeded.


work sections for concrete due to rebar shortage and embedded pipes.
ally for units such as BT, PST,FCT, SST,BSGT & PSGT.

o continue major structures.Also the Contractor could not supply embedded pipes to the
s for primary clarification and final clarification tanks.
surpless material.
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 7 May 2018

1 Weather: Sunny
Sunnywith 3 days light rain (for last month-April)
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Rebar and formwork fixing for wall section of biological treatmen
concrete casting.
- Common and rock excavation for final clarification tank (FCT)-2 a
- Backfill work and lean concrete work have been excuted for prim
3&4)
-Wall plastering & roof fixing works for chemical building.

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: IPC-3 has been sent to Client.
10 Variations: NA

Overall progress: Very Slow ; The Contractor's progress for last month is only 1% . The
Material shortage at site such as rebar, concrete and pipes to be e
11 The contractor could not make ready work sections for concrete d
This will affect project progress especially for units such as BT, PST
Even for ready-sections for concrete (biological treatment unit wal
concrete supply.

12 Any Other Remarks: Rebar shortage stopped the Contractor to continue major structures
month to continue for some units base slabs.
The Contractor couldn't obtain concrete from concrete supplier on h
been strongly advised to look for alternative concrete supplier in the
The Contractor has got approval for local pipe materials to be embe
final clarification tanks.
The Contractor has carried out disposal of surpless material found a

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
May 2018 Prepared By: Eyob T.

nth-April)

ction of biological treatment unit base slab completed (both parts)- ready for first lift

l clarification tank (FCT)-2 and backfill work is under progress.


have been excuted for primary sludge pumping station and distribution chamber (Unit-
chemical building.

last month is only 1% . The Contractor's main reason is shortage of rebar in the Country.
concrete and pipes to be embeded.
work sections for concrete due to rebar shortage and embedded pipes.
ally for units such as BT, PST,FCT, SST,BSGT & PSGT.
ological treatment unit wall and control building roof slab), the Contractor couldn't get

o continue major structures.Contractor has obtained small quantity of diam.10mm bar in this
abs.
rom concrete supplier on hand for those work sections ready for concrete.The Contractor has
tive concrete supplier in the weekly meeting.
pipe materials to be embedded to contiue subsquent activities for primary clarification and

of surpless material found along stream -2 of the Industrial Park Project/Free Zone.
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 21 May 2018

1 Weather: 4 Sunny
days sunny , 3 days rainy
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Only minor correction works. BT wall first lift section is ready for

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Overall progress:
Variations: NoNA
progress in the reporting week.The Contractor's main reason is sh
11 The Contractor has requested to pour concrete for BT wall and Co
was as of friday and the access road in the compound as well as outside up to the Condominium site became mu
reason.
Pipes to be embeded has not yet been supplied.
The contractor could not make ready work sections for concrete d

12 Any Other Remarks: Rebar shortage stopped the Contractor to continue major structures
The access problem due to rainy condition ( as of friday) has affected
The Contractor couldn't obtain concrete from concrete supplier on h
for alternative concrete supplier in the weekly meetings. Accordingly
central laboratories.
The Contractor has got approval for local pipe materials to be embe
final clarification tanks.However, the Contractor has not supplied spe
The Contractor has carried out disposal of surpless material found a
Contractor has been given instruction to continue the removal of sur
The Contractor's monthly schedule as well as master work program h
completion time will expire as of 30 May 2018.
Letter has been issued out to the Contractor to speed up the progres
We are discusssing on the slow progress at our office and Solomon is
only devoted to the civil work.
The Contractor is instructed to maintain any access road inside and o

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
May 2018 Prepared By: Eyob T.

first lift section is ready for pouring concrete but no supply of concrete.

ontractor's main reason is shortage of rebar.


concrete for BT wall and Control building roof slab on saterday and sunday. However, there has
ndominium site became muddy and the Contractor is forced to postpone the pouring for such

supplied.
work sections for concrete due to rebar shortage and embedded pipes.

o continue major structures.


n ( as of friday) has affected the Contractor to pour concrete on saterday and sunday.
rom concrete supplier on hand as per its plan.The Contractor has been strongly advised to look
eekly meetings. Accordingly, we have taken samples from other ready mix concrete suppliers to
pipe materials to be embedded to contiue subsquent activities for primary clarification and
tractor has not supplied specification and sample for approval as per our request.The
of surpless material found along stream -2 of the Industrial Park Project/Free Zone. The
continue the removal of surplus material found elsewhere in the compound.
ll as master work program have failed to comply with the actual progress and the contract
2018.
tor to speed up the progress in the reporting period.
at our office and Solomon is trying to arrange meeting at Employer's office the meeting being

any access road inside and outside at his own cost to allevaite the access problem.
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 14 June 2018

1 Weather: Mostly
Sunny claudy with few rain days
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Concrete for BT wall has been poured for half part found on the w
- Concrete for roof slab of control building has been poured
- Rebar and formwork fixing has been carried out for BT half part f
- Rebar and formwork fixing work has been carried out for SST base
- Access road maintaince work in the compound is being carried ou
- Reinstatement of turn out ditch in the compound but not complete
-

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Variations: NA
11

Overall progress:
The Contractor has carried out only the above works as of 20 Ma
works.The Contractor's main reason is shortage of rebar.
Pipes to be embeded has been supplied to site but the material s
the Engineer's request.

12 Any Other Remarks: Site instruction has been issued out to the Contracot to carry out floo
started these activities as per the instruction.
Letter has been issued out to the Employer to request the IPDC to ur
project compound.

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
June 2018 Prepared By: Eyob T.

for half part found on the west direction


ng has been poured
arried out for BT half part found on the east direction (ready for concrete pouring)
een carried out for SST base slab
mpound is being carried out but not completed
ompound but not completed

e above works as of 20 May 2018. And the Contractor could not proceed furhter with other
shortage of rebar.
ed to site but the material specification and layout proposal has not been yet submitted as per

e Contracot to carry out flood protection works & access road maintanance. The Contractor
tion.
er to request the IPDC to urge the free zone contractor to open-up the stream found in the our
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 25 June 2018

1 Weather: Rain
Sunny
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: LC / E-M issue still pending
5 Civil Construction Activities: - Concrete for SST base slab has been poured
- Rebar and formwork fixing work is being carried out for primary

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Overall progress:
Variations: NA
11 The Contractor has carried out only the above works as of 20 Ma
works.The Contractor's main reason is shortage of rebar and also
access route to and in the compound has not been completed.

12 Any Other Remarks: The weather condition has become the problem for the contractor to
condition.The Contractor has not carried out the access road earlier
Site instruction has been issued out to the Contracot to carry out floo
started these activities as per the instruction.
Letter has been issued out to the Employer to request the IPDC to ur
project compound. However, flood damage has been encountered o

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
June 2018 Prepared By: Eyob T.

oured
ing carried out for primary and biological sludge gravity thickeners base slab.

e above works as of 20 May 2018. And the Contractor could not proceed furhter with other
shortage of rebar and also the rain has not its impact on the progress of the project as the
has not been completed.

roblem for the contractor to properly carryout his activities on site due to access road
out the access road earlier inspite of repeated instructions.
e Contracot to carry out flood protection works & access road maintanance. The Contractor
tion.
er to request the IPDC to urge the free zone contractor to open-up the stream found in the our
ge has been encountered on 23 June 2018 at our project site the major damage being on Lot-1.
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 16 July 2018

1 Weather: Day
Sunny
time-Mostly sunny ( only one day rain), Night time-Rainy
2 Health and Safety: No accident
3 Environment, Access & Community: NA
4 Contractual Issues: AAWSA made a decision on the replacement of Landustrie with W
5 Civil Construction Activities: - Rebar and formwork fixing work is being carried out for primar
- Rebar and formwork fixing work is being carried out for SST wa
- Access road maintance work started

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Measurement & Payment: NA
10 Overall progress:
Variations: NA
11 The Contractor has carried out only the above works since you le
works.The Contractor's main reason is shortage of rebar and also
access route to and in the compound has not been completed.

12 Any Other Remarks: The weather condition has become the problem for the contractor to
condition.The Contractor has not carried out the access road earlier
road maintenance on last friday.
No delivery of new reinforcement bar.The Contractor is working with
other rebar sizes.

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
July 2018 Prepared By: Eyob T.

in), Night time-Rainy

ement of Landustrie with WABAG. I think you have the letter from Dr.Alem
being carried out for primary and biological sludge gravity thickeners base slab.
being carried out for SST wall - second lift
d

e above works since you left Addis. And the Contractor could not proceed furhter with other
shortage of rebar and also the rain has not its impact on the progress of the project as the
has not been completed.

roblem for the contractor to properly carryout his activities on site due to access road
out the access road earlier inspite of repeated instructions.The Contractor has started access

Contractor is working with the available rabar size of 12mm diam. by changing spacing for
Construction of Decentralised Waste Water Treatment Plant Pilot Project fo
Weekly Progress Report
LOT-II WWTP2 Date: 25 July 2018

1 Weather: Day
Sunny
time-Mostly sunny ( only little rain in the afternoon), Night time
2 Health and Safety: No accident
3 Environment, Access & Community: NA
AAWSA made a decision on the replacement of Landustrie with W
4 Contractual Issues: Contractor's document for E-M works. I think you have the letter f
5 Civil Construction Activities: - Concrete pouring has been done for base slab of primary and
- Concrete pouring has been done for first lift wall of primary pu

6 E-M Installation Activities NA


7 Testing and Commissioning: NA
8 Other Activities: NA
9 Overall progress:
Measurement & Payment: NA
The Contractor could not proceed furhter with other works.The C
10 Variations: NA
11

12 Any Other Remarks: The weather condition has become the problem for the contractor to
condition.The Contractor has not carried out the access road earlier
some part of the access road in the compound. The Contractor is no
No delivery of new reinforcement bar.The Contractor is working with
other rebar sizes.

Signature __________________________________
ent Plant Pilot Project for Koye Fetche Condominium Site
Progress Report
July 2018 Prepared By: Eyob T.

n the afternoon), Night time-Rainy

ement of Landustrie with WABAG and the Engineer is requested to evaluate


I think you have the letter from Dr.Alem
r base slab of primary and biological sludge gravity thickeners base slab.
r first lift wall of primary pumping station and base slab of distribution chamber (Unit 3)

ter with other works.The Contractor's main reason is shortage of rebar.

20000
roblem for the contractor to properly carryout his activities on site due to access road
out the access road earlier inspite of repeated instructions.The Contractor has carryied out
ound. The Contractor is now using the route through the Free-Zone.
Contractor is working with the available rabar size of 12mm diam. by changing spacing for

500

10,000,000.00

1,225,000.00
11,225,000.00