1 Failure
1 Failure
1 Failure
1. Introduction
2. Basic Construction
3. Working principle
4. Basic Installation Practices
5. Standards and Practices
6. GTP and Specifications
7. Maintenance Practice
8. Testing Procedure
9. Case Studies
10. Comparative Study with threshold Value
11. Conclusion
12. Appendix
1. Introduction
Current Transformer is the important interface between the high level of power
system and low level of protection, measurement and control circuit in terms of current.
Wherever the values of current become too high, this instrument transformer (CT) is used
in the system to produce a proportional value for a scaled down replica to the secondary
working circuit of a system.
Current transformer is used with its primary winding connected in series with the
actual line current flow of the power system. The primary winding consists of a bar
conductor or a conductor with a very few turns and causes no appreciable voltage drop
across the winding. The secondary winding has large number of turns, the exact number
being decided by the turns ratio of the CT. The instruments/equipments like indicating
meters, relays etc are connected on the secondary windings, which have very low
impedance circuit. So the secondary windings are regarded as a circuit that works nearly
with short circuit condition.
The performance of the measuring transformers (CT and PT) during and
following large instantaneous changes in the input quantity are to be considered
seriously. The response of the electrical parameters of these transformers upon the
secondary circuit should be well within the satisfactory limit for both under steady state
and transient condition. For measuring and slow speed recording application, only the
steady state accuracy is relevant, whereas for high speed protection and other application,
accuracy under transient condition is also important.
According to the requirement of the secondary circuit the cores in the secondary
circuit of the CT are designed. These are of three types
1. Measuring current transformers (Metering core)
2. Protective current transformers (Protection core)
3. Protective current transformers for special purpose of application
(Protection core PS class)
Table-1
But from the base construction of CT, it can be described here that this instrument
has certain primary winding, which generally consists of a bar conductor or a conductor
with a very few number of turns. The CT has also secondary winding wound over the
primary winding and has large number of turns as compared to primary winding.
The use of windings and the arrangement of such windings decide the
classification of current transformer. The basic arrangement primary winding upon the
core is decided as the main factor for the construction practice of the current transformer.
2.1.1.a: Current Transformer (Wound type)
For this type of transformer, the primary winding of more than one turn are
wound upon the core and provides the primary section of the transformer. Such primary
winding is so designed that it could be able to carry the short-circuit current of the
system. According to the design and turns ratio requirement, the secondary winding is
accordingly wound to provide the required current on the secondary circuit of the system.
For such current transformer, the primary winding consists of a bar conductor of
suitable size and passes from one side of the CT to the other side. This conductor
becomes an integral part of the current transformer. The primary winding is regarded as a
conductor of a single primary turn and the secondary winding in the form of a toroid,
occupies over the primary conductor, with proper insulation between primary and
secondary winding.
This type of current transformer is similar to the bar type transformer. But such
type of CT has neither any primary winding nor any insulation for such winding is
provided.
Normally the bushing of the circuit breaker or the power transformer is used as a
centrally placed primary winding for such CT. The necessary winding and the insulation
such provided over the winding, plays the role of primary part of the CT. Moreover the
secondary winding being wound over the bushing primary provides necessary secondary
current to the circuit.
2.1.1.d. Core balance current informer
This category of CT is also similar to the bushing type and bar type CT. The core-
balance CT is normally of the ring type, through the center of which the three-core cable
or three single core cables of three phases system is passed. The basic use of such CT is
to monitor the residual current in the system. The sensitive earth fault relay is used on the
secondary of this CT to operate for the unbalance current in the system either due to the
fault or unbalance load in the system.
Core balance transformers are normally mounted over a cable at a point close up
to the cable gland of switchgear of other apparatus.
This type of transformer has no any primary winding and looks like a toroidal ring
that contains only secondary winding being wound over a core. The open space in the
centre allows the active conductor to pass through the CT i.e this CT is taken through the
primary conductor. This type of CT is also called Window type current transformer. This
CT has only one core and has only one CTR (current transformation ratio) and generally
used for small voltage rating system.
Ring Type CT
This current transformer is basically applied to supply the current to the indicating
instruments like ammeters, integrating meters like watt meters, energy meters etc……
The windings and design of cores of this CT are considered on the basis of the
requirement of the circuit. Metering circuit needs better accuracy performance, than the
knee point voltage margin. So the windings, that used for this purpose should have better
steady state accuracy factor, as compared to the transient accuracy factor.
The cost of the CT depends upon the metering core accuracy limit and the cost
becomes more for accuracy class nearer to zero. Now-a-days precision CT of accuracy
limit of 0.1 is also available for field use.
This current transformer is applied to supply the current to the protective relays in
the circuit like current activated relays, power relays and impendence relays etc...
For such transformer, the design of winding and core is considered on the basis of
knee point voltage (Kn), excitation current at this knee point voltage etc. The accuracy
limit factor of the CT is not that important as compassed to the metering class. But the
action and response of this winding for both in transient and steady state condition should
be active and ready to take action for operation of the relays in the circuit.
This type of current transformer is best suitable for the secondary circuit of relays,
used for special purpose applications like balance protection scheme (differential circuit)
and distance protection schemes. The knee point voltage, excitation current and
secondary resistance of such transformer, plays the important role to decide the
performance of the CT during the working operation on the circuit. These values should
remain within the specification limit for both in both in transient and steady state
condition up to the maximum through-fault current. This CT has generally of having low
impendence.
This type of current transformer is used for connection to the secondary circuit of
having both metering circuit of having both metering and protection scheme in the
system.
The design of the winding and core is decided in such a way, so that the accuracy
factor remains within the specification limit for all the stages of current loading on the
CT. To maintain such accuracy limit, the relevant factors like design, cost, space and
withstanding capability of the instrument (CT) are accordingly considered and becomes
more in comparison. But now-a-days such type of CTs are rarely in use.
For economical practice of the use of different number of secondary circuits from
a common primary winding of the current transformer, a unit comprising more than one
core can be designed. Such type of CT is designated as single ratio, multiple cores CT.
According to the characteristics of the circuit requirement, the core of the CT can be
designed separately. So from a single CT, different cores for different purpose like
metering core, protection core and protection core for special purpose etc. can be
designed.
By the use of a single CT and with the control of CT circuiting on primary and
secondary side, more than one current transformer ratio (CTR) can be obtained. These
ratios are obtained by the use of taps on the primary or secondary windings or both, or by
series/parallel connection of separate primary or secondary windings on a common core.
The insulation material such used in the current transformer plays the vital role
for the working principle of CT. According to the type and class of insulation used in the
current transformer, the voltage rating of the CT is decided and the classification is done
accordingly. Followings are the few mode of CT classification on the basis of insulation
used have been narrated.
These are small current transformers in which a small air gap is included in the
core to produce a secondary voltage output proportional in magnitude to current on the
primary winding. Sometimes termed as “transactors” or “quadrature CT”. Such type of
CT is rarely used in main power system circuit, because of its limitations.
The insulation used for this type of transformer is of solid and dry in nature. It
does not require the use of any liquid or semi-liquid material as the insulation of the CT.
The solid insulation may be of epoxy resin bound material or polarity type material. But
polycrete instruments have better strength in comparison.
For the case of few small voltage rating transformers, paper insulation is also
provided as the solid insulation and the range of such class is restricted to 13 KV range.
The epoxy resin filled (Bound) and polycrete instruments have ranges even upon 72 KV
class and the performance is well within the satisfactory limit.
6. Environment friendly
For this type of CT, oil is used as the insulation between primary and secondary
winding. In practice high di-electric strength oil impregnated paper being dried and
degassed is used as the insulation material. The oil is also filled over to this paper
insulation. Because of this design of insulation practice, it is called paper-oil insulated CT
also. To protect the paper oil insulation from ambient temperature, maximum CTs are
hermitically sealed by bellows arrangement.
Porcelain insulator stack of suitable and required voltage range is used to provide
paper insulation for the working limit of CT. This insulator stack should also be
mechanically strong enough to withstand the physical weight of the top tank and the
tensions of the conductor to the CT connection.
The design factors of HV and EHV CTs depend upon the following points also.
1. Use of HV insulation in CT
Generally post type current transformer is used in HV/EHV system. The basic
construction of this type of CT contains a common primary conductor and an insulator
(the post). One or more cores are arranged either at the bottom of the insulator around the
primary conductor or at the top of the insulator housing with primary conductor passing
straight through the CT. So according to the use of insulation and positioning of primary
and secondary winding, this post type CT is classified in two types.
In Hairpin type design, the primary winding is taken up to the bottom box, where
secondary winding are wound over the primary winding to obtain required ratio of the
CT. The major insulation is provided on the primary winding and housed properly in the
bottom tank, which is earthed or dead. Because of housing of the conductor is connected
to the earth, so such type of CT is called “DEAD TANK CT”. This CT also looks like
pendulum and called “Pendulum Design CT”.
DEAD TANK CT with CUT- SECTION VIEW
In Top Tank type design, the primary winding is spread in a uniform and
symmetrical way around the core and available in the top tank of the CT. The secondary
windings are wound over the primary winding inside this box. In live tank CT, the core
and secondary winding is insulated against the high voltage and major part of the
insulation is kept on the core and secondary winding. This transformer looks like inverted
CT, so also called “Inverted CT” and as housed in the tank, which is the live part of the
system, so called “LIVE TANK CT”.
LIVE TANK CT with CUT- SECTION VIEW
Considering the practical design pattern and use of insulation in the system, some
comparisons can be discussed as described below.
1 The core and secondary windings The core and secondary windings are kept
are kept in the top tank, which is in the bottom tank, which is earthed or
live (charged with system voltage) dead.
2 The core and Secondary assembly In Dead tank, the primary winding is
is insulated against the high brought down to the bottom tank and is
voltage in this live tank. insulated from earthed tank.
3 Insulation is on the core and Insulation is on the primary winding
secondary winding
6. Due to minimum length of primary For this design due to more length of
winding, the I2R loss is minimum primary winding and due to complicacy in
and thermal stability would be insulation design, the heat dissipation is
better critical. Heat generated is dissipated in two
stages i.e. winding to insulating material
and to the oil.
8 Due to top tank design, the Due to dead tank is preponderant at the
mechanical strength in normal base, therefore its mechanical stability is
condition is also hot stable. more in comparison
10. For the case of insulation failure is The main insulation is at the bottom part,
observed that top chamber and the failure causes less damage due to
insulator are scattered and damage contented bottom tank.
the surrounding equipments
2.1.5 Other Special type CT :-
Sometimes, it becomes necessary to calculate the total current drawn through a set
of parallel feeder emanating from a common bus system. To achieve this, summation
CTs are used. From the associated line feeders, the secondary windings of line CT are
wound on the primary side of summation CT, forming the primary winding of the CT.
This CT has a single secondary winding, which is connected to the circuit (burden). The
ratios of the feeder CT may or may not have same ratio. If individual feeder CT ratios are
the same, number of turns of each primary winding shall be identical. If however, the
feeders CTR are different, it shall be necessary for the manufacturer to alter the number
of turns of each primary with an ultimate objective of obtaining current on the secondary
side which is proportional to the summated load current. In such cases the individual
feeder CTR must be specified.
This current transformer is interposed between the main CT and the secondary
electrical circuit (Burden) of the system. The secondary circuit (winding) of the main CT
is connected as the primary winding of the ICT. The CTR and number of turns on the
winding is decided to feed the correct current magnitude to the burdens depends upon the
correction factor. These transformers are of small rating transformers and become the
burden for the main CT in the system.
Example: Suppose main CTR of 2000/5 or 2000/10, then suitable ICT of 5/1 or
10/1 can be used to get suitable overall ratio.
4. When it is difficult to design a main current transformer with low ISF, because
of various reasons, designed ISF can be achieved by using a suitable designed
ICT.
5. For controlling the saturation factor of the main CT and to restrict the maximum
current flowing through the burden, this ICT is also used in the system.
Advantages:
1. For correct operation of electrical circuitry and to match the main CTR with
burden load current, the use of ICT is the only choice to be provided in the
scheme.
2. To achieve the desired ISF for the main current transformer, ICT becomes
suitable for use in the system.
3. Even to limit the very high primary current for suitable range, ICT is
interposed in the system.
Disadvantages
1. The accuracy class of the circuit, particularly for metering scheme is raised.
Suppose, an ICT is used with a main CT of having accuracy class 0.2 and 0.5
respectively, then net accuracy would be 0.7 for meting circuit. So the error in
measurement would be raised, for the use of ICT in the circuit.
3. As ICT is connected in between the main CT and burden of the circuit, so the
possibility and chance of opening of the circuit becomes more.
4. It increases or reduces the size of the connected burden by the square of the ratio
used in the system.
In all of the above conditions, it can be concluded that the use of ICT in the
scheme causes error with extra burden to the system. So; unless otherwise desired by
the system or circuit, the use of ICT should be avoided.
2.2 Construction practice
For detail idea upon the construction practice of the current transformer, a typical
description has been explained for a live tank CT of rating 245 KV class.
For such type of CT, following are regarded as the main components for the
construction of the transformer.
4. Bottom housing box: This box is used to take out the secondary leads for
external connections. This box also contains grounding terminal pad with external
oil drain screw, lifting lugs/holes and mounting holes being the other accessories
of the CT.
3. Working principle
Primary winding of the current transformer is connected in series with the line
conductor whose current is required to be monitored. Secondary winding is connected to
the burden of measurement and protection circuit of the system. Primary current (I1)
results an alternating flux in the core and this flux causes induced emf across the
secondary winding. According to the use of primary and secondary number of turns in
the CT, the secondary current “I2” passes through the circuit. For theoretical practice due
to quality of primary and secondary Ampere-turns, the following equation holds good for
CT.
i.e. N1I1=N2I2 (Ideal condition).
But in practical current transformer due to the effect of magnetic circuit certain
excitation current (Also called no lad current) flows in the primary winding of the circuit.
Such excitation current is the resultant of I m (magnetizing component) and I w (Iron loss
or working component). So for actual practice, the primary current responsible for the
flow of secondary current “I2” is considered as I1’, but not I1 as explained in ideal
condition. To explain the above theory, the following vector diagram can be drawn.
[
PhaseError = β = 180 / ∏ (Im Cosδ − IwSinδ ) / I1 ]
In Vector Diagram
r I1
I1 ’
Ie Iw
Im
3.1 NOTES ON ERRORS IN CT:-
Actual practice under working condition of CT ; the flow of current on primary
and secondary side do not respond to the transformation ratio fully. Certain difference
results between actual transformation ratio and rated transformation ratio. Similarly the
phase angles of both the current do not match to the actual phase angle. Certain errors
result in both current ratio and phase angle.
The primary and secondary terminals of the CT are identified with polarity
markings by the symbols like (P1 and P2) for primary and (s1 and s2) for secondary. It is
marked with a common convention that when primary current enters the ‘P1’ terminal,
secondary current leaves the ‘s1’ terminal to the load circuit. So primary ‘P1’ terminal
corresponds to the secondary of ‘s1’ terminal. It is regarded as “DOT” convention. Its
significance is in showing the direction of current flow relative to another current or to a
voltage as well as to aid in making the proper connection. The same is explained in the
Fig. 2
P1 P2
S1 S2
Fig-2
Where
1, 2, 0 designate +ve,-Ve and zero sequence components.
a, a 2 are the operators,
Note: - Current vectors are in +ve sequence only with Current on R phase is taken as
reference.
IR Vectorial expression
IR = I , angle( 00 )
IY = I, angle (-1200)
IB = I, angle (1200)
IR+ IY+ IB= IN
IB Fig 3 IY
For delta connection of the CT circuit, the pattern of connection can be made by
two possible ways. In one type of connection secondary S1 of one phase is connected to
the secondary S2 of next phase in regular sequence (R, Y, and B). In other type of
connection secondary S1 of one phase is connected to the secondary S2 of next phase in
opposite sequence (R, B, and Y). The connections of the windings are shown in fig-4 and
fig-5 .
R phase S2 S1
S1 S2
Y phase
Y phase
B phase
B phase
IR
( IR-IB) (IY-IR)
( IB-IR) ( IR-IY)
IB ( IB-IY) IY
Fig-5-A
IB ( IY-IB) IY
Fig- 4-A
R phase
Considering vector analysis principle with “R” phase as reference and balance load
connection, the following results are expressed.
Table-4
P1 C2 Connection Sequence Current Ratio
Primary Secondary
(C1 + C2) S1 – S2 Lowest Ratio
C1 P2 ( CTR1 )
(P1 + C1), (P2 + C2) S1 – S2 Middle Ratio
( 2 CTR1 )
(C1 + C2) S1 – S3 Middle Ratio
S1 S2 S3
( 2 CTR1 )
(P1 + C1), (P2 + C2) S1 – S3 Highest Ratio
Fig -8
( 4CTR1 )
Consider the resistance of each portion between two consecutive terminals being
R ohm.( Fig-6) So, Value of resistance for different pattern connection will be as follows.
It also be noted here that the VA value becomes same for all patterns because of same
CT. Now value of current in each pattern can be calculated as follows for availability of
CT Ratio.
Table-5
Pattern Of Value Of VA Value
Connection Resistance
For such condition primary side has a particular no of turns (say N1) but the
secondary turns are tapped at different points to provide different ratios according to
involvement of no of turns in the winding.
Say total no of secondary turns = N for tapping between S1 & S2
Now the no of turns for tapping between S1 & S3 = 2N
And the no of turns for tapping between S1 & S4 = 4N
Now T1 / T2 = 2 & T1 / T3 = 4
In transformer current ratio is inversely proportional to the turns ratio
So, CTR2=2CTR1 & CTR3=4CTR1
Table-6
Connection No Of Turns Ratio = Primary/
Turns Secondary
S1 & S2 N T1 = N1 / N
S1 & S3 2N T2 = N1 / 2N
S1 & S4 4N T3 = N1 / 4N
Fig. 9
Fig.10
4.3 :- Installation Practice :-
1. By the use of suitable hoist or crane, the CT is handled vertically and lifted to
a suitable height for the installation on the platform. Mounting holes are
matched according to the foundation drawing and fastened to the support
properly.
2. Proper earthing of the Transformer is important and necessary earthing bolts
are provided for this purpose.
4.3.1.:- Pre-commissioning Tests.
The following preliminary tests are to be done before installation of the CT on the
platform to confirm the CTR and the insulation condition.
Table -7
Note (1)*:- to avoid corrosion, don’t connect aluminum terminals with copper
cables/tubes directly use weather resistance protective coating and suitable washers and
wire ribbon etc.
(2)* for the case of tapped secondary winding [IS1,IS2,IS3,IS4] if secondary circuit
is connected to any section say (IS1,IS2), then the other sections (IS3,IS4) of the same
winding must not be shorted.
(3)* in general convention “P1” terminal of CT IS installed towards the
substation Bus conductor.
5. STANDARDS AND PRACTICES:
Standards and practices are the limitation terms, to which manufactures,
purchasers, customers and other utility members, refer to maintain the required
performance of the CT in India. For the formulation of this standard, assistance has been
obtained from different institutions like CPRI, ERDA, NPL, ERTL, and IDIMI, CBIP,
IEEMA, SEBs, PSU, etc. Our national standard is IS 2750 (Pt I-to IV-1992) for CT,
which is even at the par with International level.
But it is observed over the years that the purchasers, customers while placing the
order with the manufactures, maximum time over- specify the specification than the
actual requirement, keeping the margin of safety more. This practice not only increases
the size and dimension but also increases the avoidable cost of the instrument. The
purchasers should refer the present standards and recommendations, instead of copying
the old specification and standards. They should specify the information as per the
requirement and suitability of the situation. It is known that the CT technology has
experienced a considerable development in various applications and accordingly the
standards have been modified to meet the requirements.
The standard of the CT basically covers the information on the following factors.
1. Ratio
2. Accuracy class
3. Rated Burden
4. Basic Insulation level and voltage class
5. Service conditions
6. Testing of CT
7. Marking of CT
5.1. Ratio of CT:-
Ratio of CT is usually mentioned as the ratio between the rated primary current to
the rated secondary current. The selection of ratio of current transformer depends upon
the selection of primary and secondary current.
Every CT has its own limitation of highest current flow in the primary winding
with the requirement of thermal rating and dynamic rating.
(i)Rated Short Time Thermal Current
The maximum value of primary current up to which the CT withstands for a rated
time of one second with secondary circuit being short-circuited called Rated short-time
current.
Note 1- Rated short-time current ( IST ) is taken as “150Ip” for 1sec, depending
upon the value of fault current “IF” . If “IF” is less than “150Ip” then the short time
current may be “IF’ with duration “t” such that √t=150IP/IF.
Note 2- In general duration time is selected “1 sec” for this rated short time
current.
The peak value of primary current (Normally of 2.55times the rated short –time
current) is considered as the rated dynamic current.
Note: - For testing of CT with rated dynamic current, the CT secondary circuit is
to be short circuited for 1 sec.
5.1.2 Rated Secondary current:
Standard rated secondary current as per IS 2705 (P-1 / 1992) are of 1 Amp or 5
Amp. For delta connected group the standard values are of (1/√3 = 0.578 or 5/√3 = 2.89
Amp)
Points for consideration:
1. The preference of secondary current depends upon the burden on the circuit.
2. It also depends upon the type and ratio of relays and instruments to be connected
in the circuit.
The accuracy class is decided according to the application of the secondary winding
and the type of core used in practice. Basically CTs are used for metering and protection
purpose. For metering purpose, the accuracy class is required to be considered seriously as
compared to protection class. Protection class needs robust performance even during
saturation region and so.
Where K= A Parameter that depends upon the system fault level and
characteristics of the relay.
Is = Secondary reflected Current
RCT = CT secondary resistance at 750 C.
RL= Resistance of secondary circuit with lead
Vk=Minimum Knee Point Voltage
Note :- (1) The Knee Point Voltage should not be less than the Minimum Knee
Point Voltage.
(2) The value of Vk should be left to the manufacturer with assumption of RCT
also.
Example:- Consider the CT core for differential relay with following data .
20MVA, 132/33 KV Transformer, % Imp=9%, CTR1=100/1 A, CTR2=400/1 A,
Fault MVA=2000MVA
Calculation:-
H.T Full Load Current=87.5 Amp
L.T Full load Current =350 Amp
Corresponding fault current on the basis of Fault MVA (2000 MVA) for LT
side=35 KA
Now IF =Reflected Fault current to Relay=35* 103 / 400=87.5
So K=2 IF =2*87.5=175
On the basis of % impendence and rating of transformer
Fault MVA=( Trf Rating/ p.u Impedance) (Considering Zero Source Impendance)
= 20 x 100 / 9= 222.22 MVA
Corresponding Fault Current =3.888 KAmp
IF =Reflected Fault current =9.72
So K=2 x 9.72 = 19.44 = 20 (Say)
So K can be taken as “20” instead of “175”.
Note: - Refer Appendix for selection of CT as per different manufacturer.
The satisfactory operation of the scheme for protection core, depends upon the
development of voltage across the winding to drive the current through the relays or
instruments during the time of fault.
So the selection of burden and ALF of the core is considered on the basis of
voltage developed during the fault condition. It is expressed as follows
Table-9
Rated Measurement Core Protection Core
Primary
Current 0.1 0.2 0.5 1 3 5 5P10 10P10
60 2.5 5 5 - 7.5
100 5 10 15 15 10 10
200 2.5 5 15 30 30 30 15 15
300 5 15 30 30 30 30 30 30
400 10 30 30 30 30 30 30 30
500 15 30 30 30 30 30 30 30
5.4-BASIC INSULATION LEVEL (B.I.L)
To identify CT for its withstanding voltage level, different voltage ranges are
generally mentioned in name plate details. Some of the voltages like NSV (Normal
System Voltage), HSV (Highest System Voltage), power frequency withstanding voltage
and Lighting Impulse withstanding voltage are provided to study the insulation level of
the equipment.. IS 2705/1992 (part 1 ) provides different Tables for various voltage range
from 0.66kv to 765kv.
Table.10 Table.11
Rate of insulation level for HSV FROM Rate of insulation level for HSV FROM
0.66 KV TO 245 KV 420 KV TO 765 KV.
Nomi. Highest Power Lightning Nominal Highest Power Lightning
System System Frequency Impulse System System Frequency Impulse
Voltage Voltage Withstand Withstand Voltage Voltage Withstand Withstand
KV KV Voltage Voltage KV (RMS) KV Voltage Voltage
RMS RMS KV RMS KV PEAK
(RMS KV RMS KV PEAK
List 1 List 2
Upto 0.6 0.66 3 - - 220 245 360 850
3.3 3.6 10 20 40 395 950
6.6 7.2 20 40 60 460 1050
11 12 28 60 75 400 420 950 * 1175
33 36 70 145 170 1050 * 1300
66 72.5 140 325 325 1050* 1425
110 123 185 450 525 524 1050* 1425
230 550 1175* 1550
132 145 230 550
* Switching Impulse Withstand Voltage in KV (PEAK)
275 650
5.5:- Service condition
Some standards are followed to put the CTs in service condition. These standards
are generally of ambient condition, Atmosphere climate condition, Earthing to the system
etc…
The values such mentioned are as per the India standard condition.
5.5.2 Altitude
Sometimes few users insist upon the manufactures to declare altitude factor for
the installation of CVT. But this standard is not so important for the installation of CVT
in the system. However for standard practice, this factor can be chosen up to 1000m
above mean sea level.
For both protection and safety of the system, earthing to the equipment is
considered as one of the most important factors. The following points are to be followed
as the normal standard and practice regarding the earthing of the equipments.
(1) The structure, framework upon which equipment is installed should be earthed with
two different terminals. The equipment base, marked with earth point has to be
connected to solid earth point.
(2) The earthing terminals should be of required size and protected against corrosion.
(3) The earthing of secondary star terminal should be done at one point only and
preferably it is to be done at switchyard instead of at control or Relay Panel.
(4) The star terminal of different core available in CT should be separately earthed.
5.6: - Testing OF CT
It is to be discussed under the section- 8 in detail.
5.7: - Marking of CT
Marking on CT includes the detail about CT regarding the ratings, burden, ratio
etc.
(i) Identification No, like Sl No, designation, type etc.
CONNECTION DIAGRAM
P1 C2
C1 P2
S1 S2 S3
5.7.2: - Typical Name Plate Details of 132 KV CT
Particulars Rating / Value Particulars Rating / Value
Make HIVOLTRANS ELECT. Type CB-14
PVT. LTD
Ref. Standard IS 2705-1992 Normal Sys. 132KV
Voltage
Rated Pri. 600-300-150 A Highest Sys. 145KV
Current Voltage
Insulation Level 275 RMS/ 650 PEAK S.Ty.Current 18.2/3
( KV ) Ka/Sec
Frequency 50 HZ Wt. Of Oil /Ct 120/550
Kg
Min. Creep age 3625 mm Drg. No 0-325/CB-
14/B/2031
Sl. No 0-325/B/1 Suitable For Hotline Washing
CAUTION
1. Sec. Terminals Must Be Shorted Before Burdon Is Disconnected
2. P.F. Testing Terminal to Be Earthed During Operation.
S1 S2 S3
RATIO 400-200-100/1-1-1-1-1
PRI/SEC 400/1 200/1 100/1
CURRENT (A)
PRI. CONN. P1C1– C1-C2 C1-C2
P2C2
SEC. CONNECTION.
CORE 1 1S1-1S3 1S1-1S3 1S1-1S2
CORE2 2S1-2S3 2S1-2S3 2S1-2S2
CORE3 3S1-3S3,S’ 3S1-3S3,S’ 3S1-3S2,S’
CORE4 4S1-4S3 4S1-4S3 4S1-4S2
CORE5 5S1-5S3 5S1-5S3 5S1-5S2
CORE 1 2 3 4 5
OUT PUT* - - 40 - -
ACC. CLASS* PS PS 0.5 PS PS
ISF/ALF* - - 5 - -
Vk (V) Min* 1200 1200 - 1200 1200
I exc@Vk 25 25 - 25 25
*(mA) Max *
Rct at 75 0 C 5 5 - 5 5
Max*
* AT 400/1 AND 200/1 RATIO ONLY
P1 C2
C1 P2
S1 S2 S3
6. GTP and Specification:-
GTP stands for Guaranteed Technical Particulars. Sometimes it is also called as
General Technical Particulars. The manufacturer of the equipment declares the values of
different technical parameters and satisfies to the customer if so desired, during the time
of inspection, by testing the equipment before the customer. The sheet such prepared with
these particulars is called GTP. It is similar to the rating plate, but values are mentioned
in detail.
Specification is an agreement term basically designed by the customers. Purchaser
specifies the values of the technical parameters as per the requirement and suitability,
condition to the reference standard that used in practice. Explanation regarding the terms
used in specification have already been described under the title standards and practices.
7. Maintenance Practice:-
The current transformer does not need any special maintenance. Periodically it
requires some scheduled checking and some testing practice as per demand. Following
maintenance schedule may be followed for current transformer.
MAINTENANCE SCHEDULE
Table-A
No Bellow Position Results and measures to be taken
1 All the CTs in the same station should CT insulation OK
have approximately same bellow position
2 At about 10 0 C, the position is approx at CT insulation OK
half between max. and min.
3 Different Bellow position for the same Observe the CT and check the oil leakage
identical CTs in the station on min. bellow position CT
4 Min. position bellow Check Oil leakage and take corrective
action.
5 Bellow position is independent of Bellow is not sealed properly and bellow
temperature might be jammed.
6 Bellow exceeds the max. position Problem in the CT due to internal gas
formation. immediately disconnect the CT
(8) Testing Procedures:-
Different Tests are carried out to check or compare the quality and design of the
current Transformer with the reference standards. These tests are class feed of three
types.
8.1. Type Test
8.2. Routine Test
8.3 Optional Test
8.1: - Type Tests
To compare and confirm the major parameters of the electrical equipment, some
tests, are required to be done by the suitable methods, available in different standards.
These tests are called “TYPE TEST”. Followings are few tests, categorized in TYPE
TEST.
8.1.1: - Short Time current Tests
8.1.2:- Temp- RISE Test
8.1.3:- Lightning impulse test
8.1.4:- Switching Impulse Test
8.1.5:- High voltage power frequency wet withstand Test.
8.1.6:- Determination of errors and other characteristics.
8.1.1.(a) Short- Time Current Test
During this test, the secondary windings are short circuited and current is applied
at a value of ‘I’ Amp for time‘t’ second, with a condition that
I 2
t ≥ I 2
st t r
Where
I st = Rated short- time current.
tr = Rated duration= 1 sec ( standard)
“I” = Current to be applied for testing
“t” = Duration of testing time
= (0.5 to 5) second.
8.1.1.(b):- Dynamic Current Test:
This test is also done with short- circuited secondary winding and application of
primary current as per the condition like
(1) The applied primary current should have the peak value, not less than the rated
dynamic current for at least one peak
(2) Sometimes this test may be mutually agreed by both manufacture and purchaser,
for conducting with a specified connected burden also.
8.1.1. (c):- Pre-set and post – set conditions
Before conducting the tests (Short-time and Dynamic Current Test), the routine
tests have to be carried out for reference.
After conducting the tests, the same routine tests have to be checked for
comparison and conclusion.
After, testing, the core has to demagnetized and the CT to be cooled to ambient
temperature for post-test checking. Following points are to be checked.
(1) Physical condition of CT
(2) The magnetic characteristic does not differ from those recorded before and after
the tests conducted. If so differ, it should not be more than half of the permissible
limit.
Particularly the ratio error, exciting current value, knee point voltage etc…
should have to be checked.
(3) It withstands the di-electric test, with the test voltages or current reduced to 90%
of those specified
(4) The insulation next to the surface of the conductor does not show significant
deterioration. This examination can be avoided if the current density in winding
corresponding to the rated short time thermal current one second, does not exceed
160A/mm2
Where the winding is of conductivity not less than 97% of the value given in IS
613: 1984.
According to the standard IS 2071 (pt-I and II); 1974, the test voltage shall be
applied between the primary winding and Earth. (Frame work, secondary winding
terminals are to be earthed together). The peak value and wave shape of impulse voltages
shall be recorded for comparison of the results with the testing standards for finalization
of the result.
8.1.3. (a):- Application of Voltage
CT as per its type and rating of voltage class, the number of full wave impulses of
each polarity either with correction for atmospheric condition or without correction for
atmospheric condition are applied during the time of testing. The following table can be
referred for impulses for application.
Table-13
CT No of Impulse Remark
Inddoor ≤ 36KV Five consecutive full wave
impulses of each polarity
with correction for
atmospheric condition
Out door ≤ 245KV 15 consecutive full wave For external insulation it
impulses of each polarity is “3” in number and
without correction for without correction
atmospheric condition
420 KV 3 consecution Full wave
impulses of each polarity
without correction for
atmospheric condition.
5 5 5
8.1.6.1 (c):- Instrument Security Current Test:-
For this test, primary winding is kept open and secondary winding is energized at
rated frequency of rms voltage equal to the secondary limiting emf. By application of this
voltage the excitation current is measured. It should be of least 10% when compared
w.r.t. the rated secondary current being multiplied by ISF.
Iex
× 100 ≥ 10%
I sec×FS
When : - Iex :- Excitation current obtained
Isec:-Rated Secondary Current
FS:- Instrument security factor
8.1.6.2:-Protection core:-
For protection core, three different errors are considered for accuracy class
measurement. [Current error, phase angel error and composite error]
8.1.6.2(a):- Current Error and phase angle Error.
According to the method described before, the testing is done and the values such
obtained are compared to the values in the following table.
ERRORS IN ( PROTECTION CORE) –Table-16
Note:- Burden to have p.fof 0.8 larg upto 5VA and unity p.f fo IVA TO 5VA
8.1.6.2 (b): Composite Error:-
Similarly for test comparison, the values in the above table are referred but here
tests are done in both direct method and indirect method. For detail testing under direct
and indirect method, different standards can be referred [Like IS 2705 PT.3 – 1992]
Two different methods are adopted for testing of over-voltage Inter-Turn Test.
1ST Method: - By this method secondary is made open circuited and voltage of at power
frequency is applied to the primary winding.
But this method of testing is generally not adopted due to the possibility of permanent damage to
the CT.
2nd Method:- By this method, primary winding is kept open and voltage at a frequency
limited to 5 times the rated frequency is applied to the secondary winding to produce, the rated
secondary current or the current corresponding to a value of 4.5KV peak, which ever is lower. The
applied voltage should be withstood for one minute without resulting any considerable disruptive
discharge.
8.2. 5.:- Partial Discharge Test:-
Partial Discharge is always associated with the degradation of insulation systems in high
voltage equipment. To know the status of insulation, this test is conducted. Two different methods
are adopted for this test.
Vk + 10 % Vk
+50% Iem
Exciting
Voltage
( Ve )
Iem
Exciting Current ( Ie )
Fig No. 13
(ii) Maxm Exciting Current:-
Similarly for obtaining the maximum excitation current the same procedure and
same curve can be referred.
(iii) Secondary winding Resistance:-
By the prescribed and suitable method /technique the resistance value of CT
secondary can be measured. The value of this resistance should be corrected to the
temperature of 75°c to compare with the specified value.
8.3:- Special Test / Optional Test
These tests are generally conducted by the mutual understanding between
manufacture and purchaser.
Situation/problem: - Tripping of one 132 KV feeder on E/F relay was observed at a 220/132 KV
Grid Sub-station, during peak load condition for the rise of load current above a particular load.
Steps attempted: - During off-peak load condition, the currents on the secondary circuits, used for
back-up relays were measured by means of clamp-on ammeter. The results were obtained as
follows in the table-19.
Table- 19
Phase / Current Ref. from Remarks Conclusion of the readings
Wire No. in m Vector From the readings of Back-up core
Amp. Diagram as described in the table, it got concluded
R ph. C11 61 OA O.K that “Y” phase secondary CT terminals
Y ph. C31 62 OB O.K have been altered and connected in the
B ph. C51 60 OC O.K circuit. The same can be confirmed form
Neutral. 120 BD=2OB Doubt? the vector analysis.(Ref. Fig- 14 A )
C71
C11+ C31 105 AB= 3OA Doubt?
C31+ C51 104 BC= 3OC Doubt? C11 R
C11+ C51 62 CD=OA O.K
C31
Y
A
C51 B
D
E
O C71
C B Fig-14
Fig-14-A
Situation/problem: - In one 132/33 KV S/S the indicating instruments (Wattmeter, ammeter etc) on
132 KV Incomer feeder were recording erroneous readings.
Steps attempted - During loading condition of the said feeder, the currents were measured in the
metering core circuit by means of clamp-on ammeter. The results were obtained as follows in the
table-.20
Table-20
Conclusion of the readings: - From the readings of metering core as described in the table, it got
concluded that “R” phase secondary CT terminals might have been shorted.
So the detail physical connections of the R phase were checked. But no such short circuiting
of the R phase was found. Instead of short circuiting, mixing of R phase winding was observed with
other core of same phase as like shown in fig-15. The analysis was confirmed by drawing the
vector diagram (Ref 15-A).
F B
Metering Core
O
E C
Y
D31 H D G
B D51 Fig-15-A
D71
E
Fig - 15
Situation/problem:- One 33 KV feeder was tripping on E/F relay frequently for the load
Current more than approximately 45 Amp. Line CTR = 200/1, Setting of E/F PSM= 0.1
Steps attempted:- Load current was restricted to 30 ampere for measurement of secondary current
in the Back up core. The currents are measured and tabulated as in Table-21
Table-21
Phase / Current Remarks Conclusion of the readings
Wire No. in From the readings of Back-up core as described in
m Amp. the table, it got concluded that “R” phase CT is associated
R ph. C11 184 Doubt? with wrong CTR, may be due to saturation of core or
Y ph. C31 151 O.K wrong primary connection.
B ph. C51 153 O.K
E/F C71 38 Doubt? The detail secondary circuit of R phase was checked
C11+ C31 172 Doubt? and found O.K. But on physical verification it was found
C31+ C51 152 O.K with the carbonized opening of one link on Primary side of
C11+ C51 176 Doubt? the CT. (Ref. Fig 16)
P1 C2 Carbonized opening
Resulting CTR error.
C1 C4
Fig- 16
C3 C6
C5 P2
Detail analysis of the Case Study 3:- The carbonized opening between the link C6 and P2, due to
loose contact and sparking, has developed an erroneous CTR.
For correct connection of links, the CTR is 200/1 with equivalent resistance (R ohm). But
opening of one link as shown in fig-16, has resulted the rise of equivalent resistance (1.5 R ohm)
Situation/problem: One newly commissioned 220/132 KV Auto transformer was tripping in REF
relay for the external fault on any 132 outgoing feeder. HT CTR = 300/1, LT CTR=600/1.
Steps attempted: - During load condition of the transformer, the currents on various windings
were measured. The values were obtained as mentioned in Table 22.
Table-22
Phase / Wire Current Remarks
No. in
m Amp.
HT R ph. C11 450 O.K
HT Y ph. C31 454 O.K
HT B ph. C51 455 O.K
HT E/F C71 18 O.K
REF circuit 21 Doubt?
Sec. NCT 12 O.K
LT CTR = 300/1
HT CTR= 300/1
NCTR= 300/1
R
REF RELAY
Fig. 17
9.1.5 Case Study No. 5
Situation/problem:- During stability test (Load balancing test) of a 132/11 KV transformer, the
following currents were obtained in differential circuit. Auxiliary CTs are used on both side of the
CT secondary winding.
Physically the LT CT secondary side was checked and found with a wrong connection link of
both S1 terminal of Y phase and B phase on the primary side of Auxiliary CT as like shown in Fig.
18.
Wrong Connection Link
S1 R
LT Side Y
Transformer B
Winding S1
Diff. RELAY. S1 S1 S1
Aux. CT
HT
CT
Secondary
Fig-18
Analysis of Current flow for case study 5 : For the above wrong connection, the current flow in
different circuits are explained below (Fig-19)
x x/2 x/2
3x 1.5 x
3x
3x 1.5x
IR0
Fig-19
Table-23
Phase HT side LT side Operating coil
R phase BA = 3x AC=1.5x BC= DB/2
( 300 ) ( 1800 ) ( - 900 )
Y phase DB = 3x 0 DB = 3x
( - 900 ) ( - 900 )
B phase AD = 3x DE=1.5x EA= DB/2
( 1500 ) ( 1800 ) ( - 900 )
E A
C
D B
Fig- 20
Remarks on Stability Test for Transformer: - The transformer secondary circuits contain both
star and delta connections. So behavior of current flow and analysis of the same becomes difficult
for delta connection. So for easy study of the current behavior, single phasing supply connection
should be used instead of three phase connection.
9.4 Case studies on Failure of CT
Situation / Problem: In one of the 33KV CT failed with violent explosion. The flying
debris and boiling oil scattered and damaged the adjacent equipments, resulting power
interruption in the system
Post incident Report: - The damaged CT was investigated and found with the
followings
1. Sparking at the joint between stud with the primary winding.
2. Rupture of primary insulation
3. Embuldging of primary box in scattered form.
4. Splitting of bushing porcelain.
Analysis:
1. The joint between the stud with the primary winding was found improper
due to bi-metallic material.
2. It is apprehended that the insulation material might have been suffered with
degradation and deteriorations trends, for which on severe condition it has
been ruptured.
3. Due to post incident effect and reparation of the insulation, both the bushing
porcelain and primary box have been scattered.
Analysis: The secondary circuit, connections etc. were checked and found in order. The
primary links, connections were ascertained also. No specific reason was concluded upon
the analysis.
But from experiences and observations it is concluded that the insulations
including oil might have been suffered in deterioration condition. So, the testing and
maintenance personnel were inquired about the IR and PI value, just before
commissioning of the CT. As reported that IR value was around 70MΩ at 2500V range
of megger. But P.I. value was neither taken nor recorded.
It is apprehended that P.I. value might have been in declined trend. It is seen from
experience that HV equipment like CT may fail during initial energisation with voltage
only, if P.I. value becomes less than 1 (one).
9.4.3 Case Study No. 3
Investigation and Analysis: - All the necessary checking of the Circuits were done and
found in order. It was suspected regarding the problem in earthing of CT secondary
circuit.
Some of the earth terminals were found with rusting and corrosion. The earth pit
resistance was measured and found with certain higher value of approx. ≅ 10 Ω. So,
during fault condition, due to delayed clearance of the fault from the system, the
insulation such provided might have been deteriorated, leading to final rupture and failure
of the CT.
Remedy: The earth terminals and earth pits condition were improvised and failure of CT
was completely reduced.
Observation:
(1) Enbuldging of primary box of the CT.
(2) Spilling of oil insulation from the CT.
Analysis: From the detail inspection of the available healthy circuit on adjacent panel it
was found with the followings:
1. Definite O/C relays are in use with minimum time set is 0.3 sec.
2. The CT secondary wires have been terminated with ‘I’ shape TBs (Terminal
Blocks) at relay panels.
3. The CT circuits have been earthed at both switchyard console box and relay
panel end.
Explanation: Use of definite O/C relay results the tripping of the circuit according to the
definite time set in the relay, irrespective of magnitude of current. Some times due to
close fault occurrence, the tripping time sets delayed and waits for the definite time set of
the relay. So, persistence of the fault current affects the secondary circuit, in turn the
insulation of the CT also.
The joints, connecting points of the CT circuit also play the role for increase of
the secondary burden in due course of time. For every fault occurrence on the system,
certain mechanical force develops on both primary and secondary circuit. Due to use of
‘I’ pin TBs, the terminal point on the terminal block is loosen, may be of very slightest in
nature, But succeeding fault occurrence in the system cause prominent loosening of
terminals and finally leads to the open of CT secondary circuit. This nature of opening of
CT secondary causes deterioration of insulation of the CT and final failure of the CT.
Moreover earthing at both switchyard console box and relay panel causes sharing
of fault current in parallel paths to earth. So, delayed de-energisation might be considered
as the cause of CT failure also.
Remedy:
(1) The definite O/C relays were replaced by IDMT O/C relays.
(2) The “I” pin TBs were replaced by ring and nut bolt TBs to avoid the
loosening due to fault.
(3) The earthing at relay panel was removed and the earth connection was
strengthened at CT console only.
Observation:
1. The porcelain insulation was broken and scattered into pieces, causing
damage to the adjacent CT.
2. The twin primary conductor with paper insulation was caught with
fire.
Analysis:
1. This CT during summer season was drawing overload current of 25 %
extra continuously for around 6 to 8 hourly daily. So, temperature rise
is one of the reasons of CT failure.
2. The CT was causing minor oil leakage also at the CT Clamp point, as
reported by the maintenance engineer, but due to non-availability of
shut down, the same was left un-attended.
3. It was noticed with a defect in connection of line conductor with CT
clamp at the CT stud. The conductor was in down ward bent and
connected to the clamp with tension as shown in figure. This tension
might have caused the crack of the insulator porcelain ring, causing
minor leakage of oil.
During summer season the insulting oil due to contraction and
expansion might have started with deterioration. For the first few
showers, the ingress of rain water has caused further damage of the oil.
But due to connection of line conductor in down ward slope and
during drizzle the ingress of rain water becoming more due to surface
tension, has resulted the final failure of CT.
Remedy: The height of CT support was raised for connection of the line conductor in
upward slope and less tension on the clamp in comparison.
10 Comparison Study with Threshold Values:-
1. Comparison is done between rated continuous thermal current and (Max. load current
+ 25% extra) current in the system. The load current should be within the limit of rated
continuous thermal current
2. Calculation on the basis of short time current is also taken into account for selection of
primary current.
Rated Primary Current = (Rated short time current for 1 sec) / 150
The less value such obtained by comparison of primary current calculation on the
basis of short time current and on the basis of max. Load current, is considered. Now the
data (value) such obtained is taken to the nearest multiple of underlined factors for final
value of primary value.
10.2.1 Example: - Consider CTR 800/1, 5p10, 20VA, Rct =5 ohm Rl= (2x1) ohm
Rrelay= 0.2 ohm (Numerical) Let fault current =20 KA (fault Current)
11. Conclusion:- This topic related to the study on current transformer provides
information regarding the basic construction ,working principle maintenance practice etc
of the instrument transformer. Some views, comments etc are restricted to Indian culture
study. Particularly case studies on CT Circuitry cover the fundamental approach of Vector
analysis of the currents from three phase supply source. Combination of the vector
analysis and study of the current value measurement in different circuits provides the
conclusive idea regarding the faults in the system. The various case studies as described
above are the physical examples of the practical occurrences. Moreover the table
described with the fault finding study for star connected circuitry becomes quite helpful to
trace the possible faults directly, without the study of vector analysis and fundamental
approaches.
12 APPENDIX
12.1 Appendix 1:- Fault finding study for Y connected CT protection circuitry.
Appendix Table-1
Application Knee point voltage Through fault If
Vk stability X/R
Transformers, Generators, 24In [R CT +2RI ] 40 15In
Generator transformers, Motors,
Shunt reactors, Series reactors
also
Overall generator- transformer 48In [R CT +2RI 120 15In
units,
Transformers connected to a 48In [R CT +2RI 40 40In
mesh corner, having two sets of 120 15 In
CTs each Supplying separate
relay inputs.
*Not Applicable :-Relay provided with ‘ Magnetizing Inrush Restraint ’ based on Second
Har monic Content of the inrush current and hence ‘Imag ’ calculation is not
applicable...
12.2.2 ( A ) ALSTOM
V K >2I f (R CT +2R L )
Example: V K >2x10(3+4) >140V
Where, I f =sec. equivalent of Fault Current
Ie =Is-Ir =(0.15-0.10) /2 =25 m A at V K /2
12.2.2 ( B ) ABB
Where: K=(1.2/40)x(I CC /I N )
I N =Main CT primary rated current, I CC =Max short-circuit current delivered to bus bar
via the input Where MCT is installed.
RTCP=Rest. of secondary of MCT, R F =Rest. of link loop between MCT and auxiliary
CT, n=Ratio of auxiliary CT , Rd/n 2 =Value of differential resistance transposed to ACT
primary
12.2.4.( C ) ABB
12.2.5.( B ) ALSTOM
V K >NxK1xIn(R CT +XR L )
Magnetizing current<0.05xIn at 10/In V
(B)For transformer feeder differential:
a. V K >50xIn(2.2/In2+R CT +R L )-for star connected CTs.
b. V K >50xIn/v3(9.7/In2+R CT +R L )-for delta connected CTs.
12.2.6.( A ) ALSTOM
Class:5P10, Burden:5VA
12.2.6.( B ) ABB
CT class: PS V K =50/ In + (I f / N) (R CT +R L)
In -Rated Current
I f -Maximum primary steady state through fault current
N -CT ratio, R CT -CT resistance, R L -Lead Resistance
Answer to Q1-In electrical system every winding should be such connected that for the
case of fault in the system, the current could be circulated in the winding to get easy
access to earth. CT is used for two different purposes (measurement and protection) in
the system. For these two purposes CT is connected with different burdens. For any
abnormality in the primary side of the CT like unbalance currents, fault currents etc. the
reflected current on the secondary circuit also becomes unbalance/abnormal. Now this
current needs certain path to flow to earth.
Moreover every winding (R-Phase, Y-Phase, B-Phase) requires certain return path
for circulation of current. This path is provided by the connection of either side (supply
side and load side) star connections by a common wire, called neutral wire. The earth
connection of star point plays the following roles –
Remark-
1. CT secondary star point should be solidly earthed.
2. Every individual core in CT secondary should be separately star connected and earthed.
3. The spare cores of CT secondary should be shorted and earthed.
4. Earthing used in CT secondary must be checked intermittently. Because failure of earth
connection causes the problem in CT, regarding the burden to the insulation due to
delayed subsidization fault current.
2) Why the star point in CT circuits should be earthed at one point only?
Answer to Q2.-
As already explained in detail in the answer of Q1, that star point earthing is used for
reference in the circuit and quick flow of reflected fault current to the earth terminal. So
during fault condition though available protections clears the fault within the minimized
setting time, still the de-energisation of the circuit needs certain extra time to settle down.
So far quick de-energisation of the circuit earthing plays the important role. Now the
discussion is to be concentrated whether to be earthed at one point or at multi point.
It must be at one point only, because multi point earthing provides fault current to
share through the parallel paths.
3) Why it is preferred to earth the star point near CT console at switchyard instead of at
control panel
Answer to Q3.-
The important of earthing in CT circuitry has been discussed clearly in the above
answers of Q1, & 2.
As CT circuit starts from the CT secondary terminals the driving voltage for the
current to flow to be regarded from the primary side of the CTs. The following points can
be summarized for the answer to Q3.
1. Generally Fault in the circuit results on primary side of the CT. So for quick reference
of the current flow the nearer end of CT secondary should be earthed.
2. As fault current is associated to the earth-terminal of the circuit ,so during fault
condition if protection used in the system gets delayed or does not actuate, then earthing
plays the role for flow of this current. So for safety of the working personnel the earthing
is to be done at the switchyard instead of control/relay panel.
4) What happens if metering core of the CT is connected to the protection circuit and
vice-versa?
Answer to Q4
Before answering this question the characteristics of different class of the CT
cores should be studied. The following table can be considered as the reference data for
answering the question.
Appendix Table-2 :-
From the characteristics table, it
Type of Metering Protn. Protn. concludes that the metering core needs
Core Special Type high accuracy class core with certain
Type burden across it. The role of the knee point
OUT PUT 20 to 40 - 20 to 40 voltage and the value of excitation current
ACC. 0.2 Fs<5 PS 5P do not become important for such core.
CLASS
Vk (V) Min - 600 - But for the protection core the fault
to1200 current on the secondary circuit plays the
I exc@Vk - 10 to 25 - role to clear the fault by the actuation of
(mA) Max protective device (relay). Here knee point
Rct at 75 0 - 2.5 to 5 2.5 to voltage to be considered for the working
C Max* 5 operation of the protection device instead
of accuracy class.
Now as per the discussion if the cores are interchanged then metering scheme will
be affected due to less accuracy class core and will result errors in reading. Similarly the
protection scheme will be affected due to quick approach of knee point voltage during fault
condition. For such possibility, the cores may be saturated in due course of time.
Answer to Q5-
For the saturation of CT core, the development of flux resulting for induced emf
across the winding becomes saturated quickly. So, with reduced flow of primary current the
rated secondary is obtained. This behaviour results with reduced CTR.
Answer to Q6-
Answer to Q7-
8) Why it becomes now-a days to have twin core secondary cable connection to the
terminals instead of single core cable above 500m meters of secondary connection?
Answer to Q8-
9) Why (Top Tank Primary Design CT) is preferred to old type Hairpin CT?
Answer to Q9
In Hairpin type design the primary windings are taken up to the bottom box
module where secondary windings are wound over the primary winding to obtain
required ratio of the CT. The top tank primary design is also called “Inverted CT
Design”. This design has primary winding on the top head of the CT and the secondary
windings are wound over the primary winding to obtain desired ratio of the CT. The
series parallel primary arrangements are also provided to derive different CT ratio. For
this design the primary winding is spread in a uniform and symmetrical way around the
cores, avoiding local saturation and reducing the leakage flux.
Advantages of Top Tank primary design CT
Because of single HV insulated tube instead of two primary HV conductors as in the
“Hair pin “ design the volume of the insulator and the volume of oil is reduced
Internal ground conductor has sufficient cross section for handling the fault current
Tank head design prevents projection or splitting of parts in case of faults.
So for the above factors the Tank head design CT is preferable than to normal Hair pin
CT.
10) Why combined CT&PT design is preferable now days?
Answer to Q10
Advantages of Combined Instrument Transformer
Because of combined unit the equipment achieves the following advantages.
Low weight and minimum oil volume.
Use of oil paper insulation reduces the space for insulation
Use of bar type primary conductor permits higher short ckt current & avoid the
large voltage drop across the winding.
Only one foundation is required in switchyard, which in turn reduces the
installation cost.
Perfect transient performance & use of suitable corrosion resistant material
increases the life span.
Because of uniformly distributed secondary windings it enhances guarantee,
accuracy for both nominal rating & higher rating values.
Disadvantages
The one and only disadvantage by this system is that for the case of failure of
equipment both CT & PT ckt associated to the system are hampered.
So maximum Indian utilities do not prefer the use of combined CT for higher rating
value. Moreover the Indian manufacturers have not yet started the manufacturing of this
type of CT. However combined CT up to 36KV range is in use in Indian scenario.
Basic constructions of CTs are all same irrespective of voltage class. But according
to the voltage class necessary electrical clearance and insulation are provided in the CTs.
So use of 132kv CT in 33kv system is possible. But the use of 33kv CT in 132kv system
will not be possible.
14) What are the reasons for which CT gets saturated?
Answer to Q14-
Saturation of CT causes quick rise of flux in the core. The following factors are the
reason for saturation of CT:-
1.Use of over burden loads in CT secondary.
2.Use of CT for primary current more than the allowable limit.
3.Continuous use of metering core for protection purpose and vice-versa.
4.Continuous operation of CTs to faulty currents.
5.Use of CT to DC current components.
15) For Delta connection of CT Circuitry what is the meaning of “D1” and “D11”
connection
Answer to Q15-
D11 connection
D11 connection corresponds to the current relation between phase current in
positive sequence, i.e.[(Ir-Iy), (Iy-Ib), (Ib-Ir)]
(Ir - Iy ) Ir D1 connection
For D1 connection corresponds
to the current relation between phase
current in negative sequence, i.e.[(Ir-Ib),
(Iy-Ir), (Ib-Iy)]
12.4 APPENDIX -4 STANDARDS USED IN OTHER COUNTRIES
Appendix Table-3
Appendix Table-4
Appendix-Table-7
Appendix-Table-8
No. Title
IS 335 : 1983 New insulating oil