Metering System Planning Procurement 250910 PDF
Metering System Planning Procurement 250910 PDF
Metering System Planning Procurement 250910 PDF
procurement
G.K.Panchal
1
What is planning
A definite course of
actions and designing
a process
S
t
a Gap
t Required
u planning
s
Current status
T1 T2
Time
3
Different levels of planning
Corporate level
Divisional level
Departmental level
Operational level
4
Importance of planning
Success of plan
Available standards
5
Planning process
Sequence out
various activities Identification of
alternatives
6
Types of planning
7
Effectiveness of planning
• Internal inflexibilities
– Psychological
– Customer behavioral
– Capital investment
• External inflexibilities
– Political climate
– Technological change
• Time and cost factors
The planner must have adequate
knowledge on all such aspects
8
Classification for planning of meters
• Type of meters
• Nature of application
• Location
• Different types of requirements
• Who will execute
10
Classification for planning of meters
• Type of meters
• Nature of application
• Location
• Different types of accessories
• Who will execute
11
Classification of Metering
Installations
Nature of Applications Location
Type of Meter
Nature of Applications Location
Single Phase
12
Classification of Metering
Installations
Nature of Applications Location
Type of Meter
Type of Meter
Location
Single Phase
Boundary Meters
DT Meters
13
Classification of Metering
Installations
Type of Meter Location
Type of Meter
Single Phase
Boundary Meters
DT Meters 14
Classification for planning of meters
• Type of meters
• Nature of application
• Locations
Current
• Different types of accessories transformer
• Who will execute Potential
transformer
15
Classification of CT
Classification of Current transformer
• Bar primary
– Ring type tape wound
– Ring type resin cast
– Ring type plastic cased
• Busbar primary
• For transformer meter
• Block CT
• Summation CT
17
•
Classification of Current transformer
Bar primary
– Ring type tape wound
– Ring type resin cast
– Ring type plastic cased
• Busbar primary
• For transformer meter
• Block CT
• Summation CT
• Large error on mismatch
of load & CT ratio
18
Let us study
Primary wound type CT
and Meter for DT Metering
19
Primary wound Bar
Potential lead
tapped from Bus Cycloeliphetic resin cast
& embedded in CT
resin
S2
S1
Cable is connected on
LT bushings of DT
21
Installation Process using Bar
Type CT
22
Installation using Bar Type CT
23
Advantages of Bar type CT installation
• Cable is not required to be stripped
• Same old Lugs can be used
• Special skills for threading of the cable is not
required for installation
• Special skills for Crimping the Lugs at a height is not
necessary
• Voltage tapping arrangement is in-built with the
device
• Aesthetically it is good looking as CT chamber
installation
• CT box is not required
3 core cable (two terminals of
the CT & one terminal for the
potential signal) are brought
Connected between out and connected to the
the LT bushings and meter
Load cables
Please observe
these stripes
27
For Higher ratio of CT
Let us study
Bar type CT and Meter for DT Metering
28
Loose CT and
Loose control
wiring
30
Potential lead For mounting on bushing stud
tapped from
Locating Member
33
Potential transformer
• Oil filled
• Epoxy cast
• Air cooled
• Gas cooled
• Outdoor
• Indoor
34
Welded chamber Designed kiosk with
CT/PT and Meter in
one Cubical
Meter
CT
PT
35
These are rarely noticed
Voltage
400 Amp
11000 volts
11,000 Volts
Secondary Voltage
Secondary Current
Primary
Such ideal CT
Ideal CT & PT PT can never be
manufactured
No leakage impedance
110
No losses
5
110 Volts
No excitation current
5 Amp
Why PT/CT have errors
This contributes
These currents are required
to Ratio error
for operation of the CT/PT
• PT / CT needs
– Current to magnetize the magnetic circuit
– Current for leakage impedance
• These Currents produce some voltage drop in PT/CT
• Primary & secondary currents are never perfectly 1800 in phase
Phase error
For example, a Class 0.5 CT (say 100/5 Amps) typically
delivers an ‘uncertain’ 4.975 to 5.025 Amps in secondary
at full primary current of 100 Amps
To ascertain Ratio & Phase angle error we need to test it
using a standard CT/PT comparator
Applicable Standards
0.5%
% Ratio Error
0.0%
0% 20% 40% 60% 80% 100% 120%
-0.5%
-1.0%
-1.5%
-2.0%
% Load
Permissible Phase errors
(0.5 Class CT)
Primary current
100
Exaggerated
80 view
60
Error due
40
phase angle
Phase Error (Min)
20
0 Phase angle
0% 20% 40% 60% error 80% 100% 120%
-20
-40
Actual secondary
-60 “Ideal” current due to core
Secondary magnetizing current
-80
current
Normally engineers are more concerned
-100
about ratio errors, but phase
Magnetizing
% Load currentangle
of errors
core that causes phase
also contribute angle
significantly
errors
Permitted error limits for
(0.5 Class PT)
“2.2%This
errordrifting
(or 3.6%is generally
error)” of the on
newthe negative
CT/PT gets farside
worse
& we don’t know without testing how bad it has gone
Every 1% error (for 1 MVA) leads to as much as Rs 2.35
lakhs per annum at 0.9 pf (@ Rs 3 per kWh)
Burden and Load for Accuracy Testing
Accuracy is tested at multiple points (as per
standards) to determine its full range behaviour
• CT
– Burden - 100 % and 25 % Eight test points per CT
– Load - 120 % , 100 % , 20 % & 5 % 8 X 3 units
Quick set up
Time consuming
Red Phase No environmental
instrument impact Environmental
impact
Results are logged
Chances of errors
No chance of error are high
46
DG set
CT/PT
under test
Red Phase
instrument
Generating Generating
Station-A Station-B
400kV
M 220kV M Inter Utility Metering
M
.
Tie Line Metering
Utility Tariff Metering
M
220kV
Grid Station
132kV M Metering
M
Sub Station
Metering
M
Sub Station
M Metering
M M
• Purpose
– Billing
– Information
– Revenue protection
– Planning & DSM
– Energy conservation
– Tariff restructuring
49
Customer metering ( Single Phase )
KWH
• Purpose KVAH
Load limiter 50
Customer metering ( Single Phase )
KWH
• Purpose KVAH
Load limiter 51
Customer metering ( Single Phase )
KWH
• Purpose KVAH
– Billing
KWH – last day of month-24 Hrs
– Information Maximum demand
– Revenue protection Time of day
– Planning & DSM
Load profile recording
– Energy conservation
Power factor recording
– Tariff restructuring
Voltage profiling Historical billing data
Load limiter 52
Customer metering ( Single Phase )
KWH
• Purpose KVAH
– Billing
KWH – last day of month-24 Hrs
– Information
Maximum demand
– Revenue protection Time of day
– Planning & DSM
Load profile recording
– Energy conservation
Power factor recording
– Tariff restructuring
Voltage profiling Historical billing data
Load limiter 53
Customer metering ( Single Phase )
KWH
• Purpose KVAH
– Billing
KWH – last day of month-24 Hrs
– Information
Maximum demand
– Revenue protection
Time of day
– Planning & DSM
Load profile recording
– Energy conservation
Power factor recording
– Tariff restructuring
Voltage profiling Historical billing data
Load limiter 54
Customer metering ( Single Phase )
KWH
• Purpose KVAH
– Billing
KWH – last day of month-24 Hrs
– Information
Maximum demand
– Revenue protection
– Planning & DSM Time of day
Load profile recording
– Energy conservation
Power factor recording
– Tariff restructuring
Voltage profiling Historical billing data
Load limiter 55
Customer metering ( Single Phase )
KWH
• Purpose KVAH
– Billing
KWH – last day of month-24 Hrs
– Information
Maximum demand
– Revenue protection
– Planning & DSM Time of day
– Energy conservation Load profile recording
Load limiter 56
Customer metering ( Three Phase )
• Purpose
KWH KW Calendar
– Billing month
KVAH KVA
– Information RKVAH PF
RKVAH PF
– Billing
– Information KWH – last day of month-24 Hrs
– Revenue protection Tri-vector recording
– Planning & DSM Maximum demand
– Energy conservation Scrolling feature
– Tariff restructuring
Time of day
Reading – power supply off Load profile recording
Tamper detection Voltage profiling
– Billing RKVAH PF
– Billing RKVAH PF
– Information
KWH – last day of month-24 Hrs
– Revenue protection Tri-vector recording
– Planning & DSM Maximum demand
– Energy conservation Scrolling feature
– Tariff restructuring
Time of day
Reading – power supply off Load profile recording
Tamper detection Voltage profiling
– Billing RKVAH PF
– Information
KWH – last day of month-24 Hrs
– Revenue protection
Tri-vector recording
– Planning & DSM Maximum demand
– Energy conservation Scrolling feature
– Tariff restructuring
Time of day
Reading – power supply off Load profile recording
Tamper detection Voltage profiling
– Billing RKVAH PF
– Information
KWH – last day of month-24 Hrs
– Revenue protection
Tri-vector recording
– Planning & DSM
Maximum demand
– Energy conservation Scrolling feature
– Tariff restructuring
Time of day
Reading – power supply off Load profile recording
Tamper detection Voltage profiling
– Billing RKVAH PF
– Information
KWH – last day of month-24 Hrs
– Revenue protection
Tri-vector recording
– Planning & DSM
– Energy conservation Maximum demand
Scrolling feature
– Tariff restructuring
Time of day
Reading – power supply off Load profile recording
Tamper detection Voltage profiling
64
Reading methods
• Eyeball reading
• MRI optical
• MRI RS-232
• LPR
• PLC / DLC
• Dialup lines
• Optical fiber
• GSM
65
Scrolling display
66
Billing methods
• Bill printing at Discom office & distributing
• Reading& bill printing on MRI ( Spot billing )
• Reading verification & bill printing on MRI
67
Billing & payment collection
• Cash
• Cheque
• Debit / credit card
• Net / phone banking
• Direct deduction from bank account
• Pre payment
– Cash / cheque/credit card at cash counter
– Phone banking
– Net banking
68
Payment Systems at High-rise buildings
69
Seal Management
• Sound installation practices should incorporate
seals as a guard against tampering of the meter
– Seal is not a lock
– Seals are used to detect unauthorized entry
– Seals are a means of security & safety for
meters
– Seals can be made of lead, metal, engineering
plastic etc.
– Examples of sealing methods are crimping,
pressing, wrapping,seal punch, pasting(stickers)
etc 70
Questions please??
Thank You