POTLINE 6 Readiness: SL No Date Equipment

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 10

Sl no Date Equipment

1 16.08.2018 ICT#5

2 16.08.2018 Lighting Trafo PM


3 16.08.2018 PFIC 53 Testing Tan delta, & LA wiring,CT/PT Glanding
4 16.08.2018 Store and lab job

5 16.08.2018 400/220Kv Switchyard SCADA upgradation V9.2 to V9.4

6 16.08.2018 POTLINE 6 readiness

7 16.08.2018 Grass Cutting in all SWYD


8 16.08.2018 UA/UC in Switchyard

9 16.08.2018 Housekeeping LCP U-31 to 36 & 41 to 46.

Unrestricted
Unrestricted
Sub Equipment Job description

3*250 MVA ICT -5 ICT#5 Pending job/support #61 and 66 isolator mntc team

Lighting Trafo Lighting Trafo PM


PFIC 53 PFIC 53 Testing Tan delta, & LA wiring,CT/PT Glanding
Store and lab job Store and lab job
400/220Kv Switchyard SCADA 400/220Kv Switchyard SCADA upgradation V9.2 to V9.4
upgradation V9.2 to V9.4

Potline 6 POTLINE 6 readiness

Grass Cutting in all SWYD Grass Cutting in all SWYD


UA/UC in Switchyard UA/UC in Switchyard
Housekeeping LCP U-31 to 36 & 41
to 46. Housekeeping LCP U-31 to 36 & 41 to 46.

Unrestricted
Unrestricted
Responsibility Technician /Supervisor team

Dinesh/Rajiv Manoranjan,Maheswar,Manoj,

Dinesh/Rajiv Diapk,Soumy barik


Amit/Brijesh N.Majhi,Anwar,MD Salim,Tabiz,Tukunu
Brijesh Judhistir,Purna

Brijesh

Bijay Manas,Bhoi

Bijay House keeping team.


UA/UC in Switchyard

Bijay House keeping team.

Unrestricted
Unrestricted
Job Progress From To

1-220kv 89A isolator L plate removed & trial taken.


2-UA/UC point attended.
3-Red oxide painted on junk area. 6:00:00 AM 7:00:00 PM
4-33kv side one layer insulated painting completed.& IR taken.
5-House keeping of ICT 5 & 220KV side done.

Lighting Trafo PM done & charged. 9:30:00 AM 5:30:00 PM


8 CT Tan delta done. 9:30:00 AM 5:30:00 PM
9:30:00 AM 5:30:00 PM

9:30:00 AM 5:30:00 PM

1- Bay 61&66 isolator pm done with electrical operation .


2-Unit-65,64&63 DM motor no load trial done & direction
checked  and unit-64 dm motor with pump assembled.
9:30:00 AM 5:30:00 PM
3-unit-66 control wiring termination done with glanding .
4-All scrap material has been 
segregated in front of unit 64.

9:30:00 AM 5:30:00 PM

Housekeeping done from LCP U-31 to 36 & 41 to 46.

Unrestricted
Unrestricted
Duration(Hours)

13:00

8:00
8:00
8:00

8:00

8:00

8:00

Unrestricted
Unrestricted