INSPECTION REPORT
Inspection Report No : 312 Issue Date : 24/09/18
Inspection Req. Ref. : -- Date of Visit : 24/09/18
Section A: Project Details
Client : Indo Jordan project Project : Indo Jordan project
Ion Exchange Job No. : 058000180196 Client PO / LOI No. : -
Section B: Vendor Details (Place of Inspection)
20182019/01/012/N/00276 &
00277, 00278, 00279 dated
Vendor Name : Castle Rubber Vendor PO / LOI No. :
11.09.18
1) Visually Check for Surface damage, Lining Thickness, Spark Leakage, Hardness (* Refer Punch
Points)
1) Vendor need to attend Surface damage at places identified during Visit ( refer Photos) (surface cut,
Notches, Overlapping, Padding, Hole size filing for Bolt fitment ) OPEN
2) Leakage Observed during Spark Test of SAC and SBA Header along with clamping, vendor need to
attend the same and reoffer. OPEN
3) Kindly mentioned the Bolt/Stud size used for holes attachment of Header, LCSM clamping after
Rubber Lining. OPEN
INSPECTION REPORT
Section H: Inspection Photos
INSPECTION REPORT
Non-Uniform Overlapping
Excess Rubber Padding to be Grind for Smooth Level