METHOD STATEMENT
Title: MS No.: NTT-GEN-MST-M-014-
R00
INSTALLATION OF PPR PIPES
Revision: 00
Page: 1 of 10
Method Statement
STATUS 2: REVISE & RESUBMIT. WORK MAY PROCEED SUBJECT TO INCORPORATION OF COMMENTS
INDICATED.
ENGINEER’S REVIEW AND PERMISSION TO PROCEED DOES NOT CONSTITUTE ACCEPTANCE OR APPROVAL
OF SUBMITTALS INCLUDING, BUT NOT LIMITED TO, DESIGN DETAILS, CALCULATIONS, ANALYSIS, TEST
METHODS, CONSTRUCTION MEANS AND METHODS, CERTIFICATES, OR MATERIALS DEVELOPED OR SE-
LECTED BY CONTRACTOR AND DOES NOT RELIEVE CONTRACTOR FROM FULL COMPLIANCE WITH THE CON-
TRACT REQUIREMENTS.
-------------------------------- --------------------------
Client Representative Date
Issued by:
RSN
F
METHOD STATEMENT
Title: MS No.: NTT-GEN-MST-M-014-
R00
INSTALLATION OF PPR PIPES
Revision: 00
Page: 2 of 10
TABLE OF CONTENTS
2.0 References
RSN
F
METHOD STATEMENT
Title: MS No.: NTT-GEN-MST-M-014-
R00
INSTALLATION OF PPR PIPES
Revision: 00
Page: 3 of 10
The works covered by this method statement sets out the procedures for the installation and
testing of the PPR pipes for hot and cold water applications in the TINS project.
Project Manager Planning the works and organizing the resources in order to
meet the project technical and timely target.
Lead the implementation of AGC HSE policies, procedures and plan
across the project.
The project Manager shall review all accident reports to ensure
that all the necessary corrective action has been taken and that
he has addressed any items that may require action on his part.
RSN
F
METHOD STATEMENT
Title: MS No.: NTT-GEN-MST-M-014-
R00
INSTALLATION OF PPR PIPES
Revision: 00
Page: 4 of 10
HSE Manager Ensure that the work is completed as per the project HSE re-
quirements and the approved Project Health, Safety & Environ-
mental Management Plan.
The HSE Manager shall ensure that the HSE control measures
listed in the Method statement and its respective Risk Assess-
ment are discussed to the workers and that all hazards associ-
ated with work and its preventive measures are understood and
complied.
CONSTRUCTION OF NAVAL TECHNICAL TRAINING, TINS AND MARINA FACILI-
TIES
CONSTRUCTION CONTRACTOR: PRIME CONTRACTOR: CLIENT:
RSN
F
METHOD STATEMENT
Title: MS No.: NTT-GEN-MST-M-014-
R00
INSTALLATION OF PPR PIPES
Revision: 00
Page: 5 of 10
He shall Inspect the work site daily to report and correct unsafe
methods, conditions and behaviors.
Stop work when conditions present imminent risks to people’s
life.
The following types of equipment and manpower will be employed for removal of wall and
ceiling. The number is indicated and shall be adapted to suit the required works. The tools
and equipment shall be operated only by operator.
MANPOWER
Sr No Designation No. of people
1 Site Engineer 1
2 QA/QC Engineer 1
3 Foreman 1
4 Lead man 1
5 Skilled laborers 3
6 helpers 5
TOOLS REQUIRED
1 Standard Plumber Tool Kit
2 Pipe Cutter
3 Welding Machine
3 Measuring Tape
4 Knife
Clearance and permit shall be obtained from BAE & Operation and Maintenance of RSAF
prior to the commencement of the work.
CONSTRUCTION OF NAVAL TECHNICAL TRAINING, TINS AND MARINA FACILI-
TIES
CONSTRUCTION CONTRACTOR: PRIME CONTRACTOR: CLIENT:
RSN
F
METHOD STATEMENT
Title: MS No.: NTT-GEN-MST-M-014-
R00
INSTALLATION OF PPR PIPES
Revision: 00
Page: 6 of 10
Approved drawings.
• All permanent materials will be protected from damages during the transporta-
tion and storage on site.
• Materials will always be stored in such a way that deterioration does not occur.
During storage, the pipes must be protected from direct sunlight and contami-
nation from dirt and dust.
• Storage of the pipes shall be arranged to facilitate the removal of the individual
pipes so that the damages such as scratches, dents etc. are avoided.
• Storage area must be clean and the ground must not be marshy or unstable
and it must not contain any corrosive material
• Pipes of different sizes will be stacked separately or where it is not possible,
pipes with larger diameters and /or thicker walls should be placed at the bot-
tom of the stack
• Suitable mechanical lifting equipment will be used for lifting and installation of
heavy pipes at high level.
• When mechanical lifting equipment is to be used, no metallic slings, hooks or
chains should be used in direct contact with the pipe. Ropes or web slings are
preferred, as they will not damage the pipe wall
• An MIR (Material Inspection Request) shall be submitted for each delivery.
• Pipes and fittings used for hot and cold water piping system shall be plastic PPR or
as approved by BAE.
CONSTRUCTION OF NAVAL TECHNICAL TRAINING, TINS AND MARINA FACILI-
TIES
CONSTRUCTION CONTRACTOR: PRIME CONTRACTOR: CLIENT:
RSN
F
METHOD STATEMENT
Title: MS No.: NTT-GEN-MST-M-014-
R00
INSTALLATION OF PPR PIPES
Revision: 00
Page: 7 of 10
8.1 Preparation
8.2 Welding
RSN
F
METHOD STATEMENT
Title: MS No.: NTT-GEN-MST-M-014-
R00
INSTALLATION OF PPR PIPES
Revision: 00
Page: 8 of 10
Table -1
CONSTRUCTION OF NAVAL TECHNICAL TRAINING, TINS AND MARINA FACILI-
TIES
CONSTRUCTION CONTRACTOR: PRIME CONTRACTOR: CLIENT:
RSN
F
METHOD STATEMENT
Title: MS No.: NTT-GEN-MST-M-014-
R00
INSTALLATION OF PPR PIPES
Revision: 00
Page: 9 of 10
• Verify the lines are properly installed. Check all connections are ok and shall be free
of damages.
• All fixtures shall be removed before test.
• Check the supports are properly installed.
• Water hammer arrestors should be removed from the system before testing. Tap all
points with proper closure.
• Hydro test pressure shall be 1.5 times the working pressure or as agreed with BAE
Site Engineer.
• Test water shall be clean.
• Calibrated and certified Pressure gauges shall be used.
• Air vents shall be provided to release trapped air.
• Apply a preliminary test pressure of 2 bars with hand pump. Check for any leaks. If
no leaks are found at 2 bars, gradually increase the pressure to the required pres-
sure.
• Hold the test pressure to 2 hours or as agreed by BAE Engineer to verify if any drop
in pressure.
• If hydro test is passed move for further installation of sanitary fixtures.
• If any leaks found, depressurize the system, fix the leak and retest as mentioned
above.
• An RFI (Request for Inspection) will be raised prior to testing.
CONSTRUCTION OF NAVAL TECHNICAL TRAINING, TINS AND MARINA FACILI-
TIES
CONSTRUCTION CONTRACTOR: PRIME CONTRACTOR: CLIENT:
RSN
F
METHOD STATEMENT
Title: MS No.: NTT-GEN-MST-M-014-
R00
INSTALLATION OF PPR PIPES
Revision: 00
Page: 10 of 10
Safety induction and toolbox talks will be conducted by the assigned supervisors and /or
safety personnel prior to commencement of work activities.
Warning Tape and barricade shall be provided along the working Area.
Dust suppression shall have carried out in all the place, where necessary.
Adequate supervision by Safety Officer and Site Supervisor will be carried out to ensure that all
work is being done safely.
Qualified First Aider should be there for the provision of First aid.
Members of the construction team will be issued with Personal Protective Equipment (PPE)
such as cover all, safety vest, safety shoes, safety glass, hard hat, safety gloves. Additional
protective equipment shall be issued as and when required.
Sufficient welfare facilities including cool drinking water and toilets shall be provided in close
proximity to the workers.
Fire extinguishers will be place near the equipment. Periodic check of the expiry date shall
be done.
All activities shall be closely monitored and checked according to the approved method of
statement.
.
Request for Inspection (RFI) as per the approved Method of Statement for this activity will be
submitted 24 hours before to the Client Consultant for approval. Any comments must be rec-
tified immediately.
All activities will be report to Employer/Engineer for review and approval.