Major Overhaul of LP Turbine and Generator: Unit-4, (250 MW) OPJSTPP JPL Tamnar-Raigarh (15/07/2012 To 31/07/2012)
Major Overhaul of LP Turbine and Generator: Unit-4, (250 MW) OPJSTPP JPL Tamnar-Raigarh (15/07/2012 To 31/07/2012)
Major Overhaul of LP Turbine and Generator: Unit-4, (250 MW) OPJSTPP JPL Tamnar-Raigarh (15/07/2012 To 31/07/2012)
Major Overhaul of LP
Turbine and Generator
Unit-4,(250 MW) OPJSTPP JPL Tamnar-Raigarh
(15/07/2012 to 31/07/2012)
Customer Service Order No.4400002853 Dt.03.07.2012
BHEL Job Order No. 120017
Prepared by
V.Veerapandi
Dy. General Manager/ ser
Contents
1. Introduction
7. Spares consumed
8. Commissioning
9. Turbovisory Parameters
10. Conclusion
11. Recommendations
13. Reports
1.0 INTRODUCTION
JPL-OPJSTPP Tamanr-Raigarh has four (4) units of 250MW KWU design TG set. These units
were commissioned during the year 2007-2008.
JPL awarded the work of LP Turbine & Generator along with TG Bearing inspection, HP-IP
casing centering and overhauling of valves & strainers.
Unit was withdrawn on 15.07.12 at 01.45 hrs for the present overhaul and LP-Generator
was decoupled in hot condition on 16.07.12 to speed up the Generator overhauling work.
Barring gear was stopped on 19.07.12 for TG bearing inspection & other associated work.
TG Bearing inspection, Overhauling of LP Turbine, MPI testing of free standing blades ,
overhauling of valves & strainers and Generator & Exciter was completed within 10.5 days
(Barring stop to Barring start) 17 days bar to bar.
After completion of all works, TG set was put on Barring gear on 30.07.12 at 02.00 Hrs. Unit
was rolled and machine was synchronized after electrical testing on 31.07.12 at 20.00 hrs.
All turbovisory parameters including bearings temperature & vibration were found well
within limits.
This report embodies the details of various activities carried out during this overhaul and
performance of the machine after overhauling.
1. Bearing Inspection 1 To 7,
3. OH of LP Turbine
4. Overhauling of Generator
5. Overhauling of Exciter
5.20 MOP
MOP was dismantled for inspection. Impellor, wear ring & gear coupling were visually
inspected and found in order. Governor impeller & wear ring (FS) and Thrust bearing
found damaged. Damaged components were replaced by new one. MOP Shaft run out &
clearances were checked and found OK. DP test was carried out in all the components and
found in order. MOP float was checked after final assembly & was found OK.
LP Turbine was opened for first inspection after erection. Visual inspection was carried out
in all the stages of moving & guide blades and found in order. Heavy deposit found in
moving & guide blades of stage no.1 to 6 and it was thoroughly cleaned by alumina blasting.
MPI testing was carried out on last three stages of free standing blades at both sides in
position (without removal of blades from rotor). MPI test revealed that the all free standing
blades are in healthy condition. LP steam path radial clearances recorded and clearances
found less in few stages of stationary & moving blades. Those stages were grounded off to
improve the radial clearances. Inner-inner casing ovality checked and measurement was
recorded.
LP rotor was placed in zero position and final steam flow path clearances were recorded. LP
inner-inner and inner-outer, outer casing were boxed up on 24.07.12 after joint inspection
of BHEL & JPL. No loose items & No foreign material was observed during the inspection.
LP roll check was carried out after final box up and minor correction was carried out on
top/bottom and Left/Right. Final roll check was carried out after correction & found ok. LP
outer boxed up on 27.07.12 after removal of all scaffolding materials.
LP extraction compensators bellows were DP Tested and found ok. Compensator bellows
and their supports and steam space were thoroughly inspected and found in order. LP
gland box centering checked and minor correction done at both side.
Exciter:
Exciter was dismantled for inspection. Visual inspection and electrical tests were carried out
on Exciter stator, rotor, PMG and rectifier wheels.
Stator:
Powder formation was observed in the stator end winding EE at few locations and same was
removed by proper cleaning. NFT of stator end winding joints at both EE and TE was carried
out, all the joints were found in good condition.
Rotor:
The RSO (Recurrent Surge Oscillograph) test was carried on rotor and result found
satisfactory. After CC bolt O-ring was replacement, Rotor air leak test was carried out N2 gas
and no leakage & no pressure drop was observed during the test. DP test was carried out
on Retaining ring and it was found ok.
03 MOP Thrust bearing & GOP impellor & Replaced by new one
wear ring found damage
04 IP SV 1&2 spindle seat and IP SV 2 Lapping done and 100% blue contact
body seat found dent mark achieved.
05 HP CV 1&2 seat found dent mark Left as it is
8.0 COMMISSIONING:
5.0 Oil injection test was carried out before synchronization and both over speed
tripping device were found operated.
6.0 Machine synchronized on 31.07.12 at 20.00 hrs
10.0 CONCLUSION
The unit was withdrawn on 15.07.12 at 01.45 hrs for overhauling of LP Turbine, Generator
and Exciter overhaul ,TG Bearing inspection, HP-IP casing centering, overhauling of valves &
strainers along with MPI Testing of LP free standing blades. All work was completed within
10.5 days (Barring Stop to Barring Start).
Machine was rolled and synchronized on 31.07.12 after completion of electrical test.
Machine’s performance after overhauling was found smooth and the vibrations &
Turbovisory readings found normal.
11.0 RECOMMENDATIONS
11.10 One no MS strainer element may be procured and kept as emergency spares.
11.11 One set of HPCV servomotor spring discs complete set may be procured and kept as
emergency spares.
11.12 Complete set of Clamping pieces for LP free standing blades (3L/3R,2L/2R AND
1L/1R) may be procured and kept as spares.
11.13 LP free standing blades MPI & NFT test may be carried out during the next planned
LP turbine overhaul.
11.14 One set of HP/IP SV&CV valve & servomotor fasteners are to be procured and kept
as spares for future overhauling.
11.16 Hydrogen cooler pipe line flange O-rings are to be procured and kept as spares.