Handbook On Process Safety Integrity For Utility Operators PDF
Handbook On Process Safety Integrity For Utility Operators PDF
Utility Operators
IN PUBLICATION
JULY 2014
1
Preface
2
Table of Contents
3
SECTION 1 : INTRODUCTION
1.1 Introduction
At the onset the challenges faced by common process operators is to lower Operational Risk and improve
Production Efficiency or…is the Key to better optimize how we manage operation and maintenance workload
against a developed risk management policy
The aim of this book is to provide an overview of the holistic understanding of assessing and understanding
operational risks and the need for standardization & systematization of working practices for prioritization of
safety related and production critical work
In connection with link between management of assets , safety and risks which is the theme of this book the
common link is the need for a process plant to maintain safe and reliable sustainable operational performance
The challenge for example in operating ageing assets as a common issue amongst utility operators is the need
for dependable equipment, competent personnel and effective systems. Some quotations regarding ageing
equipment from the UK Regulator
“Ageing is not about how old the equipment is. It’s about what is known about its condition, and how that’s
changing over time” HSE Research Report RR509 - ‘The plant ageing guide’
“Ageing is…where a component suffers deterioration and damage (usually, but not necessarily, associated with
time in service) with an increasing likelihood of failure…. HSE Research Report RR823 - ‘Plant Ageing Study’
The underlying theme of this book therefore is a set of ten common themes towards a sustainable plan for
asset and process integrity
1. Conduct an analysis with an approved asset management integrity performance instrument (Data & KPI
Collection)
2. Develop a Management Control Reporting System (MCRS)
3. Define the system, processes, people and entities evolved programs
4. Development of documentation/process standards
5. Design and agree a verification program/process
6 .Identification of Safety Critical Equipment and processes ( Safety Case, Bow-Tie, Hazid/op)
7. Define maintenance, testing, monitoring, inspections, and operations involvement
8. Risk management assured through QA/QC (development of performance standards, assurance standards
and maintenance strategies)
9. Integration of standards and specifications with tools and reporting
10. Training & Coaching program - ( KEY TO SUSTAINABILITY ! )
Some examples of some typical general challenges in achieving this may be as follows :
Dependable equipment : Equipment projected as not fit for purpose ,Increased congestion of equipment and
removal of redundant equipment ,replacement of obsolete equipment ,operation outside original design or
lack of turn down capacity , reducing equipment and key system reliability , need to upgrade to meet latest
HSE standards
Effective systems : Lack of clarity for ownership of knowledge between operator and sub-contractors , low
implementation of documentation systems ,Compliance with current and future environmental legislation
Competent personnel : Flexible and changing workforce, leaner organisations with increased reliance on sub-
contractors
4
1.2 Organisation and Responsibilities towards safety
Before we examine the role of Operation and maintenance and assets in the overall process / risk assessment
let us start with the theme of safety
As part of the importance of an organization in developing and implementing safety management systems
which are well described in many publications and books , so is not described here , it is important that in
developing n operational organization should also understands that its employees at all levels must play their
part in ensuring safety.
Improvements to the working environment take time and money, therefore everyone must realise that the
process of improvement is a continuous one. An operational organization should consult with its employees to
identify the most effective ways to make the improvements necessary
This is clear and in terms of an organization it is typically expected that all employees at all levels are
responsible for:
It is important to realize that as a typical statement that an organization should understand that health and
safety at work depends upon the inherent safety of the working environment.
so far as is reasonably practicable. Where the working environment falls short of the above standards, the
organization should strive to improve conditions until they meet the standards.
In addition to these universal responsibilities, setting an organization within the company should ensure the
clear roles and responsibilities of the managers and supervisors towards safety – Example of the typical
responsibilities as follows:
Managing Director
An organisation’s managing director is ultimately responsible for all health and safety matters in respect of the
organisation’s activities
Other Directors
Other directors within an operational organization are typically responsible to the Managing Director for all
health and safety matters in respect of the organisation’s activities.
They are responsible for the implementation of the Company Policy in accordance with the current policy
statement.
5
They are assisted by both the External Health and Safety Adviser and the OHS Manager. Their
responsibilities typically can include the following:
Reporting Health and Safety performance to the representative director every 3 months
Accepting and reviewing the monthly Health and Safety performance reports provided by their
reports
Keeping the Health and Safety Policy under review and recommending necessary or desirable
modifications to the Managing Director
Monitoring the implementation of the Company Policy and taking such action as is necessary to
maintain its effective functioning
Being alert and encouraging others to be alert to detect hazards, particularly those arising from
changed circumstances, and arranging for appropriate precautions to be taken
Arranging that their reports have adequate training, information, instruction, supervision and
resources to undertake their responsibilities
Authorising such expert advice from outside the Company as they judge necessary or desirable
Chairing safety committee meetings
Taking all reasonable opportunities to consult employees on health and safety matters and
encouraging suggestions for improvements
Keeping abreast of the health and safety aspects of statutory employment requirements and taking
action to maintain the Company’s compliance
Setting a personal example at all times
• Reporting Health and Safety training performance to the project manager every month
• Managing the Health and Safety Training Team (when set up)
• Maintaining a database of training requests from all business units using the Training Team
administrative resource
• Scheduling and delivery of training to all business units using the Training Team administrative
resource
• Ensuring that the Training Team are adequately resourced, trained and competent
• Arranging for expert advice and guidance for the training team, including preparation of training
plans, manuals and codes of practice
• Attending safety committee meetings
• Setting a personal example at all times
Safety Manager
• Reporting Health and Safety performance to the Managing Director every month
• Keeping the Company Policy under review and recommending necessary or desirable modifications
to the Project Manager
• Monitoring the implementation of the Company Policy and taking such action as is necessary to
maintain its effective functioning
• Arranging safety audits and safety inspections as required
• Being alert and encouraging others to be alert to detect hazards, particularly those arising from
changed circumstances, and arranging for appropriate precautions to be taken
• Keeping abreast of the health and safety aspects of statutory employment requirements and taking
action to maintain the Company’s compliance
• Arranging and attending safety committee meetings
• Arranging that Health Safety and Welfare appears as a standard item on the agenda for Monthly
Staff Meetings
6
• Taking all reasonable opportunities to consult employees on health and safety matters and
encouraging suggestions for improvements
• Organising and managing an annual Training Plan for all Operational and Maintenance staff
• Organising and arranging for any training required by Safety Representatives
• Providing advice on all health safety and welfare matters to all the organisations staff
• Investigation of all accidents, near misses or ill health, and reporting any findings to the Project
Manager and taking appropriate action
• Setting a personal example at all times
Site Managers
The Site Managers within the organization are typically responsible for:
• Consulting with the operational or maintenance teams and preparing a monthly Health and Safety
performance report for the Plant Manager
• Maintaining a working environment that, so far as is reasonably practicable, is without risk to the
health and safety of anyone affected
• Identifying any shortfall in the training needs of operatives and advising the plant manager
• Being aware of the Company Heath and Safety Policy, assisting in the implementation thereof and
taking such action as is necessary to maintain its effective functioning
• Being alert and encouraging others to be alert to detect hazards, particularly those arising from
changed circumstances, and arranging for appropriate precautions to be taken
• Attending safety committee meetings
• Setting a personal example at all times
7
Safety representatives
Safety representatives may be appointed from any level within the company to represent the interests of the
workforce with regards to health and safety at work. Whilst carrying out their Safety representative functions
they do not sit within the management structure and should not feel constrained by their normal operational
role.
It is important that an organisation develops and maintain a plan for continuous improvement of the working
environment and the health and safety competency of its employees. The start point for this plan is the
condition survey report which identifies the majority of defects on individual larger sites and common defects
at well sites. The plan will be a “living document” that continuously develops as new defects and training
needs emerge. The plan will also include a list of high risk activities and environments that require specific
procedures to keep people safe.
Each site owner will contribute to the plan by confirming or otherwise the defects identified for their site, and
by identifying further defects as they become apparent. The site owner will also identify the high risk activities
and environments on his/her site.
Each line manager will contribute to the plan by identifying the existing level of safety training for their direct
reports, and by identifying the training needs of individuals in relation to the work they do.
The plan will identify the estimated cost for improvements to the physical environment and will include a
budget for implementing the improvements over a period of time. Wherever practical, the budget will be
based on a cost benefit analysis so that the maximum risk reduction can be achieved at the lowest cost.
The plan will identify the estimated cost of providing training throughout the company and will include a
budget for initial and refresher training over time. The budget will be based on a risk benefit analysis so that
those employees most at risk from their work activities will be trained first.
The organisation should ensure that they will implement the plan for physical improvements by allocating
tasks and targets to each line manager and each site owner as resources become available. Some tasks will be
undertaken in-house, and some tasks will be delivered by external contractors. Each task and target completed
will be reported to the plan owner, together with a feedback form to record whether implementation achieves
the desired effect or not. Where a task or target does not achieve the desired effect it will be investigated to
find potential improvements so that, if repeated elsewhere, it will be increasingly successful
8
The organization should also wherever practicable, implement the plan for safety training by integrating the
safety and operational features of any task so that the training improves safety and operational performance
at the same time.
It is also essential that the organization provide a Health and Safety Handbook to each employee. The
handbook will provide information and guidance on controlling high risk activities and environments. Each
employee is expected to read the handbook and sign a receipt for it. The handbook will be reviewed at least
annually, and revisions made where necessary. The handbook will identify activities that require additional
training, enabling the employee to identify their own training needs
Performance will be monitored for physical improvements and for training, with each part for example
typically being allocated 50% of the total performance report.
Normal Reports ;
Performance against a plan is typically expected to be continuously monitored using the monthly report
mechanism. A standard monthly report form will be used that records tasks and targets allocated and training
planned. The reporter will state the percentage achievement for each item. The project manager will typically
collate the reports and provide an overall report to the Director every 3 months.
It is usual that the director will collate the 3 monthly reports and provide a summary report to the Board say
every 6 months.
Exception Reports :
Occasionally an incident may occur or a site may fail significantly to meet its targets. Should this happen, a
reporter at any level may raise or pass on an exception report for immediate transmission to the next level of
management. The report will provide details of the event and reasons for its occurrence. Where possible the
report should also include suggestions for improvement
Any accident/incident investigation report relating to a reportable event shall be treated as an exception
report and will always be transmitted to the Project Manager. Reportable events are defined within the
accident/incident investigation protocol.
It can be expected that say a safety advisor will carry out a number of internal audits each month in
consultation with the site managers. These reports will be used to verify the quality of the monthly reporting
mechanism.
International best practice is now seen as “goal setting” rather than prescriptive.
This requires managers at all levels to achieve an appropriate level of risk reduction, based on the
circumstances of the hazards faced in the specific work environment and the cost of reducing that risk. The
factors used to assess the risk and the risk reduction are:
For example, if there are damaged handrails in two similar locations, one of which is used regularly, and the
other used rarely, priority must be given to the location in regular use. The UK produces “goal setting”
Regulations based on the requirements of European directives on Health and Safety at Work. These
Regulations are generally seen as setting world-wide best practice and have been adopted either directly or
9
with small changes to suit local conditions by many countries across the world. The UK Regulations have the
benefit of being specific to the typical hazard, for example, the
Confined Spaces Regulations, the Lifting Operations and Lifting Equipment Regulations, the Manual Handling
Regulations etc.
Each site owner / network manager is required to identify defects on their site, using the Guidance Note to
assist in the process. To avoid overloading the data collection process, which would in turn overload the
prioritisation process, only one or two subject headings should be tackled at a time.
A single defects sheet contains space for 5 defects to be identified. At one sheet per week, some 250 defects
could be identified each year on each site. As there are physical and financial limits on what could be done on
a site, it is expected that no more than 1 or 2 sheets per week should be returned. This constraint will also
encourage site owners to concentrate on their known safety priorities.
A defects sheet should typically be completed and returned to the asset management team. The team will
enter the data into a database, assign priorities, and arrange for the work to be processed ether via the site
owner, or via a term or maintenance contract.
The database shall meet the needs of the asset management team for the purposes of safety and operations.
The database will contain the raw information, and further fields for priority, work ordered, progress,
completion etc. Reports shall be produced showing progress against identified priority defects and against all
defects recorded
Concerning a Safety Deficiencies Guidance Note this can be described as a prime working document for site
owners, which can be adopted as a means of identifying safety and operational deficiencies. Further
information is provided in section 5 and 6 dealing with asset assessments and asset safety condition surveys
Typically also the Asset Management Team can also construct the database for collation of the information,
such that the database serves all the needs of asset management, including safety deficiencies. Typically , also
this work is carried out in-house by the maintenance teams where practical and a term contract be established
with teams of specialists to carry out the remaining specialised necessary repairs and improvements identified
and prioritised by the Asset Management Team
10
Building or area: Equipment Identifier/ Asset Equipment description:
No:
Location of Defect: Safety Defect: � Operational Defect: � Both: �
Estimated Priority (1 to 5, 1 = urgent):
Description of defect:
Note : Below is a typical/ example only which needs to be developed on site specific basis
11
• Inadequate ventilation of spaces have an adequate barrier to access.
confined spaces entered • Repair/maintain or install adequate
regularly permanent ventilation and clean any filters
as necessary
Electricity What to look for. What to do.
• Open or unlocked panels. • Close and lock all panels not being
• Isolating panels without lock‐off worked on.
facilities. • Ensure isolating panels can be locked off.
• Loose cables. • Secure loose cables to cable trays or
• Improper cable connections similar.
(chocolate block, bare wire etc.) • Remove all improper cable connections
• Live conductors in panels without from site.
shrouding. • Accessible live conductors must be made
• Sagging overhead cables. inaccessible by shrouding or similar.
• Cables on walkways • Ensure overhead cables are properly
• Unfenced high voltage supported and place warning signs if a high
transformers. vehicle hazard remains.
• Note: detailed electrical safety • Re‐route cables away from walkways.
inspections must be carried out • Fence or otherwise protect all high
by competent electricians. voltage transformers, and place warning
signs.
• Arrange for a competent electrician to
inspect the site.
Fire Safety What to look for. What to do.
• Adequate numbers of fire • Provide additional extinguishers as
extinguishers. necessary.
• Extinguishers in date and • Arrange a central contract for inspection
correctly mounted. and replacement of extinguishers.
• High risk areas (oil, grease and • Place warning signs for high risk areas.
fuel storage, packaging, stores). • Check fire hose reel operation and
• Fire hose reels in good condition. arrange for maintenance if necessary
Lifting equipment What to look for. What to do.
• Current certification. • Arrange for certification of the
• All equipment in good condition, equipment. Annual for all lifting equipment
• Lifting accessories marked with and 6 monthly for accessories.
safe working load. • Destroy or scrap all accessories in poor
condition, arrange repair or maintenance
of lifting equipment.
• Accessories not marked with safe
working load to be scrapped.
Chemicals What to look for. What to do.
• Chemicals stored in unmarked • Remove and dispose of all unmarked
containers. containers.
• Acids and alkalis stored together. Where necessary, arrange for disposal as
• Excessive storage of chemicals in hazardous waste.
containers rather than in bulk • Acids and alkalis must be stored
tanks. separately. Where both are needed in a
• Spills of chemicals. closed environment then store each type in
• Old containers of paint, oils, trays or bunds to limit the possibility of
greases etc. in workshops. mixing.
• Waste oils in transport workshops. • Limit orders of chemicals to manageable
amounts, do not order more than can be
used in a month, or consider changing to
bulk storage.
• Chemical spills to be mopped up with
absorbent material or diluted with water (if
12
safe) and washed away.
• Old containers of paint, oils and greases
should be disposed of as hazardous waste.
• Waste oils produced during vehicle
maintenance should be stored in
flameproof containers and collected from
site weekly
Slip, trip or fall What to look for. What to do.
from height • Uncovered and unprotected • Replace covers to openings where
openings into chambers, tanks practical, and place barriers around
etc. openings where the cover cannot be
• Coverings to walkways, tanks etc. in replaced immediately.
poor condition or not properly secured. • Identify covers in poor condition or not
• Loose, damaged or missing properly secured and schedule them for
handrails or toe‐boards to maintenance or replacement/repair.
elevated walkways. • Identify missing handrails and schedule
• Fixed ladders in poor condition, them for immediate replacement/repair.
corroded or loose. Loose or damaged handrails and
• Portable ladders in poor toe‐boards must also be scheduled for
condition, damaged or painted. maintenance or repair as a second priority.
• Scaffolding platforms constructed Overall priority must be given to areas in
without adequate handrails, toeboards or frequent use.
scaffold boards. • Fixed ladders in a dangerous condition
must be marked with a warning sign and
repaired or replaced as a high priority.
• Remove from site all ladders in poor
condition, damaged or painted.
• All scaffolding must be inspected on first
construction and each week thereafter.
Any scaffold that does not meet acceptable
standards must be marked with a “do not
use” sign until faults have been corrected.
Pressure systems What to look for. What to do.
• Pressure vessels out of inspection date. • Arrange inspection and certification.
• Corroded or damaged pressure • Arrange repair or replacement, if badly
vessels. corroded take out of service.
• Safety devices not functioning or • Check safety devices regularly (pressure
not tested. relief valves, pressure gauges etc.)
• Pressure vessels without a • If no plate is present, can the vessel be
manufacturer’s plate. identified in the O&M manual. If so, mark
• Pressure lines subject to damage or the pressure vessel and provide details
unprotected. nearby.
• Jubilee clip type fixings on • Pressure lines to be moved to a safe
pressure lines. location and protected as necessary.
• Jubilee clip type fixings to be replaced
with correct fixings (may need special
crimping tool).
Mobile plant What to look for. What to do.
• Keys left in. • Keys of all plant to be kept in a key press
• Plant in poor condition. when not in use.
• Plant not needed. • Arrange for repair/maintenance of plant
• Plant used by unauthorised in poor condition.
people. • Consider relocation of redundant plant.
• Passengers riding on plant. • Do not permit unauthorised persons to
use plant.
• Do not permit passengers to ride on plant
13
unless correctly seated.
Machinery What to look for. What to do.
• Unguarded moving parts of • Provide guards to all moving parts of
machinery. machinery on a risk based priority.
• Machinery that may start • Mark machinery with “warning – may
automatically. start
• Potentially hazardous machinery automatically” as appropriate.
without an emergency stop. • Fit emergency stops to potentially
• Machinery capable of being dangerous machinery that does not already
reenergized directly from an have one.
emergency stop • Check that resetting the emergency stop
• Machinery incapable of being does not reenergize the equipment
isolated and locked off. directly. If it does then place a warning sign
and arrange for re‐wiring.
• Ensure that machinery can be isolated
and locked off where necessary for safety
when carrying out maintenance or repair.
Deep water or What to look for. What to do.
sewage • Open tanks or pits without • Place barriers around all high risk tanks
barriers. and pits.
• Unguarded lagoons/reservoirs. • Place warning signs on each side of
• Missing lifebuoys and lifebuoy lagoons “warning – deep water”
ropes. • Ensure lifebuoys are replaced, with a 10
• No warning signs. m cord attached to each one.
• Access to the public. • Place warning signs on all other tanks and
pits where there is a risk of drowning.
• Prevent public access to reservoirs,
lagoons or similar. If this is not practical
ensure that adequate signage is placed.
Site security What to look for. What to do.
• Site fencing damaged or missing Site • Schedule replacement/repair of fencing
gates damaged or missing. on a priority basis.
• Locks missing or inoperative. • Replace or repair gates.
• Sites not security signed. • Ensure locks are present, functioning and
• Inadequate fencing i.e. not high in use when the site is left.
enough. • Place security signs on all gates and on
• Boundary walls in poor repair fences and boundary walls where
appropriate.
• Review security need and replace
inadequate fencing.
• Repair boundary walls.
Cutting and What to look for. What to do.
grinding • Cutting disk machines without • Replace/secure guards or take out of
equipment guards or with unsecured guards. service until
• Damaged disks guards can be replaced.
• Badly stored disks. • Dispose of any damaged disks.
• Grind wheels with missing or • Check storage of disks (vertical on pegs)
badly set guards. • Replace/secure guards or take out of
• Worn grind wheels. service until
guards can be replaced.
• Worn grinding wheels to be replaced or
dressed.
Manual handling What to look for. What to do.
hazards • Heavy covers. • Provide simple lifting equipment to aid
• Heavy chemical drums. handling.
• Valves etc. in difficult or awkward • Chemical drums and similar to be carried
14
locations. on pallets.
• Review the position of valves etc. and
change them
during maintenance.
Hot surfaces What to look for. What to do.
• Compressors with exposed • Compressor pistons should be shielded
pistons. from contact
• Air lines leading from using steel mesh or similar.
compressors to pressure vessels. • Air lines should be placed out of reach or
• Combustion engines with be
exposed exhausts. otherwise shielded from contact.
• High temperature lights in • All engine exhausts should be shielded
accessible places. from contact
by mesh guards or by being out of reach.
• High temperature lights (for example
halogen work
lights) must be protected with a mesh
cover
preventing contact with the lamp itself.
Lighting What to look for. What to do.
• Lamps not functioning. • Replace the lamps if accessible.
• Dirty lamp covers. • Arrange a cleaning programme for
• Inaccessible lights. accessible lamp
• Inadequate lighting. covers.
• Consider moving inaccessible lamps to an
accessible
point.
• Provide additional lighting at an
accessible level.
Fragile materials What to look for. What to do.
• Roof coverings with skylights and • Mark the edges of the roof with warning
asbestos cement roofs signs saying fragile roof.
Slip, trip or fall on What to look for. What to do.
the level • Waste materials on or near • Remove existing waste material, clean up
walkways. before and after any maintenance or
• Pipes, conduits and cables operation activity.
crossing walkways. • Where practical, re‐route pipes, conduits
• Leaking water, particularly onto and cables away from walkways.
hard or tiled surfaces. Alternatively, provide steps and platforms
• Oil or diesel spills on hard or tiles over the trip hazard.
surfaces. • Identify leaks for repair and schedule the
• Changes in level, slope or surface work on a priority basis.
• Clean up oil and diesel spills immediately
using an absorbent material, or use sand if
nothing else is available.
• Identify and mark changes in level or
slope that represent a trip hazard.
Noise What to look for. What to do.
• Any environment where you • Check for damaged or defective
cannot hold a conversation at 2 equipment making more noise than it
metres. Of which the following should and schedule it for
are examples: repair/maintenance.
‐ Areas where very loud noises Provide warning signs and hearing
occur regularly. protection. Where a single note noise is
‐ Generator rooms or containers. produced, select the hearing protection to
‐ Rooms where a loud single note is suit the noise. Limit or control entry to high
15
produced such as blower rooms and noise environments.
pump halls.
‐ Damaged or missing exhaust
systems from combustion
engines.
Asbestos Asbestos cement roof or shade. Asbestos management plan as per local
• Damaged or broken asbestos regulations
cement sheets. (normally in roofs or
shades) and broken pieces of asbestos
cement in walkways or roadways.
Traffic on site What to look for. What to do.
• Traffic routes causing problems • If practical, re‐route access and delivery
with access or delivery. routes to reduce or eliminate the
• Parking areas not adequate. problems.
• Dangerous corners. • Review parking needs and provide more
• Uneven or damaged roadways. if necessary.
• No separation between vehicle • Place sightline mirrors at dangerous
routes and pedestrian routes. corners.
• Repair damaged or uneven roadways.
• Separate vehicle and pedestrian routes
with bollards or with painted hatched
walkways.
1.8 Training
It is strongly recommended that the organization develops guidance note for training as the prime working
document for site owners and line managers. This is based upon Training Needs Assessment process for
identifying training needs for individual employees and an established database for collation of the
information and scheduling training.
It can also be noted that design of courses and delivery of “Train the Trainer” courses, required the initial
delivery of training be contracted out to a competent qualified person and also training validation is also
required over a period of time to confirm the appropriateness of the training and the quality of delivery.
As example regarding the provision of personal protection it is only personal protective equipment such as
head protection, foot protection and reflective vests do not require training. The following table lists
equipment with its essential training requirements
16
Safety line – used to prevent or limit falls during Tying off the safety line (use of standard knots)
access to Selection of anchor points
confined spaces or when working over openings into Correct position of snatch lock
tanks etc. Operation of the snatch lock during a descent
Difference between fall prevention and fall arrest
Fall arrester- can limit a fall to less than 2m, can also When to use a fall arrestor
be used to restrict the likelihood of a fall How to secure it
What happens to it after use
Gas detector – used to identify hazardous Turning it on and checking function, including sensors,
atmospheres self
calibration, battery life
Understanding the readings and hazard levels
Peak and average readings and their meanings.
The below is example which needs to be developed for site specific and organization requirements. This gives
an outline indication only of the type of requirements for an organisation to identify a training need, and to
assign a priority to it for operations and maintenance personnel
17
chlorine emergency repair kit.
Lifting operations 1 day initial, 1 day refresher Maintenance and
Checking equipment – safe working load, operations personnel
equipment condition, slings, shackles etc. carrying out lifting
Lifting pumps – connections to pumps, operations
isolation
and lock‐off, lifting procedure, safe set‐up,
cleaning pumps for inspection.
Lifting other equipment – slinging, centre of
gravity, securing slings, tag lines and
control,
hand signals
Work equipment ½ day initial, ½ day refresher Operations and
Work equipment general hazards – maintenance personnel
electrical,
cutting equipment, fire hazards, guards,
safe
operation.
Fault finding and reporting – daily checks,
taking
out of service etc.
Safe use – location, other persons, noise,
public
etc.
Manual Handling 1 day Operations and
Human body – capabilities, strength, maintenance personnel
weaknesses, age effects
Handling loads – general lifting, pushing,
pulling
Inspection chamber covers – problems and
solutions, lifting techniques, two person
lifting,
key length
Fire fighting ½ day Operations and
Causes of fire – air, ignition, fuel, electrical. maintenance personnel +
Hazards from fire – burns, asphyxiation, 10% of office staff.
property damage.
Types of fire extinguishers – water, CO2,
powder, foam, checks to be carried out.
Use of extinguishers ‐ practical
Emergency first aid ½ day Operations and
Accidents – types and seriousness maintenance personnel +
Dealing with an injured person 10% of office staff.
Responses
Breathing
Airway
Circulation
Resuscitation
Permit writing ½ day Selected operations and
Types of permit – permit to enter, permit to maintenance personnel
work, permit to dig.
Responsibilities of permit writer
Practical exercises
Electrical safety 2 days Electricians
Basic electrical safety
Isolation procedures
18
Locking off procedures
Safety checks
Test equipment
Sanction to test
Permit and permit writing
Working lock‐off
Construction 2 days Construction
safety Excavations supervisors/foremen
Scaffolding and ladders
cranes
plant and machinery
traffic management
concreting
site wiring
power tools
cutting and welding
operability of finished work
stores management
waste materials
welfare facilities
COSHH ½ day Laboratory staff and
Handling chemicals personnel handling
Storage of chemicals chemicals
Protective clothing
Managing incidents and spills
Effects of chemicals
First aid for chemicals
Table of contents
• Preface
• Objective
• Responsibilities
• Natural & Chemical Features
• Synonyms
• Classification
• Usage Of Chlorine
• Chlorine Cylinders & Containers
• Chlorine Hazards
• Relation Between The Size Of Gas & Liquid
• Interaction With Water
• Fire
• Chemical Interaction
• Hygienic Effects
• Provisions Of General Erection & Building
• Design & Erection
• Exhaust & Ventilation Fans
• Gas Anti Leakage System
• Heating Temperature
• Electric Systems
• Fife Fighting Systems
• Security Measures
• Components Of Chlorine Dozing Room
• Preventive Operation Procedures
19
• Preventive Handling Procedures
• Preventive Procedures To Replace The Containers
• Emergency Procedures In Case Of Leakage
• Emergency Procedures In Case Of Fire
• Area Clearance In Case Of Leakage
• Leakage Treatment Tools
• Emergency Tools
• Security Containers
• Personal Protection Tools
• Eye Protection
• Skin Protection
• Respiratory System Protection
• Personal Protection From Chlorine Gas
• First Aid
• Chlorine Inhale
• Chlorine In Contact With The Skin
• Chlorine In Contact With The Eye
• Training
• Appendices
• Official Rules
• References
Table of contents
20
• Fall Down
• Cross Roads
• Standing Under The Raised Forks
• Persons Transportation
• Lifting Persons
• Allowing Others To Operate The Fork Lift
• Safety Measures
• Seat Belt
• Horn
• Reverse Horn
• Turn Flashers
• General Safety Rules
Chapter Five : Maintenance
• Check Up The Safety Equipment
• Check Up The Steering Unit
• Check Up The Brakes
• Check Up The Hydraulic System
• Check Up The Wheels & Tires
• Check Up The Mileage
• Leakages
• General Check Ups
• Daily Check Ups
• Daily Report
Chapter Six : Fueling
• Supply Fuel
• Charge Batteries
• Change Batteries
Table of contents
• Preface
• General Principles
• Schedule Of Training Programs
• Candidate Forms
• First Aid
• Vocational Protection Principles
• Personal Protection Tools
• Dealing With Poisonous Gases And Dangerous Chemicals
• Fires And Protection Principles
• Industrial Security Principles
• Safety Measures In Using Fork Lifts
• Traffic Guidance At The Job Sites
• Outline of Safety Measures In the site
• Emergency Plans And Crisis Administration
• Higher Administration Of Safety & Security
• Consultants & Contractors Safety At The Projects
• Training Locations
21
Annex : Health, Safety & Environment (HSE) Management System Framework
There is a wide pleuthoria of information available on developing HSE Management systems , in line with
recognised international standards. Due to this reason we have not delved into this issue in this book and only
give the outline of typical framework of system.
This would also be in line with the quality process for continual improvements
1. HSE policy
2. Planning for hazard identification & risk assessment (HIRA) & control:
22
2.2 Action management (link with hazard register)
2.5 Hazard management standards / fatal risk control protocols / major hazard installations
2.6 Workplace risk ratings (based on inspections & audits – linked with hazard register)
2.7 Hazard & near-hit reporting – hazard of the month
3. Legal requirements:
Safety regulations
Corporate legal advice and from Industrial Security & Government Affairs
4. Objectives:
23
6. Structure & responsibility:
24
8.3 Exchange leading / best practice within industry, sharing & learning between the
organisation & other companies
8.4 HSE quarterly workshops / seminars for leadership team
9. Documentation
9.1 System to reviewed periodically, update where necessary
9.2 Reporting:
Internal / corporate
Insurer – national requirements / broker
9.3 Hazardous materials management – includes Material Safety Data Sheets (MSDS)
9.4 Registers:
Hoists
Wire ropes
Chains
Fire extinguishers
Breathing apparatus
Height rescue equipment
Training records
First aid equipment
10. Document & data control
Electronic business management system (EBMS) – Document management, or via intranet
11. Operational control
11.1 Purchasing – safety specifications – products
11.2 Tagging, lock-out & (energy isolation)
11.3 Safety cones & signs, notices & barricades
11.4 Underground:
Mobile equipment
Fixed plant & machine guarding
Cranes & lifting equipment
Scaffolding
Working at height (fall prevention)
Unsupported ground (underground & surface ground control)
Unventilated areas, confined space & hot work
Remote loading
Conveyors
Boilers / pressure vessels system
Dust suppression
Barricades, notices & signage
Tag board
Gas detectors
11.4 PPE & clothing, including safety harnesses / other fall arrest devices
11.5 Vehicles & traffic safety
11.5 Workshop safety
11.6 Equipment license register
11.7 Pre-use inspections
11.8 Access control
11.9 Visitor controls
11.10 Underground & surface fire prevention
11.11 Chemical / hazardous substances management
11.12 Change management
11.13 Standards – e.g. electrical testing
11.14 Safe work procedures – for safe systems of work
11.15 Standard operating procedures
11.16 Job safety analyses & pre-emptive risk assessment - forms part of change management –
technical, HR, emergency response, procedural, management & operational nature
11.17 Task analysis forms
25
11.18 Machine guarding
11.19 Permit System:
Hot work
Dig
Access pit mining area
Confined space entry
Working at heights
Electrical safety - high voltage
Ionizing radiation
Blasting
Isolation from stored mechanical energy
11.20 Emergency preparedness & response:
First aid
Site evacuation drills
Fire risk plan
Crisis management plans / contingency plans, emergency action plan
communication on crisis
Dealing with media / public
Plant evacuation siren & PA
Flooding
Cyanide
Power failure, gas leak
Explosive device or bomb threat
12. Performance measurement & monitoring
12.1 Information system for HSE, risk management, document control and action management
12.2 Statistical analyses, using HSE information system
12.3 Performance management
Lagging (trailing) indicators – LTIFR, NLTIFR, AIR, severity ratio, damage incidents etc (contractors +
employees)
12.4 Leading (proactive) Indicators – hazards, near-hits, observations, audits, % safe behavior etc
13. Investigations, inspections & corrective action
13.1 Incident/accident reporting & investigation
13.2 Pre-use checklist - operational
13.3 Safety inspections
13.4 Incident reporting, investigation/analysis (using systematic root cause analysis) &
management
14. Records & records management:
Statistics & scorecard
15. Audits
15.1 Internal audits (with protocols/checklists) – GOSI, regulations, hazardous substances,
contractor safety management
rd
15.2 3 Party System Audits – CAP
rd
15.3 OHSAS 18001– 3 party audits or internal
15.4 Insurance brokers
15.5 Housekeeping
15.6 Corporate safety audits
15.7 PPE compliance
16. Management review
Weekly senior management meetings
Weekly site operational review
Internal HSE management review
Hazard register review
Regulatory compliance review
Performance management reviews
Post-accident review
H&S management committee
26
2. Example of a Typical Health Management System
27
3. Typical example of Environment Management System
28
5.14 Hydrocarbon management
5.15 Land management plan – future use
5.16 Rehabilitation (through mining life cycle, concurrent reclamation, alternative
productive land use, returning land to previous or better use, re-contouring)
5.17 Revegetation studies / research
5.18 Bonding / closure plans – provide additional security to stakeholders
5.19 Contractor environmental management (incl. sub-contractors), including suppliers /
customers - environmentally-focused supplier program
5.20 Hazardous materials management
5.21 Exploration – environmental guidelines
29
6.3.5 Non-government organizations
6.3.5 Annual public reporting / community report (accessible to public via internet &
some posted), feedback from
stakeholders sought prior to publication – comments incorporated
6.3.6 Consult communities on environmental consequences of activities – completed at
licensing phase
6.3.7 Complaints register – feedback and response
6.3.8 Community liaison
Manual
8. Document control:
9. Operational control:
30
Total suspended particulates
Respirable particulates
Meteorological conditions
o Post-closure monitoring programs
o Quarterly monitoring reports
o Trend analyses / statistics
13. Records:
Registers
Library
Databases
o Management review
o Management system review
o Continual improvement
31
SUSTAINABLE DEVELOPMENT CONSIDERATIONS – LINKS WITH HSE
32
SECTION 2 : HAZARD IDENTIFICATION ANALYSIS
2.1 Introduction
In this chapter we go through the various phases of Hazard Identification Analysis ( HAZID ) for which the
objectives are to identify main hazards, to review the effectiveness of selected safety measures and, where
required, to expand the safety measures in order to achieve a tolerable residual risk.
By means of the HAZID analysis the primary process, but also non-process, hazards as well as their possible
escalations can be identified due to the structured manner of the procedure. Employees can be advised of the
relevant hazards concerning their working area
HAZID analyses are usually to be revised when considerable modifications, upgrades or re-design of existing
facilities are carried out or if events like accidents, critical situations or near misses call for this. In this context
a change, upgrade or re-design is to be considered as essential if process modifications associated with
consequences for safety or safety related equipment are involved. This also applies for utilities including
buildings, machinery, equipment etc. that do not necessarily contribute to the primary operating objective but
which are associated with the process facilities in terms of layout or operation and that are safety relevant.
Those being in charge of operations and maintenance and those working in the facilities should have the initial
HAZIDs at the start of the project and then thereafter to go through the formal process for possible changes. In
principle operators are expected to repeat the analyses at least every few years ( 3 to 5 years as example ) in
order to maintain the residual risk as low as reasonable practical
Process Hazard Analysis (PHA) which are a well structured approach, and according to recognised and
international best practice and standards. These follows specific requirements as example of which :
EPSC, IChemE & Chemical Industries Association, 2000, "HAZOP – Guide to Best practice for the
process and chemical industries".
IEC 61882:2001 - Hazard and Operability studies (HAZOP Studies) - Application Guide
F.P. Lees, 1996, “Loss Prevention in the Process Industries”, Butterworth-Heinnemann, 2nd edition.
Chemical Industries Association (CIA), 1977, "A Guide to Hazard and Operability Studies".
AIChE Center for Chemical Process Safety (CCPS), 1992, "Guidelines for Hazard Evaluation
Procedures", USA, 2nd edition.
Wells, G., 1996, "Hazard Identification and Risk Assessment", IChemE, UK.
ISO-17776:2000, "Guidelines on tools and techniques for Hazard Identification and Risk Assessment"
PHA is mandated by regulations in many countries, for example:
USA: OSHA Process Safety Management (PSM) programs under 26 CFR 1910.119
USA: EPA Risk Management Plan under 40 CFR 68.67
European Union: Seveso II Directive
UK: Control of Major Accident Hazards (COMAH)
The above regulations themselves and associated guidelines provide valuable information on best practices for
PHA. In particular, the US regulations go into considerable detail on what a PHA should contain and how it
should be conducted.
The Center for Process Studies (CCPS) of the American Institute of Chemical Engineers (AIChE)has published
several documents containing guidelines on PHA, including "Guidelines for Hazard Evaluation Procedures" and
"RevalidatingProcess HazardAnalyses".
The CCPS has described procedures for12 methods of performing a PHA. The six most commonly used are said
to be:
1. What-If
33
2. Checklist
3. What-If/Checklist
4. Hazard and Operability Study (HAZOP)
5. Failure Mode and Effects Analysis (FMEA)
6. Fault Tree Analysis (FTA)
The OSHA and EPA regulations permit the same six methods as listed above but allow any other functionally
equivalent method to be used. Combinations of methods may also be used.
According to AIChE, the range of applicability of the above six methods is as shown in Table.
The CCPS publications and the OSHA and EPA regulations are perhaps the most useful source of general
information on PHA. For specific PHA methods, other more detailed standards are sometimes available.
For HAZOP, an important reference is IEC 61882 "Hazard and operability studies (HAZOP studies). Application
guide (British Standard)".
For FMEA, an important standardisIEC-60812 "Analysis Techniques for System Reliability - Procedure for
Failure Mode and Effects Analysis (FMEA)". Useful information is also available in the standards of the
automotive industry, which uses FMEA extensively; e.g. AIAG's "FMEA" Standard and SAE-J-1739" Potential
Failure Mode & Effects Analysis in Design".
For FTA, IEC 61025 "Fault Tree Analysis" is available.
Numerous books and articles have also been written describing best practices for PHA.
Table: Applicability of PHA techniques
Basically PHAs are structured analysis of the Process Deviations potentially triggering Hazardous scenarios and
problems in safely operating the plant. The form of PHA most widely utilized in modern industry is HAZOP
(Hazard and Operability Study), which is by far the most structured and useful form of qualitative Hazard
Identification for Process. HAZID analysis can be applied as well and example checklists are provided in this
chapter which also , providing an hazard identification more aimed to events external to the process, and
entering into process hazards in a less systematic way.
Application of Reliability Improvement Program are not normally part of the PHA Review, however during PHA
Review these will need to interface with these parallel activities, and one of the final useful outputs of the
Review will be the identification of the gaps to be fulfilled for aligning the PHAs to a suitable level sufficient to
input in systems specifications, design and IPF analysis (e.g. during SIL - Safety Integrity Level assessment and
verification, although this is obviously excluded from present proposal).
34
2.2 Methodology
Appendix 1 provides a simplified review of the hazard identification exercise as ‘ high level review ‘ For
Activities of a review specific for the process or activity this will be developed according to the following plan :
1. Kick-Off Meeting (KoM) : this activity will involve an initial kick-off meeting for the high-level coordination
and contacts needed to carry out the job. As part of this, the specialists from our project Team will
interface with the relevant specialists from engineering – operation / maintenance and asset teams and
they will define jointly the priorities for the PHA Review;
2. Data Collection: this activity will be developed sequentially with the KoM, exploiting the same business
trip. It will involve collection of all existing PHAs, and all the applicable reference material from the Project
Management. to this end, a suitable interface shall be set-up, from both sides, At the end of data
collection a register of documentation (PHAs and supporting documents) will be prepared and circulated
for approval. This list of PHAs will represent the agreed scope of work for the initial reviews.
3. PHAs Reviews (Core Activity): A series of Reviews will be developed by the Project Team to verify the
compliance as previously described. The Team will comprise, as a minimum, a Senior HAZOP/HAZID and SIL
Specialist (with experience of Chairmanship, follow-up, reliability verifications), co-teamed as needed by a
Senior Process Specialist and a Senior Instrument Specialist, available on call as needed. For each existing
PHA, the necessary verifications will be carried out, by either using appropriate checklists and by
engineering expertise. Each PHA will be critically examined producing a Review Report, which will state: (1)
Level of Compliance with Best Practice, (2) Quality of the PHA, (3) identified GAPs and Omissions, (4) further
recommendations and actions to be taken, and (5) high level Priority Plan for suitable integration to
acceptable levels. This activity is a Table-Top task and it is expected to be carried out at our premises in
Italy. Meetings to discuss specific issues can be convened if necessary, and a final review meeting where
the results of the PHA review are presented and discussed to the O &N M and asset specialists and
Managers will be convened.
4. Following completion of all PHAs review, the full list of actions and the priority plans produced will be
harmonized and consistently collected in an Overall Plan, inclusive of the estimated costs and planning for
implementation (which can be used to start the subsequent PHASE 2).
The detailed development of the PHAs will be aligned with the international standards and best practice
previously mentioned (see below section), and it will be essentially carried out as a structured brainstorming,
thus requiring a Team Work.
Activities are expected to be carried out for the most part at NWC premises in KSA (although they can be also
held at our premises in Italy, if more appropriate), as described below.
35
The studies will be carried out on the most updated available sets of P&IDs and C&E Matrixes, plus the other
additional supporting documentation (PFDs, Plot Plants, etc.). The Role of each Technical Team Member is
briefly explained in the following:
PHA CHAIRMAN:
He is an experienced, independent technical specialist. He is responsible for dividing the
P&IDs and the systems into suitable nodes, leading the study with appropriate guidewords,
establishing the detailed work schedule, ensuring that the correct procedure is followed
and that notes and results of the study are properly recorded without omissions. He will
also resolve any conflicts that may arise during the study, ensuring that the team works
toward a common goal by utilizing all team members expertise, and checking on progress
of the study. The Chairman is also responsible for issuing the PHA Report, after completion
of the review.
PROCESS AND INSTRUMENTATION EXPERTS:
They are experienced technical personnel with extensive background in the Process,
Technical and Instrumentation discipline, and their role is to support and assist the NWC
Team in the analysis, by adding expertise, coaching the team in their respective fields of
expertise, and by adding value to the analysis with their knowledge of engineering.
O & M / ASSETS TECHNICAL GROUP:
Members of the Technical Group are responsible for providing comments and answers
based on their knowledge and experience of the plants, for resolving issues emerged
during the study. General rule is that total number of Team members should not exceed 6-
8 people to avoid disorganized sessions. The O & M / assets project team should comprise
as a minimum the following experts:
- Process Specialist;
- HSE Specialist;
- Instrument Specialist;
- Other discipline experts (mechanical, electrical, maintenance etc.): available on
call.
The PHA technique is a systematic analysis that uses a guide word structured approach to identify deviations
from intended process design. The most commonly applied form of PHA to assess safety of process systems is
HAZOP, and basically all PHAs of PHASE 2, for being comprehensive, will be structured as a HAZOP. The
primary goal of PHA is the identification of Process Safety Hazards and Operability Problems. The main type of
document for the application of the PHA procedure is the Piping and Instrumentation Diagram (P&ID),
therefore it is fundamental to rely on the most updated issue of the Project P&IDs and to complete the
appropriate internal reviews prior to the start of the Activities.
The analysis is based on a number of discrete systems (nodes) in which each P&ID is appropriately divided. In
this way the team can focus close attention on a single circuit and then produce recommendations for each
system.
Each node will be reviewed by examining which deviations for normal operation can lead to undesired
outcomes, and exploring the details of these outcomes. All applicable deviations will be examined combining
appropriate guidewords to the relevant process parameters. Standard guidewords, parameters and applicable
deviations for a continuous process are listed in the below table
Each deviation will be analyzed identifying the primary potential cause, including, but not limited to:
Malfunction of process control systems;
Blockages;
Operational Error (e.g. opening wrong valve);
Faulty maintenance activities;
Failure of power supply, cooling water, instrument air or other utilities.
36
For each realistic deviation/cause identified, the session will continue analyzing the consequences associated
to the deviation/cause and assessing whether these consequences can cause a hazard (where the term
"hazard" is intended from a safety or operational point of view, such as fire, explosion, release of flammable or
toxic material, off-spec. products, loss of production, etc).
Where a deviation will be found to be credible and the consequence, examined without considering the
existing safeguard, will show the potential for a hazard, the Team will consider what mitigating features might
exist (e.g. relief valves, shutdown systems, alarms, etc) and whether they could be considered sufficient or not,
depending upon the severity of the expected outcomes.
All discussion will be recorded on the spreadsheet, and for each node a complete digression of all relevant
parameters/guidewords and related deviations will be compiled under the Chairman and the Team
supervision. The complete record of the whole PHA Sessions will be reported in the PHA Report for easy
reference during the Follow-up process.
When considered necessary, remedial measures will be required depending on the expected (qualitative)
likelihood of the event and its consequence; These measures will be recorded in the worksheets in the form of
recommendations aimed at identifying actions to be subsequently followed-up by the project team. Each
Recommendation/Action will be identified via a unique reference number.
Each Node discussed during the meeting will be marked in colour in the Master Copy of the P&IDs, to ensure
no items is missed and to facilitate the explanations during the sessions. The marked-up P&IDs representing
the PHA Master Documents will be eventually attached to the Report for easy reference.
37
Table Typical PHA/HAZOP Guidewords/Parameters and Related Deviations for Continuous Processes
(only applicable Parameters shall be analyzed)
The main steps involved in the PHA study process which was discussed above are schematically indicated in
the flow chart of the above figure and are summarized here below in a step-by-step list:
selection of a Node which contains the specific section of the plant and definition of Node's
design intent and process conditions;
Selection of a relevant Parameter and selection of a Deviation applying a suitable Guide
Word to the Parameter (the GW, Parameters and Deviation not applicable for the specific
cases will be normally skipped without further analysis);
identification by brainstorming of potential and credible Causes associated with the
deviation and assessment of the possible Consequences associated with each cause (Team
work);
identification of the Safeguards included in the design to protect the System (by preventing
the hazard and/or mitigating the consequences);
agreement on suitable Recommendation(s) for action if the existing safeguards are
considered to be inadequate based on the Team judgment. If an immediate solution is
available and acceptable to the team, the proposed solution is recorded in the Worksheet
to facilitate the follow-up. Where solutions are unlikely to be found without a more
detailed technical evaluation, the Chairman will record the problem for a separate later
assessment. All recommendations shall be appropriately evaluated during the follow-up
activity, which is NOT part of the PHA;
repetition of the above procedures until all relevant GWs have been applied to all
Parameters within each Node of the process system until the complete system within the
scope has been examined by the Team.
38
A typical format of the Working sheets is shown in the figure below and includes General Information, Node
description, Parameter, possible deviation (parameter and guide word), deviation causes, consequences,
existing safeguards, recommendations, responsible party (action owner) and possible comments. The
appearance of the Worksheet and the Columns can be customized.
Sessions Organization
The Work is organized in daily sessions of the approximate duration of 6-7 hours, with short breaks. Typically,
considering the normal development, the following tasks are scheduled for each PHA session:
First day: Introductory Part:
- Formal Opening of the Session,
- Overview of the Project,
- Overview of the PHA process;
First day to Last day: Perform the PHA (core activity);
The HAZOP leader will introduce the study, setting out objectives, the HAZOP process for
team members, and roles.
The design engineer will give a brief description of the operation of the system under
study, outlining the major issues he has had to address in the design, and the key design
parameters and conditions.
The leader will select a line diagram and mark up the first section of pipework and
equipment that is to be studied (the node) . He will use the list of guidewords to determine
possible deviations from the design intent, the likely causes and the consequences. The
team should consider to what extent alarms, trips and ultimate protections such as the
design envelope mitigate the effects of the deviation.
If the deviation from the design intent is considered to be serious and any mitigations do
not ameliorate the situation adequately, the team should consider if there is an obvious
solution. If this solution cannot be found quickly, the team should define the problem as a
simple action for resolution outside the study session.
39
The cause, the consequence, the safeguards (eg protective systems), any proposed actions
and the person nominated to resolve the problem should be recorded on a worksheet
(Appendix 2 shows a typical worksheet).
Each page of the worksheet should be clearly identified by means of the P&ID number, the
node number being studied and a continuation number.
The review process will proceed from one guideword to the next, iterating steps (c) to (e).
It is the task of the team leader to draw from his experience to prompt the team to
consider all potential hazards appropriate to the area under study, if necessary by him
making reference to check list 3 .
As the examination each line or piece of equipment (the node) is completed, it will be
colour coded on the P&ID to indicate it has been studied. The study then moves on to the
next node. Depending upon the complexity of the P+ID’s and the intent of the HAZOP,
there can be a number of nodes on each P+ID or alternatively a single node could extend
across several P+ID’s.
When each P&ID has been studied, it should be checked for lines or equipment that have
not been colour coded. Lines that have not been colour coded must be HAZOP’d using the
procedure defined above unless those parts of the P+ID’s are excluded from the scope of
the HAZOP. The breakpoints between the excluded scope and the study scope must be
clearly marked. The parts of a P+ID not HAZOP’d should be labelled accordingly .
Last day: Closure of activities:
- Review main findings of the PHA,
- The team at the first opportunity will review recorded actions - ideally at the
next meeting and the agreed actions passed to the client at the earliest stage.
- Some clients require the HAZOP worksheet is projected on to a screen in the
meeting whilst it is being created. This method allows consensus over what is
recorded on the worksheet to be seen to be achieved. However it significantly
prolongs the review process since time can be spent debating semantic issues
which distract from consideration of the technical ones the team has been
assembled to deal with.
- The most expedient method is for the team leader/secretary to edit the draft
minutes and provide a hardcopy for review the next day by team members. If
time and cost are not a consideration and the layout of the HAZOP room
permits it, then projecting the worksheet onto a screen in the meeting room
should be considered.
- If agreed in advance the HAZOP Secretary will provide the client with a copy of
all the worksheets generated in the meeting and a recommendations summary
list before the HAZOP team demobilises. Depending upon the recording
software being used and the needs of the client, copies of the action response
sheets can be passed on before the team demobilises. Where the client
requires the generation of action response sheets, the normal arrangement will
be for these to be submitted whilst the final report is being drafted.
- Formal Close-out of session.
A final written report will be prepared. It will typically include some the
following, depending upon the intent of the HAZOP and the needs of the
operator:
A summary
An introduction
The terms of reference and scope
The methodology
A presentation of the main findings
A list of recommended actions
A list of HAZOP attendees, as an appendix
40
All worksheets, as an appendix
A list of HAZOP drawings, as an appendix
A3 sized P+ID’s marked up with HAZOP nodes, as an appendix
At the end of all PHAs a Recommendations Register will be produced, including all recommendations aroused
from the PHAs executed in Phase 2.
41
Check List (2) - Equipment
42
Check List (3) - General
Access
Area Classification
Auto Ignition
Blanketing
Carcinogen/Toxic Materials
Compatibility
Condensation/Heat Loss
Control
Corrosion
Cracking
Cyclic Loading
Drainage/Slope of line
Electric Shock
Electro Potential
Emergency Equipment Fixed/Portable
Erosion
Failure Mode
Fire
Foam
Frothing
Hammer
Impact
Inerts
Interlocks
Lightning
Metallurgy
Monitoring
Noise
pH
Pre Commissioning/Construction
Pulsation
Electro Magnetic
Radiation Thermal
Nuclear
Rain Water/Sea Water
Reaction (Chemical)
Reaction (Mechanical)
Sampling
Spading
Specification Change
Start/Stop
Static Electricity
Short Term Exposure Level/Threshold Limit
Value
Syphon
Time
Un-revealed fault
Vacuum
Vibration
Vortex
Winterising
43
Sheet No:
Date:
Line No / Tag No
Description:
44
Appendix 1 : Example HAZID Worksheets as high level review
45
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
1.3.1 Disease Hazards Endemic diseases, Personal Health issues No possibility None
infection, malarial
mosquitoes,
hygiene - personal
and/or catering,
contaminated
water or foodstuff
1.3.2 Asphyxiation Asphyxiating Same as above PPE (Personal Protection Operation manual should
hazards atmospheres, Equipment) are required to clearly include the usage of
failure to use be carried essentially portable H2S detector and
appropriate PPE, PPE by the personnel.
vessel entry,
working in
confined spaces,
smoke, exhaust
1.3.3 Toxic Hazardous Same as above No possibility None
atmosphere,
asphyxiating
atmosphere,
chemicals in use
1.3.4 Physical Noise, radiation Same as above Noise expected to Ear plugs are required for Operation and Maintenance
(ionising, e.g. rise only during this operations manual should clearly include
radioactive scale or venting at the time the usage of ear-plugs by the
non-ionising, e.g. of maintenance personnel
flares, UV,
sunlight),
ergonomics
1.3.5 Mental Shift patterns Stress Unmanned None
operation
46
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
1.3.6 Transport Excessive journeys, Tiring Limited distance; None
extreme weather, Travelling schedule
quality of roads is flexible
47
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
1.6.1 Level of Indigenous Quality of local Maloperation ATHEER have similar NPCC to ensure that local
Training workforce and set-up existing and workforce will be competent
contractors competency will be to execute the job as per HSE
incorporated within regulations to ensure
corp. policies minimisation of human error
1.6.2 Training Same as above
Requirements
1.6.3 Level of Technology Same as above
48
Section 2: Process specific items
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
2. 1 Control Methods/Philosophy
2.1.1. Manning/operations Effect on design, Only patrolling is NI
Philosophy effect on locality planned as per
(Manned, existing stations
unmanned, visited)
2.1.2 Operations Concept Over simplification Well established Ensure Standard Operating SOP to be implemented.
procedures as per Procedures (SOP)
existing systems
2.1.3 Maintenance Plant/train/equipm Preventative Ensure effective PMP to PMP and permit to work
Philosophy ent item, heavy maintenance minimise downtime etc. systems to be implemented.
lifting, access, programme (PMP) Access and egress to be
override, bypass, unhindered and allow safe
commonality of working (e.g., collision free).
equipment,
transport
2.1.4 Control Philosophy Appropriate Any Automatic operation? Same as above NI
technology,
(DCS/local panels)
2.1.5 Manning Levels Accommodation, NI
travel, support
requirements.
Consistency with
operations and
maintenance, etc
philosophies
2.1.6 Emergency Isolation, ESD Back-up systems Loss of utilities to be Ensure effective back up
Response philosophy, managed via back up support and periodic checks
blowdown, flaring support taken.
requirements
2.1.7 Concurrent Production,
Operations maintenance
requirements
2.1.8 Start-up Shutdown Modular or plant Well established
49
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
wide procedures as per
existing systems
2.2 Fire and Explosion Hazards
2.2.1 Stored Flammables Improper storage, NI
operator error
(release), defect,
impact, fire
(mitigation
measures include:
substitute non
flammable,
minimise and
separate inventory)
2.2.2 Sources of Ignition Electricity, flares, NI
sparks, hot
surfaces
(mitigation
measures include:
identify, remove,
separate)
2.2.3 Equipment Layout Confinement, Congestion Layout of parallel Incorporate in QRA QRA issue
escalation equipment (filters,
following release of pressure reduction
explosive or and metering) to be
flammable fluid reviewed with
(operator error, regard to jet fire and
defect, impact impingement effect.
process control
failure, corrosion),
module
layout/proximity,
orientation of
equipment,
predominant wind
direction
50
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
(mitigation
measures include:
reduce degree of
confinement,
spacing based on
consequence
assessment,
escalation barriers)
2.2.4 Fire Protection and Active/passive None specific (NS) other Emergency response
Response insulation, fire/gas than generic action procedure to be addressed in
detection, HSEIA
blowdown/relief
system philosophy,
firefighting
facilities
2.2.5 Operator Protection Means of escape, NS NI
PPE,
communications,
emergency
response, plant
evacuation
2.3 Process Hazards
2.3.1 Inventory Excess hazardous NS NI
material
(mitigation
measures include:
minimise
hazardous
inventory,
alternate processes
and utility systems)
2.3.2 Release of inventory Excessive process Refer to comment QRA aspect QRA issue
stress, impact under impingement
(penetration by effect and QRA
foreign object),
51
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
process control
failure, structural
failure, erosion or
corrosion
(mitigation
measures include:
recognise and
minimise process
hazards during
design, inherently
safe plant,
containment and
recovery measures)
2.3.3 Over Pressure Offsite sources, NI NS
process blockage,
thermal expansion,
connection of
process to utility
systems, chemical
reaction
2.3.4 Over/under Atmospheric NI NS
Temperature conditions,
blowdown, fire, hot
surfaces, chemical
reaction
2.3.5 Excess/zero Level Overfill storage
tanks, loss of
function in
separation vessels,
blowby to
downstream
vessels
2.3.6 Wrong Offsite Covered in HAZOP
Composition/Phase contamination,
failure of
52
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
separation process,
build-up of wrong
phase (sand,
hydrates, etc), toxic
substances
2.4 Operational Hazards
2.4.1. Rupture of Adjacent Rupture may cause Unsafe situation Refer to comment QRA aspect QRA issue
pipeline in the hazardous situation under impingement
corridor effect and QRA
53
Section 3: Site specific items
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
54
3.3 Environmental Damage
3.3.1 Continuous Plant Flares, vents, HSEIA To be addressed in HSEIA HSEIA
Discharges to Air fugitive emissions,
energy efficiency
3.3.2 Continuous Plant Target/legislative HSEIA To be addressed in HSEIA HSEIA
Discharges to Water requirements,
drainage facilities,
oil/water
separation
3.3.3 Continuous Plant Drainage, chemical HSEIA To be addressed in HSEIA HSEIA
Discharges to Soil storage
3.3.4 Emergency/upset Flares, vents, HSEIA To be addressed in HSEIA HSEIA
Discharges drainage
3.3.5 Contaminated Previous use or HSEIA To be addressed in HSEIA HSEIA
Ground events
3.3.6 Facility Impact Area minimisation,
pipeline routing,
environmental
impact assessment
3.3.7 Waste Disposal HSEIA To be addressed in HSEIA HSEIA
Options
3.3.8 Timing of Seasons, periods of NI NS
Construction environmental
significance
3.4 Utility Systems
3.4.1 Firewater Systems NI NS
3.4.2 Fuel Gas NI NS
3.4.3 Inert Gas Carried as and when
required in
controlled manner
3.4.4 Diesel Fuel NI NS
3.4.5 Power Supply Loss of signal Back-up power NS – refer to loss of utilities None
(UPS) for all signals
3.4.6 Communication Loss of information Alarm is provided.
in Control room
55
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
3.4.7 Drains
3.4.8 Inert Gas Use of Nitrogen Maintenance Ensure effective control and Control and SOP
purging procedure within SOP
3.4.9 Waste Storage and NI NS
Treatment
3.4.10 Chemical/fuel NI NS
Storage
3.4.11 Potable Water NI NS
3.4.12 Sewerage NI NS
3.5 Maintenance Hazards
3.5.1 Access Refer to Process – Existing
Requirements Control Methods maintenance
procedure to be
followed
3.5.2 Override Necessity
3.5.3 Bypasses Required
3.5.4 Commonality of
Equipment
3.5.5 Heavy Lifting
Requirements
3.5.6 Transport
3.6 Construction/ Existing Facilities
3.6.1 Tie-ins (shutdown All aspects to be NS Ensure hot tapping etc all Management and control
requirements) within SOP and conducted under controlled
Concurrent executed under Nothing further conditions.
Operations strict supervision.
As above
3.6.2 Reuse of Material As Above Nothing further
3.6.3 Common Equipment As Above Nothing further
Capacity
3.6.4 Interface - As above Nothing further
Shutdown/blowdow
56
No. Guide word Potential Hazards Threats Controls Recommendations Action
and effects
n/
ESD
3.6.5 Skid Dimensions As above Nothing further
(weight
handling/equipment
(congestion)
3.6.6 Soil Contamination As above Nothing further
(existing facilities)
3.6.7 Mobilisation/ As above Nothing further
Demobilisation
3.7 Contingency
3.7.1 Geographical Plant location, NI NS
Infrastructure plant layout
3.8 Planning
3.8.1 Recovery Measures Medical support, NI NS
firefighting
support, spill
leak/clean-up
support,
security/military
support,
evacuation
57
SECTION 3 : CRITICAL ASSET IDENTIFICATION
3.1 Introduction
The approach to the AIMS ( asset integrity management systems ) which is to be discussed in the next chapter will
be explained as involve several technical, operational and organizational issues:
Checking the identified integrity risks and if necessary update them (revision and comparison with equipment
supplier standards and business expectations .
Assessing the potential impact of loss of integrity and malfunctions on the business, people and the
environment.
Determine appropriate strategies for the integrity risk management (fit-for-service, residual life etc.).
Establishing and implementing the policies, processes and procedures appropriate for the asset management.
Revise and update Key Performance Targets (KPTs) and Indicators (KPIs) to monitor the effectiveness of
processes and systems performance
Reviewing , revising and updating the implementation of appropriate responsibilities within organization –
this includes the providing the tool to estimate adequate resources in terms of time, budget, resources and
information , maintain and ensuring skills (i.e. through specific training) and of course the systems to support
communication, cooperation and change management.
Effectiveness of failure and malfunction investigation
Although not part of the context of this book the role of the internal auditing to verify how best to optimize the
asset life cycle can be achieved quite often without major capital expenditure by better planning, improved
training and clear statement of performance standards in testing and maintenance routines
The auditing process, which again , is not covered in this book involves the process of
Interviews with operations and maintenance management personnel to understand the processes in place
and implementation of standards and procedures
Interviews with contractors and maintenance personnel to verify the competency
Sampling of equipments records for completeness and compliance with procedures
Observation of operation and maintenance work in progress for compliance with procedures
In this chapter we cover the system for critical identification of assets. It is noteworthy to point out that the the
IIMM (International Infrastructure Management Manual, NAMS Limited, 2011) defines Maintenance as:
“All actions necessary for retaining an asset as near as practicable to its original condition, but excluding
rehabilitation or renewal”
Maintenance does not increase the service potential of the asset or keep it in its original condition, it slows down
deterioration and delays the time when rehabilitation or renewal is required. It is a mechanism to ensure that
assets continue to deliver the required level of service.
58
Maintenance requirements and costs change over the life of the asset. They will sometimes be apparent early in
the life (“cradle” failures) but more typically maintenance needs increase as the asset ages and deteriorates.
Maintenance needs and priorities also depend on asset criticality, function, geography, environment and operating
procedures.
Given the significant costs of maintenance over the asset life cycle and the importance of the service provided, it
is vital that an approach to maintenance management based on world class practice is fostered within the
organization.
Life cycle decision making involves making choices between different mixes of maintenance, rehabilitation and
renewal activity across an asset portfolio. Typically, maintenance costs are regarded as operational or OPEX,
with rehabilitation and renewal being replacement capital or CAPEX costs. Maintenance cannot be addressed in
isolation, it must be linked to the rehabilitation or renewal strategies for the asset.
In situations where asset renewal is deferred, the condition of an asset will typically deteriorate increasing the
maintenance need. On the other hand, an asset which is regularly rehabilitated or replaced would be expected to
have a lower maintenance demand.
The Anatomy of Asset Management states: “Organizations from a wide range of industries are quoting 20%, 40%
or even 50% gains in business performance, while simultaneously controlling costs, risks and long term
capability.”( reference 1)
Chris Lloyd at al (including Australia’s Dr Penny Burns, publisher of the AMQI ( reference 2) writes: “Economic and
natural resources are finite, unlike the demands made on them. Organizations seeking to make best use of limited
resources have hard choices to make. Choices which concern the reliability and availability of physical assets are
particularly difficult.”( reference 3 ) Asset efficacy could be added to reliability and availability.
This contemporary thinking highlights the importance of ensuring that assets meet the required standards in
respect of functionality, operability, durability, reliability, availability, maintainability, safety, risk management,
effectiveness, and efficiency through the planned lifecycle of the asset. The primary objective is ensuring asset
contribution to business outcomes continuity as well as stable, effective and efficient service delivery from assets
to the required standard, founded on optimum asset performance
The Institute of Asset Management: An Anatomy of Asset Management: Issue 1.0, December 2011 advocates
that: “Most organizations that are dependent on assets (owners and operators), face growing pressure to reduce
cost, capital investment and operational budgets!” and poses the following questions:
- Are future business consequences understood?
- Is the risk profile associated with the asset portfolio, and how this may change over time, understood?
- Can planned asset expenditures be justified to external stakeholders?
- How effectively can project spend be prioritized when facing funding or cash flow constraints?
- Is the appropriate asset data and information to support AM decision-making easily available?”8
This contemporary thinking goes on: “As organizations are coming under increasing pressure to deliver more for
less, it is imperative that these types of questions can be answered. Where these decisions impact on assets,
asset performance, risk or net value realization, it is the Asset Management communities’ responsibility to
articulate these implications and the adoption of a holistic Asset Management approach is essential to enable this.
Organizations that have developed their capabilities in Asset Management to a relatively high level of maturity can
answer these questions with a high degree of confidence. This helps enormously when dealing with shareholders,
regulators, customers, investors or politicians who do not have the time or the skills to understand the long-term
implications of the decisions they make.”
Application of this approach, combined with an understanding of the critical aspects that can significantly impact
the way asset management is applied in practice, can be achieved through the development of an Asset
Management Framework. This is then rolled out through the various elements in a controlled, structured and
prioritized way to ensure limited resources are applied to maximum efficacy.
World class organizations have a well defined asset management framework that they align their asset
management practices with.
This includes a high level alignment between the organization’s mission and vision and its asset management
59
policy and strategies. Maintenance protocols form an integral component of the overall approach to how the
assets are managed and the maintenance policies, strategies and protocols should be guided by an all-
encompassing an Asset Management Framework.
Best practice asset management practices, methodologies, tools, information systems and data structures will be
used to make decisions that optimize the balance between levels of service, risk and life cycle cost for customers
and stakeholders.
Asset management frameworks to be considered with respect to the Asset Maintenance Strategy and Asset
Maintenance Manual are:
- PAS 55
- ISO 5500 Asset Management Standard
- The Institute of Asset Management (IAM)
- International Infrastructure Management Manual (IIMM)
The aim of this section is to describe the asset maintenance activities need to be prioritized as outage time and
budget for the maintenance work that needs to be carried out are often limited.
With a finite quantum of time, resource and funding availability, it is critical for an organization to have a
systematic, transparent and consistent process for identifying maintenance type and prioritizing maintenance
activity. This framework is required for an organization to documents the rules, assumptions and logic to be used
in selecting suitable maintenance types, and provides an organization’s asset team a framework for the decision
making process. This will assist also the organization to maximise the return on investment and minimise the risk
under the constraints of time and budget.
In order to implement an optimized and prioritized maintenance regime, asset criticality and asset failure risks
need to be assessed. This section describes the steps to be undertaken in carrying out risk and criticality
assessment.
Regular gap analyses of appropriate and current practices of an organization or site’s asset management strategy
will help drive the ongoing identification of improvement actions. It is critical to evaluate and prioritize
improvement actions in order to define the highest priority area that has the greatest impact on asset
management outcomes.
The asset management improvement actions should be structured around the following areas:
- Processes improvements
- Systems improvements
- Data improvements
- Implementation improvements
Increasing the sophistication of maintenance strategy requires the optimization and balancing of technical levels
of service, life cycle cost, and the criticality of each asset. Maintenance planning Improvement needs to be
focussed on ongoing review and adjustment of levels of service and/or maintenance budget to achieve an
optimized maintenance plan
An appropriate action plan as a general approach towards identifying problems and solutions is as follows. This is
an underlying general working concept
60
Problem Solving Deliverables Tools & Tips
Step
1. Define the Write a problem statement Select one problem to begin (if there are several,
problem and consequence of failure explain
their relationship with the one chosen)
Include the metric this problem supports
2. Collect data and Quantify needs with “Walk the process” and document using a process
evidence metrics map (if
Collect & check data applicable)
Establish current state Gather data to quantify the problem with the “as-
Establish future state / goal is”
process, ensure data accuracy
Establish a target / improvement goal for project
3. Identify root Make a list of inputs Ask “why, why, why?” to facilitate brainstorming
causes Prioritize the list of inputs Prioritize root causes by “voting” or by gathering
data
4. Identify Generate solutions; either Brainstorm multiple solutions to address each
corrective actions existing or new cause
Prioritize solutions Apply “mistake-proofing” if possible; what can be
done to
ensure the process is done correctly each time
Assess solutions and determine which best
addresses the
needs
5. Implement Pilot & implement the Test the solution or process change
corrective action selected solution(s)
6. Review action Review the effectiveness of Validate that solution provides the expected
the solution(s) benefits;
identify other changes as needed to meet target
7. Observation to Validate the change Gather data to determine if desired performance
ensure efficiency has been
achieved over time
8. Document the Develop plan to monitor Monitor and document outputs & control inputs
result process
All assets must all be properly and efficiently managed in order for the system as a whole to function as intended,
delivering continuous services to customers, minimising failure risk, and achieving optimum economic life-cycle
costs over the life of all assets. This involves many different work activities, including inspections, operational
activities, planned and unplanned maintenance, rehabilitation and asset replacement over the life of the assets.
Lifecycle activities include operating, maintaining, repairing, refurbishing, replacing, expanding or improving
assets, and possibly disposing of them altogether when no longer required. Throughout this cycle, there are three
key principles that underpin the effective management of public assets:
recognition of the economic value of assets, including economic consumption over time and delivering
long
term equity to stakeholders and customers who use the service (i.e. today’s users are not financially
penalised to benefit tomorrow’s users)
targeting economic efficiency using economic and risk-based analysis techniques to optimize asset
expenditure over the asset’s lifecycle (i.e. the right actions are taken at the right time to maximise value for
money)
61
the role of the business as a “steward” of the assets, a long-term role that can be quantified in performance
terms (i.e. there is a sense of responsibility for the long term well-being or sustainability of the assets).
Even for commercial organizations, similar principles apply. Long term investment decisions in new and upgraded
assets may also be driven by mandated standards, future service expectations, the price customers are prepared
to pay for the service, and the level of risk.
Asset management decisions involve selecting the most appropriate actions to take during the life-cycle of the
asset. For example, do you do nothing, maintain, repair, refurbish, replace or upgrade an asset? Is preventive
maintenance worthwhile on an asset?
Typically, there is some uncertainty as to the life an asset will achieve before it “fails”, as shown by the two red
curves, and the blue bell curve shows an expected distribution of asset lives amongst a group of similar assets.
Intervention or management tactics will differ depending on the criticality of an asset, which in turn relates to the
consequences of failure on the service outcome. For example, a sole pump serving an important plant would be
regarded as critical. An intervention should be targeted earlier in the life-cycle of the asset in managing this risk.
For assets for which failure is not critical, where there are minimal consequences and the asset can be readily
repaired or replaced, then a “run-to-failure” strategy would be appropriate.
In making decisions targeting economic efficiency, the following need to be considered:
Expected future stream of operating and maintenance costs over the lifecycle compared to the periodic
costs of renewal or major treatments, using net present value (NPV) analysis. These represent direct costs
to the agency and analysis should result in an internal economic efficiency outcome
Economic impacts of risk, which can be considered solely internally or at society level. For example, if an
asset failure results in closure of a facility for an extended period of time there will be an economic impact
on customers who are adversely affected as well as any direct cost impacts to the agency. Economic
impacts can be assessed using standard risk management techniques (consequence and likelihood), and
converted into equivalent financial terms if appropriate.
The level of acceptable risk to the business as well as its customers also needs to be considered. For example, a
significant investment to only marginally improve system reliability may be judged not worthwhile. Such
consideration helps to determine the threshold for intervention.
In economic analysis of lifecycle costs and risk, different strategies are tested and an optimal solution determined
which maximizes economic value. High value investments or significant risks should be assessed in this way.
Routine, lower cost, lower impact decisions typically use simple qualitative risk analysis.
Maintenance Philosophy is the guiding protocol and determines the application of maintenance practice. Over the
decades maintenance philosophy has evolved from wholly reactive to various protocols of scheduled
maintenance including amongst others:
Each of these approaches offers benefits, and the cost of each varies. Due to the potential broad nature of an
organisation’s asset base and the risk attached to asset failure, both direct and consequential, no single
maintenance regime will offer the optimum maintenance solution. Leading maintenance practices involve a
62
mixture, or combination of the maintenance regimes mentioned above, tailored to the performance requirement
of the asset and how this can be met in the most economical fashion.
Undertaking unplanned maintenance root cause analysis is a structured process to help an organization or a site to
improve the maintenance strategy by preventing the recurrence of asset failure. The analysis supports asset
integrity management and reliability centred maintenance. It is a technique to help the asset team identify
repetitive failures, providing corrective action that can keep undesirable events from occurring in future, reduce
downtime, reduce cost of maintenance, and increase safety.
Reference 4 mentioned at the back of this section demonstrates the importance of performing maintenance at the
optimum level and demonstrating that under-maintaining and over-maintaining can both have unfavourable
outcomes
The IIMM includes an asset management maturity scale so organizations can assess their strengths and
weaknesses within each functional area – such as levels of service, demand, risk management, operations,
maintenance, capital projects, and financial management.
This recognizes the need for an organization to decide the level of maturity that is appropriate to the scale,
complexity and level of risk associated with their infrastructure asset portfolio(s).
Typically, an organization would conduct a gap analysis to identify its current position, define its desired position,
and then develop an improvement plan to enable it to progress to the desired level in a structure and prioritized
manner.
There are also gap analysis tools that can be used to assess asset management practice and develop
improvement plans.
Successful implementation of an Maintenance Strategy and Asset Maintenance Manual will help facilitate an
organization to move to sophisticated techniques such as RCM and FMEC A.
The quantum and timing of renewals work required depends on several factors, including:
Nature and age of the assets and their condition deterioration pattern, and whether a condition based failure
has occurred or is likely to occur.
Performance of the assets, where they fail to deliver the required service capacity. The monitoring of
asset reliability, capacity and efficiency during planned maintenance inspections and operational activity
can help identify non-performing assets.
New asset expansions or other development that may dictate asset upgrade, replacement or removal.
Criticality of the assets in terms of the degree of risk to service provision, including associated financial,
environmental and social impacts.
Economics. The cost of maintenance is deemed to be uneconomic when the annual cost exceeds the
annualised cost of renewal. Economic factors may also come into consideration in order to co-ordinate
renewals with other major works. Operating and maintenance histories are used to identify current and
projected costs.
63
Unlike maintenance, historical renewals costs are not necessarily an indicator of future need other than on a
broad whole of lifecycle basis.
As described in the IIMM, renewals programs are typically based on a combination of the following methods:
Forward projections of historic expenditure, possibly combined with some level of judgment to make
broad parametric adjustments.
Broad estimates based on replacing the asset at the end of its useful life.
Predictive modelling of varying degrees of complexity (from a forward works program based on staff
judgment through to advanced mathematical techniques that have complex relationships between
models).
Bottom up approaches where needs are identified via observation of defects in the existing assets and
compiled into work bank of projects. Projects within the work bank are prioritized and then funding
allocated until the budget is reached.
Renewal planning requires consideration of a range of different options or lifecycle treatment strategies,
The three generic strategies shown involve different patterns of repair, refurbishment or
replacement. Lifecycle economics involves testing the timing and costs of different strategies, and requires good
data on the costs of general maintenance for each.
Contemporary asset management requires clearly defined performance measures, aligned with the Mission and
spanning from the Mission to the operational activities conducted on the assets.
Performance measures provide information about achievement and trends that may affect the service in the
future. The general descriptions on the right hand side of this diagram provide a basis for developing a set of
performance measures at each level. The more important of these measures are typically known as KPIs (Key
Performance Indicators), as together they provide a view of overall performance.
Performance measures for customer and technical levels of service (LoS) can be categorized as asset measures,
financial measures, functional performance measures, and efficiency measures. These measures are typically
known as KPIs (Key Performance Indicators) and overall performance can be illustrated as a performance
dashboard or by an aggregation of measures.
Performance evaluation measures the ability of the organization’s assets to deliver the required level of service.
Technical level of service is the level at which maintenance achievements are to be assessed.
A performance measurement system can also be used for comparison and benchmarking purposes
The table below shows an example of a level of service and associated performance measures for response time to
a particular failure type or fault. In this case, current performance and future targets are specified reflecting a
desire or customer expectation for faster response than has occurred to date. It is important to note the cascade
of information, from a level of service statement which can be communicated to a customer, using performance
measures to establish a target.
64
Mean time to repair (MTTR) is a basic measure of the maintainability of repairable items. It represents
the average time required to repair a failed component or device. Expressed mathematically, it is the total
corrective maintenance time divided by the total number of corrective maintenance actions during a given period
of time. MTTR are expected to be reported in internal and outsourced contracts where a system whose MTTR is
24 hours is generally more valuable than for one of 7 days if mean time between failures is equal, because its
Operational Availability is higher.
However, in the context of a maintenance contract, it would be important to distinguish whether MTTR is meant
to be a measure of the mean time between the point at which the failure is first discovered until the point at which
the equipment returns to operation (usually termed "mean time to recovery"), or only a measure of the elapsed
time between the point where repairs actually begin until the point at which the equipment returns to operation
(usually termed "mean time to repair"). For example, a system with a service contract guaranteeing a mean time
to REPAIR of 24 hours, but with additional part lead times, administrative delays, and technician transportation
delays adding up to a mean of 6 days, would not be any more attractive than another system with a service
contract guaranteeing a mean time to RECOVERY of 7 days.
Mean time between failures (MTBF) is the predicted elapsed time between inherent failures of a system during
operation. MTBF can be calculated as the arithmetic mean (average) time between failures of a system. The MTBF
is typically part of a model that assumes the failed system is immediately repaired (mean time to repair, or MTTR),
as a part of a renewal process. This is in contrast to the mean time to failure (MTTF), which measures average time
to failures with the modeling assumption that the failed system is not repaired (infinite repair rate).
The definition of MTBF depends on the definition of what is considered a system failure. For
complex, repairable systems, failures are considered to be those out of design conditions which place the system
out of service and into a state for repair. Failures which occur that can be left or maintained in an unrepaired
condition, and do not place the system out of service, are not considered failures under this definition. In addition,
units that are taken down for routine scheduled maintenance or inventory control are not considered within the
definition of failure.
Mean time to recovery (MTTR) is the average time that a device will take to recover from any failure. Examples of
such devices range from self-resetting fuses (where the MTTR would be very short, probably seconds), up to whole
systems which have to be repaired or replaced.
The MTTR would usually be part of a maintenance contract, where the user would pay more for a system MTTR of
which was 24 hours, than for one of, say, 7 days. This does not mean the supplier is guaranteeing to have the
system up and running again within 24 hours (or 7 days) of being notified of the failure. It does mean the average
repair time will tend towards 24 hours (or 7 days). A more useful maintenance contract measure is the maximum
time to recovery which can be easily measured and the supplier held accountable.
Equipment Availability – annual hours run of critical equipment / annual critical equipment hours availaibility
planned * 100 ( refer to criticality assessment )
65
Condition and Performance
Condition is used to describe the physical state of an asset, while performance describes its ability to deliver the
required level of service. Most Customer and Technical Levels of Service should have either a condition or
performance measure associated with them. Condition and performance are monitored at the operational level to
facilitate maintenance, operational and renewal decisions.
All measurements of customer and technical levels of service should be recorded and displayed in charts that
allow valid year-on-year comparisons of historic and projected performance to be made and readily understood
The shape of the condition curve is fundamental in predicting future condition or performance of the asset, and by
extension the network.
Progressive capture of condition data, in a robust and consistent manner, will allow an organization to be able to
associate condition with the asset’s position in the life cycle – the horizontal axis in the diagram above.
Contemporary asset management also requires that asset managers understand and communicate the
66
relationship between performance, risk and life cycle costs at both the portfolio level and the asset level.
At the portfolio level, this means communicating with the Board, key stakeholders, funders and regulators about
the overall performance of the asset system, its risk profile and its funding envelope needs, and how these are
expected to change over the planning period – which should span at least 10 years, preferably 20 years.
At the asset level, technical staff need to perform analyses of asset criticality, condition, performance, failure risk,
life cycle cost requirements, and to determine relative priorities for maintenance and capital renewal expenditure
over the forward life of the asset. This requires the capture, not only of asset condition and performance data, but
also maintenance cost histories by location at the equipment or component level.
This need to balance the three elements of risk, service and life cycle cost for the impacts of excessive risk on the
left hand side (such as service disruptions, health and safety issues) against excessive spend on the right (such as
waste and inefficiency).
Best practice asset management means the “right” level of service is being delivered, the costs are efficient, and
the level of risk is acceptable to customers and stakeholders
Effective condition deterioration prediction underpins proactive asset management programs and enables whole
life cycle costs to be optimized using economic analysis.
Current condition information along with knowledge of future service demand is an input to the prediction of the
future state of the assets, thus facilitating multi-year financial analysis and long term planning and budget
allocation.
Figure : Relationship between Condition, Levels of Service and Risk in Optimizing Work programs
As will be discussed in section 4 on Condition and Performance Evaluation , The physical integrity of assets is
measured by carrying out condition assessments throughout the asset’s life cycle. The level of assessment depends
on the type, scale and criticality of the asset to be inspected. Assessment types differ from simple visual
inspections through detailed engineering testing.
The knowledge that needs to be acquired includes the likely physical failure mode of the asset and the likely time
67
for maintenance, rehabilitation or renewal
Inspection types, techniques, intervals and the recording process all need to be addressed.
A condition grading approach enables quantitative data consistency, as well as providing the capability to
benchmark and compare assets among other units or authorities. For example, current practice for most water
and wastewater agencies uses a mix of a 1 to 5 grading scale supplemented where appropriate by non destructive
testing techniques such as CCTV or ultrasonic testing, and plant monitoring techniques such as vibration
monitoring
A reliable forecasting methodology is to be used for long-term planning for maintenance and renewal and the
allocation of OPEX and CAPEX budgets. Clearly, the expected asset condition decay curve affects the optimization
of asset interventions.
Degradation patterns for condition and performance are key factors in establishing maintenance programs,
upgrades, refurbishments and renewal planning for assets. There are several factors affecting the degradation
process such as age, material, usage and environment exposure. The deterioration progression affects the
likelihood of failure and interruption to service; and consequently, the risk evaluation of assets. A consistent
condition inspection process will enable an organisation to determine decay curves for its assets over time.
Markov Chain statistical modelling can then be performed to address the probabilistic nature of deterioration of
the assets
Demand forecasts may affect infrastructure planning in various ways, and the resulting scenarios and options
need to be evaluated. Forecasting demand also involves risk and uncertainty. Therefore, the risk related to
demand prediction needs to be assessed and a sensitivity analysis performed to identify the essential factors and
any variables that could affect the decision making process.
For prioritizing maintenance activity an organization s asset team needs to define the current condition, criticality
rating, and risk rating of each asset and how these three factors influence the agreed level of service.
Maintenance prioritization is evaluated against three criteria, namely:
- Condition Rating
- Criticality Factor
- Asset Risk Factor
Typically, there is a relationship between condition and the risk of asset failure.
An approach to using these criteria in a “balancing” approach is described below.
An overall prioritization index can be determined to evaluate and prioritize maintenance activities, calculated using
the following equation:
68
The table below illustrates this example for assets with a range of rating and factor scores. The overall
prioritization index defines the priority levels for maintenance action on the assets.
Another factor to be considered in prioritizing maintenance is the packaging of tasks with similar requirements. It
is essential to identify and group maintenance works that have a similar requirement such as isolation points,
resources, skills, tools, machinery, as this is typically more efficient and cost effective than carrying out similar
tasks separately.
Based on the overall priority index result, assets can be “ranked” for the purposes of establishing maintenance
levels of service, as illustrated in the table below for response times.
An alternative approach is to select the most critical assets first, then use the risk assessment process to identify
the priorities for critical assets. This approach is particularly appropriate when funding levels are highly
constrained, and there is only sufficient available to treat the most important assets.
An alternative structured evaluation methodology to identify critical equipment whether mechanical, electrical
civil, or instrumentation, control or automation ( ICA ) can identify which equipment has the most serious
potential consequences on the buisiness performance . If it fails for example consequences on the buisiness can
include :
69
Criticality is determined by integrating the probability and consequence of failure. Factors such as safety,
environmental impact, risk to production loss, replacement cost and maintenance costs are included and
consequence of failure can be weighted and used to determine the overall risk ranking. The following table shows
a simplified assessment of assets covering operations, environment and safety impacts
Severity
After assessing these four factors the criticality number is scored as follows
Criticality number = ( Sum of production, environment, safety score ) * probability
70
APPENDIX
Reliability Centred Maintenance (RCM) is an industrial improvement approach focused on identifying and
establishing the operational, maintenance and capital improvement policies that will manage the risks of
equipment failure most effectively. RCM is an engineering framework that enables the definition of a complete
maintenance regime. It regards maintenance as the means to maintain the functions a user may require of
machinery in a defined operating context. As a discipline it enables machinery stakeholders to monitor, assess,
predict and generally understand the working of their physical assets. This is embodied in the initial part of the
RCM process which is to identify the operating context of the machinery and write a Failure Mode Effects and
Criticality Analysis (FMECA). The second part of the analysis is to apply the RCM logic, which helps determine the
appropriate maintenance tasks for the identified failure modes in the FMECA. Once the logic is complete for all
elements in the FMECA, the resulting list of maintenance is packaged, so that the periodicities of the tasks are
rationalised to be called up in works packages. Lastly, RCM is kept live throughout the in-service life of machinery,
where the effectiveness of the maintenance is kept under constant review and adjusted in light of experience
gained.
RCM can be used to create a cost effective maintenance strategy to address dominant causes of equipment failure.
It is a systematic approach to defining a routine maintenance programme composed of cost effective tasks that
preserve important functions.
The important functions of a piece of equipment to preserve with routine maintenance are identified, their
dominant failure modes and causes determined and the consequences of failure ascertained. Levels of criticality
are assigned to the consequences of failure. Some functions are not critical and are left to run to failure, while
other functions must be preserved at all cost. Maintenance tasks are selected that address the dominant failure
causes. This process directly addresses maintenance preventable failures.
Failures caused by unlikely events, non-predictable acts of nature, etc. will usually receive no action provided their
risk (combination of severity and frequency) is trivial (or at least tolerable). When the risk of such failures is very
high, RCM encourages (and sometimes mandates) the user to consider changing something which will reduce the
risk to a tolerable level.
The result is a maintenance programme that focuses scarce economic resources on those items that would cause
the most disruption if they were to fail.
RCM emphasises the use of Predictive Maintenance (PdM) techniques in addition to traditional preventive
measures and recognises three principal risks from equipment failures, which are:
Threats to safety
Threats to operations
Threats to the maintenance budget
Modern RCM gives threats to the environment as a separate classification, though most forms manage them in the
same way as threats to safety.
RCM offers four principal options among the risk management strategies:
RCM also offers specific criteria to use when selecting a risk management strategy for a system that presents a
specific risk when it fails. Some are technical in nature (can the proposed task detect the condition it needs to
71
detect ( does the equipment actually wear out with use?). Others are goal oriented (is it reasonably likely that the
proposed task and task frequency will reduce the risk to a tolerable level?). The criteria are often presented in the
form of a decision logic diagram, though this is not intrinsic to the nature of the process.
Breakdowns in industrial manufacturing systems can have a significant impact on the performance of a business.
Expensive equipment is made idle, labour is no longer optimised and the ratio of fixed costs to output is negatively
affected. Rapid repair of ‘down’ equipment is critical to improving performance and the process of addressing
equipment breakdowns after occurrence is known as Corrective Maintenance. However, when equipment does
breakdown the problems and cost can go well beyond the period of repair. Often process lines, such as Water
Treatment Plants, require significant run time after start-up to begin producing water of the correct quality and in
the required quantities. Because of the impact both during and beyond the immediate equipment downtime,
facilities have sought to prevent equipment breakdown by a process known as Preventive Maintenance
With preventive maintenance equipment is routinely inspected and serviced in an effort to prevent breakdowns
from occurring. Such inspections are based on either calendar periods or equipment process time, and generally
include recorded data that can be compared over time to determine if negative changes in performance indicate
an imminent equipment problem.
The Corrective Maintenance and Preventive Maintenance approaches have been in use for decades, but each have
some important drawbacks.
To try to maintain equipment at the right time, condition based maintenance is introduced. CBM is based on using
real time data to prioritise and optimize maintenance resources. Observing the state of the system is known as
condition monitoring. Such a system will determine the equipment’s health, and act only when maintenance is
actually necessary. Developments in recent years have allowed extensive instrumentation of equipment and
together with better tools for analyzing condition data the maintenance personnel of today are able to decide the
right time to perform maintenance on equipment. Ideally condition based maintenance will allow maintenance
personnel to limit their interventions to carrying out only the required tasks at the right time thus minimising spare
parts costs, system downtime and time spent on maintenance.
First and most important of all, starting to use CBM is costly partly because it requires improved instrumentation
of the equipment. Often the cost of sufficient instrumentation can be quite large, especially if this has to be retro-
fitted to equipment that is already installed. It is therefore important to decide whether the equipment is
sufficiently important to justify the investment. A result of this is that the first generation of CBM usually focuses
on vibration in heavy rotating equipment such as large pumps and motors.
Secondly, introducing CBM invokes a major change in how maintenance is performed, and potentially to the whole
maintenance organisation in a company. Organisational changes can be difficult to implement.
Also, the technical side of it is not always as simple as would be hoped. Even if some types of equipment can easily
be observed by measuring simple values as vibration (displacement or acceleration), temperature or pressure, it is
not trivial to turn this measured data into actionable knowledge about the health of the equipment.
As operational systems get more expensive to install and maintain, and instrumentation and information systems
tend to become less expensive and reliable, CBM becomes an important tool for managing plants in an optimal
manner. Optimising operations will lead to lower production cost and reduced use of resources. Minimising the
use of resources may be one of the most important differentiators in a future where environmental issues become
more important by the day.
72
Failure Mode Effects and Critical Analysis ( FMECA )
Introduction to FMECA
FMECA is an Analysis technique that facilitates the identification of potential design problems by examining the
effects of lower level failures on system operation
Severity of failure
SEVERITY classifies the degree of injury, property damage, system damage, and service loss that could occur as the
worst possible consequence of a failure. For a FMECA these are typically graded from I to IV in decreasing severity.
The standard severity levels, defined in various national standards may be used or equipment specific severities
may be defined. The latter of these is recommended to ensure applicability to the local environment.
For the flashlight example above the severity levels would be:
Severity of failure
SEVERITY classifies the degree of injury, property damage, system damage, and service loss that could occur as the
worst possible consequence of a failure. For a FMECA these are typically graded from I to IV in decreasing severity.
The standard severity levels, defined in various national standards may be used or equipment specific severities
may be defined. The latter of these is recommended to ensure applicability to the local environment.For the
flashlight example above the severity levels would be
73
Item Failure Mode End Effect Severity
Criticality
Integrated FMECA
FMECAs are often used by other functions such as Operations, Health & Safety, and Logistics.
Coordinate your effort with other functions up front
Integrate as many other tasks into the FMECA as possible that make sense (Operations, Health & Safety, and
Logistics, etc.)
Integrating in this way can save considerable cost over carrying out separate assessments and will usually produce
a better product.
If possible, use the same analyst to accomplish these tasks for the same piece of hardware. This improves
consistency of approach and can be a cheaper option.
Examples of Condition Based Maintenance Monitoring for rotating machinery such as pumps and electric
motors
The most commonly used method for rotating machines is called vibration analysis. Measurements are taken on machine
bearing casings with seismic or piezoelectricity transducers to measure the casing vibrations, and on the vast majority of
critical machines, with ‘eddy-current’ transducers that directly observe the rotating shafts to measure the radial (and axial)
vibration during normal operation.
The level of vibration can be compared with historic baseline values to measure the degree of degradation and identify the
need for intervention in the form of adjustment, calibration or replacement of the whole unit or its some of its constituent
parts. Interpreting the vibration signal obtained is a complex process that requires specialised training and experience. One
commonly employed technique is to examine the individual frequencies present in the signal. These frequencies
correspond to certain mechanical components (for example, the various pieces that make up a ‘rolling-element’ bearing) or
certain malfunctions (such as shafts out of balance or misaligned). By examining these frequencies and their harmonics, the
analyst can identify the location and type of problem, and sometimes even the root
74
Cause. For example, high vibration at the frequency corresponding to the speed of rotation is most often due to residual
imbalance and is corrected by balancing the machine. As another example, a degrading rolling-element bearing will usually
exhibit increasing vibration signals at specific frequencies as it wears. Special analysis instruments can detect this wear
weeks or even months before failure, giving ample warning to schedule replacement before a failure which could cause a
much longer
Down-time.
Other techniques
The most rudimentary form of condition monitoring is visual / audible inspection by experienced operators and maintenance
engineers. Failure modes such as cracking, leaking, corrosion, abnormal noise levels etc can often be detected by inspection
before failure is likely. This form of condition
Monitoring is generally the cheapest and is a vital part of workplace culture to give ownership of the equipment to the people
that work with it. Consequently, other forms of condition monitoring should generally augment, rather than replace, visual
inspection.
Slight temperature variations across a surface can be discovered with regular visual inspection and non-destructive with
thermograph. Heat is indicative of failing components, especially degrading electrical contacts and terminations.
Thermograph can also be successfully applied to high-speed bearings, fluid couplings, conveyor rollers, and storage tank
internal build-up.
Ultrasound can be used for high and low-speed mechanical applications and for high-pressure fluid situations. Digital
ultrasonic meters measure high frequency signals from bearings and display the result as a dBuV (decibels per microvolt)
value. This value is trended over time and used to predict increases in friction, rubbing, impacting, and other bearing defects.
The dBuV value is also used to predict proper intervals for re-lubrication. Ultrasound monitoring, if done properly, proves out
to be a great companion technology for vibration analysis.
References
1 An Anatomy of Asset Management; Issue 1.0, December 2011 The Institute of Asset Management
2 Asset Management Quarterly International
3 Lloyd, Chris at al, Asset Management: Whole-life management of physical assets, Thomas Telford Limited, 2010
4 Herbaty, Frank; Handbook of Maintenance Management – Cost Effective Practices, Second Edition (1990), Noyes
Publications
75
SECTION 4 : ASSET INTEGRITY ASSESSMENT
1 Introduction
Asset Integrity Management Systems (AIMS) can be defined as the ability of an asset to perform its required
function effectively and efficiently whilst protecting health, safety and the environment and the means of ensuring
that the people, systems, processes and resources that deliver integrity are in place, in use and will perform when
required over the whole lifecycle of the asset and assist owners and operators safely, effectively, and efficiently
manage the integrity and realize the maximum potential from their assets during its lifecycle without harm to
people, environment, or business.
Asset Register
An asset register is a business statement showing the assets that are owned. It consists of clearly stated costs of
assets both direct and incidental, the date of purchase, the suppliers name and address, serial number, internal
reference number, and depreciation rate and method
Operations (POMS):
Any piece of equipment, operated as designed, will normally yield a safe and profitable life. This is addressed in
the inclusion of Intranet based Plant Operations Manuals (POMS) that focus on the Facilities (Processes and
Equipment)
Corrosion Management (CMS)
Each item of equipment and its system has defined “degradation” management strategies that are enforced by
the materials of design and the operating conditions. These strategies encompass corrosion monitoring and
control.
Corrosion Anomalies – POE (Probability of Exceedence)
PoE leak and rupture represent anomalies such as Leak and rupture . There is also a definition of Remaining life
PoE Leak and Remaining life PoE Rupture The Remaining life PoE is normally based on when the individual anomaly
will reach the user specified PoE confidence limit
Inspection Management (IMS)
Inspection and testing is a verification that predicted degradation mechanisms are correct and that less likely
mechanisms are not increasing risks to an unacceptable level. The inspection process is covered in the Inspection
Management System
Maintenance Management System (MMS)
Maintenance, in the context of AIMS ( asset integrity management program ) , is the routine work on the assets as
defined by the manufacturers and designers. It is considered separate from corrosion management and
inspection but as an integrity management process it is fully integrated with those processes
Pipeline Integrity Management System (PIMS)
Each phase in the life cycle of the pipeline is treated in PIMS software including design (route selection, material
selection and corrosion protection), operations (routine pigging, intelligent pigging and condition monitoring)
removal, planning and performance monitoring, QA/QC, corrosion management, . Additional procedures support
mothballing, pipeline defect verification etc. The Emergency Pipeline Repair System (EPRS) is a subsystem of PIMS.
Structural Integrity Management System (SIMS)
Threats addressed in an SIMS include corrosion and fatigue and implementation plans such as risk based
inspection methodologies, and protective coatings are also addressed. The Lifting Equipment Management System
(LEMS) covers lifting equipment.
Pressure Equipment Management System (PEMS)
PEMS addresses boilers, pressure vessels, piping, and safety equipment. Requirements for risk based inspection;
periodic inspection and first in-service inspection are addressed along with repair, mothballing and a summary of
methods of inspection. PSV inspection and testing requirements are covered in a subsystem of PEMS. Pressure
equipment such as pressure vessels and piping, including the testing and maintenance of pressure relief valves and
fuel storage tanks are also included typically in a PEMS.
Instrumentation, controls & alarms ( ICA )
ICA issues are typically encompassed in Reliability Centered Maintenance (RCM) for Electrical, Instrumental and
Alarms like on line instrumentation , pressure gauges, gas sensors etc
76
In terms of the word ‘ integrity ‘ this can be subcategorized in the following :
In the context of condition assessments therefore for an asset it is clear that an organization needs to follow the
appropriate accounting basis and valuation methodologies for each category or types of assets which has been
discussed and agreed with the management of organization . Condition data is typically used to determine the
need and timing of some preventative or remedial action to prevent loss of service or economic loss.
Understanding asset failure modes and risks leads to better asset management decision-making. Being aware of
the failure modes allows effort to be focused on understanding the timing and consequences of the failure, and
the expected expenditure patterns. The methodology use “risk” also helps to prioritize and manage the efforts of
an asset integrity management program as an effective risk based program results in a reduced level of risk for a
given level of inspection/management activity. In any operating plant, a relatively large percentage of the risk is
usually associated with a small percentage of equipment. A Risk Based methodology permits the shift of inspection
and maintenance resources to provide a higher level of coverage on the high risk items and an appropriate effort
on lower risk equipment.
In terms of corrosion and the types of acid attack, pitting corrosion, hydrogen blistering and cracking, sulphide
stress / corrosion cracking etc etc may occur without proper management when not expected or not initially
expected; existing mitigation systems might not be effective ( ie paints, overlay, plating, cathodic protection ) and
also the process may be different from what the original design intent.
For example in the wastewater services sector H2S is a major contributor to environmental cracking such as
Sulphide Stress Cracking (SSC). Assessing the integrity and risk rating of components in contact will include a delve
into the issues such as H2S partial pressure, in situ pH, Concentration of dissolved chloride, presence of elemental
sulphur or other oxidant ,temperature ,galvanic effects ,mechanical stress ,time of exposure to contact ,predictivity
corrosion, corrosion resistance, field assessments and supplier specific material selection details etc
An alternative example in the case of pipeline integrity assessments are the parameters of the results of
conducting close-interval potential survey (CIS) ( ie through survey procedure of correct interruption ratio ) and
identification of areas for additional survey or exploratory excavations and feedback of detailed surveys ( for
example involving DC voltage gradient ,pipeline current mapping, electromagnetic survey, soil resistivity surveys,
drainage , topography and support/ welding reviews , CCTV feedback etc ) and finally the results from any past
fracture/ leakages and remedial actions
It is not the purpose of this book to go into such details which need to be looked at on specific basis – It is however
noteworthy to mention that the general principle of undertaking the details assessment of the integrity and
condition of assets can drive enterprise value , enable more intelligent decisions about the lifecycle of the asset
and enable the synergy of information and efforts with the owners, contractors and sub contractors involved in the
up keep of the assets
Plants will always have to perform some amount of routine, preventive, predictive or proactive maintenance
Methods to determine the best cost scenario are still evolving. The questions are: how to predict an assets’
condition including integrating with the need for maintenance, and determination of the maintenance schedule
proactively
77
Assessing the condition of assets need to consider the effectiveness of resources, skills, governance and
implementation of the O & M procedures and reflect also the level of risk associated with the loss of integrity
and/or malfunction of the assets and also in line with supplier performance specifications and good industry
practice
The benefits of developing a more sophisticate and exact methodology for knowing the current condition and
performance level of an asset are:
Ability to plan for and manage the delivery of the required level of service.
Avoidance of premature asset failure, leaving open the option of cost effective renovation.
Risk management associated with asset failures, and mitigation of the consequences of failure.
Accurate prediction of future expenditure requirements through understanding remaining asset life and
capital investment needs.
Refinement of maintenance and rehabilitation strategies
From a financial perspective estimates can be made of the Gross Modern Equivalent Asset Value (MEAV) as a
vehicle for presenting asset condition information. The value is the current cost of replacing the asset concerned
with one of a similar capability but to modern standards.
As an accounting base for example reference is made to the IFRS accounting standards dealing with individual
assets – property, plant and equipment (fixed assets), capital work in progress and inventories
IFRS – IAS 16 Property, Plant and Equipment.
IFRS – IAS 2 Inventories.
IAS 38 – Intangibles.
IFRS 3 Business Combinations
The aim of this chapter is not to present a financial lesson in asset valuation as this is under a different subject and
under a strict financial discipline where issues such as accounting books, statutory , tax and insurance
requirements prevail. The objectives of this section for example do not cover financial issues which are under the
realm of financial disciplines and not under the objectives of this book .
For example for issues such as following then the reader should note that examples as listed below are not
covered or intended to be mentioned at all in this book :
Methods for measurement and recording of costs for capitalization and depreciation.
Methods for monitoring budgeted capital expenditure against actual expenditure or financial controls over the
ownership of assets or their financial safeguarding
Compliance with Accounting Standards as per regulatory requirements or assets register ,assets information
systems and financial statements
The alternative objective of this section is to provide an overview from process risk perspective for assessing the
condition of assets and putting a measurable and benchmarkable assessment
Best practice use of condition or serviceability assessment is based upon having good knowledge, at an
appropriate level, of the company’s assets in terms of condition, performance and cost of ownership. This enables
each component of the asset base to be assessed and categorised by its ability to deliver the service required of it
at minimum whole-life cost. Such information is used to devise optimum capital maintenance strategies, that
combined with operational maintenance standards, ensure the best service / cost balance.
78
Asset Condition reflects the physical state of the asset, which may or may not affect its performance. The
performance of the asset is the ability to provide the required level of service to customers. Generally this can be
measured in terms of reliability, availability, capacity, and meeting customer demands and needs. All of this is
critical information for determining the remaining useful life of an asset and more importantly the timing for
possible intervention steps to bring levels of service, provided by the asset, back to a desired standard
Other factors can also determine useful life. Factors such as:
Technical advances which might make the existing asset obsolete.
Changes in community expectations meaning that the asset no longer has the capacity to meet community
standards.
Growth impacts meaning that the asset’s capacity falls short of the new demands.
Compliance - changing standards mean the asset becomes non-compliant.
Economic life - whereby the costs of continuing to operate the asset warrant it now being replaced.
It is critical that service organisations have a clear knowledge of the condition of their assets and how they are
performing. All management decisions regarding maintenance, rehabilitation and renewal revolve around these
two aspects.
Not knowing the current condition or performance of an asset may lead to the premature failure, which leaves the
organisation with only one option - to replace the asset (generally the most expensive option!). The unforeseen
failure of an asset can have major consequences that constitute a business risk or potential loss to the
organisation.
This is the any organization s objective in this area but a number of enabling initiatives must be completed first:
The process of determining serviceability by best practice methods requires them being fully integrated into day-
to-day operational activities for them to be effective.
Operational assets: are the assets acquired or used in the income generating of the business – in a water utility
this applied to items such as water network, wastewater network, water plants, waste water plants, pumps,
reservoirs, and wells etc
Real estate: is the land and anything fixed, immovable, or permanently attached to it such as buildings ..
Based upon the Uniform Standards of Professional Appraisal Practice (USPAP) the following would be the
approaches of land valuation:
Direct market comparison approach
Income approach
Cost approach
Non operational are the assets which not be used in the operations of a business such as equipment and
machineries, motor vehicles, leasehold improvements, office equipments, furniture and fixtures, safety and
security etc
79
2. 1.1 Physical Inspection Approaches
In a non quantifiable manner based upon detailed information from operation and maintenance databases , a
broad view of condition would considers an asset’s value to the business for delivering service to customers rather
than simple physical condition; this principle takes account of best practice principles of serviceability
In other words an asset can be considered to be in good condition when the asset can perform its required task
reliably and at optimum cost. It can be considered poor condition to be the opposite of this.
This approach enables us to identify assets that may appear to be in good physical condition but in practice cannot
deliver the service required. A typical example of this would be a pump that is in perfectly good physical condition
but has, for whatever reason, been designed or specified incorrectly and cannot meet its duty requirements
at the required cost. We would record this as being in poor condition. Conversely a pump that may appear to be in
poor condition on initial inspection but delivers reliable and adequate service would be considered in good
condition providing maintenance costs were moderate.
In order to conduct asset surveys by physical inspections only it would be expected that typically a valuation team,
comprised of professional engineers from the business would conduct an exercise of both physical inspections and
interviews with those people responsible for maintenance and operation t and its associated ICA and
SCADA/telemetry equipment. This for example would record data such as for example whether pumps are duty or
standby , the date of the last major overhaul and obtain information on the level of historic maintenance.
In this assessment of the condition of these assets the objective would be not only to determine the remaining
useful life of the assets , but also to some degree an understanding of whether the assets are being used
efficiently - for example this may require hydraulic analyses to determine whether they are of adequate capacity,
and operational information such as to interruptions in supply, plant breakdowns, preventive maintenance
schedules and quality etc
The data and information needed to be collected would typically include:
This would enable the team to build up a detailed assessment of condition and age at a component level. These
results can then be aggregated on a criticality-weighted basis to provide effective age and condition at the
valuation level of process stage.
The replacement costs used for the valuation can be based on Modern Equivalent Values using benchmarks at
process level. The below figure illustrates how the age and condition assessments made by our survey at detailed
80
component level, are used as weighted averages and combined with modern equivalent prices to derive net asset
values for the balance sheet.
Using the above approach age assessment can be based on available records and knowledge of the Operation and
Maintenance employees and other circumstantial evidence. Condition assessment can be based additionally on
the surveying engineer’s professional judgement. The method would involve identifying, counting and
categorizing assets based upon either standardised level of counting or the classification of assets using an agreed
assets grading system or as an optimum based upon the tagging / labelling of the assets based upon a pre-
established asset management database and this would entail the logging and use of bar code scanners in the
physical site visits
Condition of equipment comprising the assets would then be assessed typically on a scale of 1 to 5 using criteria
appropriate to the types of asset. In general these grades reflected the following
In normal accounting practice, the book value of an asset is derived from its original capitalized value less the
amount of depreciation. The depreciation calculation is based on local accounting standards and tax regulations. In
a simplified case of linear depreciation for example assumptions would be based upon operational assets falling
into one of two categories; civil assets depreciated say over 40 years and Mechanical and Electrical assets say over
20 years . The useful lives of fixed assets should be re-examined on a periodic basis. If the estimate of the
asset’s life changes, the depreciation expense should be adjusted for the current and future periods.
81
Figure – Depreciated Asset Value
The figure above shows a line of depreciation. “A” represents an asset which has been depreciated normally in the
accounts. However, “B” and “C” represent possible points, which this valuation recognises, where neither age nor
condition is consistent with the original depreciation line.
The reality of the valuation exercise is that the accounting history of the asset is not known or doesn’t exist. The
figure below shows what we would expect to have occurred to explain the cases of “B” and “C”.
Where an asset is in poor condition for its age, as in example “B”, this should have been reflected in the accounts
as impairment, i.e. a premature right-off of asset value. Where an asset is still operating beyond its normal life
expectancy, as in example “C”, this is most likely to be reflected by additional investment during its life, i.e. the real
life of the asset is less than it seems and the total capital cost being depreciated is greater.
82
Figure – Impairment and Capital Addition
Based upon the above an algorithm would be used to combine age and condition to generate a discounting
percentage to apply to the replacement cost and hence derive the net asset value.
For non-operational assets , primary valuation would be based on the underlying cost information which would
typically be obtained from the suppliers contracts, assets invoices and purchase orders . In the absence of values in
suppliers contracts, assets invoices and purchase order records, the benchmark market pricing approach would be
used based upon cost information for similar assets, typically obtained from suppliers. Where the values are not
available in the benchmark markets, the next best approach would be to estimated the asset values of nearest
possible similar assets. The effectiveness of this approach depends on a number of factors such as :
The extent and level of comparability of each property compared to the property under evaluation.
Time of sale.
Verification of sale data eg legal obligations or title deeds for the properties;.
Lack of any conditions which may be affecting the sale.
The income approach considers the income that an asset will generate over its remaining useful life and estimates
value through a capitalisation process. This process applies an appropriate yield, or discount rate, to the projected
income stream to arrive at a capital value. The income stream may be derived under a contract or contracts, or be
non-contractual, eg, the profit generated from either the use of or holding of the asset.
Two methods which may be used under the income approach are:
Income capitalisation, where an all risks yield is applied to a fixed income stream, or
Discounted cash flow where the cash flows for future periods are discounted to a present value.
A method for example which can be used to assess the value of the commercial properties using (the residual
value) is based on the assumption of the best possible usage for the location and on the assumption that the
construction was built with the highest quality and for the maximum generation of income for the land. The value
of the real estate project is then derived by capitalizing the income through the use of the standard rates and
requirements that are commonly used in the market and then the value of the building and the construction works
are deducted from it to get the net value of the designated land.
83
The cost approach applies the basic economic principle that a buyer will pay no more for an asset than the cost to
obtain an asset of equal utility, whether by purchase or by construction. Unless undue time, inconvenience, risk or
other factors are involved, the price that a buyer would pay for the asset being valued would not be more than the
cost to acquire or construct a modern equivalent. Often the asset being valued will be less attractive than the cost
of a modern equivalent because of age or obsolescence; where this is the case, adjustments will need to be made
to the cost of the modern equivalent. This adjusted figure is known as the depreciated replacement cost.
The cost approach analysis is defined as the “the method of which is derived the value of properties by introducing
the asset replacement cost and deduction from the estimated depreciation rate”. In order to determine the
depreciation rate, the skills and expertise of the assessor is key to determine the depreciation factor. For
example in the case of buildings the equation could be
Market Fair Value = Residual Life / Useful Life of the asset x Cost of the new asset
Condition Assessment should not be carried out in isolation. Related issues need to be considered, such as:
Risk Management.
Maintenance Management Planning
Data Collection Techniques eg Has the asset failed, or is it in the process of failing? , Is the proper process
safety management (PSM) system in place and is it operating properly? , What is the reliability strategy? Does
it need to be changed? , What is the implementation of O & M procedures in the site against the supplier
initial recommendations and against optimal best practice work ?, Are there any constraints or barriers that
inhibit the best practice? When will the asset fail again?, Can any additional opportunity costs be harvested?
What is the software tools available and how they are used eg PRIMAVERA Project management SIDAM 3
data field collection, inspection management ANTEA documentation management RBI Risk based inspection
SAP asset costs, resource planning, financial ADM maintenance analysis, reliability data, EAM , enterprise asset
management programmes ?
What are the Key Performance Targets (KPTs) and Indicators (KPIs) to monitor the effectiveness of processes
and systems performance ?
The objectives of systems to monitor asset condition and performance should be to:
The development and continued use of condition assessment data will allow preparation of verifiable predictive
decay curves for particular asset types and hence permit prediction of remaining life. By considering the current
condition point on an assumed decay curve, the profile can predict the effective life (time) before failure. This
failure time can be physical end of life, minimum level of acceptable service, or limit of capacity of the asset.
The Core approach focuses on data collection for managing risks associated with critical assets and monitoring key
performance measures
For passive assets the extent and repetition of condition assessment will be influenced by:
The type of the asset
The criticality of the asset
The relative age of the asset
The rate of deterioration of the asset
The economic value of the outcomes to the business.
84
We have made the distinction between two types of asset and the approach taken for the assessment of
condition of these two groups is necessarily different:
Aboveground assets which are observable and can be readily inspected. The condition assessment can utilise
physical inspection supported by investigation of operational experience and reports obtained from appropriate
staff and business information systems. This class of assets comprises all assets within sites, including buried pipe-
work, and will normally be recorded within the maintenance management system asset database. These assets
have been split into two categories:
Civils works: For example, structures, buildings, ancillaries, pipe-work and fencing
M&E and Control : All mechanical & electrical and control equipment
Underground assets which are buried and cannot be easily inspected. Universal physical inspection is impossible
or impracticable and can be severely restricted within a water utility organization to CCTV surveys of small
diameter sewers so a condition assessment has been made based upon operational experience and reports
obtained from business information systems. For the water utility sector this class of assets comprises entirely of
pipes, fittings, manholes and hydraulic structures outside of operational sites. These assets are normally recorded
in a GIS system.
In the simple approach the use of condition grades to assign relative condition values to assets and in common
with best practice regulatory principles is a 5-level system as used by regulatory authorities in the UK and Australia
where:
• Grade 1 is equivalent to best possible condition
• Grade 5 represents worst condition
These grades would also be linked to a likely capital maintenance requirement in that grade 5 indicates immediate
remedial action is necessary, grade 4 would mean actionin the short to medium term etc.
The grades and definitions are statements of general principle chosen to reflect a pragmatic assessment of an
asset’s ability to deliver the required service. In practical terms grades 4 and 5 indicate capital maintenance
interventions are necessary while grade 3 indicates additional maintenance interventions are required
85
Safety and Safety Grades
An approach to a high-level safety assessment at sites would be similar to that used for condition assessment as
mentioned above where
Safety of staff going about their work is of paramount importance and the grading reflects a high-level assessment
of risk observed during the physical inspection of facilities. The grading is designed to highlight issues rather than
provide detailed solutions and will be combined with detailed safety audits at representative sites to
establish remedial programmes and implemented through an investment programe
The survey would consider what hazards were present and whether any provision has been made to mitigate the
risks. The grading is presented below. The grade reflects the degree to which the risks have been mitigated so
Grade 1 reflects that all reasonable measures have been taken to modern best practice standards while Grade five
reflects absence of provision and serious hazard risk.
This system of grading is aimed at identifying observable issues that can be addressed in detail within a Safety Plan.
Issues that may not be observable such as the presence of unbound asbestos or PCBs will be addressed by specific
studies undertaken in a Safety Plan developed specifically for the site or organisation. The following aspects of
safety risk would be considered:
• Slips, trips and falls
• Machinery (moving parts, rotating equipment etc.)
• Electrical
• Asbestos
• Chemicals
• Lighting
The approach shown in the below figure involves the enhancement of the organisation’s ability to rank more
effectively those assets that constitute a significant problem at condition levels 3, 4, and 5.
86
The simple and intermediate approaches allow development of predictive decay curves. The sophisticated
approach using greater numbers of parameters, will generate more accurate curves and give greater certainty to
the current condition of the asset.
The adoption of sophisticated condition ranking systems may not be justified for all assets. However, with the
advancements being made in AM techniques and practices, it is likely that in the future most asset owners will
employ sophisticated methods for all their assets
In general it would be necessary for survey teams would need to made prior appointments to visit sites to ensure
access and the presence of appropriate staff from operations to explain the context of operation and to describe
any operational issues that were relevant to condition and serviceability assessment. Surveys should be conducted,
as far as possible, following the process stream through the site. In the simplified approach inspections will be
visual; where access to asset sets are for example impractical or dangerous the knowledge of operations staff
should be used as the sole basis for the grading; for example surveyors would not enter confined spaces, such as in
the water utility industry - wet wells, chambers etc.
Where several similar assets made up an asset set within a functional unit, for example a pump-set within a
pumping station or cells within a filter then the condition grade given for the set would normally reflect the
condition of the worst component. If considerable disparity existed between components within a set, for example
one pump may have been new, then a note would be made on the data collection forms and this would be taken
into account at the moderation stage.
Photographic evidence is an important aspect of the process and can be used to illustrate grading decisions,
illustrate safety hazards etc.
Questioning operations staff about the ability of the assets to deliver the required service is also a crucial aspect of
the inspection process. For inspections, questions should be asked of suitably knowledgeable staff about the
reliability of the asset and its ability to deliver the required service. The QA check for bias can for example be
undertaken by sending teams to each others’ sites to review and amend the condition grading taken as initial, if
necessary.
87
4 Water and wastewater utility assets
Adopted best practice approach wherever possible is clearly the best methodology for any organization utilising
the information existing within the business regarding the underground assets. However best practice approaches
to reliably establish serviceability rely heavily upon the collection, collation and analysis of accurate condition and
performance data over several calendar years. Where such information is not available to a utility, the best
practice approach is to convene expert panels to consider what information is available and to make judgements
Within the simplified 5-tier framework described earlier the approach necessarily adopted for assets that
cannot be inspected was to utilise all available performance data and knowledge of asset capability.
The following are more specific condition grading standards for a range of infrastructure types
namely: wastewater distribution systems, water mains
Grade Definition
1 Average failure rate up to 125/1,000km/annum (more than 1,600m between failures over 5-
years)
2 Average failure rate greater than 125 up to 250 failures/1,000 km/annum (<1,600m but >800m
between failures over 5 years)
3 Average failure rate greater than 250 up to 500 failures/1,000km/annum (<800m but>400m
between failures over a 5-years)
4 Average failure rate greater than 500 up to 1,000/1,000 km/annum (<400m but >200m
between failures over 5 years)
5 Average failure rate greater than 1,000/1,000 km/annum (less than 200m between failures over
five years).
In cases data is not available for distinguishing pipe performance between pipe materials and diameters directly
using mains failure data directly, condition can be prescribed by developing a guidelines given to materials and
diameter categories of pipe – for example Concrete Cylinder Pipe water mains are normally of large diameter and
therefore critical to network operations and service delivery in addition to pipes of Ductile iron water and Precast
Concrete
Good Few failures. Few areas not complying with engineering standards.
Fair Failures beginning to occur. Significant areas not complying with engineering standards.
Poor Regular failures occurring and significant corrosion. Increases operating costs resulting. Many
must be replaced.
( Source 1 http://www.municipal.gov.sk.ca/Assessment/Asset-Management/Grading-Standards )
Source 2 : Guide to Accounting for and Reporting Tangible Capital Assets.
(http://www.psab-ccsp.ca/other-non-authoritative-guidance/item14603.pdf)
88
Table – Example of Condition Grade Definitions for sewers
For accurate performance and comprehensive survey data for sewer networks. , CCTV information would be
required for representative survey Size banding of sewers can also be simplified to just two bands:
Band 1: Up to and including 700mm diameter
Band 2: Over 700mm diameter
It can be considered that the principal influence upon performance of sewerage network is material and
age and in certain circumstances diameter within a material category. This is due to the progressive influence of
hydrogen sulphide corrosion and to the fact that materials and construction practice has improved over time.
Water Supply, Storm water and Wastewater Condition Grading Standards: Civil Structures
Grade Condition Description
0 Non existant Asset abandoned or no longer exists
1 Very good Sound physical condition. Asset likely to perform adequately without major
work for 25 years or more.
2 Good. Acceptable physical condition; minimal short-term failure risk but potential
for deterioration in long-term (10 years plus). Only minor work required (if
any).
3 Fair Significant deterioration evident; failure unlikely within next 2 years but
further deterioration likely and major replacement likely within next 10
years. Minor components or isolated sections of the asset needs
replacement or repair now but asset still functions safely at adequate level
of service. Work required but asset is still serviceable.
4 Poor Failure likely in short-term. Likely need to replace most or all of asset within
2 years. No immediate risk to health or safety but works required within 2
years to ensure asset remains safe. Substantial work required in short-term,
asset barely serviceable.
5 Very poor Failed or failure imminent. Immediate need to replace most or all of asset.
Health and safety hazards exist which present a possible risk to public
safety or asset cannot be serviced/operated without risk to personnel.
Major work or replacement required urgently.
( source http://www.municipal.gov.sk.ca/Assessment/Asset-Management/Grading-Standards )
89
Water Supply, Storm water and Wastewater Condition Grading Standards: Mechanical and Electrical Assets
1 Very good Plant in sound physical condition designed to meet current standards.
Operable and well-maintained. Asset likely to perform adequately within
routine maintenance for 10 years or more.
No work required
2 Good. Acceptable physical condition but not designed to current standards, or
showing minor wear.
Deterioration has minimal impact on asset performance. Minimal short-
term failure risk but potential for deterioration or reduced performance in
medium term (5 – 10 years). Only minor work required (if any).
3 Fair Functionally sound plant and components, but showing some wear with
minor failures and some diminished efficiency. Minor components or
isolated sections of the asset need replacement or repair but asset still
functions safely at adequate level of service. For example, bearing and
gland wear becoming evident and some corrosion present. Deterioration
beginning to be reflected in performance and higher attendance for
maintenance. Failure unlikely within 2 years but further deterioration likely
and major replacement required within next 5 years. Work required but
asset is still serviceable.
4 Poor Plant and components function but require a high level of maintenance to
remain operational. Likely to cause a marked deterioration in performance
in short-term. Likely need to replace most or all of assets within 2 years. No
immediate risk to health or safety but work required within 2 years to
ensure asset remains safe. Substantial work required in short-term, asset
barely serviceable.
5 Very poor Failed or failure imminent. Plant and component effective life exceeded and
excessive maintenance costs incurred. A high risk of breakdown with a
serious impact on performance. No life expectancy. Health and safety
hazards exist which present a possible risk to public safety, or asset cannot
be serviced/operated without risk to personnel. Major work or replacement
required urgently.
( source 1 http://www.municipal.gov.sk.ca/Assessment/Asset-Management/Grading-Standards )
Source 2: International Infrastructure Management Manual – Version 3.0, 2006
(http://openlibrary.org/books/OL21245688M/International_infrastructure_management_manual)
90
SECTION 5 : EMERGENCY RESPONSE PLANNING
1 Introduction
The majority of organizations and businesses recognize the need to plan for the unexpected and there are few
organizations that do not have some form of a plan to deal with the consequences of an unwanted incident or
disaster. For example, This could be a hazardous materials spill that may necessitate evacuation or , a severe
weather warning that leads to concern about flooding or infrastructure damage,
Organisations realize also to stay in business after a major incident requires careful pre-planning and this means
taking action before an incident occurs, not after
An the outset it is necessary to define an “emergency” and relate the definition to other non-emergency events
Criticality can be considered as Assessment of a risk while crossing its likelihood and the seriousness of its
consequences. Other criteria can be taken into account to evaluate the criticality, such as the ability to monitor or
to tackle the risk.
Contingency plan can be considered as Set of actions to be undertaken to prevent the hazard from happening
(Preventive Actions).
Emergency can be considered as a serious “incident”. and an Emergency plan can be considered as set of actions
to be undertaken once the hazard has occurred (Corrective Actions). An emergency Response Plan provides “A
professional, strategic and tactical managed response protocols: (i) to mitigate the effect of an emergency upon
the business; (ii) that are scaled to the severity of the emergency and (iii) which set out the relationships for
response teams, within and outside the business.”
Emergency Response Plan provides: “professional, strategic and tactical managed response protocols: (i) to
mitigate the effect of an emergency upon the business; (ii) that are scaled to the severity of the emergency and (iii)
which set out the relationships for response teams, within and outside the business”
Emergency Room – this is a location where the Strategic Response Leader and his team can plan the response and
manage the situation. It is essential that the Emergency room remains a “quiet” area and not become a melee of
people, thus only those appointed by the Strategic Response Leader as a part of the Strategic Response Team shall
be permitted within the Emergency room.
This will be the central command post should have necessary equipment and supplies including:
Operational information:
1. maps of distribution system and city maps
2. engineering information
3. access to other system information
4. copies of standard operating procedures
5. human resources information (including contract information, copies of relevant legislation, training and
certification information, and emergency contact information)
6. access to vital contact information (including – but not limited to - all relevant contact information for key
staff, suppliers, contractors, and other individuals and organizations that will be needed to assist in emergency
response.)
7. access to information about consumers including contact information
8. list of all chemicals stored at CBU sites and MSDS information
9. other vital records
Emergency Plans
10. copies of the Organisation’s Emergency Plan
11. copies of the City Emergency Plan (and appendices to this plan – including a city based Flood Plan and Crisis
Communications Plan)
12. copies of the Water Security Emergency Plan
13. copies of the Wastewater Emergency Plan
91
14. copies of relevant legislation
92
Performance Indicator The important criterion to be measured is the frequency of emergencies. A falling
frequency over the period of the contract will indicate a number of favourable trends: a. Improved reliability and
sustainability of the assets; b. The effectiveness of risk management in “designing” risk out of the system;
c. Improved workforce operational performance reducing the frequency of incidents becoming emergencies;
d. Introduction of operational procedures to avoid the occurrence of an emergency; e. Demonstrable effectiveness
of training provided. An indicator could therefore be Number of events for which a response is made divided by
Number within a year , for high, medium and low events as collected from the central control room log
Records – Evidence of historical activities that reports the outcome or result of an activity or task. Records can not
be modified although they may be subject to updating with additional data as it is acquired. Examples include
completed forms (regarding such things as inspections, training, manifests, etc.); monitoring log sheets, audit
reports, incident reports, final reports and meeting minutes (compare Documents, above).
Root Cause – The management system breakdown that permitted a substandard action or condition (immediate
cause) to occur. Root Causes may also be referred to as System Causes or Underlying Causes.
Safeguards can be considered as the devices that help to reduce the occurrence frequency of the deviation or to
mitigate its consequences. Safeguards helps in monitoring, preventing or compensating the deviation.
Strategic response will be that which is necessary to protect the business from undue criticism and will be handled
centrally within the Emergency room. The strategic response will, instinctively, support the onsite team by
mobilising, finding and, if necessary procuring resources – labour, materials, plant and equipment, as well as any
specialist skills. The strategic response team will take strategic action such as changing supply systems and bringing
in additional sources. A key task of the strategic team will be communication with external parties to be notified
and with the media and public.
Tactical response will be the site focused response i.e. by the repair team and local management. The tactical
team will (i) attend to the cause of the emergency to affect a repair; (ii) otherwise end the emergency and (iii) deal
with any local consequences of the emergency e.g. in the case of a water utility this would be property flooding
from a sewer collapse or broken water main
The approach to be adopted by a business unit typically for the response to an emergency is a four layer response
as follows .
1. Provide a procedure to trigger an emergency alert. One of the most common failings in responding to an
emergency is the slow realization that an “incident” has or is progressing to an emergency, or that an emergency
has commenced;
2. Analyse the risk. When the emergency event is alarmed, the next steps are to analyse the risk by:
a. Identifying the Nature and Reasons for the Emergency
b. Assessing the consequences
c. Considering the effects
3. Determine the Required Level of Response. Only and after the risk has been analysed is it possible to ascertain
the required level of response
4. Manage the Emergency. The emergency event is to be managed (i) strategically and (ii) tactically, as discussed
below
Typically organizations will set up a multilevel organisational structure, which is functional, and includes for
standby rotas to provide for seven days per week, 24 hours a day. There needs to be a clear escalation process that
matches response with risk. The process is typically initiated by a Head of an Emergency Department and, as
the level of the severity of the emergency increases, provides for Strategic and Tactical Response Leaders.
When a crisis is identified, all necessary resources are to be mobilized promptly in accordance with the appropriate
level of severity of the emergency.
For example in a utility business locally, the alert is conveyed by treatment plant or pumping station operators
and/or by network O&M staff to the central control room; is observed by the control room staff from the SCADA or
93
is notified to the control room by a member of the public or outside organisation. Depending on the severity of the
emergency, local or national teams may be mobilized from other than the organization themselves.
The goals of an emergency response plan are to document and understand the stages needed to:
Ensure the professional management of the emergency
Delegate authority to those required to take emergency response actions
The right people are in place to handle the emergency – the formulation of the strategic and tactical
response teams
The resources are available, or can readily be made available to resolve and/or mitigate the situation to
minimise the effect upon customers, the environment and the wider public
The response teams have at hand a full list of support and back-contacts and those to be notified at the
start, during and at the end of the emergency
Provide emergency public information concerning progress on the emergency and where to obtain
alternative water supplies and generally keep customers informed
A feed-back facility is in place as a means for on-going learning from an emergency
Develop the organisation’s experience of emergency handling through the holding of regular exercises
Rapidly restore business as normal service after an emergency
Minimise asset system damage
Minimise impact and loss to internal and external customers
Minimise negative impacts on public health and employee safety
Minimise adverse effects on the environment
Keep customers and other concerned organisations informed of progress with the emergency Respond
positively to criticisms of performance
It is vital that any organization developing contingency procedures must take the development of these
contingencies seriously as a serious incident can affect the organization at any time
1. The planning out of the system identified risks that can be removed at a reasonable cost.
2. Secondly, for risks that have been identified – specific or generic – that cannot be designed out of the system, or
are awaiting investment of the solution, the effects of the emergency can be mitigated:
a. Before an Emergency by holding regular Emergency Exercises with feedback into Business Plans
b. During an Emergency by having in place an Emergency Response Plan
3. Finally, emergency planning includes for managing the emergency with a:
a. Strategic response – to manage the impact on the business and is directed from a central incident room location
b. Tactical response – the on-site action to correct the event and reduce local effects
The organization would need to prepare a comprehensive list of all potentially serious incidents that could affect
the normal as -is operations. Each serious incident should be given a probability rating related to the potential
impact severity level if the incident did occur.
Emergency planning is contained within a Risk Management approach that comprises the planning out of the
system identified risks that can be removed at a reasonable cost and secondly, for risks that have been identified –
specific or generic – that cannot be designed out of the system, or are awaiting investment of the solution, the
effects of the emergency can be mitigated:
Before an Emergency by holding regular Emergency Exercises with feedback into Business Plans and Operating
Procedures and during an Emergency by having in place an Emergency Response Plan
The following figure illustrates the place of the Emergency Response Plan within a risk management approach.
94
Risk Assessment
to identify risks that:
Emergency
Development
HR Plan O&M Plan Exercises
Plan
Feedback
The Emergency Response Plan should be maintained as a “live” document. As such the Plan is to be regularly
updated and modified in the light of changed circumstances and experiences gained both in responding to
emergencies and from emergency exercises.
The goals of this plan would be to document and understand the stages needed to:
95
Procedure Owner: Managing Director
Purpose: To set out the procedure and frequency for revisions to the Emergency Response Plan and the
methodology for issue.
1. Methodology and type of Review
The Procedure shall be updated under the control of the Head of the Emergency Department at a specified
frequency as mentioned below. In order to develop the framework of the emergency response planning it is
important that an organization or business unit sets up a dedicated committee is set up to structure and lead Risk
Management. This normally has no specific empowerment within the organization and is aimed to be both a think-
tank and a taskforce intending to help and propose solutions to the management of the business which is in charge
of making appropriate decisions and implementing them. The aims would be as follows
2. Frequency of Review
The Emergency Response Plan shall be reviewed and updated in the event of one of the following:
Change of circumstances related to the commissioning and decommissioning of assets.
Changes in staff within posts or nominations to committees
Changes in the organisation structure of the company
Any requirement that has been specified within the Plan that has subsequently found to be inadequate or in
some way insufficient e.g. facilities within the Incident Room
After an Emergency Exercise has been held and the wash-up meetings has revealed a requirement for change;
Any other event or happening that removes the currency of the Plan, as issued.
Developing the plan in itself is not enough and before it can be implemented it should be vigorously tested. This
process needs to be properly planned and carried out in as realistic and authentic conditions as feasible. The
objective of enacting the emergency plans at any time would be also to test the procedures and simulations
employing both operational and technical failures. To avoid complacency, regular audits of the staff
will take place on a monthly basis to check the readiness of staff in case an incident arose. The essentials of this
planning process and audits will include: The emphasis of the plan must be on the response to the incident and
not the cause of the incident, the plan must be flexible - it has to work on holidays, weekends or in extreme
weather conditions (e.g. sandstorms) , it is clearly written and easily understood and all involved must clearly
understand their role
96
The key individuals highlighted in developing the plan need to be fully involved in any testing activities and the test
procedures need to be documented, results recorded and any feedback used for fine tuning the contingency
procedure. The suggested roles are mentioned below
The organization also needs to recognizes the need to audit the plan itself and the backup arrangements
supporting it on a regular basis. To properly implement the contingency procedures it is imperative that the
personnel, who will be involved in implementing these procedures, are fully aware of their responsibilities and
properly tested.
It is also important that appropriate resources will be held available and deployed at the earliest opportunity to
protect the interests of customers and the company’s assets. For example, adequate plant, equipment and
emergency stores are to be available for dealing with the emergency and chemical reserves retained in case
enhanced treatment is necessary at the treatment plants. The resources need not be owned by the buisiness but
could be hired or otherwise made available.
1. The strategic response will be that which is necessary to protect the business from undue criticism and will be
handled centrally within the Incident Room. The strategic response will, instinctively, support the onsite team by
mobilising, finding and, if necessary procuring resources – labour, materials, plant and equipment, as well as any
specialist skills from another business unit or organization for example. A key task of the strategic team will be
communication with external parties to be notified and with the media and public
2. The tactical response will be the site focused response by the repair or other action team, and by local
management.
97
The Emergency Tactical Response Leader would normally be expected to undertake the following tasks. The
Tactical Response Leader is to appoint assistance as he thinks appropriate and, if the emergency is expected to be
of long duration, assemble a stand-by team and a deputy Tactical Response Leader.
If the “normal” response team i.e. standby gang is employed for the emergency, the Emergency Tactical Response
Leader will assemble a second response team to cover for any other emergency that might arise. This might
require the use of staff from say outside of the affected location and will be arranged through the Emergency
Strategic Response Leader :
Immediately go to the site of the emergency
Appraise the situation and make a report to the Emergency Strategic Response Leader
Manage the on-site response and assemble the strategic response team
Take appropriate action to rectify the emergency and manage the on-site activities
If appropriate, evacuate the building and/or ensure the public are kept away
Request additional resources as may be required
Keep the Emergency Strategic Response Leader informed of progress with as early warning as possible of
difficulties
Provide assistance to members of the public who may have been affected by the emergency
At the end of the emergency prepare a report upon the emergency
Clearly, effective communication is the key to successful emergency management and communication is required
between:
1. The strategic and tactical response teams;
2. Appropriate external entities;
3. Media and other means of communication with customers;
4. Internal support staff;
5. Strategic and tactical response back-up teams
3 Training
Effective emergency management requires that emergency managers have good knowledge of their
responsibilities, that managers are trained in the use of a comprehensive emergency plan, and that the team of
emergency managers works effectively together.
The organisation should ensure that specific emergency response training is to be provided regularly in:
Other training requirements (including technical and safety training) may prove necessary and will be identified
through the emergency exercises and/or the various senior managers following an emergency event or not.
The exercise should be used to test the efficiency and capability of the organisation to react professionally and
competently to an emergency as well as the adequacy of the Emergency Response Plan’s components.
The nature of the exercise shall be determined by the senior management of the organisation based upon likely
scenarios that could occur.
The only advance notice of the exercise shall be a general note to all staff that say, an exercise will be held within
the next 4 weeks. The exercise say , can be held anytime within that four week period. Senior managers of the
organisation are also not normally informed of the date or nature of the exercise.
98
Unless otherwise considered as a special need, the exercise shall take place during “normal” working hours. The
exercise can be conducted when key players are not available due to leave, training, meetings or other such
reasons in order to test the standby procedure
The note shall also set out the extent to which the exercise is to be played out. For an exercise that is simulating a
burst main, for example, this will usually be limited to people attending a site, checking location and operability of
valves but not actually operating the valves; checking availability of plant and repair couplings etc.
The exercise is to be given a code name and all messages prefixed with the words: “For the purposes of Exercise
[Name] only” to differentiate from a real emergency.
During an exercise, all procedures, actions described in the various component and procedures of the emergency
response applies with the exception of external bodies/entites (e.g. fire fighters) unless previously agreed with
them.
During the exercise, participating staff shall maintain a record of their actions, communications made and other
information that will be required for the subsequent debriefing meeting.
Following the exercise, a debriefing meeting shall be held to which key players are to be invited. The actions taken
within the exercise are to be critically discussed as an aid to improved performance.
After the debriefing meeting the Managing Director or a person designated by him is to prepare a report of the
exercise and, if required, amend the Emergency Response Plan.
Notes
1. Informal training may be done with video simulations of emergencies or refresher programs.
2. Reviewing emergency case studies may help managers understand emergency scenarios, and achieve
consensus on what was done well, and what could be done better.
3. The organisation’s emergency Team should share news stories about industry related emergencies in other
countries in the world in order to stimulate discussion and stay up-to-date. These news stories may also be
used to stimulate discussion about how to improve emergency management and the emergency plan.
4. The organisation’s Emergency Team should participate in annual emergency management scenarios (see
below).
Emergency Scenarios
The scenario should be planned in such a way as to avoid having it be interpreted as a real occurrence. Care must
be taken to avoid alarm. It is important that all written material and oral communications clearly indicate that ‘this
is a drill.’
99
3. Develop an exercise that will be a positive experience.
a. Start with simple exercises, and work up to more complex exercises.
b. Set objectives that are attainable. Do not attempt to test the group to the point of failure.
c. Determine whether the team should be told the basic characteristics of the planned scenario in advance
to allow review of relevant documents.
4. Determine what type of exercise is appropriate.
a. In a static (or tabletop) exercise, an emergency scenario is created on paper. Successive events are
presented on paper, by a facilitator who is present in the meeting room, by incoming telephone calls, or
via radio messages. These are simple to run, and require few resources; however, they only test some
aspects of emergency response. In addition, the exercise must be planned carefully to ensure that the
limitations of the exercise do not preclude effective emergency management.
b. Telecommunications exercises are used to test the effectiveness of emergency notification systems,
communications systems, and may be used to analyze effectiveness of risk communications with the
media and the public. Telecommunications exercises may not require the assembly of all members of the
organisation’s Emergency Team.
c. Field exercises are the most complicated type of emergency scenario. They test information flow and
decision-making under realistic conditions. During a field exercise, all members of the organisation’s
Emergency Team should be assembled and a Command Post should be established ). The organisation’s
staff may be involved in response activities and on-site investigations may be performed, depending on
the characteristics of the scenario.
5. Setting up the exercise
a. Is this a static, telecommunications or field exercise?
b. Plan a schedule of exercises.
c. Create a scenario, and a sequence of events.
d. Identify the information needs of the group, and plan appropriate cues.
e. Review the scenario, sequence of events and cues to determine the appropriate responses of the
organisation’s Emergency Team. If the team does not earn the information required to keep the exercise
on track, the facilitator may interrupt the exercise when it is appropriate and provide the required
information. The problem in the exercise or in team responses should be reviewed later.
f. Identify any control or safety requirements.
g. Identify staff requirements.
h. Identify resource requirements:
i. Assemble maps showing all facilities
ii. Obtain all necessary forms
iii. Gather an adequate number of emergency plans
iv. Set up a meeting room with a blackboard or a whiteboard, an overhead projector, a flip chart,
communications tools (radios, telephones, fax, computers), and any other requirements.
v. Create message cues, and determine how they will be delivered.
i. Plan site preparation and clean-up.
j. Plan debriefing.
6. Explain the expectations of the exercise. Note that this is a friendly exercise, designed to be used to determine
the adequacy of emergency management tools and training, rather than as a test of individual member’s
performance.
7. Give the participants instructions:
a. You will be given a scenario, with necessary information at the outset. Your actions will determine what
additional information you obtain.
b. Use appropriate procedures and other documentation.
c. Document your actions and fill out applicable forms.
d. Plan response activities with the assumption that adequate staff and resources are available. Document
your intended responses.
e. Do not operate equipment.
f. Be careful to always indicate on papers and in oral communications that ‘this is a drill.’
g. Communications with outside groups, including the public, media and staff who are not involved in the
100
emergency scenario should be simulated by contacting the facilitator.
8. Perform the exercise.
9. Immediately debrief all participants.
a. Assess the success of the exercise and make recommendations for improvements.
b. Recommend changes to the emergency plan.
c. Recommend changes to task allocation among the organisation’s Emergency Team Members.
d. Evaluate the effectiveness of communications among the organisation’s Emergency Team members.
e. Evaluate the effectiveness of decision-making of the organisation’s Emergency Team.
f. Evaluate the effectiveness of communications with other agencies (if applicable).
4 Resilience
In the event of a credible warning or threat of a potentially serious incident or circumstance, the organisations’
Emergency Team should be informed immediately. The team may decide to activate the Emergency Plan
Alternatively, the team may prefer to remain in an alert condition. During an alert situation the buinsess
operations may be changed, and the team should be kept informed of changes in circumstances, , for example as
follows for a water utility - but formal implementation of the plan is not required
Example of Water Utility - Ensuring maximum resilience in the system
1. Ensure maximum resilience in the system. This may involve increasing the amount of water in storage by
filling reservoirs and towers, switching operations to generator power, implementing water use restrictions ,
etc.
2. Consider implementing precautionary water-use restrictions.
3. Consider shutting down or increasing monitoring of sources or areas of the distribution system that may be
affected by the incident.
4. Determine whether to isolate areas of the system or turn off non-critical sources.
5. Prepare for the loss of electrical power or telephone lines. Do computerized control systems operations need
to be altered? Should operations be set to manual mode in anticipation of loss of phone systems or failure of
computerized control systems?
5 Simplified Assessments
The aim of hazard identification is to identify all relevant potential causes of harm to people, damage to the
environment and damage to property. Once hazards are identified they can be assessed and if necessary avoided,
prevented or controlled.
Formalised: The hazard identification should be carried out according to a documented procedure.
Thorough: The hazard identification process should be complete within a boundary, which should be defined
beforehand.
Repeatable: Experienced personnel carrying out the same hazard identification exercise should furnish similar
results.
Structured: The procedure used should ensure that adequate attention is given to all parts of the plant, procedures
or other items under study and that nothing is missed.
The technique selected for a particular application should take account of the specific requirements of that
application, especially the end use of the hazard identification process.
The output of the hazard identification process should be followed up to ensure that risks are assessed and control
measures implemented as appropriate. Typically, a hazard identification type study will result in a series
of actions such as the requirement to:
101
Modify operational procedures.
Modify maintenance procedures.
Evaluate the need for modifications to plant, procedures or maintenance activities.
Carry out more detailed assessments.
An appropriate action tracking system should be used to ensure that all actions are carried out and closed out in a
timely fashion, including further actions and recommendations that may result from detailed studies. The action
tracking system should record all data necessary to ensure that the action is properly closed out including:
As part of the preparedness for emergency response planning also the understanding of hazards should be clear
with the associated use of the Management Information System ( MIS ) – where accessing data and other
information from the MIS will mean that the data is current and common to all users. It follows that data held on
the MIS for the hazards applicable to the business unit should be accurate and current and that hardware is
available so that those who require the data, can freely access the MIS.
Hazards can be classified regarding their causes and consequences – further example is provided in the Appendix 1
Causes Consequences
Quality management Deviation from: Customer non-satisfaction
- Customer expectations; Legal prosecution / fees
- Regulatory Rules;
- Business policies.
Health and Safety Hazardous situation Injury or diseases for:
Management Unsafe practices - Employees
- Contractors
- Customers
Environment protection Environment pollution or damages
A simplified approach can be as follows with example taken for a water utility company, where the risk rating would also effect
the escalation and level of management involvement
Probability
Construction accident
Low -Manageable Failure of IT systems
Where High Probability and High Severity = High risk and Low Probability and Low Severity =Low risk
102
Definitions of severity
103
They would in all probability require the assistance of the destroyed or seriously
outside agencies ( eg police , military etc ) and would be damaged could for
tackled at regional, if not national level. example contribute to a
severe water shortage, lead
to an inability to maintain
sewage lift or treatment
operations, seriously affect
drinking water distribution
or alternatively affect the
availability of water for
fighting fires
An alternative more sophisticated approach would be to utilize methodological tools such as the Ishikawa diagram
(also known as the 6M Methodology: Manpower, Material, Method, Milieu, Machine, Measurement).
The criticality of a risk is defined as C = L x S
Severity
Low Medium High Very high
Likehood
The likelihood means the probability for a hazard to occur. It can be evaluated regarding the following table
Consequence
Quality Health & Safety Environment Severity Rating
Deviation from regulatory Death Irreversible effects or wide area Very high 4
rules impacted (more than 1km )
Deviation from international Irreversible effect Long-term reversible effects, High 3
standards Impact area around one hundred
meters
Deviation from the Accident with work Short term reversible effects. Medium 2
organization’s leave - reversible Impact area around ten meters
Policies effects
Deviation from Minor injuries, Negligible impact Low 1
Site / company rules without work leave
104
For risk whose criticality is rated beyond 8, the risk control level shall be assessed.
It is calculated by the formula Ct = Mt x Mn
Where:
Mt means the mitigation of the risk
Mn means the monitoring of the risk
This criterion evaluates the monitoring of the risk. It could include either technical equipment
(probes, detectors…) or management scheme (legal review…).
Once the risk are assessed and their criticality and level of control are calculated, the global risk level can be
calculated by RL = C x Ct.
The final ranking according to the Global Risk Level will highlight the risks that should be tackled in priority.
105
Appendix : Risk Assessment Matrix
Environment pollution ( E)
Criticality, = L*S
Seriousness
Monitoring
Mitigation
Likelihood
Risk level
Control
Q 2 3 6 N 3 3 Rank
E 2 4 8 Y 2 3 6 48 1
HS 4 4 16 Y 2 2 4 64 1
In the above example there may be additional or alternative codes to suit the business applications – for example
AM Asset Management
CD Capital Delivery
CS Customer Services
ICT Information and Communication Technologies
ISS Industrial Security and Safety
OM Operating and Maintenance
P&C Procurement and Contracts
106
Causes
Consequences
Criticality
L Likelihood
1 Rare
2 Unlikely
3 Possible
4 Likely
5 Certain
S Seriousness of consequences
1 negligeable
2 Marginal
3 Critical
4 Catastrophic
107
SECTION 6 : RISK REVIEW CHECKLISTS
1 Introduction
Webster’s New Collegiate Dictionary defines sustainable as “maintain, or cause to continue, in existence or a
certain state.” The word ‘sustainable’ is now used to define a world that is able to “maintain in existence” all life
that now exists. To attain that goal, human activities will need to change. With respect to the utility sector this
means the efficient and economic use of the utilities without losses or upsets In a related vein, inherently safer
processing addresses the need to prevent catastrophes that not only pose immediate danger, but also can result in
environmental contamination. The challenge is therefore to have the sustainable processes that not only meet the
definition above, but that are also profitable, meet or exceed regulations, satisfy customers needs, maintain
support from the customers, and fulfill the capacity building and institutional strengthening needs of the
organization
The International Process safety Group (IPSG) and the AIChemE Center for Chemical Process Safety (CCPS) have
published a working definition of Inherent Safety Design which will be applied in this section to the review
checklists as a general means of risk mitigation as well . There are the following four key words for mitigations.
Decision for the mitigation measures may quite often be dependant upon further studies eg modeling, further
sampling and analysis , trials etc – but the below checklist provides an indicative start towards assessing the risks in
your working places
Minimize: (or intensify): eg reducing the period of risk or for example in the case of use of hazardous chemicals
using smaller quantities
Substitute: eg changing the working conditions or O &M parameters which the risk is exposed to – or for example
using less hazardous materials, processes, conditions.
Moderate: (or attenuate):reduce risk conditions through change in O & M , design conditions or in the case of
chemicals using less hazardous conditions of forms of substance.
Simplify: eliminate unnecessary complexity, “user friendly” plants or design processes that eliminate unnecessary
complexity and are tolerant to human error. In this case it should also be noted that the use of Human
Factors/Ergonomics is defined as the systematic process of designing for human use through the application of our
knowledge of human beings to the equipment they use, the environments in which they operate, the tasks they
perform, and the management systems that guide the safe and efficient operations . Keeping it simple, stupid’,
whether in design or operation, is general seen as key to encouraging good human performance. However, the
disadvantage of the simplification concept is that it can engender boredom, which can result in errors. In this
respect ensuring operators are involved earlier in plant design and modification is important as is also ensuring
control rooms and systems were are designed with ergonomic and practical issues for the optimization of O & M
activities including issues such as validation of data inputs, screens and graphics, ‘alarm flooding’, simplicity and
consistency. Simulations in operator rooms might be used for emergency situations.
The below checklists are intended to be a representation only and not an exhaustive or comprehensive list. The
below is intended to show the reader the need to develop a unique checklists for review, auditing and verification
based upon site or business specific needs
108
2 General Example of Global Checklists
109
safety boots, gloves, eye protectors, respiratory
protection equipment and life jackets been provided
where appropriate?
Have suitable toilets been provided and are they kept
clean?
Is suitable clothing provided for those who have to
work in wet, dirty or otherwise adverse conditions?
Does the facility have a chemical safety specific
training program on safe use and handling of chlorine
that is documented for employees, new hires,
contractor.
Are accidents and incidents investigated and reviewed
with operating personnel
Is a current MSDS available for all chemicals used
Are warning signs, Chemical Safety Wall Charts,
and/or other safety information used and visible
Does the facility have a Personnel Protective
Equipment (PPE) policy for chemical loading and
unloading?
Does the facility have a policy for respiratory
protection in all aspects of chemical handling and
emergency response?
Are safety showers and eyewash stations adequately
located and easily accessible from all areas of the
unloading site?
Are the safety showers and eyewash stations
periodically inspected for proper operation?
Are there facilities for changing, drying and storing
clothes?
Is drinking water available?
Is there a site hut or other accommodation where
workers can sit, make tea and prepare food?
Are welfare facilities easily and safely accessible to all
who need to use them?
1.4 Protection of the Public
Are the public fenced off or otherwise protected from
the work?
At the end of the working shift:
Is the site secured?
Is the perimeter fencing secure and undamaged?
Are all ladders removed or their rungs boarded so that
they cannot be used?
Are excavations and openings securely fenced?
Is all plant immobilised to prevent unauthorised use?
Are materials safely stacked?
Are flammable or dangerous substances locked away
in secure storage places?
2.0 Training
Has an induction programme been established?
Have all persons working on the site been inducted?
Is specific training given on specialist health & safety
110
issues related to the site?
Are toolbox talks an established part of the work
arrangements?
3.0 Good Housekeeping
Are all working areas and walkways level and free
from obstructions such as stored material and waste?
Is the site tidy and are materials stored safely?
Are there proper arrangements for collecting and
disposing of waste materials?
Is hazardous waste kept separate from general waste?
4.0 Fire First Aid & Emergency Provision
Has the workforce been properly advised as to how
and where to raise the alarm and call for assistance?
Does the alarm system consider the difficulties of
language when raising the alarm?
Is the alarm tested at weekly intervals?
Does the site test emergency and evacuation
procedures?
Are portable fire extinguishers provided at
appropriate points?
Are portable fire extinguishers inspected regularly?
Is there a procedure for replacing 'used' fire
extinguishers?
Are appropriate persons trained in the use of fire
extinguishing equipment?
5.0 First Aid
In the event of an accident, are steps taken to protect
casualties from further harm?
Is First Aid and medical treatment facilities, including
trained personnel, provided on site?
Are records of all treatment and injuries maintained?
Is the workforce aware of how to obtain first aid or
medical treatment?
6.0 Emergency Response
Is there a site emergency response plan (ERP) that is
up to date and reviewed annually?
Have emergency responders received training and if
so is this training satisfactory ?
Are periodic drills performed by emergency
responders?
Are the appropriate emergency kit(s) on-site,
complete, inspected, and located in an appropriate
location?
Is the emergency responder equipment (BA, suits,
etc.) inspected regularly and maintained in suitable
condition?
Are wind socks or other means of determining wind
direction appropriately located and easily visible from
all areas of the plant?
Has the facility assessed the need for process and
111
perimeter monitoring, and implemented as
appropriate?
Have emergency procedures been developed, e.g.
evacuating the site in case of fire or rescue from a
confined space?
Are workers aware of the procedure?
Is there a means of raising the alarm and does it
work?
Are there adequate escape routes and are they
maintained?
Is there a site emergency response plan
(ERP) that is up to date and reviewed annually?
Have emergency responders received
training and if so is this training satisfactory ?
Are periodic drills performed by emergency
responders?
Are the appropriate emergency kit(s) on-site,
complete, inspected, and located in an appropriate
location?
Is the emergency responder equipment (BA, suits,
etc.) inspected regularly and maintained in suitable
condition?
Are wind socks or other means of determining wind
direction appropriately located and easily visible from
all areas of the plant?
Has the facility assessed the need for
process and perimeter chemical residue monitoring,
and implemented as appropriate both in the
workplace and on the perimeters ?
Is there a site emergency response plan (ERP) that is
up to date and reviewed annually?
Have emergency responders received training and if
so is this training satisfactory ?
Are periodic drills performed by emergency
responders?
Are the appropriate emergency kit(s) on-site,
complete, inspected, and located in an appropriate
location?
Is the emergency responder equipment (BA, suits,
etc.) inspected regularly and maintained in suitable
condition?
Are wind socks or other means of determining wind
direction appropriately located and easily visible from
all areas of the plant?
Has the facility assessed the need for process and
perimeter monitoring, and implemented as
appropriate?
7.0 Safe Means of Access
7.1 Safe Places of Work
Can everyone reach their place of work safely, i.e. are
roads, gangways, passageways, passenger hoists,
staircases, ladders, scaffolds and other access
112
equipment in good condition?
Are there guard rails, equivalent protection or other
control measures in place to stop falls from open
edges, e.g. scaffolds, mobile elevating work platforms,
buildings, gangways, excavations, etc.?
Are holes and openings securely guard railed, provided
with an equivalent standard of protection, or provided
with fixed, clearly marked covers to prevent falls?
Where it is essential to work at an open edge is the
opening fenced as far as possible and is safety
harnesses used by operatives?
Are structures stable, adequately braced and not
overloaded?
Are all working areas and walkways level and free from
obstructions such as stored materials and waste?
Is the site tidy, and are materials stored safely?
Are there proper arrangements for collecting and
disposing of waste materials?
Is the work area adequately lit? Is sufficient additional
lighting provided when work is carried on after dark or
inside buildings?
7.2 Scaffolds
Are scaffolds erected, altered and dismantled by
competent persons?
Is there safe access to the scaffold platform?
Are all uprights provided with base plates (and, where
necessary, timber sole plates) or prevented in some
other way from slipping or sinking?
Are all uprights, ledgers, braces and struts in position?
Is the scaffold secured to the building in enough places
to prevent collapse?
Are there adequate guardrails and toe boards or an
equivalent standard of protection at every edge from
which a person could fall 2m or more?
Where guard rails and toe boards or similar are used:
Are the toe boards sufficiently high (at least 150 mm)?
Is the upper guardrail positioned at a suitable height
(at least 910mm) above the work area?
Are additional precautions, e.g. intermediate
guardrails or brick guards in place to ensure that there
is no unprotected gap of more than 470mm between
the toe board and upper guardrail?
Are the working platforms fully boarded and are the
boards arranged to prevent tipping or tripping.
Are there effective barriers or warning notices in place
to stop people using an incomplete scaffold, e.g. one
that isn’t fully boarded?
Has the scaffold been designed and constructed to
cope with the materials stored on it and are these
distributed evenly?
Does a competent person inspect the scaffold
113
regularly, i.e. at least once a week; always after it has
been substantially altered and following extreme
weather?
Are the results of inspections recorded?
If it is not reasonable to provide a scaffold or
alternative safe means of access where persons may
fall more than 2 metres, are safety harnesses etc.
used?
7.3 Powered Access Equipment
Has the equipment been erected by a Competent
Person?
Is fixed equipment, e.g. mast climbers, rigidly
connected to the structure against which it is
operating?
Does the platform have adequate guardrails and toe
boards or other barriers to prevent workers and
materials falling off?
Have precautions been taken to prevent people being
struck by the moving platform, projections from the
building or falling materials, e.g. a barrier or fence
around the base?
Are the operators trained and competent?
Is the power supply isolated and the equipment
secured at the end of the working day?
7.4 Ladders or similar means of access
Are ladders the right means of access for the job?
Are they secured to prevent them slipping sideways or
outwards?
Do ladders rise about 1m above their landing places? If
not, are there other handholds available?
Are the ladders positioned so that users don’t have to
over-stretch or climb over obstacles at work?
Are all ladders in good condition?
7.5 Roof Work
Are there enough barriers or is there other edge
protection to stop people or materials falling from
roofs?
Do the roof battens provide safe hand and foot holds?
If not, are crawling ladders or boards provided and
used?
During industrial roofing, are precautions taken to stop
people falling from the leading edge of the roof or
from thin or partially fixed sheets, which could give
way?
Are suitable barriers, guardrails or covers, etc.
provided where people pass or work near fragile
material such as asbestos cement sheets and glass or
near roof lights?
Are crawling boards provided where people must work
on fragile roofs?
Are people excluded from the area below the roof
work? If this is not possible, have additional
114
precautions been taken to stop debris falling onto
them?
8.0 Hot Work & Fire Prevention
Are method statements presented to a Site HSE Officer
before commencing work on or adjacent to plant
containing flammable substances?
Is the quantity of flammable material on site kept to a
minimum?
Are there proper storage areas for flammable liquids
and gases, e.g. LPG, acetylene, solvents, paint
thinners?
Are containers and cylinders returned to these stores
at the end of the shift?
If liquids are transferred from their original containers
are the new containers suitable for flammable
materials?
Is smoking banned in areas where gases or flammable
liquids are stored and used? Are other ignition sources
also prohibited?
When gas cylinders are not in use, are the valves fully
closed?
Are adequate bins or skips provided for storing waste?
Are cylinders kept safely upright?
Are gas cylinders stored outdoors when not in use?
Where gas cylinders are connected to heaters or
cookers in temporary buildings, are the cylinders kept
outside the building?
Is flammable waste regularly removed?
Are the right number and type of fire extinguishers
available and accessible?
Are work areas inspected one hour after completion of
welding / burning activities?
Are adjacent work areas protected during hot work by
the use of screens or mats?
Are workers using appropriate PPE during hot work
operations?
9.0 Site Electrical Supplies
Is the supply voltage for tools and equipment the
lowest necessary for the job (could battery operated
tools, reduced voltage tools, e.g. 110V or lower in wet
conditions, be used)?
Where mains voltage has to be used, are trip devices,
e.g. residual current devices (ELCBs) provided for all
equipment?
Are ELCBs protected from damage, dust and dampness
and checked daily by users?
Are cables and leads protected from damage by
sheathing, protective enclosures or by positioning
away from causes of damage?
Are all connections to the system properly made and
are suitable plugs used?
115
Is there an appropriate system of user checks, formal
visual examinations by site managers and combined
inspection and test by competent persons for all fixed
& portable tools and equipment?
Are scaffolders, roofers, etc. or cranes or other plant,
working near or under overhead lines? Has the
electricity supply been turned off, or have other
precautions such as ‘goal posts’ or taped markers been
provided to prevent them contacting the lines?
Have underground electricity cables been located
(with a cable locator and cable plans), marked, and
precautions for safe digging been taken?
Are all installation, modification and maintenance
work carried out only by trained and competent
persons?
Does the installation include high standards of
electrical insulation?
10.0 Special Processes & Procedures
10.1 Confined Spaces
Has a system for safe working in confined spaces been
established, e.g. permit for work system?
Are suitable steps taken to ensure that confined
spaces are vented and purged of toxic, flammable and
asphyxiating gases?
Have workplaces in which gases, vapours or fumes
could accumulate or a shortage of oxygen could arise
been recognised and clearly identified?
Does a competent person sign a declaration that an
area is safe to enter prior to work commencing?
Are guards positioned at all points of access whilst
work is being carried out in confined spaces?
10.2 Excavations
Is an adequate supply of timber, trench sheets, props
or other supporting material made available before
excavation work begins?
Is this material strong enough to support the sides?
Is a safe method used for putting in the support, i.e.
one that does not rely on people working within an
unsupported trench?
If the sides of the excavation are sloped back or
battered, is the angle of batter sufficient to prevent
collapse?
Is there safe access to the excavation, e.g. by a
sufficiently long, secured ladder?
Are there guardrails or is there other equivalent
protection to stop people falling in?
Are properly secured stop blocks provided to prevent
tipping lorries falling in?
Does the excavation affect the stability of
neighbouring structures?
Are stacked materials, spoil or plant stored near the
edge of the excavation likely to cause a collapse of the
116
side?
Does a competent person at the start of every shift
inspect the excavation; and after any accidental
collapse or event likely to have affected it’s stability?
Is a suitable system of formal control of excavations in
place? Is this procedure followed for all excavations?
11.0 Chemicals and Hazardous Substances
Have all harmful materials, e.g. asbestos, lead,
solvents, paints, etc. been identified?
Have the risks to everyone who might be exposed to
these substances been assessed?
Are method statements produced for all work
involving removal or installation of thermal insulation
material?
Have precautions been identified and put in place, e.g.
is protective equipment provided and used; are
workers and others who are not protected kept away
from the exposure?
Are proper storage facilities allocated and used?
12.0 Noise
Are breakers and other items of plant or machinery
fitted with silencers?
Are barriers erected to reduce the spread of noise?
Is work sequenced to minimise the number of people
exposed to noise?
Are others not involved in the work kept away?
Is ear protection provided and worn in noisy areas?
What are the maximum permissible noise levels
adjacent to the construction site?
Are controls set up to monitor noise levels adjacent to
the construction site?
13.0 Radiography
If appropriate have procedures for the control and safe
use of radiation generators or radioactive sources
been produced?
Is the procedure properly implemented when
radiography is carried out?
14.0 Work Equipment & Safe Working Practises
14.1 Compressed Air
Have all workers been trained in the correct use of air-
operated tools?
Have the dangers of directing compressed air at the
body been highlighted to the workforce?
Are heavy-duty hose clamps used?
Are quick-acting couplers, designed to seal upstream
air pressure on disconnection and slowly vent on the
downstream side, used?
Are hoses kept clear of walkways/roadways?
Is regular maintenance of equipment, including safety
devices carried out?
117
14.2 Manual Handling
Are hoists, telehandlers, wheelbarrows and other plant
or equipment used so that manual lifting and handling
of heavy objects is kept to a minimum?
Are materials such as cement ordered in appropriate
size bags for safe manual handling?
Can the handling of heavy blocks be avoided?
14.3 Hoists
Is the hoist protected by a substantial enclosure to
prevent someone from being struck by any moving
part of the hoist or falling down the hoist way?
Are gates provided at all landings?
Are the gates kept shut except when the platform is at
the landing?
Are the controls arranged so that the hoist can be
operated from one position only?
Is the hoist operator trained and competent?
Is the hoist’s safe working load clearly marked?
If the hoist is for materials only, is there a warning
notice on the platform or cage to stop people riding on
it?
Is the hoist inspected weekly, and thoroughly
examined every six months by a competent person?
Are the results of inspections recorded?
14.4 Cranes and Lifting Equipment
Is the crane on a firm, level base?
Are the safe working loads and corresponding radii
known and considered before any lifting begins?
If the crane has a capacity of more than one tonne,
does it have an efficient automatic safe load indicator
that is inspected weekly?
If an excavator is used as a crane, does it have the
necessary check valves and is its maximum safe load
clearly marked?
Are all drivers trained and competent?
Have the banksman and slingers been trained to give
signals and to attach loads correctly?
Do the driver and banksman find out the weight and
centre of gravity of the load before trying to lift it?
Are cranes inspected weekly, and thoroughly
examined every 12 months by a competent person?
Are the results of these inspections recorded?
Does the crane have a current test certificate?
Has a Lifting Plan for carrying out heavy lifting
operations been prepared? Is this plan implemented
Are areas where lifting operations are taking place
clearly identified? Are unauthorised persons excluded
from this area?
Is lifting equipment kept under strict control?
Is the SWL and unique identity marked on every item
of lifting equipment?
118
Is there proof of inspection/certification of all lifting
equipment?
15.0 Plant and Machinery
Are all dangerous parts, e.g. exposed gears, chain
drives, projecting engine shafts, guarded?
Are guards secured and in good repair?
Is the machinery maintained in good repair and are all
safety devices operating correctly?
Are operators trained & competent?
16.0 Hand and Power Tools
Are the correct tools provided and used properly for
each task?
Are regular checks of tools carried out to ensure that
they are in good condition?
Are steps taken to ensure that untrained persons do
not use tools?
When cartridge operated tools are used, are method
statements made available to the HSE Officer?
Are home made tools only used after authorisation by
a competent person?
17.0 Vehicles
Are vehicles maintained? Are maintenance records
available? Do the steering, handbrake and footbrake
work properly?
Have drivers received appropriate training and do they
hold written authorisation for the type of vehicle?
Are site vehicles locked when not in use?
Are vehicles, which operate inside buildings fitted with
both visual and audible warning devices?
Are vehicles securely loaded?
Are passengers prevented from riding in dangerous
positions?
18.0 Working near water
Have appropriate controls, e.g. barriers, warning signs,
been erected to warn workers of open water?
Do persons working on or over water use life jackets &
safety lines or safety nets?
Are buoyancy aides provided where a high risk of
individuals falling into water exists?
Is a safety boat provided downstream of work over /
on rivers?
Have supervisors and persons who work on, over or
adjacent to water received appropriate training?
Are boats and vessels suitable for purpose?
Is there a suitable emergency procedure and adequate
back up?
19 Containers Securement / Preparation
Are gas detectors present in packaging and process
areas that are interfaced into an alarm system with
appropriate detection limits being utilized for the
alarm set points? ( if applicable )
119
Are cylinders and ton containers segregated between
full and empty? ( if applicable )
Are full ton containers stored so that each end is
accessible in case a repair is needed? ( if applicable )
Are written operating procedures available and being
utilized by employees that address the appropriate
steps for evacuating and filling cylinder and ton
containers? ( if applicable )
Do procedures exist for testing for leaks prior to
filling each cylinder and ton container? ( if applicable
)
Do procedures exist for proper evacuation of lines
before disconnecting?
Do procedures exist for inspection and change out of
valves? ( if applicable )
Do procedures exist for appropriate torque settings
of valves and packing nuts? ( if applicable )
Do procedures exist for proper labeling and marking
of cylinders and ton containers? ( if applicable )
Are ton containers secured to prevent them from
rolling? ( if applicable )
Are appropriate lifting devices being utilized to move
ton containers? ( if applicable )
Are gas detectors present in packaging and process
areas that are interfaced into an alarm system with
appropriate detection limits being utilized for the
alarm set points? ( if applicable )
Do facility procedures verify that delivery vehicles are
properly placarded with the Hazchem system
Is lighting or emergency lighting provided to allow for
safe operation and emergency response?
Is a checklist or other procedure used to
assist with the performance of pre- unloading, post
unloading, and prerelease inspections?
Are workers performing higher risk activities like line
breaks or disconnections being appropriately
monitored?
Are unloading lines and air padding lines purged,
evacuated, disconnected, and capped immediately
when not in use to minimize moisture entry into the
piping system?
Are piping leak checks conducted prior to unloading (
if applicable )
Do operating procedures require leaks to be repaired
before allowing operations to begin or continue?
Are liquid angle valves completely open when
unloading is in progress? ( if applicable )
If the container is disconnected, lines capped, and
protective housing cover closed and sealed after
unloading has ceased for the day? ( if applicable )
Are piping connections purged to a scrubber or VOC
containment, process application, or containment
120
prior to piping disconnection? ( if applicable )
Are all the staff ( including labourers ) involved in
unloading the fuel or chemicals from the delivery
vehicles trained
Is PTFE tape or non-reactive pipe dope used on
threaded connections? ( if applicable )
Are procedures in place to prevent PTFE tape from
interfering with angle valve closure? ( if applicable )
Have lubricants being used in the chemical handling
been confirmed to be compatible
Is there a remotely operated or automatically
actuated emergency shutoff valve system in place
which can safely isolate both ends of transfer
hoses / flexible piping? ( if applicable )
Is the emergency shut-off system tested routinely?
Are there shutoff valves on both sides of transfer
hoses
20 Process Piping
Do piping and all components comply with
recommendations of such as metallurgy, schedule,
welding requirements, etc?
Are all hoses in contact with fuel or chemicals tested
or replaced on a preventive maintenance basis?
Is the piping system adequately supported / braced
with pipe shoes or other support ?
Is the piping system protected from vehicular traffic?
Is new or replacement piping properly cleaned and
inspected ?
Are the gaskets used compatible
21 Underground Piping
Is underground piping system continuously
monitored for leaks? How?
Has cathodic protection, used for underground
piping, been considered?
22 Building Systems
Is there potable gas monitors for monitoring of areas
within and around the building for gas leaks - ( if
applicable ) (are there alarms, warning lights)?
All facilities having leakage test kit (e.g. ammonia,
water and swabs or other acceptable detector) to be
provided in clearly marked locations
Is sufficient and appropriate ventilation provided (i.e.
reference to be made to NIOSH standards)
What are the safety systems in place such as
pressure type switch located on the doors to
chlorination rooms which shall activate the exhaust
fan automatically when the door is opened. ( if
applicable )
23 VOC / scrubbing / venting systems
Is there a means available to process vent gases and
the emergency evacuation of equipment containing
Gas ? ie Maintaining safe vent conditions
121
Is the venting design based upon the worst case
Preventing fires, explosions, and toxic releases
Is the system clear for understanding normal process
operations, such as intentional routine controlled
venting and emergency operations, like overpressure
relief
Does the system mitigating the impacts of end-of-line
treatment devices, such as scrubbers, flares, and
thermal oxidizers, on the vent header system
If so does the scrubber capacity designed to process
the facility’s most probable release scenario?
Does the scrubber have ‘passive’ scrubbing capability
or is it equipped with emergency stand-by power
sources?
Are the materials of construction Adequate
Is the scrubbing solution either designed or
monitored / analyzed to confirm required minimum
capability?
Is the scrubbing vent monitored to detect gas
breakthrough?
Is there adequate backflow detection
Does the system comply with regulations
24 Containment , Bunding and Overflow
Is there systematic assessment of safety integrity
level requirements ie what is the overall systems for
tank-filling control is this of high integrity and with
sufficient independence to ensure timely and safe
shutdown to prevent tank overflow. Do Site
operators meet the latest international standards
Does the methodology of safety
integrity level (SIL) requirements for overfill
prevention systems take into account of the
existence of nearby sensitive resources or
populations; the nature and intensity of depot
operations; realistic reliability expectations for tank
gauging systems; and
the extent/rigour of operator monitoring.
Is the Protecting against loss of primary containment
use of high integrity systems in line with the
appropriate standards
Does the management systems for maintenance of
equipment and systems to ensure their continuing
integrity in operation include, but not be limited to
reviews of the arrangements and procedures for
periodic proof testing of storage tank , overfill
prevention systems to minimise the likelihood of any
failure that could result in loss of containment;
review of the effectiveness of equipment and
systems in preventing loss of containment or in
providing emergency response , high integrity,
automatic operating overfill prevention system (or a
number of such systems, as appropriate) that is
122
physically and electrically separate and independent
from the tank gauging system.
Does the overfill prevention system (comprising
means of level detection, logic/control equipment
and independent means of flow control) should be
engineered, operated and maintained to achieve and
maintain an appropriate level of safety integrity in
accordance with the requirements of the
recognised industry standard for ‘safety
instrumented systems’ detection, logic/control
equipment and independent means of flow control) –
ie is this engineered, operated and maintained to
achieve and maintain an appropriate level of safety
integrity in accordance with the requirements of the
recognised industry standard for ‘safety
instrumented systems’
Is the engineering, design, operation and
maintenance against escalation of loss of primary
Secondary and tertiary containment in line with
required international standards
20 Security
Have security guards received information and
training of dealing with alarms or dealing with
emergency events
The below provides an general suggestion of checklists – It is of course very important that there should be a well
developed and implemented emergency response plan for the site which details the plans and actions required for
all such events
123
drainage is discharged
heavy rainfall on the site Moderate : The normal acceptable options would
be to (i) include for the additional flow within the
treatment capacity; (ii) provide storm water
overflows within the collection system; (iii) provide
specific landscaped areas to which storm water can
be discharged or (iii) provide a storm water holding
reservoir on the works site.
flooding from an adjacent flood plain Moderate : earth bunds can be
constructed around the works or critical plant
raised to a height above a reasonably
expected flood level.
2. Loss of Power
Moderate : ensuring adequate on-site generating
capacity for essential plant / critical drives eg on
site electrical standby generation with appropiate
maintenance scheduling or arrangement with hire
companies from whom plant and equipment such
as mobile generators can be obtained.
Substitute : by having two separate and
independent electricity supplies into the Works.
3 Pollution or Debris arriving in inlet
Pollution may cause environmental damage , Moderate : Should the biomass be killed as a result
particularly in cases there is no storm water or of the pollution action plan for dealing with
overflow tank into which a polluted sewage can be reformulation of the biomass through transplating
safely discharged and action taken to remedy the ( ie sourcing new biomass and reseeding ) and in
matter, it could cause breach or non compliance of cases of foaming to ensure appropriate mitigation
discharge limits and may make the operator liable to measures for analysis of the foam and use of
prosecution by the environmental enforcement antifoaming measures. Remember that it is
agency - difficult to determine by sight if activated sludge is
failing so that it is necessary to measure oxygen
consumption and parameters of treatment
performance such as MLSS, SSVI, SRT etc for a true
ongoing understanding of performance ( this can
include the use of on line plant SCADA systems
and portable dissolved oxygen monitoring
equipment )
124
streams ( ie where “spare” treatment capacity is
available ) as dictated through the asset
management and operation / maintenance plan.
Note : this option may also be assisted by
preplanning of modeling scenarios in the design
analysis ; operation and maintenance and
emergency response plans
125
b. During an emergency ( according to the defined
strategic and response team role )
i. Ascertain the extent of the damage and the
consequences including plan of response for
dealing with staff affected by the leakage and for
the site response leader to adopt the controlling
and management of the incident;
ii. If the consequences will have an effect upon the
neighbouring area, the emergency response plan
should cover the appropriate notifications and
evacuation procedures;
iii. Site staff involved in the implementation of the
emergency response plan and depending upon the
severity and criticality of alarms according to the
plan if of tactical response then wearing breathing
apparatus and when safe to do so, isolate the
cause of the leak; if of strategic level response then
evacuating the area and as per the response plan
calling in the civil defence / emergency ambulance
services
iv. When safe to do so, isolate the tank and re-
direct the gas for safe disposal,
v. Assess the extent of any damage and ascertain if
a repair can be affected.
126
7 Loss of IT systems
In general, when information technology (IT) Single points of failure in the supervisory control
vulnerabilities are addressed, robust and flexible and data acquisition (SCADA) system
technology solutions can be assured to continue to Periodic identification and back up of “operational-
support business functions under a wide variety of critical” applications, databases,
conditions and to an off-site facility
Vulnerability/penetration tests on SCADA systems
The SCADA system connection to the LAN/WAN
Secure locations for the SCADA system
components (RTUs, central monitoring)
As above the below provides an general suggestion of checklists – It is of course very important that there should
be a well developed and implemented emergency response plan for the site which details the plans and actions
required for all such events
127
2 Water Quality Failure
This would be linked to the implementation of water a. Prior to an emergency :
quality safety plans ( in line with the principles of i. Vulnerability assessment with consideration of
HACCP ) and of course the integration of the O & M various scenarios of deteriation in situations and
and water quality sampling & analysis and emergency how the problems can worsen - this may require
plans GIS/network modeling to assess service impacts to
the network, how the spread can be limited and
the pre-planning of actions such as alternative
supplies , what reservoirs need emptying and how
and flushing mains programmes etc
iii. Consider PR implications and actions required of
Customer services/ Public relations(if appropriate )
iii. Ensure that all stakeholders including the water
quality safety plan driven by the chemist and the O
& M , emergency response plans are integrated for
schedule of proposed preplan actions
b. During an emergency:
i. The actions would be dependant upon site
specific requirements as developed with the
emergency response plan ( for example alternative
supplies , impacts ( if appropriate ) to reservoirs
and network flushing and cleaning etc etc
128
data and actual system data for detecting trends
early it would be important to ensure the O & M /
emergency response plan includes SIMPLIFIED
measures such as systematic graphical monitoring
charts
Recommended procedures would be as required
to be developed with the supplier covering any
possible deviant events in down stream such as
variations in individual ions ( and flushing needs ) ;
fluctuation pressure ( or possible water hammer )
and need for automation and control sequence of
valve operations etc etc
4. Loss of Power
Moderate : ensuring adequate on-site generating
capacity for essential plant / critical drives eg on
site electrical standby generation with appropiate
maintenance scheduling or arrangement with hire
companies from whom plant and equipment such
as mobile generators can be obtained.
Substitute : by having two separate and
independent electricity supplies into the Works.
5 Loss of IT systems
In general, when information technology (IT) Single points of failure in the supervisory control
vulnerabilities are addressed, robust and flexible and data acquisition (SCADA) system
technology solutions can be assured to continue to Periodic identification and back up of “operational-
support business functions under a wide variety of critical” applications, databases,
conditions and to an off-site facility
Vulnerability/penetration tests on SCADA systems
The SCADA system connection to the LAN/WAN
Secure locations for the SCADA system
components (RTUs, central monitoring)
Clearly ,the best-designed landfill is of little value unless it is constructed and operated properly – from
perspectives of personnel responsibilities, safety practices, machinery and the overall operations of the landfill
To show the value of adhering to a specific procedure for all landfill employees there should be
a list of benefits/consequences that may result from compliance or non-compliance to the procedures
Landfill sites require careful planning and operation. How a landfill is operated and managed effects the public
health, environment and economics.
Some basic issues , which apply to any type of waste landfill are as follows .
Apropiate documentation , monitoring and control is important in ensuring that landfill sites are
operated and managed safely, efficiently and effectively from both the technical and financial
perspectives.
The rate and method of waste deposition for landfill sites should be considered in terms of its
minmizing its impacts to the environmental and general public health and safety.
Landfill operations need to be reviewed with respect to optimizing the usage of land space and should consider the
optimisation of multiple issues such as landfill placement, compaction and covering and the types /
129
characterization of the wastes. Some general problems associated with landfill sites which do not have proper
operational and management plans can be described as follows :
The objectives of reviewing and studying the existing operation of the landfill sites and producing management /
emergency contingency plans can be outlined as follows :
- To ensure the cost effective and efficient operation of the sites with respect to the usuage of
land , equipment and manning resources.
- To ensure the minimsation of risks to the public health and safety of the staff and users of the
landfill sites through the adoption of working procedures and instructions that ensure the
implementation of best practices.
- To ensure the sustainable development of the landfill sites through the adoption of appropiate
plans and strategies
- To implement the high standards of quality and professionalism of best landfill practices.
130
refuse spreading and compaction and allowing
site equipment to be operated easily. The size
and operation of the working face should be
regularly reviewed as part of the recording
and inspection of the site activities.
Operating a cellular method of filling should enable
waste to be deposited in a tidy manner; preferably
bunds, walls or some form of demarcation should
be created to define, restrain and conceal the
active waste tipping area and optimize the void
space age. Bund walls would be created by the
utilization of suitable incoming waste or by the use
of cover material which could be removed at the
end of the day and used as the face cover.
The design and operation of the cells should
be influenced by the rate of waste input and
its absorptive capacity, number of incoming
vehicles and sufficient space for safe turn-
round of vehicles.
3. Environmental nuisance
This refers to uncontrolled environmental effects on Mitigation measures : Mitigation measures would
internal or external receptors – for example odour, normally be developed as part of the
fly ( vector ) nuisance, leachate etc environmental impact assessment process for the
regulatory and concerned stakeholders this would
include the design , operation and emergency
response planning in accordance with required
standards ( example include the design of lining
and operational monitoring of groundwater
boreholes and leachate control programmes )
4. Vehicle Safety
Typically, ( subject to the most efficient and Simplify : All staff and users of the landfill site
economic heavy plant for the particular application ) should be fully aware of site safety regulations.
landfill sites may use vehicles such as steel wheeled These need to be displayed also to the users of the
compactors, tracked bulldozers, rubber tyred front sites; this perhaps will require site boards and
wheel loaders (shovellers). instructions. Examples of which need to be
included in the site operation plan include issues
such as Speed limits and control ( eg working areas
at a landfill site is dangerous since people and
131
vehicles are maneuvering in close proximity to
each other ) , Overhead power lines (Raising tipper
lorries and tail gates of waste collection vehicles) ;
Lack of stability possible for large vehicle whilst
discharging their waste ; or the issue of
Overloaded vehicles and their stability, where in
particular the surface of landfill may be unsuitable
132
Minimise : Based upon the above O & M and
emergency planning consideration may be for
ensuring supply of liquid with suppressant agent
and possibly foam supply to carry out remedial
actions..
References
There is a plethoria of excellent in depth guidelines and reference materials available for further reference. Below
is a representative example only
EU Publications
Chemical Agents Directive (98/24/EC),
http://www.bbp-facts.com/C-L/Legislation/98_24_Chemical_Agents_at_Work_Directive.pdf
Guidance on the Preparation of a Safety Report to Meet the Requirements of Council Directive (96/82/EC) (Seveso
II), 1997. http://mahbsrv.jrc.it/downloads-pdf/Safety-report.pdf
Guidance on Inspections as Required by Article 18 of the Council Directive 96/82/Ec (Seveso II), 1999,
http://mahbsrv.jrc.it/downloads-pdf/inspecf.pdf
HSE Publications
Assessing compliance with the law in individual cases and the use of good practice,
http://www.hse.gov.uk/dst/alarp2.htm
Designing and Operating Safe Reaction Processes, 2000,
HSG 143, Health and Safety Executive, ISBN: 0 7176 1051 9
A guide to the Control of Major Accident Hazards Regulations 1999 HSE, L111, priced publication
Preparing Safety Reports: Control of Major Accident Hazards Regulations, 1999, HSG190, priced publication
Reducing Risks, Protecting People; HSE’s decision-making process, http://www.hse.gov.uk/dst/r2p2.pdf
The Safety Report Assessment Manual, http://www.hse.gov.uk/hid/land/comah2
Principles and Guidelines to Assist HSE in its Judgements that Duty- Holders Have Reduced Risk As Low As
Reasonably Practicable, http://www.hse.gov.uk/dst/alarp1.htm
Dangerous Substances and Explosive Atmospheres Regulations 2002 (DSEAR).
http://www.hmso.gov.uk/si/si2002/20022776.htm
The UK Health and Safety at Work Act (http://www.healthandsafety.co.uk/haswa.htm)
USA Chemical Safety Board , http://www.csb.gov
Organization for Economic Cooperation and Development (OECD), chemical safety
http://www.oecd.org/chemicalsafety/
rd
ACSNI ( 1993 ) Organising for safety “ Study Group on Human Factor , 3 Report. HSE Books ISBN 0 7176 08655
Aloray Inc Safety Management , : A Human Approach , ISBN 0 913690 12 0
Aloray Inc, Techniques of Safety Management : A systems approach , ISBN 0913690 147
Aloray Inc, Safety Behaviour Reinforcement, ISBN 0 913690 139
American Institute of Chemical Engineers, Guidelines for integrating process safety and SHE with a quality
management framework, ISBN 0 816906831
American Institute of Chemical Engineers, Guidelines for technical planning for on site emergencies
ISBN 0 81690653 X
American Institute of Chemical Engineers, Guidelines for writing effective operating and maintenance procedure
ISBN 0 81690658 0
American Institute of Chemical Engineers, Guidelines for safe process operations and maintenance , ISBN 0
81690627 0
American Institute of Chemical Engineers, Guidelines for implementing process safety management systems, ISBN
0 816909908
American Institute of Chemical Engineers, Guidelines for process safety fundamentals in general plant operations
133
ISBN 0 816905649
American Institute of Chemical Engineers, Tools for acute risk decisions with applications to process safety , ISBN 0
816905576
American Institute of Chemical Engineers, Guidelines for auditing process safety management systems ISBN 0
816905568
American Institute of Chemical Engineers, Guidelines for preventing human error in process safety, ISBN 0
816904618
American Petroleum Institute ( 1990 ) Management of Process Hazards, API recommended practice 750
Washington, USA
Booth RT , Lee TR ( 1995 ) the role of human factors and safety culture in safety management, Journal of
Engineering Manufacture, Vol 209 , 393-400
Ashford, N. A. (1997). “Industrial Safety: The Neglected Issue in Industrial Ecology.” J. Cleaner Prod. 5, 1-2, 115-21.
Ashford, N. A. (1997). “Policies for the Promotion of Inherent Safety.” New Solutions, (Summer), 46-52.
Bendixen, L. M. (2002). “Integrate EHS for Better Process Design.” Chemical Engineering Progress 98, 2 (February),
26-32.
Canadian Journal of Chemical Engineering, Khan and Amyotte’s paper, (2003). “How to Make Inherent Safety
Practice a Reality.” 81, 2-16 (2003)
Crowl, D.A. and J.F. Louvar, “Chemical Process Safety Fundamentals with Applications”, 2nd ed., Prentice Hall PTR,
Upper Saddle River, NJ (2002).
Center for Chemical Process Safety (CCPS), “Guidelines for Chemical Process Quantitative Risk Analysis”, 2nd ed.,
American Institute of Chemical Engineers, New York, NY (2000).
Center for Chemical Process Safety (CCPS), “SACHE News: Safety and Chemical Engineering Education – Fall 2001”,
J. Wagner, Ed., American Institute of Chemical Engineers, New York, NY (2001).
Center for Waste Reduction Technologies (CWRT)/Center for Chemical Process Safety (CCPS), “Making EHS an
Integral Part of Process Design ”,American Institute of Chemical Engineers, New York, NY (2001).
Dow Chemical Company, “Chemical Exposure Index Guide”, 2nd ed., American Institute of Chemical Engineers,
New York, NY (1993).
Dow Chemical Company, “Fire & Explosion Index Hazard Classification Guide”, 7th ed., American Institute of
Chemical Engineers, NY (1994
Edwards, D.W. and D. Lawrence, “Assessing the Inherent Safety of Chemical Process Routes: Is There a Relation
Between Plant Costs and Inherent Safety?”, Process Safety and Environmental Protection 71, 252– 258 (1993).
Englund, S. M. (1994). “Inherently Safer Plants - Practical Applications.” American Institute of Chemical Engineers
1994 Summer National Meeting, August 14-17, 1994, Denver, CO, Paper No. 47b.
Englund, S. M. (1990). “Opportunities in the Design of Inherently Safer Chemical Plants.” Advances in Chemical
Engineering 15, 69-135.
Englund, S. M. (1993). “Process and Design Options for Inherently Safer Plants.” Prevention and Control of
Accidental Releases of Hazardous Gases, ed. V. M. Fthenakis, 9-62. New York: Van Nostrand Reinhold.
Etowa, C. B., P. R. Amyotte, M. J. Pegg, and F. I. Khan (2002). “Quantification of Inherent Safety Aspects of the Dow
Indices.” Journal of Loss Prevention in the Process Industries 15, 477-87.
Gupta, J. P., D. C. Hendershot, and M. S. Mannan (2003). “Real Cost of Process Safety - A Clear Case for Inherent
Safety.” Trans. IChemE 81, Part B, (November), 406-13.
Hendershot, D.C., “Some Thoughts on the Difference Between Inherent Safety and Safety”, Process Safety Progress
14, 227–228 (1995b).
Hendershot, D.C., “Measuring Inherent Safety, Health and Environmental Characteristics Early in Process
Development”, Process Safety Progress 16, 78–79 (1997a)
ILO , International Labour Office , 1990 ( Prevention of major industrial accidents, Geneva ,
http://www.ilo.org/global/publications/lang--en/index.htm
Institution of Chemical Engineers (IChemE)/International Process Safety Group (IPSG), “Inherently Safer Process
Design”, Institution of Chemical Engineers, Rugby, UK (1995).
OSHA, Occupational Safety and Health Adminstration https://www.osha.gov/
Khan, F.I., T. Husain and S.A. Abbasi, “Safety Weighted Hazard Index (SWeHI): A New User-Friendly Tool for Swift
Yet Comprehensive Hazard Identification and Safety Evaluation in Chemical Process Industries”, Process Safety and
Environmental Protection 79, 65–80 (2001).
134
Kletz, T.A., “Process Plants: A Handbook for Inherently Safer Design” Taylor & Francis, Bristol, PA (1998).
135