TPE Lecture 8
TPE Lecture 8
Lecture 8
12
Runway Configuration Relative to Terminal (I)
Runway Configuration Relative to
Terminal (II)
Airport Drainage
Need
Drainage system for removal of surface/ subsurface water is vital for
safe operations and durability of pavements.
Poor drainage can result early deterioration of the pavements.
Flat longitudinal and transverse grades and wide pavement surfaces
make the drainage difficult.
Purpose
1. Interception and diversion of surface and subsurface flow water
originating from land adjacent to the airports.
2. Removal of surface runoff from airport.
3. Removal of subsurface flow from airport.
15
Airport Drainage
Layout of surface drainage:
A finished grade contour map of runway, taxiway and apron is helpful
in the layout of storm drain system.
Water from the drainage area is collected into storm drain by means of
inlets. Inlet structures consists of a concrete box covered with a C.I.
grating.
The grating must support the aircraft wheel loads and designed for
contact pressure of aircraft which will be served by the airport.
16
Airport Drainage
On long tangents, inlets are spaced at 200-400 ft, location depending on
grading/ contour plan.
If there is a taxiway parallel to runway, inlet are placed in the valley
between the taxiways and runway, otherwise the drains placed near
the edge of runway pavement.
On aprons, inlets are placed in the pavement properly.
This is the only way to drain a large apron area.
All grates should be securely fastened to frames so that they will not be
jammed loose with the passage of traffic.
Adequate depth of cover should be provided over the pipes in order to
support traffic loading. Recommended minimum depth of cover is 2’.
17
Airport Drainage
Subsurface Drainage
Functions:
1. To remove water from base course.
2. Remove water from sub-grade beneath pavement.
3. Intercept, collect and remove flowing water.
Sub-grade drainage
Desirable where the water may rise to less than 1’ below base course under
the pavement.
Base drainage
Required where ground water is expected to rise to the level of base course
or where the pavement is subjected to frequent inundation and sub-grade is
highly impervious.
Intercepting drainage
Desirable where it is known that subsurface water from adjacent areas are
seeping towards airport pavements.
18
Cross-section of runway
QUESTIONS ???