Chapter 2 Project
Chapter 2 Project
Chapter 2 Project
Introduction to Project
1.1 Projects vs. Operational Work
1
Organizations perform work to achieve a set of objectives. Generally, work can be
categorized as either projects or operations, although the two sometimes overlap.
They share many of the following characteristics:
Performed by people
Constrained by limited resources
Planned, executed, and controlled.
Projects and operations differ primarily in that operations are ongoing and
repetitive, while projects are temporary and unique. The objectives of projects
and operations are fundamentally different. The purpose of a project is to attain
its objective and then terminate. Conversely, the objective of an ongoing operation
is to sustain the business. Projects are different because the project concludes
when its specific objectives have been attained, while operations adopt a new set
of objectives and the work continues.
Projects are undertaken at all levels of the organization and they can involve a
single person or many thousands. Their duration ranges from a few weeks to
several years. Projects can involve one or many organizational units, such as joint
ventures and partnerships.
The difference and common feature that characterizes both operation works and
project works can be summarized as follows by using the figure 1.1 below:
1
Figure 1.1: Differences and common features of operational and project
works
2
Project- is an investment activity in which specific resources are committed
within a given time frame, to create capital assets over an extended period of
time in expectation of benefits that exceed to the committed resource.
Project- is a task of considerable magnitude that must be completed within
a budget and by a specific time; usually but not always carried out at once.
Project- is a non repetitive activity that is goal oriented, that has a
particular set of constraints, the output of which is measurable, and that
changes something when carried out.
Project- is a set of proposal for investment of resources in to a clearly
defined set of actions that are expected to produce future benefits of a fairly
specific kind, the whole series of actions being the subject of individual
planning and examination before being adapted and implemented within a
single overall financial and managerial framework.
3
1. Based on Ownership:
a. Private sector- mostly projects undertaken by business enterprise.
b. Public sector- projects undertaken by national and local
government body.
c. NGO’s – development projects are most often undertaken by non-
government and not for profit organizations
2. Based on the Sources of Finances:
a. Government treasury- projects may be entirely financed by
government budget as per its priority. For instance, construction of
regional airport.
b. Government treasury and external sources- most projects are
financed by the joint partnership of the government and donor
groups. For example, a road project may be financed 50% by
government and 50% by foreign donors.
c. External Sources of Finance- Projects may be financed totally by
parties other than the government but established for the wellbeing
of the citizens and the ownership may be for the government or the
public.
3. Based on the Forces Behind;
a. Demand driven/need driven- based on identified unsatisfied
demand project can be created or on unsatisfied basic needs like
food, water and shelter.
b. Donor Driven- the force behind the financing organization. Donors
will have their own say and influence the types of projects to be
established.
c. Political Driven- Projects may be established in response to some
political situation such as for example because of National
Elections, projects by religious organizations, etc.
4. Based on their Nature:
a. Civil engineering, Construction, petrochemical, mining,
quarrying projects- projects far away from the contractors’ home
4
office, and involve especial risk as well as problems organizational
communication.
b. Manufacturing projects- conducted in a factory or other home
based environment and enable exercising on the spot management.
c. Research Projects- established for pure research consuming large
sum of money and lasting over years resulting in dramatic
profitable discovery or proving waste of money.
d. Management projects- projects that require the employment of an
external project manager or managing contractor for issues such as
relocating head quarters, developing and introducing a new
computer system, preparing for a trade exhibition, producing a
feasibility or other study report, restructuri9ng the organization,
etc.
There are some degree of relationships between projects, plans and programs.
There are also significant differences. Their hierarchical relationship is given
based on the following chart.
5
Development goals/Objectives
Development Strategy
Developmental Plans
Most forward looking (futuristic)
Broad and require systematic thinking, preparation,
and appraisal
Attempts to bring welfare in the society
Programs
Derived from developmental plans
Exceptionally large with long term objectives
Explores specific area with broader scope
Projects
Derived from a program
A development activity with specific objectives
A tool for realization of a given set of objectives
Funded by a program
A unique implementation entity
Tasks
Work elements under a project
Specific approaches for doing things
Set of activities comprising a project
Work Packages
Sub-elements of a given task (or undertaking)
Something accomplished stage by stage
The collection of work packages define a given task
Development Strategy
7
Plans and Projects
In this regard, we can explain the relationships between development plans and
projects as follows:
10
resources are used to create capital assets that produce benefits over
time, having a beginning and an end, and specific objectives pursued;
Whereas a program is an on-going development effort or plan. A
program is, therefore, a wider concept than a project.
Projects that are not linked with others to form a program, however, are
sometimes referred to as ―Stand-Alone" projects.
In general, programs and projects have got their own differences and
similarities. For purpose of clarity, it is important to outline the major
differences and similarities between the two concepts.
11
Differences
Projects Have: Programs Have:
Similarities
Projects and programs have similar characteristics in that both are:
Having objectives;
Requiring financial, human, material, and other inputs (or resources)
Generating outputs of value (i.e. goods/services);
Serving as instruments for the execution of development plans and
attain national goals.
o Cultural and Social Environment is that how a project affects the people
and how they affect the project. This requires understanding of economic,
demographic, ethical, ethnic, religious and cultural sensitivity issues.
o International and Political Environment refers to the knowledge of
international, national, regional or local laws and customs, time zone
differences, teleconferencing facilities, level of use of technology, national
holidays, travel means and logistic requirements.
o Physical Environment is the knowledge about local ecology and physical
geography that could affect the project, or be affected by the project.
12
1.7 Project manager
13
4. Identification of strengths, weakness, opportunities and threats-
what might prevent us from getting there and what might help us to get
there? (SWOT analysis).
5. Action plans and implementation- What do we need to do, where do
we need to do it, how will we do it and who will do it?
6. Monitoring and evaluation- What do we need to do to be on course,
can we do it, and how do we know when we have arrived?
7. Budgeting- Involves quantification of the costs involved.
14
1.10 Project Parameters
The following five constraints operate on every project:
Scope
Quality
Cost
Time
Resources
These constraints form an interdependent set— a change in one constraint can
require a change in another constraint in order to restore the equilibrium of the
project. In this context, the set of five parameters form a system that must
remain in balance for the project to be in balance. Because they are so important
to the success or failure of the project, each parameter is discussed individually
in this section.
Scope
Scope is a statement that defines the boundaries of the project. It tells not only
what will be done but also what will not be done. In the information systems
industry, scope is often referred to as a functional specification. In the
engineering profession, it is generally called a statement of work. Scope may also
be referred to as a document of understanding, a scoping statement, a project
initiation document, or a project request form. Whatever its name, this document
is the foundation for all project work to follow. It is critical that the scope be
correct.
Quality
The following two types of quality are part of every project:
Product quality— The quality of the deliverable from the project. The
traditional tools of quality control are used tonsure product quality.
Process quality— The quality of the project management process itself. The
focus is on how well the project management process works and how can it
be improved. Continuous quality improvement and process quality
management are the tools used to measure process quality..
Cost
The birr cost of doing the project is another variable that defines the project. It is
best thought of as the budget that has been established for the project. This is
particularly important for projects that create deliverables that are sold either
commercially or to an external customer.
Time
The client specifies a time frame or deadline date within which the project must
be completed. To a certain extent, cost and time are inversely related tone
another. The time a project takes to be completed can be reduced, but costs
increase as a result.
15
Resources
Resources are assets such as people, equipment, physical facilities, or inventory
that have limited availabilities, can be scheduled, or can be leased from an
outside party. Some are fixed; others are variable only in the long term. In any
case, they are central to the scheduling of project activities and the orderly
completion of the project.
Figure 1-3 illustrates the dynamics of the situation
It is evident that any change in any one of dimensions would affect the other. For
example, if the scope is enlarged, project would require more time for completion
and the cost would also go up. If time is reduced the scope and cost would also
be required to be reduced. Similarly any change in cost would be reflected in
scope and time. Successful completion of the project would require
accomplishment of specified goals within scheduled time and budget.
Conceptualization Phase
Conception phase, starting with the seed of an idea, it covers identification of the
product or service, Pre-feasibility, Feasibility studies and Appraisal and Approval.
The project idea is conceptualized with initial considerations of all possible
alternatives for achieving the project objectives. As the idea becomes established
a proposal is developed setting out rationale, method, estimated costs, benefits
and other details for appraisal of the stakeholders. After reaching a broad
consensus on the proposal the feasibility dimensions are analyzed in detail.
16
Planning Phase
In this phase the project structure is planned based on project appraisal and
approvals. Detailed plans for activity, finance, and resources are developed and
integrated to the quality parameters. In the process major tasks need to be
performed in this phase are
Identification of activities and their sequencing
Time frame for execution
Estimation and budgeting
Staffing
A Detailed Project Report (DPR) specifying various aspects of the project is
finalized to facilitate execution in this phase.
Execution Phase
This phase of the project witnesses the concentrated activity where the plans are
put into operation. Each activity is monitored, controlled and coordinated to
achieve project objectives. Important activities in this phase are
Communicating with stakeholders
Reviewing progress
Monitoring cost and time
Controlling quality
Managing changes
Termination Phase
This phase marks the completion of the project wherein the agreed deliverables
are installed and project is put in to operation with arrangements for follow-up
and evaluation.
17