Planning II Chapter I
Planning II Chapter I
Planning II Chapter I
PROJECT ANALYSIS II
Econ 3132
CHAPTER ONE
The Basic Concepts of Project Planning
1.1 The Basic Project Concepts
Introduction:
Project planning involves estimating and comparing
beneficial effects of an investment with its costs.
2
Identifying national dev’t objectives, selecting priority
areas for investment, designing effective policies and
mobilizing resources are all critical.
4
Definition of a Project
A project is:
5
A project is a unique activity noticeably different
from preceding similar investments, and it is likely to
be different from succeeding ones.
6
Basic Characteristics of Project:
These characteristics are elements that make a project.
1. A single definable purpose, end-item or result: This is
usually specified in terms of cost, schedule and
performance requirements.
9
7. Project is the process of working to achieve a
goal: During the process, projects pass through several
distinct phases, which form and are called the project
life cycle.
The tasks, people, organizations, and other resources
will change as the project moves from one phase to the
next.
The organizational structure and the resource
expenditures build with each succeeding phase, peak
and then decline as the project approaches completion.
10
Classification of Projects
1. New, Extension and Rehabilitation projects
11
2. Blue Print Projects:
Where a project can be planned in considerable and
predictable detail before implementation begins, has few
opportunities for revision once implementation is underway,
tends to be capital and equipment intensive, and is top-down
in relation to project beneficiaries.
Most appropriate for engineering type projects.
3. Participatory projects:
People or process or labour intensive
Evolves and alters as it is implemented
Unpredictable,
Owned by the beneficiaries
Difficult to appraise
12
4. Single versus Multiple-intervention projects
Projects may comprise single/multiple interventions.
Single intervention projects are simple to appraise.
13
6. Single and Multi-purpose projects
Some projects are single purpose while others are set out to
be multi-purpose.
14
Program and Project
• Program, which is a bigger package of action is composed of a
number of projects aiming at attaining one or more related
objectives of plan
• Project on the other hand achieve goals which lead to the
accomplishment of specific objectives within program
Basic differences
A program is broader in scope than a project
A program is a domain out of which project can be found
A program has general objective while projects have a specific
objectives. For example, if the objective of the extension program
is self food efficiency, the objective of the project could be
increasing crop production, milk production, honey production etc
15
Project has a specific project area while program don't have a
specific program area
Projects have specific beneficiary groups.
Similarities
Has purpose/objectives
Require input (financial, manpower, material)
Generate output (goods or services)
Operate over space and time
16
1.2 The Project Cycles
• The way in which projects are planned and carried out
follows a sequence and that is known as the project
cycle
• The “project cycle” is a natural sequence for project
planning
• The cycle may be divided in to equally valid
phases/stages. These are
Identification phase
Preparation/Formulation phase
Appraisal phase
17
Implementation stage
Evaluation phase
A) Identification phase
• The first stage is to identify project ideas for potential
projects that are in line with the development objectives
and local problems
• The most common sources for project ideas are well-
informed technical specialists and local leaders
• Suggestions for new projects may arise because of
problems facing the society or short supply products
• projects ideas also come from the funding/operating
agencies responsible for project implementation.
18
• National governments, non-state actors such as civil
organizations, NGOs, multilateral/regional development
agencies, etc. are also bring project ideas
• Logical framework analysis (LFA) and institutional
assessment is very important in this stage
• This may involves consultation with the intended
beneficiaries, an analysis of the problems they face (by
using problem tree), and identification of options to
address these problems
19
B) Preparation/Formulation stage
Once projects have been identified, a process of
progressively more detailed project plan starts
The first step in project preparation is to carry out a
feasibility study to get sufficient information for deciding
whether to begin a more advanced planning
This stage is also called the feasibility study phase
Detailed assessment for feasibility (whether it is likely to
succeed) and sustainability (whether it is likely to
generate long-term benefits for the beneficiaries) must
be done
Details of the feasibility study will depend on the
complexity of the project
20
• As projects are planned in greater and greater detail, the
investment of time and money becomes more and more
substantial and expectations of vested interest continue
to grow
• To conduct the detail financial, economic and
environmental analysis a group of experts or external
consultants may be selected
• Once the feasibility studies have indicated that the
proposed project is worthwhile, detailed planning and
analysis may begin
• Detailed project preparation takes time, often a year or
more for complex projects and may be quite expensive
21
Contents of Project Proposals
1. Cover Page
2. Table of Contents
3. Executive Summary
4. Description of Organization
Mission, Goals and Organizational Structure
5. Project Description (also called Project Narrative or
Research Plan)
5.1. Introduction/Background of the Projects
5.2. Rationale of Project (also called Problem Statements)
5.3. Objective of the Project (also called specific aims)
Describe overall purposes and objectives
22
5.4. Project Work Plan
Physical plans in terms of targets, activities, expected
outputs/outcomes should be explained
Financial plan should be described
5.5. Human Resource of project
5.6. Project Site (Geographic, Physical, Virtual etc. )
5.7. Project Monitoring (Progress Report)
5.8. Proposed Budget with sources
5.9. Appendices (also called Attachments)
23
C) Project Appraisal Phase
Project appraisal can be defined as a detail review of a
project report by a person or an institution that is in no
way involved in its preparation.
Thus, appraisal needs an external and entirely
independent body to view the project.
Appraisal is the comprehensive and systematic
assessment of all aspects of the proposed projects.
Appraisal provides an opportunity to re-examine every
aspect of the project plan to assess whether the
proposal is appropriate and sound before investing more
money
24
If the appraisal team concludes that the project plan is
sound, the investment may proceed.
25
D) Implementation Stage
The objective of any effort in project planning and
analysis is to have a project that can be implemented to
the benefit of the society.
27
Implementation is the process of refinement and
learning from experience-in effect it is a kind of “mini-
cycle” within the large project cycle
E) Evaluation Phase
The final phase in the project cycle is evaluation
29
Evaluators want to know if these objectives were
made clear to planners , project beneficiaries or
outcomes and impacts were met
30
Aspects of Project Analysis
1. Demand and market analysis
4. Social aspects
5. Financial aspects
6. Economic aspects
7. Ecological/environmental aspects
31
1. Demand and Market Aspect Analysis
First step in this analysis is to estimate the potential size
of the market for the product proposed to be
manufactured and get an idea about the market share
likely to be captured.
32
These are very important but difficult questions in project
analysis.
34
If such a situational analysis generates enough data to
measure the market and get a reliable handle over
projected demand and revenues, a formal study need
not be required.
36
Data Collection
To answer questions listed in delineating the
objectives of market study, information may be
obtained from secondary/primary sources.
39
Jury of Executive Method
This method involves soliciting the opinions of a group
of managers on expected future sales and combining
them into a sales estimate.
Advantages:
i. a quick method to develop a demand forecast.
Disadvantages:
i. The biases underlying the subjective estimates cannot be
easily discovered.
41
Delphi Method
This method is used for eliciting opinions of a group of
experts with the help of a mail survey.
43
Trend Projection Method
This method involves:
Determining the trend of consumption by analyzing past
consumption statistics.
b
TY nT Y
T nT
2 2
a Y bT
45
e.g. Let’s use the following demand data to illustrate
the use of the trend projection method.
46
Solution: For purpose of linear trend analysis, it is
convenient to change the time axes as follows.
ΣT = 91
ΣY = 269
ΣTY = 1998
ΣT2 = 819
50
Calculation in the least squares … Continued
b = (ΣTY – nĪŸ)/(ΣT2 – nĪ2)
= [1998 – (14)(6.50)(19.21]/(819 – 14(6.5)2
= (1998 – 1748.11)/(819 – 591.5)
= 249.89/227.5 = 1.098 = 1.1
a = Ÿ - bĪ = 19.21 – 1.1(6.5) = 12.1
Remark:
1. The forecaster has to specify n.
2. No a priori way to determine n; it can be arrived at by
experimentation.
54
Example:
To illustrate the use of the moving average
method, consider the following time series data.
Year 1 2 3 4 5 6 7 8 9 10 11 12
55
Solution: If n is set equal to 4 (n has to be specified by the
forecaster), the first forecast for period 5 will be equal to
56
T St Ft Ft + 1 = (St + St - 1 + St - 2 + St - 3)/4
1 28.0
2 29.0
3 28.5
4 31.0
F5 = (28.0 + 29.0 + 28.5 + 31.0)/4 = 29.1
5 34.2 29.1 F6 = (29.0 + 28.5 + 31.0 + 34.2)/4 = 30.7
6 32.7 30.7 F7 = (28.5 + 31.0 + 34.2 + 32.7)/4 = 31.6
7 33.5 31.6 F8 = (31.0 + 34.2 + 32.7 + 33.5)/4 = 32.9
8 31.8 32.9 F9 = (34.2 + 32.7 + 33.5 + 31.8)/4 = 32.9
9 31.9 33.1 F10 = (32.7 + 33.5 + 31.8 + 31.9)/4 = 32.5
10 34.3 32.5 F11 = (33.5+ 31.8 + 31.9 + 34.3)/4 = 32.9
11 35.2 32.9 F12 = (31.8 + 31.9 + 34.3 + 35.2)/4 = 33.3
12 36.0 33.3
57
Chain Ratio Method
• The potential sales of a product may be estimated by
applying a series of factors to a measure of aggregate
demand.
• The chain ratio method uses a simple analytical
approach to demand estimation.
• However, its reliability is critically dependent on the
ratios and rate of usage employed in the process of
determining the sales potential.
• Some of these ratio and rates of usage may be based
on objective proportions, while others will have to be
subjectively defined.
58
Consumption Level Method
• It is useful for a directly consumed product.
• It helps to estimate consumption based on elasticity
coefficients (income and price elasticity).
• Income elasticity: measures responsiveness of demand to
variations in income. It is defined as
EI = [(Q2 – Q1)/(I2 - I1)]*[(I1 + I2)/(Q1 + Q2)]
where, EI = income elasticity of demand
Q1 = quantity demanded in the base year
Q2 = quantity demanded in the following year
I1 = income level in the base year
I2 = income level in the following year
59
Cons’n Level Mtd … Cont’d
60
Cons’n Level Mtd … Cont’d
• Price elasticity: measures the responsiveness of demand
to variations in price. It is defined as
EP = (Q2 – Q1)/(P2 - P1)*(P1 + P2)/(Q1 + Q2)
where,
EP = price elasticity of demand
Q1 = quantity demanded in the base year
Q2 = quantity demanded in the following year
P1 = price per unit in the base year
P2 = price per unit in the following year
61
Cons’n Level Mtd … Cont’d
• Future demand may be estimated based on price
elasticity and expected price change.
62
End Use Method
• This method is suitable for estimating intermediate
products.
64
Leading Indicator Method
• Leading indicators are variables which change ahead
of other variables, the lagging variables.
65
Leading Indicator Mtd … Cont’d
• Two basic steps are involved in this method:
i. Identify the appropriate leading indicator(s).
ii. Establish the relationship between the leading
indicator(s) and the variable to the forecast.
66
Econometric Method
• An econometric method is a mathematical
representation of economic relationship(s) derived
from economic theory.
68
2. The simultaneous equation model portrays economic
relationship in terms of two or more equations
e.g. consider the model given by
GNPt = Gt + Ct + It + Et …………………………(2)
It = a0 + a1GNPt …………………….……….(3)
Ct = b0 + b1GNPt……….…………….………(4)
where
GNPt = gross national product for year t
Gt = government expenditure for year t
It = gross investment for year t
Ct = consumption for year t
Et = error term and a0, a1, b0 & b1 are constants
69
Econometric Method … Cont’d
70
Econometric Method … Cont’d
• Econometric model involves four broad steps:
1. Specification: Expression of an econometric relationship
in a mathematical form.
2. Estimation: Determination of the parameter values &
other statistics by a suitable method.
3. Verification: Accepting or rejecting the specification as a
reasonable approximation to the truth based on
estimation results.
4. Prediction: Projection of the value of the explained
variable(s).
71
Advantages:
i. The process of econometric analysis sharpens the
understanding of complex cause-effect relationships.
ii. Econometric model provides a basis for testing
assumptions and for judging how sensitive the
results are to changes in the assumptions.
Limitations:
i. It is expensive and data demanding.
ii. The difficulty in obtaining the projected values of the
independent variable(s) may be the main limiting
factor in employing the econometric method for
forecasting purposes.
72
Marketing Strategy
• Marketing strategy covers: target segment, positioning,
product line, price, distribution, sales force, sales
promotion and advertising.
73
Positioning: This is how long a product is placed in the
mind of the customer. Having decided on targeting
students, a company could be positioned as
“romantic” or “rugged”. Similarly, if entry level
executives are targeted, the positioning could be “self
confidence” or “daylong freshness”.
74
Price: Will a company be launched in mid-price
segment because the segment is growing? Will the
price decision change depending on whether the
positioning is “romantic” or “rugged”?
75
Sales Promotion: Direct consumer promotion is
usually expensive because it covers thousands of
individual customers.
76
• The remaining goes to mainstream advertising like
newspapers, and TV.
77
Material Inputs and Utilities
These are classified into four broad categories:
i. Raw materials
ii. Processed industrial materials & components
iii. Auxiliary materials and factory supplies
iv. Utilities
79
Material Inputs & Utilities … Cont’d
81
Material Inputs & Utilities … Cont’d
83
Material Inputs & Utilities … Cont’d
iv. Utilities
• A broad assessment of utilities (power, water, steam,
fuel, etc.) may be made at the time of input study
though a detailed assessment can be made only after
formulating the project with respect to location,
technology and plant capacity.
84
Material Inputs & Utilities … Cont’d
85
Location, Site and Environment
Location and Site
• The choice of location and site follows an assessment of
demand, size & input requirement.
88
Availability of Infrastructure
• Availability of power, transportation, water, and
communications should be carefully assessed before
a location decision is made.
89
Availability of Infrastructure … Cont’d
• In evaluating power supply, look into the following
aspects: the quantum of power available, the
stability of power supply, the structure of the power
tariff, and the investment required by the project for
a tie-up in the network of power supplying agency.
90
Availability of Infrastructure … Cont’d
91
Availability of Infrastructure … Cont’d
relative qualities
92
Labour Situation
• In labour-intensive projects, the labour situation in
particular location becomes important.
93
Government Policies
• Government policies have a bearing on location
decision.
95
Other Factors
• Several other factors have to be assessed before
arriving at a location decision. These are:
Climatic conditions,
96
Climatic Conditions
97
Living Conditions & Proximity to Ancillary Units
General Living Conditions:
• The general living conditions like the cost of living,
housing situation, safety, and facilities for education,
health care, transportation and recreation need to be
assessed carefully.
98
Ease in Coping with Environmental Pollution
• A project may cause environmental pollution in
various ways. It may :
Emit gaseous pollutants
Produce solid and liquid discharges
99
Site Selection
• Once the broad location is chosen, attention needs
to be focused on the selection of a specific site.
101
Environmental Aspects
• As discussed earlier, a project may cause
environmental pollution in several ways.
102
Environmental Aspects … Cont’d
• Hence, the environmental aspects of these projects
have to be properly examined. The key issues that need
to be considered are:
103
Engineering and Technology
Plant Capacity:
• Plant capacity is the volume (number of units) of a
product that can be produced during a given period. It
may be defined in two ways: feasible normal capacity
and maximum normal capacity.
105
Technological Requirement
• For many industrial products, particularly in process
type industries, there is a certain minimum economic
size determined by the technological factor.
106
Input Constraints
107
Investment Cost
• When serious input constraints do not exist, the
relationship between capacity and investment cost is an
important consideration.
• Solution:
Given: Q2 = 5000, Q1 = 10, 000, C2 = 200, 000,
α = 0.6, C1 = ?
Q 10,000
0.6
C C 1 200,000
1 2 Q 5,000
2
200,0002 0.6 200,000(1.516)
303,200
109
Market Conditions
• If the market for the product is likely to be very strong,
a plant of higher capacity is preferable.
110
Resources of the Firm
111
Government Policy
• The government policy may influence the capacity
level.
114
Machinery and Equipment
• The need for machineries and equipment depends on
production technology and plant capacity.
115
Machinery & Equipment … Cont’d
• To determine the kinds of machinery and equipment
required for a manufacturing industry, follow the procedure
outlined below:
i. Estimate the likely levels of production over time.
116
Machinery & Equipment … Cont’d
iv. Instruments
v. Controls
vii.Others
117
• In addition to the machineries and equipment, a list
should be prepared of spare parts and tools required.
118