Project Appraisal and Implementation
Project Appraisal and Implementation
Project Appraisal and Implementation
1. DEFINITION OF A PROJECT
There are many written definitions of a project. For those looking for a formal definition of a
project, the Project Management Institute (PMI) defines a project as a temporary endeavor
undertaken to create a unique product, service, or result. The temporary nature of projects
indicates a definite beginning and end. The end is reached when the project’s objectives
have been achieved or when the project is terminated because its objectives will not or
cannot be met, or when the need for the project no longer exists.
A more tangible (but less interesting) description is that project management is everything
you need to make a project happen on time and within budget to deliver the needed scope
and quality.
In order to really get our heads around these definitions, we need to discuss some of the
terms. A project is distinguished from regular work in that it’s a one-time effort to change
things in some way. So the creation of a new web site would be a project; ongoing
maintenance and minor updates would not.
Time and budget are familiar terms—perhaps the project is intended to take six weeks and
have a budget of $20,000. Scope refers to the list of deliverables or features that have been
agreed—this is where the scale of the required solution is identified. For instance, creating a
new web site for the company may realistically be possible in six weeks, but rewriting all the
accounting software isn’t. Quality is exactly what it says on the tin, but in project-speak,
quality may include not only the quality of the finished product, but also the approach.
Some industries require that particular quality management approaches be used—for
instance, factories producing automotive parts have to meet particular international
standards.
These four aspects (time, budget, scope, and quality) make up what’s known as the balance
quadrant. The balance quadrant demonstrates the interrelationship between the four
aspects and how a change to one aspect will unbalance the quadrant. For instance, an
increase in the project’s scope will have an impact on the time, the cost, and the quality of
the project.
3. CHARACTERISTICS OF A PROJECT
• A project contains a well-defined objective. The project objective is defined in terms of
scope (or requirements), schedule, and cost
• A project has a definite start date and an expected completion date. The actual
completion date may not always be the same as the expected date.
Sometimes project monitoring is considered the fifth stage. This stage then has a special
status because it runs in parallel to the other stages.
The activities within a stage depend on the type and volume of the project. We list activities
that are present in most projects (the main aim of the stage is indicated in brackets).
There are always some project-related activities that are performed after project completion.
The division of the life cycle of the project into stages gives an opportunity to break off the
project after the initiation and planning stages if it will be unreasonable to proceed with the
project. It would cause huge losses if the project would be cancelled in a later phase. A
project can have two or even more planning phases. If, for example, a project proposal was
rejected, then based on additional information (explanations, reports, etc) the project plan
should be changed accordingly. Sometimes a successful project can be repeated in another
context by making only a few necessary modifications.
We will discuss the stages and activities in more detail in subsequent sections; here we point
out the most important aspects only.
• The target group benefiting from the outcome of the project is big
In the identification of the needs it is important to understand the interests of the decision
makers.
Needs analysis should reveal the most important factor(s) the project should deal with.
The determination of the main objective and resource analysis is usually performed in
parallel. The main objective should be formulated very clearly and in measurable terms. The
objective cannot be “to analyse” or “to investigate” something. Analysis and investigations
can only be tools for achieving the project objective. Ambitious objectives can be reached
by two or more projects.
Resource analysis and especially deciding on partners should act as an assurance that
the project will not have big problems and that in case the project faces difficulties the
partners will support each other.
The project charter serves primarily to create the project team and obtain acceptance to
start project planning. The charter is a short (usually 1-2 pages) document that states the
main objective, lists the main activities and outcomes, necessary resources, etc.
The composition of a project plan is a good success indicator of the project’s success
potential. If the partners complete the tasks correctly and in a timely manner in the
preparation process, then it can be expected that the project will be successful as well. A
perfect project plan is another success indicator while a poor project plan can be rejected
even if the objective of the project is great.
• Convincing potential donors that you are able to successfully run the project.
Industrial projects also referred as commercial projects, which are undertaken to provide
goods or services for meeting the growing needs of the customers and providing attractive
returns to the investors/stake holders. Following the background, these projects are further
grouped into two categories i.e., demand based and resource / supply based. The demand
based projects are designed to satisfy the customers’ felt as well the latent needs such as
complex fertilizers, agro-processing infrastructure etc. The resource/ supply based projects
are those which take advantage of the available resources like land, water, agricultural
produce, raw material, minerals and even human resource. Projects triggered by successful
R&D are also considered as supply based. Examples of resource based projects include food
product units, metallurgical industries, oil refineries etc. Examples of projects based on
human resource (skilled) availability include projects in IT sector, Clinical Research projects
in bio services and others.
Development projects are undertaken to facilitate the promotion and acceleration of overall
economic development. These projects act as catalysts for economic development
providing a cascading effect. Development projects cover sectors like irrigation, agriculture,
infrastructure health and education.
The essential differences between Industrial projects and Developmental project are
summarized in the table below:
4. Solving problems/conflicts both inside the project team as well with other parties.
6. Informing the project team and other parties involved about the state of the art of the
project, as well as about success and problems.
• Scope.
• Cost.
• Schedule (Time).
• Gantt Chart: A specific type of chart showing time and tasks. Usually created by a
Project Management program like MS Project.
• Stakeholder: Any person or group of people who may be affected by your project
• Need: refers to the gap or discrepancy between a present state (what is) and a desired
state (what should be). The need is neither the present nor the future state; it is the gap
between them.
It is therefore very important for organizations to perform and attain their aspirations of
why they began. Progressively more, organizations are becoming concerned in finding out
how best they are meeting the customers’ needs, acclimatising to changes in the
organization’s external and internal environments, identify the organization’s added-value
or position in the competitive global environment and identify as well as address the risks
and challenges which may potentially affect the organization’s future efficacy, sustainability,
and relevance (Winston, Stevens, Sherwood, & Dunn, 2013). These are the core pillars of
performance that any organization must aim at achieving. Missoni & Alesani (2013), states
that organizational performance can be achieved through its strategies, adaptive leadership,
evidence-based practices and resource capacity. They further observed that strategies shape
the optimal methods to achieving the organization's long-term impact while adaptive
leadership encourages innovation. Evidence based practice helps an organization to make
decisions based on data and not intuition and the resource capacity enables it to function
effectively and efficiently. The evidence based practice is a central link in project appraisal
and therefore cannot be ignored by organizations in its pursuit of performance. It is this link
that the study attempted to examine and how it enables an organization to perform highly.
• Pre-investment phase – A phase in which the project idea is generated and conceived.
This includes the identification of relevant investment opportunities, preliminary filtrations,
project formulation and trial evaluation decision.
• Investment phase – The second phase comprises the formulation of detailed design and
implementation. This involves several inter-disciplinary tasks comprising negotiation and
contracting, preparation of detailed project design and its implementation.
• Operations phase – This is the third and final phase in which the actual operation
commences. This involves the day to day operation of the completed project resulting in
anticipated benefits and attainment of desired objectives.
4. TECHNICAL APPRAISAL
You may well appreciate that a project can be considered for implementation once it is
technically fit for implementation. We should also consider the different alternative
technology options that are more cost effective and environmental friendly. A technology is
considered appropriate only if it is assessed to be satisfactory and relevant, vis-à-vis the
following aspects in the specific situation to the project.
• Required gestation period versus the time available for the project.
• Safe characteristics
5. MARKET APPRAISAL
It is imperative that you should consider the requirements of your customers before
finalizing any project idea. To survive in the market you have to be forward looking, carry
out market/ demand analysis and develop strategic business policies. In this session we will
discuss the various aspects that should be considered in market appraisal.
ii) Industry Level: Forecast demand for the industry on a whole at the national, state or
regional levels (may be undertaken jointly by group of companies)
iii) National Level: Forecast demand to facilitate the government to take policy decisions
on import, export etc.
iv) International Level: Forecasting demand for companies operating at the multinational
level.
i) Accuracy in forecast: The accuracy of your forecast depend on the basic assumptions
based on which you developed the prediction. It can be measured in terms of past forecast
against, current revenue and by the present as of deviation from actual demand.
ii) Plausibility of forecast: You may note that the forecasts of demand must be reasonable,
consistent and plausible
iii) Economy of forecasts: You may carry out your forecast exercise with minimum effort
and cost
iv) Quick results: The method you have selected should be capable of yielding quick and
useful results v) Flexibility: Flexibility of forecast is an added advantage. You may be able to
adjust co-efficient of variables from time to time the cope with the changing conditions.
You may now be curious to know how a systematic demand forecasting can be carried out.
Different qualitative and quantitative techniques are available for conducting a reasonably
accurate forecast of demand. We may now further discuss some of those techniques.
i) Collective opinion survey: The sales/field personnel attached to an area will collect the
opinion of the customers on the product/ services of a firm. These estimates are collated,
reviewed and revised to work out a realistic demand forecast.
You may note that quantitative techniques such as simple average method, moving average
method, exponential smoothing method, Regression analysis, Econometric models etc are
available for demand forecasting.
In this section we will discuss the economic and financial appraisal for the final selection or
rejection of a project.
• When the cash flows are constant throughout the life of the project
The objective any business organisation, in the modern context will be to maximize the net
present value or net present worth of an organisation. The NPV technique, therefore, is in
perfect agreement with the wealth maximization objective of the firm duly considering the
time value of money, which are absent in the conventional techniques.
Let us now understand what is NPV and how it is calculated. NPV is the difference between
Gross Present Value of expected future benefits and initial investment the Gross Present
Value of expected future benefit is calculated by multiplying the cash flow after taxes of
each years with an appropriate discounting factor.
Discounting factor, which is otherwise known as cost of capital or cut off rate is the
minimum rate of return expected by an invests to keep the market value of his share
unchanged.
You may note that the calculations of IRR is a difficult task. IRR is a powerful financial tool to
assess the financial viability of the project. It can be accomplished through trial and error
method. However, there is an easy method to calculate IRR if we follow the steps in the
sequence given below.
Step 2: Refer Present value an annuity of Rs. 1 table and find out the factor which is almost
near to the fake pay back factor (Table given in appendix 2) look horizontal to the last years
cash flow. e.g. if cash flow is upto 10 years, look horizontal to 10th year.
Step 3: Find out NPV based on that factor (look vertically at the top and find out
percentage). If NPV so calculated is negative, try at a lower rate and continue the process till
you arrive at a positive NPV. You may reverse the process if the originally calculated NPV is
positive.
Step 4: Now you have positive and negative NPV. The exact value of NPV now can be
calculated by applying the formula of interpolation as given below:
You can start with highest rate also. If you follows highest rate, NPV will be as per the
following equation.
7. SOCIAL COST BENEFIT ANALYSIS
Social cost benefit analysis is done from the view point of society or economy as a whole.
The evaluation is done on a wider angle not merely on financial terms. Social appraisal of
projects should cover the following whether.
The concept of social cost benefit analysis, as you are aware, is fairly simple and well known.
The application of cost benefit analysis on a limited scale, started in India in the sixties. The
SCBA has not widely been used except in case of some irrigation project. It is only in the last
few years that the planning commission has been insisting upon CB analysis as a criterion
for ‘passing’ a project for public investment. SCBA thus reflects the opportunity cost of the
project.
• Estimating economic, social and environmental inputs and outputs of the project.
The third category of benefits and costs which can neither be quantified nor translated in to
money terms. Continuing our example of the dam to be constructed as part of the hydro-
electricity project, it would also render benefits to the environment of its existence
beautifies the area and improves the landscape because of he availability of water. However,
these benefits rendered to the society by the creation of the dam would be of an intangible
nature which can neither be quantified nor translated into money terms.
You may be aware that the prevailing market prices need not reflect the true scarcity value.
In SCBA you may go what is behind market prices. The shadow prices express prices in
terms of opportunity cost. If for example, the real resources used for producing a ton of
fertilizer cost Rs.2000/-, its shadow price should be Rs.2000/- per ton even it may be
supplied to the farmer at a subsidized rate of Rs.1500/- per ton. Hawala rate will be a fair
reflection. You may look at another example. If the prevailing rate of foreign exchange is
higher than the officially fixed rate, then the price of imports in to country is understated. In
such a case, the shadow price of foreign exchange used in social cost benefit analysis would
be higher than the official exchange rate. Also, while determining shadow price of a
commodity, taxes are renewed from the market price, as these are considered to be transfer
payments and therefore not a cost to the society.
8. CONTROLLING COSTS
Controlling project costs includes monitoring cost performance, ensuring that only
appropriate project changes are included in a revised cost baseline, and informing project
stakeholders of authorized changes to the project that will affect costs. The project
management plan, project funding requirements, work performance data, and
organizational process assets are inputs for controlling costs. Outputs of this process are
work performance measurements, budget forecasts, organizational process asset updates,
change requests, project management plan updates, and product document updates.
Earned value management involves calculating three values for each activity or summary
activity from a project’s WBS.
1. The planned value (PV), also called the budget, is that portion of the approved total cost
estimate planned to be spent on an activity during a given period.
2. The actual cost (AC) is the total direct and indirect costs incurred in accomplishing work
on an activity during a given period.
3. The earned value (EV) is an estimate of the value of the physical work actually
completed. It is based on the original planned costs for the project or activity and the rate at
which the team is completing work on the project or activity to date. The rate of
performance (RP) is the ratio of actual work completed to the percentage of work planned
to have been completed at any given time during the life of the project or activity.
The cost performance index can be used to calculate the estimate at completion (EAC) an
estimate of what it will cost to complete the project based on performance to date.
Similarly, the schedule performance index can be used to calculate an estimated time to
complete the project.
There can be a portfolio for information technology projects, for example, and portfolios for
other types of projects. An organization can view project portfolio management as having
five levels, from simplest to most complex, as follows:
3. Divide your projects into two or three budgets based on type of investment, such as
utilities or required systems to keep things running, incremental upgrades, and strategic
investments.
5. Apply modern portfolio theory, including risk-return tools that map project risk on a
curve.
UNIT 3 A STRATEGY FOR THE APPRAISAL OF INVESTMENT PROJECTS
It should be clear from the above that in cases where stakeholder interests play a significant
role, and/or where the viability or success of a project in vulnerable to avoidable financial
contingencies, these elements should be taken into account at each successive stage of the
appraisal process. It is not prudent to leave them to be dealt with, almost as an
afterthought, only at or near the final stage. This is why we, in this book, have tried to
present an appraisal that permits the analyst to focus on economic, financial, and
stakeholder considerations within a substantially integrated framework.
3. PRE-FEASIBILITY STUDY
The pre-feasibility study is the first attempt to examine the overall potential of a project. In
undertaking this appraisal, it is important to realize that its purpose is to obtain estimates
that reflect the right “order of magnitude” of the variables in order to roughly indicate
whether the project is attractive enough to warrant more detailed design work.
Throughout the appraisal phase and, in particular, at the pre-feasibility stage, estimates
which are clearly biased in one direction are often more valuable than mean estimates of
the variables, especially when these latter are only known with significant uncertainty. In
order to avoid acceptance of projects based on overly optimistic estimates of benefits and
costs, the pre-feasibility analysis should use estimates with a downward bias for benefits
and an upward bias for costs. If the project still looks attractive even in the presence of
these biases, then it stands a good chance of passing a more accurate evaluation.
The pre-feasibility study of any project will normally cover six different areas. These can be
summarized as follows:
a) Demand module in which the demand for the goods and services, and prices, or the
relative needs of social services are estimated, quantified, and justified.
b) Technical or Engineering module in which the input parameters of the projects are
specified in detail and cost estimates developed.
e) Economic module in which the project’s economic costs and benefits as a whole are
appraised from the viewpoint of the economy.
g) Stakeholder module in which the project is appraised from the point of view of who
receives the benefits and who pays the costs of a project. Where possible, quantification
should be made to determine by how much each of these groups benefits or pays.
Whenever possible, the pre-feasibility study should utilize secondary research. Secondary
research examines previous studies on the issues in question and reviews the specialized
trade and technical journals for any important data that may be relevant to the appraisal of
the project. Utilization of the research on commodities and technical aspects of projects
from institutions or associations disseminating pertinent information is essential. Most
technical and marketing problems have been faced and solved before by others. Therefore,
a great deal of information can be obtained quickly and cheaply if the existing sources are
utilized efficiently.
For the demand analysis of tradable goods, the key variables are the prospective levels and
likely trends of their prices, relative to the domestic price level (and to that of tradable
goods generally). Here one can often find market analyses by the relevant producer
associations and professional experts with projections of prices and world output.
For the demand analysis of a product to be sold in the domestic market, it will be more
important to begin primary research at the pre-feasibility stage of the project appraisal. The
analysis will need to assess the overall marketing plan of the organization undertaking the
project. The potential users of that product will often have to be surveyed before an
accurate picture of its potential demand can be determined. If the product is to be sold in a
competitive environment, then a judgment should be made to as to how the competitors in
the market are likely to react. Such a judgment can be based on reviews of past actions, as
well as the institutional strengths and weaknesses of the competitors. Ultimately, the
demand for the project’s output will depend on the nature of the product, the competitive
advantages of the project in supplying the product and the resources spent to market the
output.
In the case of public monopolies such as public utilities, government policies themselves
may be important in determining the demand for the output. Extension of electricity supply
to new rural areas and the development of new industrial complexes can have an important
bearing on the future demand. The growth in the demand for the output of a public utility
can often be projected accurately by studying the relationship over time of demand with
respect to variables such as disposable income, industrial output, household formation and
relative prices. The study of growth in demand experienced by utilities in other countries
with similar circumstances can also help to provide a good basis for projecting future
trends.
2) Quantities of expected sales and prices for goods to be sold domestically and not in
competition with internationally traded goods.
3) Sales taxes and export taxes that are expected to be paid on the project’s output of the
traded goods.
6) Government regulations (such as price ceilings and floors, or quotas), affecting the sales
or price of the output.
7) Product trends in terms of technological developments and the expected product cycle.
8) All trade restrictions that are not created by government regulation must be identified
and their impact should be quantified.
The output from the technical module of a pre-feasibility study should obtain the following
information:
1) The quantities of inputs by type which will be required for the construction of the project.
2) The likely time paths of the real prices of these inputs and their probable sources of
supply.
3) The time paths of the labor requirements of the projects, for each occupation and each
category.
4) The physical input requirements for the operation of the project by year and by volume
of output.
5) The likely sources of supply for these inputs and the assumptions on which the time paths
of their future real prices are based.
7) The nature and extent of the impacts that the project is expected to have on the
environment.
This module must reconcile the technical and management requirements of the project with
the supply constraints on manpower available to this project. If they cannot be reconciled,
then the project should not be undertaken. A careful study of the labor markets should be
made in order to ensure that the estimates of expected real wage rates to be paid are
soundly based and that the planned sources of manpower are reasonable in the light of
labor market conditions.
Initially, the financial cash flows will be expressed in terms of nominal prices overtime
because certain key variables such as taxes and debt repayments are calculated in terms of
their nominal values. These nominal values are then converted into their real value
equivalents by dividing by a numeraire price index. It is usually necessary to examine a
project financed performance over time in terms of the real values of the financial variables
in order to determine its financial robustness over time and, hence, its financial
sustainability.
Because of the need for estimates of particular variables (e.g., foreign exchange
requirements) for the purpose of making economic and stakeholder project appraisals, the
level of financial detail required is considerably greater than what is usually found in the
financial appraisal of a private sector project. The financial module should answer a series of
basic questions concerning the financial prospects and viability of the project. Four of the
most important of these questions are outlined below:
1) What relative degrees of certainty do we place on each of the revenue and cost items in
the financial analysis? What factors are expected to affect these variables directly and in
what way?
2) What sources of financing will be used to cover the cost of the project? Does this
financing have special features, such as subsidized interest rates, grants, foreign equity or
loans?
3) What is the minimum net cash flow required by this investment to be able to continue
operations without unplanned requests being made to the government treasury for
supplementary financing?
4) Does the project have a large enough net cash flow or financial rate of return for it to be
financially viable? If not, what sources of additional funds are available and can be
committed to assist the project if it is economically and socially justified?
If any one of these questions points to future difficulties then adjustments should be made
in either the design or financing of the project to avoid failure.
In the cases where the benefits or costs (and damages) cannot be quantified but the
impacts are considered significant, they should be listed, substantiated and properly
documented in the analysis. For those intangible or qualitative items, they may have
significant impacts on decision-making.
4. FEASIBILITY STUDY
After completing all the modules of the pre-feasibility study, the project must be examined
to see if it now shows promise of meeting the financial, economic, and social criteria that
the government has set for investment expenditures. A sensitivity analysis must be made on
the project to identify the key variables which determine its outcome.
The function of the feasibility stage of an appraisal is to improve the accuracy of the
measures of key variables if this particular project indicates it has a potential for success. In
order to improve the accuracy, more primary research will have to be undertaken and
perhaps a second opinion sought on other variables.
The important risk variables that affect the project’s performance need to be identified. The
methods of risk reduction, allocation and management need to be developed and applied
to the identified risk variables as part of the feasibility study.
It is at the end of this stage that the most important decision has to be made as to whether
the project is financially attractive to all interested parties in activity and if it should be
approved. It is much more difficult to stop a bad project after the detailed (and expensive)
design work has been carried out at the next stage of appraisal. Once sizable resources have
been committed to prepare the detailed technical and financial design of a project, it takes
very courageous public servants and politicians to admit that it was a bad idea.
5. DETAILED DESIGN
After the feasibility study, if the decision-makers give their approval to the project, then the
next task being is to develop a detailed project design and make detailed arrangements for
financing the project. Preliminary design criteria must be established when the project is
identified and appraised but usually expenditures on detailed technical specifications are
not warranted at this time. Once it has been determined that the project will continue, the
design task should be completed in more detail. It involves setting down the basic
programs, allocating tasks, determining resources and setting down in operational form the
functions to be carried out and their priorities. Technical requirements, such as manpower
needs by skill type should be determined at this stage. Upon completion of the blueprints
and specifications for construction of the facilities and equipment, then the operating plans
and schedules along with contingency plans must be prepared and brought together in the
development of a formal implementation plan.
In summary, the detailed design stage of a project appraisal is the point where the accuracy
of the data for all the previous modules is improved to the point where an operational plan
of action can be developed. Not only is the physical design of the project completed at this
stage, but so is the program for administration, operating, and marketing.
When this process is completed, the project is again reviewed to see whether it still meets
the criteria for approval and implementation. If it does not, then this result must be passed
on to the appropriate authorities for rejection.
6. PROJECT IMPLEMENTATION
If the appraisal and design have been properly executed then the selection of the project for
implementation should only entail the completion of negotiations to finalize the conditions
for financing and the formal approval of the project. The formal approval will require the
acceptance of funding proposals and agreement on contract documents, including tenders
and other contracts requiring the commitment of resources.
The appointment of a project manager means that responsibility for implementation will fall
within his or her jurisdiction. This will involve decisions regarding the allocation of tasks to
groups within the organization and decisions regarding the procurement of equipment,
resources and manpower. Schedules and time frames need to be established. Control and
reporting procedures must be activated to provide feedback to policy makers and the
project manager.
When the project nears completion preparation must be made for phasing out of the
construction activities and hand over to the new operational management. The project
completion will necessitate a scaling down and dismantling of the project organization. A
transfer of project personnel and equipment to other areas of the operation will be
required. These activities may occur over a considerable period of time. However, as the
project becomes operational it is essential that the skills, plans and controlling organization
be available to carry on with the function of the project in order to avoid excessive start up
costs which can easily undermine the overall success or failure of the project.
7. EX-POST EVALUATION
In the short history of formal cost benefit analysis or project appraisal considerably more
effort has gone into the pre-evaluation of projects than into the review of the projects
actually implemented. For the development of operational techniques of project appraisal it
is essential to compare the predicted with the actual performance of projects. In order that
this review of the strengths and weaknesses of implemented projects be of the maximum
value to both policy makers and project analysts it is important that some degree of
continuity of personnel be maintained within the organization’s project evaluation teams
through time.
In carrying out this evaluation a review of the administrative aspects of the project
development should be made immediately after the project becomes operational. The
managers of the operational phase of the project must be made aware of the fact that an
indepth evaluation of the project’s performance is to be carried out through time. In this
way the necessary data can be developed through the normal financial and control activities
of the operation to enable an evaluation to be carried out at minimum cost.
The ex-post evaluation helps not only to assess the performance of a project and to give an
ultimate verdict on its contribution to the country’s development but also to identify the
critical variables in the design and implementation of a project that have contributed to its
success or failure. The ex-post evaluation helps an organization to repeat the successful
experiences and to eliminate the failures.
UNIT 4 ESTIMATING PROJECT COSTS AND BENEFITS
1. WHAT IS COST?
Webster’s dictionary defines cost as something given up in exchange. Costs are often
measured in monetary amounts, such as dollars, that must be paid to acquire goods and
services. (For convenience, the examples in this unit use dollars for monetary amounts, but
monetary amounts could be in any currency.) Because projects cost money and consume
resources that could be used elsewhere, it is very important for project managers to
understand project cost management. Estimating costs involves developing an
approximation or estimate of the costs of the resources needed to complete a project. The
main outputs of the cost estimating process are activity cost estimates, basis of estimates,
and project document updates. A cost management plan is created as part of integration
management when creating the project management plan. It should include information
related to the level of accuracy for estimates, variance thresholds for monitoring cost
performance, reporting formats, and other related information
4. ESTIMATING COSTS
Project managers must take cost estimates seriously if they want to complete projects within
budget constraints. After developing a good resource requirements list, project managers
and their project teams must develop several estimates of the costs for these resources. For
example, if an activity on a project is to perform a particular type of test, the list of activity
resource requirements would describe the skill level of the people needed to perform the
test, the number of people and hours suggested to perform the test, the need for special
software or equipment, and so on. All of this information is required to develop a good cost
estimate. This section describes various types of cost estimates, tools and techniques for
estimating costs, typical problems associated with information technology cost estimates,
and a detailed example of a cost estimate for an information technology project.
In addition to creating cost estimates, it is also important to provide supporting details for
the estimates. The supporting details include the ground rules and assumptions used in
creating the estimate, a description of the project (scope statement, WBS, and so on) used
as a basis for the estimate, and details on the cost estimation tools and techniques used to
create the estimate. These supporting details should make it easier to prepare an updated
estimate or similar estimate as needed.
A cost management plan is a document that describes how the organization will manage
cost variances on the project. For example, if a definitive cost estimate provides the basis for
evaluating supplier cost proposals for all or part of a project, the cost management plan
describes how to respond to proposals that are higher or lower than the estimates. Some
organizations assume that a cost proposal within 10 percent of the estimate is acceptable
and only negotiate items that are more than 10 percent higher or 20 percent lower than the
estimated costs.
Another important consideration in preparing cost estimates is labor costs, because a large
percentage of total project costs are often labor costs. Many organizations estimate the
number of people or hours they need by department or skill over the life cycle of a project.
5.1. Profits
Profits are revenues minus expenditures. To increase profits, a company can increase
revenues, decrease expenses, or try to do both. Most executives are more concerned with
profits than with other issues. When justifying investments in new information systems and
technology, it is important to focus on the impact on profits, not just revenues or expenses.
Consider an e-commerce application that you estimate will increase revenues for a $100
million company by 10 percent. You cannot measure the potential benefits of the e-
commerce application without knowing the profit margin. Profit margin is the ratio of
revenues to profits. If revenues of $100 generate $2 in profits, there is a 2 percent profit
margin. If the company loses $2 for every $100 in revenue, there is a 2 percent profit margin
5.9. Reserves
Reserves are dollars included in a cost estimate to mitigate cost risk by allowing for future
situations that are difficult to predict. Contingency reserves allow for future situations that
may be partially planned for (sometimes called known unknowns) and are included in the
project cost baseline. For example, if an organization knows it has a 20 percent rate of
turnover for information technology personnel, it should include contingency reserves to
pay for recruiting and training costs for information technology personnel. Management
reserves allow for future situations that are unpredictable (sometimes called unknown
unknowns). For example, if a project manager gets sick for two weeks or an important
supplier goes out of business, management reserve could be set aside to cover the resulting
costs.