Project - Ch-1&ch-2
Project - Ch-1&ch-2
Project - Ch-1&ch-2
General Introduction
1.1 Projects vs. Operational Work
1
Organizations perform work to achieve a set of objectives. Generally, work can be
categorized as either projects or operations, although the two sometimes overlap.
They share many of the following characteristics:
Performed by people
Constrained by limited resources
Planned, executed, and controlled.
Projects and operations differ primarily in that operations are ongoing and
repetitive, while projects are temporary and unique. The objectives of projects
and operations are fundamentally different. The purpose of a project is to attain
its objective and then terminate. Conversely, the objective of an ongoing
operation is to sustain the business. Projects are different because the project
concludes when its specific objectives have been attained, while operations adopt
a new set of objectives and the work continues.
Projects are undertaken at all levels of the organization and they can involve a
single person or many thousands. Their duration ranges from a few weeks to
several years. Projects can involve one or many organizational units, such as joint
ventures and partnerships.
The difference and common feature that characterizes both operation works and
project works can be summarized as follows by using the figure 1.1 below:
1
Figure 1.1: Differences and common features of operational and project
works
3
1. Based on Ownership:
a. Private sector- mostly projects undertaken by business enterprise.
b. Public sector- projects undertaken by national and local
government body.
c. NGO’s – development projects are most often undertaken by non-
government and not for profit organizations
2. Based on the Sources of Finances:
a. Government treasury- projects may be entirely financed by
government budget as per its priority. For instance, construction of
regional airport.
b. Government treasury and external sources- most projects are
financed by the joint partnership of the government and donor
groups. For example, a road project may be financed 50% by
government and 50% by foreign donors.
c. External Sources of Finance- Projects may be financed totally by
parties other than the government but established for the wellbeing
of the citizens and the ownership may be for the government or the
public.
3. Based on the Forces Behind;
a. Demand driven/need driven- based on identified unsatisfied
demand project can be created or on unsatisfied basic needs like
food, water and shelter.
b. Donor Driven- the force behind the financing organization. Donors
will have their own say and influence the types of projects to be
established.
c. Political Driven- Projects may be established in response to some
political situation such as for example because of National
Elections, projects by religious organizations, etc.
4. Based on their Nature:
a. Civil engineering, Construction, petrochemical, mining,
quarrying projects- projects far away from the contractors’ home
4
office, and involve especial risk as well as problems organizational
communication.
b. Manufacturing projects- conducted in a factory or other home
based environment and enable exercising on the spot management.
c. Research Projects- established for pure research consuming large
sum of money and lasting over years resulting in dramatic
profitable discovery or proving waste of money.
d. Management projects- projects that require the employment of an
external project manager or managing contractor for issues such as
relocating head quarters, developing and introducing a new
computer system, preparing for a trade exhibition, producing a
feasibility or other study report, restructuri9ng the organization,
etc.
There are some degree of relationships between projects, plans and programs.
There are also significant differences. Their hierarchical relationship is given
based on the following chart.
5
Development goals/Objectives
Development Strategy
Developmental Plans
Most forward looking (futuristic)
Broad and require systematic thinking, preparation,
and appraisal
Attempts to bring welfare in the society
Programs
Derived from developmental plans
Exceptionally large with long term objectives
Explores specific area with broader scope
Projects
Derived from a program
A development activity with specific objectives
A tool for realization of a given set of objectives
Funded by a program
A unique implementation entity
Tasks
Work elements under a project
Specific approaches for doing things
Set of activities comprising a project
Work Packages
Sub-elements of a given task (or undertaking)
Something accomplished stage by stage
The collection of work packages define a given task
6
Exhibit 1.2 Hierarchical Relationships
Development Goal/Objectives
Development Strategy
7
Plans and Projects
In this regard, we can explain the relationships between development plans and
projects as follows:
10
A project, in this regard, refers to an investment activity where
resources are used to create capital assets that produce benefits over
time, having a beginning and an end, and specific objectives pursued;
Whereas a program is an on-going development effort or plan. A
program is, therefore, a wider concept than a project.
Projects that are not linked with others to form a program, however, are
sometimes referred to as “Stand-Alone" projects.
In general, programs and projects have got their own differences and
similarities. For purpose of clarity, it is important to outline the major
differences and similarities between the two concepts.
In this regard, the following table depicts, comparatively the differences between
projects and programs.
11
Differences
Projects Have: Programs Have:
Similarities
Projects and programs have similar characteristics in that both are:
Having objectives;
Requiring financial, human, material, and other inputs (or resources)
Generating outputs of value (i.e. goods/services);
Serving as instruments for the execution of development plans and
attain national goals.
o Cultural and Social Environment is that how a project affects the people
and how they affect the project. This requires understanding of economic,
demographic, ethical, ethnic, religious and cultural sensitivity issues.
o International and Political Environment refers to the knowledge of
international, national, regional or local laws and customs, time zone
differences, teleconferencing facilities, level of use of technology, national
holidays, travel means and logistic requirements.
12
o Physical Environment is the knowledge about local ecology and physical
geography that could affect the project, or be affected by the project.
13
3. Identification of alternatives and strategies- How can we reach to
the place that we want to go in the indicated time limit?
14
maximization of return on equity. They will also have indirect objectives of
creating employment opportunities, and other social benefits.
CHAPTER TWO
2. THE PROJECT CYCLE
The project cycle considers various stages in which each stage not only is
grown out of the proceeding ones (i.e. activities in progress) but also leads into
the subsequent ones.
Project cycle is a self-renewing cycle in that new projects may grow out of the
old ones in a continuous process and self-sustaining cycle of activity. These
processes can usefully be considered as a comprehensive sequence in the
sense that for the project that is implemented, each stage naturally follows the
proceeding one and leads on to the next.
15
A project with the characteristics already outlined above typically run through
at least several separable stages that can be thought of as constituting a
definite sequence, which some writers and institutions have called “a project
cycle”. In this regard, the first basic model was developed by Warren C.
Baum in 1970, which was by then adopted by the World Bank as a project
cycle. Initially, this model had recognized only four main stages in the project
cycle, namely:
1. Identification
2. Preparation
3. Appraisal and Selection; and
4. Implementation
Later in 1978, the author has added additional two stages called “Negotiation”
and "Evaluation”. In this version of the Baum model, the issue of negotiation
comes when projects pass the appraisal process and become a candidate for
realization. It is after appropriate negotiations that projects become
implementation entity. Then, projects already implemented will be the concern
for evaluation, which usually closes the cycle as evaluation often gives rise to
the identification of new projects. This model, therefore, includes six identifiable
stages in the project cycle. The World Bank accepted the amendment and
adopted the new version since then.
1. Identification
The first stage in the project cycle and in the planning process too, is to search
for and identify potentially feasible projects. The sources for identifying such
projects may be one or more of the following:
Technical specialists could identify areas with technical deficiencies, where they
feel that new investments might be profitable; while local leaders may
provide some insights regarding existing problems and bottlenecks, where
investments need to be carried out for alleviating the same.
Ideas for new projects also come from “proposals to extend and/or
expand existing programs and projects” as well as from identifying
technological alternatives. In general, most projects start as an elementary
idea. Some simple ideas are elaborated to the extent that eventually the name
“project” can formally be given to it.
2. Preparation
Once projects are identified, there begins a new stage that calls for
progressively more detailed preparation and analysis of a project's aspects. At
this stage, the project is being seriously considered as a definite investment
action.
17
The project now exists as a set of tangible proposals. Practically, project
design and formulation is an area in which local and international
consultants are very active, especially for big projects that cover large
areas and have big budgets.
check if all are correctly valued. Socio-economic aspect is the other name
given to the same.
6. Managerial: this aspect of the appraisal process examines if the capacity
exists for operating the project and see if those responsible ones can
operate it satisfactorily. Moreover, it tries to see if the responsible are
given sufficient power and scope to do what is required.
7. Organizational: the appraisers examine the project if it is organized
internally and externally into units, contract, policy, institution, etc so as
to allow the proposals to be carried out properly and to allow for change
as the project develops.
The appraisal process builds on the project plan, but may involve new
information if the appraisal team feels that some of the data used at
preparation or some assumptions are faulty.
The implications and/or impacts of the project on the society and the
environment are also more thoroughly investigated and documented. Similarly,
the technical design, financial measures, commercial aspects, incentives,
and economic parameters are thoroughly scrutinized. These issues are the
subjects of specialized appraisal report. Based on an appraisal report, decisions
are made whether to go ahead with the project or not. The appraisal may also
change the basic project plan or develop a new plan. To this end, comments
often made at the appraisal stage frequently give rise to alterations in the
project plan (project proposal).
After appraisal, the viable project proposals are chosen for implementation
on the basis of the priorities of the stakeholders and the available resources.
For instance, the Treasury, for public projects, may impose a ceiling on the
19
ministries with a big portfolio of investments, calling for prioritization of the
core over lower priority projects. In practice, there can be quite sequence of
project selection decisions.
If the project involves loan finance, the lender will almost certainly wish to
carry out its own appraisal before completing negotiations with the borrower.
Following appraisal, some projects may be discarded as well.
5. Implementation
The objective of any effort in the process of project planning and analysis,
clearly, is to come up with projects that can be implemented and/or realized to
the benefit of the society.
Thus, implementation is, perhaps, the most important part of the project
cycle.
In this stage, funds are actually disbursed to get the project started and
keep running.
20
A major priority during this stage is to ensure that the project is
carried out in accordance with the basic plan (i.e. within the cost,
quality, and time standards).
Problems frequently occur as the economic and financial environment
during implementation often differ from the expectations at the time of
appraisal.
21
Frequently, original proposals are modified, though usually only with
difficulty, because of the need to get agreement between the parties
involved.
i The first is that, the better and more realistic a project plan is, the more
likely that the plan can be carried out and the expected benefits realized.
This emphasizes once again the need for careful attention to each
of the seven aspects of projects.
6. Evaluation
The final phase in the project cycle is evaluation. Once a project has been
carried out, it is often useful, (though not always done),
22
To compare actual progress with the plans, and
To judge whether the decisions and actions taken were responsible and
useful.
The extent to which the objectives of a project are being realized provides the
primary criterion for an evaluation. The analyst looks systematically at the
elements of success and failure in the project experience to learn how better to
plan. Evaluation is not limited only to completed projects.
Each of these three phases is divided into stages, some of which constitute
important consultancy, engineering, and industrial (manufacturing) activities.
In this regard, increasing importance should be attached to the pre-investment
phase as a central point of attention, because the success or failure of an
industrial project ultimately depends on the marketing, technical, financial, and
economic findings and their interpretations, especially in the feasibility study.
According to the UNIDO, Manual for Industrial Feasibility Study, the pre-
investment phase comprises several stages. These are:
24
Support or functional studies are also part of the project preparation stage
and are usually conducted separately, for later incorporation of the findings in
a pre-feasibility study or feasibility study as appropriate. Though it is easier to
grasp the scope of an opportunity study, it is not an easy task to differentiate
between a pre-feasibility and a feasibility study in view of the frequently
inaccurate use of these terms.
This also ensures that the subsequent project appraisal task, made by
national or international financing institutions, becomes an easier task when
based on well-prepared studies. All too often, project appraisal actually
amounts to project preparation, given the low quality of the feasibility study
undertaken and poorly prepared document submitted.
A. Opportunity Studies
Natural resources,
The existing agricultural base (it may be the basis for agro-industries),
Future demand for consumer goods,
Imports substitution and export possibilities,
25
Environmental impacts (mandatory or non-revenue producing projects),
Expansions of existing capacity,
Manufacturing sector (benchmarking from other countries),
Diversification
Opportunity studies are rather sketch in nature and rely more on aggregate
estimates than on detailed analysis. To this end, opportunity studies could be
general or specific.
26
Therefore, before assigning larger funds for such a study, prior assessment of
the project's idea might be made in a pre-feasibility study. This helps to see if:
The contents of a support study vary, depending on the type and nature of
projects. However, as it relates to a vital aspect of the project, the conclusions
could be clear enough to give directions to the subsequent stage of project
preparation. In most cases, a support study when undertaken either before or
together with a feasibility study, form an integral part of the latter and lessen its
burden and cost.
27
D. Feasibility Studies
The financial part of the study covers the scope of the investment, including
the net working capital, the production and marketing costs, sales revenue,
and the return on capital invested. Final estimates on investment and
production costs and its subsequent calculations of financial and
economic profitability are only meaningful if the scope of the project is
defined unequivocally in order not to omit any essential part and its related
cost.
28
including the identification of commercial, technical, and entrepreneurial
risks.
The sensitive parameters such as the size of the market, the production
program, or the mechanical equipments selected should be examined more
closely. Moreover, a feasibility study should be carried out only if the
necessary financing facilities, as determined by the studies, can be identified
with a faire degree of accuracy.
E. Appraisal Report
When a feasibility study is completed, various parties will carry out their
own appraisal of the investment project in accordance with their individual
objectives and evaluation of expected risks, costs, and gains.
29
in line with these criteria center around technical, commercial, market,
managerial, organizational, financial, and, possibly, socio-economic aspects.
30
purchase and installation of machinery and equipment, and financing. This
stage covers the signing of contracts between the investor or entrepreneur,
on the one hand, and the financing institutions, consultants, architects, and
suppliers of raw materials and required inputs, on the other.
31
applications of production techniques, operation of equipment, or inadequate
labor productivity owing to lack of qualified staff and labor. Most of these
problems have their origin in the implementation phase and hence, relatively
easy to overcome as there is learning over time.
32
The DEPSA’s Project Cycle
This model is developed in Ethiopia in 1990 by Development Projects
Studies Authority (called “The DEPSA’s Model”), which is nearly identical
with the UNIDO cycle, will be briefly discussed. There are various ways in
which the project cycle may be viewed and portrayed depending on the
purpose, emphasis, and detail required to illustrate. According to the
Guidelines to project planning in Ethiopia (1990) of Development Project
Studies Authority (DEPSA), the project cycle comprises three major phases.
33
3. Operating phase
Each of these three phases may be divided into stages. The Guideline has
divided the above phases into six stages as follows:
1. Identification,
2. Preparation,
3. Appraisal/decision,
4. Implementation,
5. Operation, and
6. Ex-post evaluation
The pre-investment phase consists of the first three stages, while the
investment phase includes the fourth stage, and the operation phase covers
the last two stages.
34
The results and/or outputs of a given stage serve as the input or
part of the input of the next stage, if it is decided to proceed to the
next stage;
The output or part of the output of one stage may be used as new
input (feedback) to reconsider or revise, where necessary, the results
of proceeding stages; and
Most importantly, the results of the implementation, operation, and ex-post
evaluation stages of a project constitute valuable experience for the
preparation of subsequent projects, provided these inputs are systematically
documented and analyzed
35
36
37