Power Transformer
Power Transformer
Power Transformer
TRANSFORMER Sheet : 2
AT : Rev. A
I.03.H.DAE.0000
1 PURPOSE OF TEST 3 A
2 EQUIPMENT REQUIRED 3 A
3 PRECONDITIONS 3 A
4 PRELIMINARY CHECKS 4 A
5 ELECTRICAL TESTS 4 B
7 ENERGIZING 26 B
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 3
AT : Rev. A
I.03.H.DAE.0000
1 PURPOSE OF TESTS
These tests cover all inspections and tests to be performed on an oil-immersed power
transformer on site and prior to energization.
2 EQUIPMENT REQUIRED
- Omicron CP TD1
- temperature-controlled bath
- digital multimeter
- clamp-on ammeter
- thermometer
3 PRECONDITIONS
- any cable, shealt or line disconnected from the primary and secondary windings of the
reactor and connected to ground.
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 4
AT : Rev. A
I.03.H.DAE.0000
4 PRELIMINARY CHECKS
Using the reference drawings and the installation report, check the following :
- availibility and conformity of all constituent parts of the transformer and local auxiliary
board
5 ELECTRICAL TESTS
5.1.1. Test Of Continuity Between All Accessible Metal Parts And Local Auxiliary Board Ground
The earthing countinuity is considered being satisfactory when the reading is lower or equal
to 400 mOhm.
5.1.2. Insulation Resistance Test Of Power And Control Circuits Of Local Auxiliary Board
- disconnect the power and control cables from the local auxiliary board
- measure at 500V DC the insulation resistance of each circuit to ground
- the measured value should be equal to or higher than 100 Megohms
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 5
AT : Rev. A
I.03.H.DAE.0000
. the motor terminal connections are made for the supply voltage.
. the motor insulation resistance measured at 500 V DC is higher than or equal to 100
Megohms.
- note the current ratings and check the motor thermal protection settings.
. the motor terminal connections are made for the supply voltage
. the motor insulation resistance measured at 500 V DC is higher than or equal to 100
Megohms.
- note the current ratings and check the motor thermal protection settings
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 6
AT : Rev. A
I.03.H.DAE.0000
- Buchholz relays are generally fitted with a test button for checking their operation
- in addition to the transformers, these relays can be used to protect the load tap changer
and the oil bushing cable boxes.
- the thermal image relay gives the winding temperature image relative to the oil
temperature and the current through the winding.
- using a test power supply and a temperature-controlled bath, check the relay operation
and adjust to the specified settings.
- to perform the thermal image inspection and tests, refer to field test specification n° I 03 H
HAD 0012 appended
- check the :
. alarm indications
. tripping command
. cooling device operations.
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
5.1.5.4. Pressure relief valve
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 7
AT : Rev. A
I.03.H.DAE.0000
Simulate pressure relief valve operation and check the effect on the automatic system.
- ratio adjusters are used to adjust within a range the transformer turns ratio with the
transformer de-energized.
. manual control
. position indicator
. mechanical actuator
. lock
Figure 1:Setup for a tap changer test - winding resistance and interruption
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 8
AT : Rev. A
I.03.H.DAE.0000
Navigate to the parameter fields, and enter the values according to your testbrequirements:
Range: output range
Note: The DC 400A output range provides maximum current 100 A.
Itest: nominal test current
Tmeas: actual ambient temperature
Tref: this is the reference temperature at which the manufacturer
measured the taps’ winding resistance values. Generally, this value is
specified in the transformer’s data sheet. The winding resistance value at this
temperature always represents the nominal resistance value.
Tap: Data entry field to enter the transformer’s tap number for each
measurement. The possible entry range of -999 ... 0 ... 999
allows for the first digit to be used as a phase identifier.
Example for 3 phases:
– phase L1 (A): -101, 100, 101, 102, 103...
– phase L2 (B): -201, 200, 201, 202, 203...
– phase L3 (C): -301, 300, 301, 302, 303...
Example for 1 phase:
– phase: -001, 000, 001, 002, 003...
Tap combo box:
The selection made at this combo box specifies the counting
order of the taps in the measurement table’s column "Tap".
Possible selections are "Count up", "Count down" and "OFF".
The number specified at the data entry field "Tap" (see above)
represents the starting number.
"OFF" means, all lines in the measurement table show the
same tap number.
When results are measured, the AUTO KEEP RESUL T menu key is available.
After pressing the AUTO KEEP RESUL T menu key, CPC 100 waits until
stable results with a deviation less than 0.1% within the time period of
10 seconds are achieved. After then, a new result line is added and the next
measurement
This document starts.
is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 9
AT : Rev. A
I.03.H.DAE.0000
Measurements
4. isAtthethe
This document transformer,
property set
of PT. AT and thebetap
cannot displayed
used, reproduced in the last toresult
or transmitted line. prior written permission.
thirds without
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 10
AT : Rev. A
I.03.H.DAE.0000
. HV windings to ground
. MV windings to ground
. HV to MV windings
- apply a reduced three-phase AC voltage (about 380 V) on the HV windings using a three
phase supply.
- measure the voltage on the secondary windings for each position of the load tap changer
or ratio adjuster :
R = Applied voltage
Induced voltage
- check if the calculated ratio corresponds to the theorical ratio given by the manufacturer
for each position of load tap changer or ratio adjuster.
- measure the consumption in mA on each HV phase and for each load tap changer or ratio
adjuster (checking that there is no break during tap changing)
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 11
AT : Rev. A
I.03.H.DAE.0000
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 12
AT : Rev. A
I.03.H.DAE.0000
Table 1 below shows the Vprim and Vsec settings on the TRRatio test card for
different connections of the transformer under test.
Tabel.1
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 13
AT : Rev. A
I.03.H.DAE.0000
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 14
AT : Rev. A
I.03.H.DAE.0000
Navigate to the parameter fields, and enter the values according to your test requirements:
Vprim: nominal primary voltage with the option "value x 1/√3"
(can be set individually for each measurement)
Vsec: nominal secondary voltage with the option "value x 1/√3"
(can be set individually for each measurement)
Ratio: nominal ratio, calculated from Vprim nom / Vsec nom
here: (110000.0V / √3) / 10000V = 6.3509
Note that this value is automatically calculated. It does not
need to be entered. If Vprim is set individually for each
measurement, the ratio value differs for each tap.
Vtest: nominal primary injection voltage.
f: output frequency
Tap: Data entry field to enter the transformer’s tap number for each
measurement. If the transformer’s ratio was specified on the
Settings page, the Vprim and Vsec values for
the tap are taken from there. The possible entry range from
-999…999 allows the first digit to be used as a phase identifier.
Example for 3 phases:
– phase L1 (A): -101, 100, 101, 102, 103...
– phase L2 (B): -201, 200, 201, 202, 203...
– phase L3 (C): -301, 300, 301, 302, 303...
Example for 1 phase:
– phase: -001, 000, 001, 002, 003...
Tap combo
box: The selection made at this combo box specifies the counting
order of the taps in the measurement table’s column "Tap".
Possible selections are "Count up", "Count down" and "OFF".
The number specified at the data entry field "Tap" (see above)
represents the starting number.
"OFF" means, all lines in the measurement table show the same tap number.
Pressing the SE T T I NGS menu key opens the Settings page. The Settings
page of the TRRatio test card has another functionality as on other test cards.
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 15
AT : Rev. A
I.03.H.DAE.0000
The Settings page allows adding the transformer’s ratio per tap as follows. After
pressing the ADD TAP menu key first, the Vprim and Vsec values for the first
tap are taken from the main page. Change the tap number to the lowest tap of
the transformer under test (e.g. –16 or 0). Add the next tap by pressing the
ADD TAP menu key and enter the corresponding Vprim and Vsec values. After
then, pressing the ADD TAP menu key repeatedly adds more taps with a step
calculated from the values for the first two taps. After adding all taps, press the
MA I N PAGE menu key to transfer the data to the main page.
Note: After the transformer’s ratio was specified on the Settings page for one
phase, by pressing the SAVE A S DEFAULT menu key you can save the data.
Then a new test card for the next phase will be inserted with the transformer’s ratio
preset.
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 16
AT : Rev. A
I.03.H.DAE.0000
Use the RWinding test card to measure the resistance of a power transformer’s
winding. To do so, loop the I DC current signal from CPC 100’s 6A DCoutput via
IAC/DC as shown in figure 8 and inject it into the transformer’s winding.
IAC/DC measures the injected current, and V DC input measures the voltage
generated at the transformer’s winding. From these values the winding
resistance is calculated.
Alternatively, inject the current directly from 400A DC output (see figure 9).
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 17
AT : Rev. A
I.03.H.DAE.0000
Due to the significant time span needed for the transformer’s inductance to finish
its loading process, this test evaluates the deviation of measured values within
a time interval of 10 seconds. The winding resistance is continually measured
and stored in CPC 100’s internal memory. The calculated difference between
the maximum and minimum measured values in % within the last 10 seconds is
displayed.
Furthermore, this test comprises the option to take a temperature compensation
for copper (Cu) into consideration
Navigate to the parameter fields, and enter the values according to your test
requirements:
Range: output range
Note: The DC 400A output range provides maximum current 100 A.
Itest: nominal test current
TRANSFORMER Sheet : 18
AT : Rev. A
I.03.H.DAE.0000
Depends on the value of the nominal test current and the measuring range:
– 400A DC: Rmax = 5V / Itest.
– 6A DC: Rmax = 10V / Itest.
– VDC (2 wire): Rmax = 20kΩ
Measurements
Functional Components
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 19
AT : Rev. A
I.03.H.DAE.0000
As the first step, before you set a CPC 100 / CP TD1 composite into operation,
link CPC 100, CP TD1 and, if applicable, the equipment trolley with a min. 6 mm²
grounding cable as displayed.
Never use the CPC 100 / CP TD1 composite without a solid connection to ground.
1. Switch off CPC 100 at the main power switch.
2. With trolley:
Properly connect the CPC 100 and CP TD1 grounding terminals to the
trolley’s ground bar. Connect the ground bar to earth. All grounding cables
minimum 6mm².
Without trolley:
Properly connect the CPC 100 and CP TD1 grounding terminals to earth.
Both cables minimum 6mm².
3. Connect CP TD1’s "BOOSTER IN" to CPC 100’s "EXT. BOOSTER" with the
OMICRON supplied booster cable.
4. Connect CP TD1’s "SERIAL" to CPC 100’s "SERIAL" with the OMICRON
supplied data cable. This cable also provides the power supply for CP TD1.
5. Pull out the measuring cables from the cable drum and connect the test
object to CP TD1’s measuring inputs IN A and IN B.
6. Pull out the high voltage cables from the cable drum and connect the test
object to the CP TD1’s high voltage output.
7. Make sure that all cables are screwed tight.
8. Switch on CPC 100.
9. Selecting the TanDelta test card from any of the CPC 100’s menus
TRANSFORMER, OTHERS, CT or VT automatically turns on CP TD1. If
no CP TD1 is connected to CPC 100, an error message occurs.
10.Set up your measurement in the TanDelta test card.
11.Press CPC 100’s I/O (test start/stop) push-button.
TRANSFORMER Sheet : 20
AT : Rev. A
I.03.H.DAE.0000
is highly recommended.
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 21
AT : Rev. A
I.03.H.DAE.0000
Reminder :
TRANSFORMER Sheet : 22
AT : Rev. A
I.03.H.DAE.0000
- I and ------ correspond to the phase lag of a low voltage side behind the corresponding
high voltage side whatever the transformer function is (step-up or step-down).
- the vector ground index shall be measurement at the mid-position of the tap changer or
ratio adjuster and shall be checked at all the other tap positions.
a b c
o o o
A B C
o o o
. apply a three phase voltage reduced by means of a variable transformer (to about 380V)
on the HV windings (A,B,C).
NOTE
The B-a and C-a voltages are equal to the voltages between phases of the power source.
. knowing the source characteristics, draw the ABC voltage triangle to scale
. since the HV and LV systems have a common point at A-a, the voltage pairs measured at
terminals A, B, C can be used to build the two missing corners of the voltage triangle on
the LV side (b, c).
. measure the phase angle between the corresponding HV and LV voltages and deduce
the vector group index.
Take samples of the oil from the location where the oil is supposed to be the most
contaminated, e.g. from the bottom of the tank.
Slowly pour the oil sample into the test cell of the liquid dielectric tester
Perform the test as instructed in the table below with reference to the equipment used
and the applicable standard.
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 23
AT : Rev. A
I.03.H.DAE.0000
Non
This document is thetreated >30KV
property of PT. AT and cannot be used, 30KV
reproduced or transmitted >30KV
to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 24
AT : Rev. A
I.03.H.DAE.0000
In Service Oils
Equipment voltage
>170KV >50KV
70 to 170KV >40KV
<70KV >30KV
If the minimum breakdown voltage value is not reached, oil treatment should be performed.
Perform the inspection and tests of the current transformers associated with the transformer
as instructed in field test specification n° I.03.H.DAF.0000.
Perform the inspection and tests of the associated voltage transformers as instructed in field
test specification n° I.O3.D.DAF.0100
Perform the inspection and tests of the transformer electrical protective devices as
instructed in the following test specifications :
TRANSFORMER Sheet : 25
AT : Rev. A
I.03.H.DAE.0000
- removed any entrapped gas from the three phase neutral reactor high points, protection
accessories and cooling devices
- check if the desiccant (silica gel) is blue and check for oil in the breather.
. oil level.
. spark gap setting where applicable.
. terminals not subject to tension.
7 ENERGIZING
This document is the property of PT. AT and cannot be used, reproduced or transmitted to thirds without prior written permission.
PT. AREVA TRANSMISSION OIL IMMERSED Ref.
TRANSFORMER Sheet : 26
AT : Rev. A
I.03.H.DAE.0000
- meanwhile, to test the adjuster winding and the load tap changer, perform a tap changing
cycle. Take care not to exceed the mains capacity
CAUTION
At first, when power is applied and after several hours of energizing, a Buchholz relay fault
may occur due to air or gaz entrapped during oil filling. In such a case, bleed this air or gas
from the Buchholz relay and where applicable (for an Atmoseal type conservator), the oil
gas separation compartment. Check if this gas is nonflammable (otherwise, suspect an
internal fault and contact the transformer manufacturer's representative. In such a case, DO
NOT ENERGIZE AGAIN WITHOUT THE MANUFACTURER'S APPROVAL.)
Progressively set the transformer under load. During this switching to the mains, check the
temperature rise with reference to the load and the equipment operation.
During AC generator no-load tests or overvoltage tests, do not apply a voltage 5 % above
the rating nor a frequency 2.5 % lower than the line frequency (VDE 0532/8.24) to a voltage
transformer (to avoid over-saturation).