Method Statement & Quality Control Procedure For CCTV System
Method Statement & Quality Control Procedure For CCTV System
Method Statement & Quality Control Procedure For CCTV System
For
CCTV System
INDEX
1 Scope 2
2 Reference Documents 2
3 Definitions 2
4 Responsibilities 2-4
5 Control Measure 4
6 Material 4
8 Preparatory Works 4
9 Work Procedure 4
10 Record List 5
3 DEFINITIONS
CCTV - Closed Circuit Television
Installation of CCTV
Wiring in concealed Entrance and All area
3.1 Wire, Pulling wire
conduits and surface Building
conduits
4 RESPONSIBILITIES
The MEP Head - Projects shall be ultimately responsible for all Contractual matters,
representing Contractor’s management. He shall:
4.3.1 Project Coordinator is the Management Representative reporting to the MEP Head
and has the authority to review project plan, Project Material procurement, Project
Quality and HSE plan and he shell provide the guidance to the site execution In
charge and the material procurement team to ensure that the work progress In line
with the project schedule and the company quality control procedure.
4.4.1 Execution In charge (Electrical) shall be the focal point for Electrical works.
4.4.2 Maintain HSE regulations and ensure safe working practices.
4.4.3 Implement and follow-up QA/QC procedures and maintain Quality Records.
4.4.4 Ensure the successful completion of tasks identified in line with the drawings and
specification, construction program, PQP, Project HSE Management Plan.
4.4.5 Co-ordinate with subordinate staff and execute the works in accordance with the
planned schedule and liaise with the other Execution in charge for effective co-
ordination and execution of site activities.
4.4.6 Continuously assess the actual progress of work against planned program and inform
the Project Head. Assess manpower, equipment and other resources required to
achieve milestone / target dates, in co-ordination with the Discipline Engineer.
4.4.7 Check resources required for each activity as per planned construction program and
ensure all necessary resources are available at site to deliver the schedules.
4.4.8 Conduct regular meeting with Supervisors and check the schedules planned and
achieved, if any delay noticed, reasons for delay to be brought to the management and
remedial action to be taken.
4.4 Supervisor/Foreman:
5.1.1 Ensure availability of latest “Approved for Construction drawings and specifications.
5.1.2 Ensure materials used are as per approved Material Approval Requests (MAR)
5.2 Safety:
5.2.1 All activities will be executed in accordance with company’s HSE Plan.
5.2.2 Safety risk assessment shall be performed for every job or task, which has the
potential for harm.
6.0 MATERIALS
The materials received at site shall be checked for make and quantity as per delivery
note and approved MAR to ensure delivery is correct.
9.1.1 Install conduits and carry out wiring as per the approved CCTV layout drawings
9.1.2 Install camera’s base screwed to the true ceiling / false ceiling and fix the camera and
terminate its respective wires in line with the terminal indication
9.1.3 Complete the installation checklist and offer for Consultant’s inspection.