Control of Drop Height and Weight of Drop Hammer: Depth From Ground Level (M) Max Drop Height (M)
Control of Drop Height and Weight of Drop Hammer: Depth From Ground Level (M) Max Drop Height (M)
Control of Drop Height and Weight of Drop Hammer: Depth From Ground Level (M) Max Drop Height (M)
PPV contour
with 1 piling
machine
Piling Machine
PPV = 2mm/s
PPV = 1mm/s
3. Control of concurrent pile driving
PPV contour
with 3 piling PPV = 2mm/s
PPV = 4mm/s
Piling Machine
1 1
2 1
4. Sheet-piling by press-in
method
Test and Trial Piles
◦ According to approval letter,
5 piles selected to be test piles
to verify the design assumption
4 piles selected to be trial piles
to verify the design assumption
to verify the performance of piles under particular ground
condition
Loading test is required
2 piles were selected to drive concurrently
to assess the vibration effect
to verify the design parameter
Pile Testing Report
◦ The back analysis of coefficient kp based on data
collected from the test piles and the effects of the
piling operation during installing of test piles
V5,V6,V
PPV for village house (Tai Kiu
9,
Village), mm/s - 1.5 - 2 3 3 - - 3
V10,V1
(Continuous/Transient)
1,V12
PPV for low-rise building,
V2,V3,V
mm/s - 3.7 - 5.6 7.5 7.5 - - 1
4
(Continuous/Transient)
Receive Complaint
Identify Nature
of Complaint
Old
N
Driven H-Pile
Photo 10 – Preboring Photo 11 – Sand Backfilling
Photo 12 – Extraction of Photo 13 – Setting Out
Casing
Photo 14 – Vibro Hammer Photo 15 – Welding
Photo 16 – Hydraulic Photo 17 – Drop Hammer
Hammer
Photo 18 – Final Set
Driven H-Pile (Test and Trial Pile)
Photo 19 – Concurrent Photo 20 – Concurrent
Driving by Hydro Hammer Driving by Drop Hammer
Photo 21 – Vibration Photo 22 – Loading Test
Monitoring (Compression)
Photo 23 – Loading Test
(Tension)
Construction Sequence Preboring from the center of circle first (red circle)
5m
The next preboring region (green circle)
Bored Pile
Photo 24 – Predrilling Photo 25 – Setting Out
Photo 26 – Soil Excavation Photo 27 – RCD
Photo 28 – Bellout Drilling Photo 29 – Extracting Rock
Head Material
Photo 30 – Airlifting Photo 31 – Koden Test
Photo 32 – Reinforcement Photo 33 – Place the steel
Fixing cage
Photo 34 – Concreting Photo 35 – Extract the
Casing