QUALITY MANGEMENT SYSTEM

PREVENTIVE MAINTENANCE SCHEDULE

DOC.NO. ISSUE NO. REV. NO. PAGE NO.


KIFO/MNT/F/08 DATE:01/10/11 DATE:01/10/11 1 OF 1
DATE- PM START TIME- PM FINISH TIME-
MACHINE - BAR FEEDER MACHINE NO. : - LOCATION - MACHINE SHOP PERIODICITY :- MONTHLY
SR. MECHANISM ACTIVITY HOW TO DO CONDITION ACTION SPARES REMARK
NO. SUB ASSEMBLY At incoming Switch for 440 V in R,Y & B OBSERVED TAKEN USED
1 General 1. Check incoming supply and earthling. phase.
2. Check loose wiring & rectify if required . At connector.
3. Measure motor currents & set relay accordingly . On load condition at motor terminal .
4.Check fittings and oil lubrication lines for leackage check visually and change fittings if required
and proper oil flow

6.check oil level of machine and fill if required check with level guage and fill up to required
marking position
7.Check hydrualic lines for leackage check visually.
8.check for forward/reverse operation of feeder check for smooth operation of cylinder
9.check for arm open and close operation check for smooth operation of cylinder

10.check all the solenoid valves are working proper check with operation and LED indications must
on for all solenoids
11.check FAR controller in remote box check for cable tightness on controller
12.check all the controls are working properly check it by taking trial for each function
13.control panel and remote wire terminals tighness check all control terminals for tightness.

14. Clean complete machine . clean complete panel with blowering and cotton
waste
MAINTENANCE SUPERVISIOR SIGN : PRODUCTION SUPERVISIOR/OPERATOR SIGN :
PREPARED BY: APPROVED BY :
DATE : DATE :