To Falsework: Guide
To Falsework: Guide
To Falsework: Guide
This Guide provides information on the design, construction and dismantling of falsework.
It is part of a series of guides for formwork and falsework that includes the:
! Falsework
Falsework means the temporary structure used to support a permanent structure, material,
plant, equipment and people until the construction of the permanent structure has advanced
to the stage where it is self-supporting.
Although commonly referred to as being part of formwork assembly, the formwork supports
including joists, bearers, bracing, foundations and footings are technically referred to as
falsework. Further information is in the Guide to formwork.
Falsework can be used to support a range of permanent structures before their completion
including:
Further information on high risk construction work, SWMS and a SWMS template is in the
Code of Practice: Construction work.
! Design
The falsework designer must be competent in falsework design including documenting temporary
work platforms and special equipment needed for safe falsework construction on-site.
Falsework should be designed to carry all loads that may be applied during the various stages
of its use including dead, live, environmental and other loads.
The design drawings should include design assumptions and a statement of the loads and
dimensional changes expected due to loading in all members of the falsework. The drawings
should detail member sizes and materials, dimensions, levels, erection procedures and other
relevant details including bracing, connections and foundations to ensure erecting, inspecting
and using the falsework can be done safely. The design should also include details of methods
to provide safe entry to working zones of temporary and permanent structures.
Where falsework is required to support a complex structure during construction, for example
a stone arch bridge, the structure designer should involve the falsework designer to minimise
falsework complexity and health and safety risk during construction and dismantling.
Off-the-shelf support systems are generally not suitable for complex falsework unless
incorporated into a specifically designed solution as documented by the designer.
The foundations and footings of the falsework should be designed to prevent excessive
settlement and rotation of supports and to maintain overall structural integrity of the
falsework and the permanent structure or formwork being constructed.
The risks that need to be controlled in erecting and dismantling falsework are similar to those
for formwork including:
The certifying engineer should complete and provide a Formwork Structural Certificate to
the person with management or control of the falsework, often the principal contractor. An
example of a Formwork Structural Certificate is included in the Guide to formwork.
! Monitoring loading
A competent designated observer should continuously monitor the falsework assembly during
loading and be provided with an appropriate communication system to alert others
in case an emergency arises.
! Dismantling falsework
Prior to falsework removal, a competent person, for example an engineer with experience
in structural design should provide written confirmation the permanent structure is self-
supporting and the falsework can be safely removed.
Falsework should generally be dismantled in the reverse order of its erection. Back propping
arrangements should also be verified before starting removal.
For in-situ concrete structures, all or most of the formwork should be removed before the
falsework is removed to minimise the risk of formwork falling onto people.
Further information
Codes of practice, guidance material and other resources are available on the Safe Work
Australia website (www.swa.gov.au).
JULY 2014