MS Sheet Piling RB011
MS Sheet Piling RB011
MS Sheet Piling RB011
: Page 1 of 9
Revision : 1
UE Construction Sdn Bhd Issued : Sept 2001 :
UEC/MS/RB011/SP/002
ELECTRIFIED DOUBLE TRACK IPOH - RAWANG
IMPORTANT
The information contain herein is the proprietary property of UE Construction Sdn. Bhd.
The holder agrees to the following:
1. Not to reproduce; copy; reveal; publish; or, distribute it in whole or any portion of it without authorisation; and,
2. To maintain this document in confidence.
METHOD STATEMENT Page No. : Page 2 of 9
Revision : 1
UE Construction Sdn Bhd Issued : Sept 2001 :
UEC/MS/RB011/SP/002
ELECTRIFIED DOUBLE TRACK IPOH - RAWANG
CONTENTS
Pages
1.0 SCOPE 3
2.0 MATERIALS 3
4.0 METHOD 4
9.0 DOCUMENTATION 9
METHOD STATEMENT Page No. : Page 3 of 9
Revision : 1
UE Construction Sdn Bhd Issued : Sept 2001 :
UEC/MS/RB011/SP/002
ELECTRIFIED DOUBLE TRACK IPOH - RAWANG
1. SCOPE
This method statement describes the method and procedure involved in the
installation of temporary shoring and cofferdam for braced excavation to
facilitate the work relating to the construction of the proposed overhead bridge
at chainage 218.608.
Retaining walls at this location are used to protect both the existing railway
and road / bridge. Shoring is also required during the construction of deep
pilecaps at at Pier 1 and Pier 1. Please refer to the layout plan.
The retaining wall will comprise of sheet piles and waler with ground anchor at
calculated intervals (Refer to drawings) along sheet pile wall.
2.0 MATERIALS
2.1 Sheetpile
U Sections will be used for steel sheet piling. They shall be installed
vertically by a vibro hammer to resist lateral earth force.
As the pile comes in 12m or shorter lengths, welding will be used to join
the sheetpiles if a longer length is required. On the other hand, oxy-
acetylene will be used to cut the sheetpiles if these protrude out and
causes a danger to the trains passage. FSP Type IV sheetpiles will be
used for the sheetpile wall next to the existing track, all other areas will
utilise FSP type III sheetpiles.
2.2 Waler
The use of tie back anchorage to support the side of wide excavation.
Load on cable anchors transferred to sheet piles through horizontal
waling.
4.0 METHOD
Steel plates will be provided at locations where the ground is soft and
unable to support the machinery.
METHOD STATEMENT Page No. : Page 5 of 9
Revision : 1
UE Construction Sdn Bhd Issued : Sept 2001 :
UEC/MS/RB011/SP/002
ELECTRIFIED DOUBLE TRACK IPOH - RAWANG
Gas palettes and welding machines will be located close to the place
of work.
3. Arrange the piles at each point with the use of a timber frame to
ease and maximise installation.
1. Cutting of strand
PC strand will be cut to designed lengths. The strands will
than be arranged into a bundle and necessary spacer blocks
installed to form a “Basket weave” pattern for bond length
portion of anchor. The PC strands will be cleaned free from
mud and other deleterious materials.
METHOD STATEMENT Page No. : Page 6 of 9
Revision : 1
UE Construction Sdn Bhd Issued : Sept 2001 :
UEC/MS/RB011/SP/002
ELECTRIFIED DOUBLE TRACK IPOH - RAWANG
2. Drilling
Drilling is carried out using a wash drilling machine. The
depth of the drilled hole shall be verified by contractors
engineer using the Site investigation data obtained previously
(refer to attachment and calculations) and the actual material
encountered during the drilling process. Upon reaching the
required design depth, the drill hole is to be flushed clean
with water or air.
3. Installation
Installation and homing of anchor into the drilled hole shall be
carried out after or before waler installation depending on site
conditions.
4. Grouting
The grout mix of design strength 40N/mm 2 will be produced
using a mechanical mixer that is capable of producing uniform
colloidal grout (design mix and trial mix of the cement grout
will be carried out for consultant’s approval prior to start
grouting). Mixing will be done for a period of 3 minutes before
sieving through a nominal sieve prior to injection. All the
QA/QC requirements will be followed as per UEC Inspection &
Test Plan.
5. Stressing
The stressing operation shall be carried out when the grout
has attained a minimum strength of 30N/mm2. A Hydraulic
jack of minimum will be used to stress all the strands of the
ground anchor. The general procedure is as below: -
Fabrication of tendon
Drilling of hole
Installation of anchor
Grouting
Stressing of Tendon
Locking of tendon to anchor head
De-stressing of tendon
Removal of anchor head
Removal of Waler
Extraction of Sheetpiles by Vibro-hammer
Stockpiling and removal off site.
Testing shall follow the procedure laid out in the DRB-HICOM Inspection and
Test Plan.
METHOD STATEMENT Page No. : Page 8 of 9
Revision : 1
UE Construction Sdn Bhd Issued : Sept 2001 :
UEC/MS/RB011/SP/002
ELECTRIFIED DOUBLE TRACK IPOH - RAWANG
Tool box meeting will be carried out on construction area at regular interval
to ensure compliance with the Safety Plan and familiarity with accideent and
emergency procedures
Mandatory PPE attire will be worn at all times within ROW ( high visibility
vest, safety helmet, safety shoes,etc )
A line block will be applied during sheetpiling works as the sheetpile wall will
be installed very near to the track and might pose a danger to trains as well
as to the track. All KTM regulations regarding lineblocks will be adhered to.
A joint inspection of the track will be carried out with the consultants and
KTM before work commencement. Existing track levels will be monitored at
every 5m by checking the settlement marker using survey equipment within
the bridge ROW before work commencement. The settlement will be
monitored continuously by visual inspection and survey at every 2-hrs
interval. If the track settles more than 18mm (refer to Table 5.2.1.1 in
specification Rev B1), all work will be stopped and a track repair team will
be informed to repair the track immediately. Similar checking will be carried
out for lateral alignment by setting a reference line. If the alignment out by
18mm, all work will be stopped and a track repair team will be informed to
repair the track immediately.
After installation of the sheet piles, the movement of the sheet piles will be
monitored regularly during and after the excavation work.
9.0 DOCUMENTATION