Tata Steel - Blast Furnace PDF
Tata Steel - Blast Furnace PDF
Tata Steel - Blast Furnace PDF
Vineet R Tripathi
Head Operation ‘I’ Blast Furnace
S. Subhachandhar
Manager Operations & Support ‘I’ Blast Furnace
1
1 500
First Integrated Steel Plant One of the few steel industries to
in Asia feature in FORTUNE500
28 81K
Over 28 Million tonnes of Steel Conglomerate with over 81,000
Produced p.a employee
5
Providing customized solutions across 5
continents
110 Years of Successful operation
110
© Copyright 2017 Tata Steel. All Rights Reserved 2
1
‘I’ Blast Furnace… Journey of Excellence : 2012 - 2017
Commissioning of I BF – 4th April 2012
INDEX
6’
Project and Team Selection Slides – < 5 - 17 >
1
7’
Current Situation and Improvement Slides - < 18 – 31>
Opportunity Analysis 2
5’
Slides - < 32 – 48 >
Solution / Improvement Development 3
6’
Implementation and Results Verification 4 Slides - < 49 – 59 >
3’
Sustaining Results Over Time 5 Slides - < 60 – 63 >
3’
Beyond Results : Awards & Accolades 6 Slides - < 64 – 66 >
2
1 Project and Team Selection
3
Improvement
Development
4
Implementation &
Result Verification
5
Sustaining &
Communicating 2
Results Background Information for the selection of the project
© Copyright 2017 Tata Steel. All Rights Reserved 6
3
1.2.0 Project Selection Process
1 1.2.1.1 – How was the gap or opportunity brought to the attention of the project identification group ?
Project & Team
Selection
1.2.1.2 – What was the opportunity (process improvement) ?
5
Sustaining &
Communicating The current position of I BF also states that
Results there is scope of improvement
© Copyright 2017 Tata Steel. All Rights Reserved 7
2
Current Situation
and Improvement
Opportunity Analysis
3
Improvement
Development 60 % of Cost of Hot metal is
incurred through Coke & Coal
consumption in Blast Furnace ‘I’ Blast Furnace
4
Implementation & 2 What ? 3 Where ?
Result Verification
42% of the cost of Finished steel comes from the coke and Area of Opportunity
coal consumed in Blast Furnace – OPPORTUNITY TO Identified
5
Opportunity REDUCE THE COKE CONSUMPTION & IMPACT
Sustaining & THE BOTTOMLINE ‘Blast Furnace’
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 8
4
1.2.0 Project Selection Process
1 1.2.2.1 – What data was generated to help select the project ?
Project & Team 1.2.2.2 – What methods and tools were used to assess or prioritize the need for the project ?
Selection
1.2.2.3 – Why were these methods and tools used to select the project ?
1
Data Generated
From Business
9 Reducing Sinter Return Fines I 2.3 2.7 3.4
parameters 12
13
incidences
Ore and Coke drying system
Increasing drill machine mist flow from 3
M
L 1.9
1
2.2
1.2
4
2
Development 14
to 8
Reduction in Emissions at I BF
Commissioning of Alternate Raw Coal
N 2 2.4 6
15 O 1.3 3.6 6.2
Supply
16 Improving sampling practices at I BF P 1 1.1 3.2
17 Minimizing raw flux addition Q 1 3.7 3
Reduction of operation contract man
18 R 1.7 3 3
power gate pass
Reduction in off chemistry dumping by
19 S 1.1 3.5 5
50%
4 20
21
Reduction in gas concentration in
Furnace Proper
Developing model road in the I BF
T
U
0.5
0.4
0.2
0.6
4.5
3.2
premises
Result Verification
2
Prioritization Method used
3 ‘Project Prioritization Matrix’
5
Sustaining & Why ??
Communicating Holistic Approach to rank the projects selected based on business
Results Proj Rank #1 – Reduction of Coke Rate at ‘I’ BF impact, ease of implementation and strategic priority
5
1.3.0 Team Selection and Preparation
1 1.3.1.1 – How was the stakeholder groups identified ?
Project & Team
Selection 1.3.1.2 – What or who were the stakeholder groups ?
1 All the Stakeholders were identified through the tool SIPOC
2 Raw Materials Hot Metal Logistics
Current Situation
Management
and Improvement Steel Making Shop
Opportunity Analysis Coke Plant
Fuel Management
Sinter Plant Division
3
Improvement Pellet Plant Slag Granulation
Development and Drying Plant
Fuel Management
Division Coke, Sinter, Pellet, Iron Blast Furnace Hot Metal, Slag, BF
4 ore, Nut Coke, Fluxes, Cold Process Gas, Electric Power
Blast, BF Gas, Humidity,
Implementation & Power House
Oxygen, Coal, Nitrogen
Result Verification
Maintenance Team Project Steering
Committee
5 Project Mentor
Sustaining &
Communicating 2
Project Team Process Owner *Stakeholders
Results
© Copyright 2017 Tata Steel. All Rights Reserved 11
3
Improvement
Development
4
Implementation &
Result Verification
3
5
Sustaining &
Communicating
Results 2 Stakeholder Knowledge assessment was made and accordingly training requirement was identified
Y – Already Trained, NA – Not Applicable, N – To be Trained
© Copyright 2017 Tata Steel. All Rights Reserved 12
6
1.3.0 Team Selection and Preparation
1
Project & Team 1.3.3.1 – Before the project started, what specific training was done ?
Selection
1 Specific Training Imparted to specific Team Based on the Gaps identified
2
Current Situation
and Improvement
Opportunity Analysis
3
Improvement
Development
4
Implementation &
Result Verification
• Training were imparted based on the Gaps Identified, from the brainstorming sessions of the team.
5 • Dedicated classroom sessions were organized with the help of Tata Management Development Centre & Total
Sustaining &
Communicating Quality Management
Results
© Copyright 2017 Tata Steel. All Rights Reserved 13
7
1.3.0 Team Selection and Preparation
1
Project & Team 1.3.4.1 – What roles and expectations were determined ahead of the project ?
Selection
1 Roles & expectation from the Team Members
8
1.3.0 Team Selection and Preparation
1 1.3.4.3 – Before the project started, what team routines, including communications, were established ?
Project & Team
Selection
3 Team Routines
9
2.1.0 Key Measures Expected of the Project
1 2.1.1.1 – What specific goals and/or measures was the team trying to achieve with the project ?
Project & Team
Selection 2.1.1.2 – What additional potential benefits, other than the specific goals and / or measures was the
project expected to impact ?
1 Project Statement : Improvement Current Performance Target
2
Current Situation Reduction of Coke Rate of ‘I’ Blast Furnace by 5%, Opportunity (kg/thm) (kg/thm)
and Improvement
Opportunity Analysis thereby save INR 20 Cr in FY 16 Coke Rate 428 408
Thereby the reduction of Cost of Hot Metal
3 2 Project Benefit
Improvement
Development
Reduction of Carbon Footprint
4
Implementation & Reduction of Coke Rate Reduction of Hot Metal Cost
Result Verification
5
Improvement in Productivity
Sustaining &
Communicating
Results *Additional Benefits
© Copyright 2017 Tata Steel. All Rights Reserved 19
10
2.2.0 Possible Root Causes / Improvement Opportunities
1
Project & Team
2.2.3.1 – How was the team prepared to use these methods and / or tools ?
Selection
3 Preparation of Team for using the Tools
Ishikawa Diagram
2 Training Imparted to (Six Sigma Green Belt)
Current Situation
and Improvement 1. Project leader Control &
Opportunity Analysis Stability Charts 3 Hours hands on
2. Project Members & refresher training
3. The Process Owner Brainstorming imparted on the
3 7 QC Tools and a
Improvement 3 day training 6 day six sigma
Development Benchmarking program on Six training program
5 Hours training Sigma Green Belt was organised
Process Mapping Program and use
on Systematic
4 of Statistica
1 day training Focused group
Implementation & discussion and
Result Verification
program on
3 hours of hands Benchmarking brainstorming
on training methodology
imparted on The Effectiveness of training was verified by
5
Sustaining & Creation of conducting Pre Course and Post Course Assessments
Communicating Process Maps
Results
© Copyright 2017 Tata Steel. All Rights Reserved 21
2
Current Situation Tools used to identify Improvement Opportunities
and Improvement
Opportunity Analysis
1. What ?? 1. How ??
Tools Used Data Generated How
3 Process Inputs, Outputs, Sub Processes and Process Mapped through group
Improvement Process Mapping Performance Indicators discussion
Development
In - Processes were also benchmarked KPIs Collected from various Blast
Benchmarking along with the major KPIs Furnace and Studied
4
The various affecting parameters Dedicated Group discussion to answer
Implementation & Brainstorming
were jotted what can improve the efficiency
Result Verification
The was found stable under 100 %
Control Charts & Stability Charts Using Statistical Tool to predict
availability
5
Sustaining & Various Affecting parameter were All the affecting Parameters that were operating
Communicating Ishikawa Diagram in not optimized range were identified
drilled down
Results
© Copyright 2017 Tata Steel. All Rights Reserved 22
11
2.2.0 Possible Root Causes / Improvement Opportunities
1 2.2.2.2 – What were the possible root cause / improvement opportunities ?
Project & Team
Selection
12
2.3.0 Final Root Cause / Improvement Opportunity
1
Project & Team
2.3.1.3 – How was the team prepared to use these tools ?
Selection
3 Preparation of Team for using the Tools
2
Current Situation
Training Imparted to Multiple Regression Analysis
and Improvement 1. Project leader (Six Sigma Green Belt)
Opportunity Analysis
2. Project Members &
3. The Process Owner 6 days training
3 KPI Drill Down
Improvement program on Six Sigma
Development Methodology
Correlation Matrix 3 hours of hands on including Multiple
4 training imparted on Regression Analysis
Implementation & building and
Result Verification 3 day training conducting KPI Drill
program on Six Sigma Down Analysis
Methodology
5 including Correlation
Sustaining & The Effectiveness of training was verified by
Communicating Matrix conducting Pre Course and Post Course Assessments
Results
© Copyright 2017 Tata Steel. All Rights Reserved 25
3 Tools Used
1 Data Generated
Improvement
Development KPI Drill Down Analysis
Correlations (Spreadsheet22 19v*297c)
4 BGV
Result Verification K
13
2.3.0 Final Root Cause / Improvement Opportunity
1 2.3.3.1 – How was (were) the final root cause(s) / improvement opportunities validated ?
Project & Team
Selection 2.3.3.2 – What evidence showed that the final root cause(s)/improvement opportunity(ies) were
validated prior to solution development ?
2
Current Situation Validation Expert Validation – BF PIT Modeling Software
and RC /
Opportunity Analysis Category Meeting
Implementation &
2 Uttam Singh
Sanjiv Kumar
AS Reddy
Johannes de Lange
Sustaining & B
C
IJmuiden coal preparation plant
Typical report on hearth temperature behaviour
Lange)
IJmuiden (de
Open
Open
tation on
sharepoint
PDF on
Communicating D
as presented in morning meeting
I BF Project on Coke Rate- Key Factors that
affect Coke Rate
Lange)
I BF,
Jamshedpur
Closed
sharepoint
Panel reached
a conclusion
Optimized regime
Results 3
Pending points from previous meetings
Information on sealing material used to arrest
tuyere leakage. Material, equipment, procedure,
IJmuiden
(Nugteren)
CF
Separate lync
to be set up
etc. Work in progress. in week 42
Jsr & SCP
Information sharing on type of eyes and face info on share-
3
Improvement
Development
4
Implementation &
Result Verification
14
1. No change
2.4.0 Project Management Update
1 2.4.1.2 – How were stakeholders involved and / or communicated with during root cause /
Project & Team
Selection improvement opportunity phase of the project ?
2
Current Situation 2
and Improvement
Opportunity Analysis
3
Improvement
Development
4
Implementation &
Result Verification
5
Sustaining &
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 29
15
2.4.0 Project Management Update
1 2.4.1.4 – How was the appropriateness of the initial team membership and management routines
Project & Team
Selection confirmed ?
4
2 Team Membership & Confirming Appropriateness Changes needed
Current Situation Management Routines
and Improvement
Opportunity Analysis
Team Membership • Project Charter Review – No Change required
Completion as per timeline
3
Improvement • Stakeholder Matrix Analysis –
Development Work done as per plan
Management Routines • Documentations were found No Change Required
4
in place
Implementation &
Result Verification • Procedures followed
• Proper Communication to all
5
stakeholders were evident
Sustaining &
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 31
16
3.1.0 Possible Solutions or Improvements
1
Project & Team 3.1.1.1 – What methods and / or tols were used to identify the possible solutions / improvements ?
Selection 3.1.1.2 – Why were these methods and / or tools selected ?
2
Current Situation
and Improvement
Tools used to identify Improvement Opportunities
Opportunity Analysis
1 2
Tools Used Why
3
Improvement To facilitate cross learning among the European
Development Expert Consultation - PIT
and Indian Opportunity
Comparing various in processes to identify the
4 Benchmarking
directionality towards solution
Implementation &
Result Verification Focused Group Discussion – LEO (Learning from Experts views from Blast Furnaces in
Each Other) Jamshedpur were taken
5
Sustaining & Literature Review To identify the best practices in the industry
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 33
Training Imparted to
2 Literature Review
Current Situation 1. Project leader
and Improvement Focused Group
Opportunity Analysis
2. Project Members &
Discussion Dedicated Topic
3. The Process Owner Research were given
3 to each member of
Benchmarking 5 Hours training on the team and a period
Improvement
Development Systematic Focused of 1 week to come up
Expert group discussion and
1 day training with solutions
Consultation brainstorming
program on
4
Benchmarking
Implementation & All the Root Causes methodology
Result Verification identified were
compiled and sent
across to the experts The Effectiveness of training was verified by conducting Pre
5 from various Tata Course and Post Course Assessments
Sustaining &
Communicating Steel Plants around The progress was also tracked in the Weekly review meeting
Results the world
© Copyright 2017 Tata Steel. All Rights Reserved 34
17
3.1.0 Possible Solutions or Improvements
1 3.1.2.1 – What data was generated and how was the data analyzed to determine the possible solutions
Project & Team
Selection / improvements ?
18
3.1.0 Possible Solutions or Improvements
1 3.1.2.3 – What evidence showed that the solutions / improvements identified were possible instead of
Project & Team
Selection final ?
3 Evidences showing the solutions were possible instead of final
2 PFMEA – Showing the parameters with most affecting capability
Current Situation
and Improvement Process No. Process Function
Product (Output)
Characteristics
Requirements
Potential Failure Mode
Potential Effect(s) of
Failure
A
Severity
(Out of 10)
Potential Cause (s) / Mechanism (s) of Failure These evidences show that the
Opportunity Analysis 40.I1 Fluctuation in Wind Volume
40.I2 Raw material quality(Sn-RDI, C-Ash,
identified solutions were possible
P-SI)
40.I3 Cooling water Flow instead of final
40.I4 Physical and Chemical Properties of
3 Raw Material
40.I5 Stock line
Improvement 40.I6 Distribution of RM Modeling results depicting the gas temp at
Development 40.I7 Fluctuation of Top Gas Pressure
40.I8 Variation in input coal quantity and various conditions
quality
Hot Metal Si (40.O1) Si < 0.44% 40.I9 Variation in agglomerate percentage
Hot Metal S (40.O2) Si >1.04%
Hot Metal 40.I10 High input moisture load
40.I11 %Sn in burden
4 40
Furnace
Operation
Temperature (40.O3)
Slag Chemistry(MgO,
S >0.065%
MOU Non compliance 9 40.I12 Oxygen Enrichment
Al2O3 & B2) (40.O4) 40.I13 Burden Distribution
Implementation & Coke Rate (40.O5)
Coke Rate <440
kg/thm
40.I14 Low Sinter basicity
40.I15 High Al2O3 in raw material
Hearth liquid level
Result Verification (40.O6) 40.I16 Phosphorus in input raw material
40.I17 Hot Metal Temperature
40.P1 SLC
40.P2 Coal Injection
40.P3 RAFT
40.P4 water Circuit make up
40.P5 Fuel rate
5 40.P6 Slag Chemistry
Sustaining & 40.P7 ECO
40.P8 E H2
Communicating 40.P9 Amount of dust dumped from dust
catcher
Results 40.P10 Heat Flux (Circuit#3 Heat Loss)
19
3.2.0 Possible Solutions or Improvements
1 3.2.1.3 – How was the team prepared to use these methods and / or tools ?
Project & Team
Selection 3 Preparation of Team for using the Tools
Training Imparted to
2
Current Situation 1. Project leader Modelling
and Improvement
Opportunity Analysis
2. Project Members &
3. The Process Owner Modelling of different
Pay Off Matrix
3 scenario and its results
Improvement analysis were
Development Affinity Diagram 4 hours session in imparted to the team
hands on training of in a 2 day training
Pay off Matrix module
4 Usage and creation of
Implementation & Affinity Diagram was
Result Verification instructed and activity
was carried out by the
Project team along The Effectiveness of training was verified by conducting Pre
5 with the process Course and Post Course Assessments
Sustaining &
Communicating owners The progress was also tracked in the Weekly review meeting
Results
© Copyright 2017 Tata Steel. All Rights Reserved 39
2
2
Current Situation
and Improvement Tools used to identify Improvement Opportunities
Opportunity Analysis
1
3
Tools Used How
Improvement
Development Brainstorming helped
Affinity Diagram
categorizing the solutions
Final Improvement
4 Categorized the available Opportunities
Implementation & Payoff Matrix
solutions
Result Verification
Validated various scenarios
Modelling
after building in the model Increasing cold strength of coke, Adjusting Screening size,
5 optimize the slag composition, reduce wind volume, increase
Sustaining &
Communicating oxygen enrichment, coal injection and hot blast temperature
Results and improve the cast house operation
20
3.2.0 Final Solutions or Improvements
1 3.2.3.1 – How were the final solutions / improvements validated ?
Project & Team
Selection 3.2.3.2 – What evidence showed that the validation was performed prior to implementation ?
4
Time: 03.30 PM (India); Chaired by Mr. Uttam Singh
Meeting No. PIT/BF/09/16 Date: 04/12/2015
2 Evidence
12.00 (NL); 11.00 (UK)
Attendees :
Jamshedpur IJmuiden Port Talbot Scunthorpe
Uttam Singh Johannes de Lange Andrew McGregor No attendance
Implementation &
Sanjiv Kumar Mark van den Berg
AS Reddy Jan van der Stel (R&D)
Shambu Nath Gerard Tijhuis (CoE)
Padma Pal
Result Verification
Shantanu Mallick
Krishnendu Mukhopadhyay
Manish Pandey
Vineet Tripathi
5 B
MoM of BF Pit with the
Damage to stove #2 at KPO during heat-up. What
is recommendation of TSE for start-up ? Blow-in All sites Open
adviced not to
start with only
2 stoves. Risk
Communicating
C in I BF were discussed and deliberated – More Jamshedpur Open
discussion to held in person
PFMEA
Document on trough discharge in Jsr is made
Results
measures
Outcomes to
Port Talbot mentioned an investigation on the
E Port Talbot Open be shared for
torpedo collision (~one month ago) is still ongoing.
learnings.
*Additional Benefits
5
Sustaining &
Communicating
Results
2 These Benefits were anticipated from the implementation of solution
© Copyright 2017 Tata Steel. All Rights Reserved 42
21
3.2.0 Final Solutions or Improvements
1 3.2.5.1 – What data was generated and how was the data analyzed to justify why the chosen final
Project & Team
Selection solutions / improvements should be implemented ?
3.2.5.2 – What evidence showed that the justification was performed prior to the implementation of
the solution ?
2 1 Final Solutions to be implemented
Current Situation 2 Evidence that the justification
and Improvement - Final implementable solutions were decided based on the matrix was performed
Opportunity Analysis tabulated below
Method Increa Adjust Optimi Softe Oxyge Coal Optimizin Hot
sing ing ze Slag r n Inje g Cast Blast
3 CSR of Coke Compo Blowi Enrich ctio House Temp
Improvement Coke Screen sition ng ment n Operation eratu
Development Size Rate re
Expert
Consulta Y Y Y Y Y Y N Y
4 ncy
Implementation &
Result Verification Brainstor
Y Y N Y Y Y Y Y
ming
Correlati
N Y Y Y Y Y N Y
5 on Matrix
Sustaining &
Communicating Final
Y Y Y Y Y Y N Y Evidence of Brainstorming session and its
Results Decision
finalized MoM
© Copyright 2017 Tata Steel. All Rights Reserved 43
3
Improvement
Development
4
Implementation &
Result Verification
22
3.3.0 Project Management Update
1 3.3.1.2 – How were the stakeholders involved and / or communicated with during the solution /
Project & Team
Selection improvement phase of the project ?
2 2
Current Situation
and Improvement
Opportunity Analysis
3
Improvement
Development
4
Implementation &
Result Verification
5
Sustaining &
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 45
TRT Power Generation may Reduction of Generation Inreased Top Pressure and
Maintenance
reduced at softer blowing rates during pilot implementation Inlet pressure of TRT
4 Project Steering Committee None None None
Implementation & Internal Project Team None None None
Result Verification
Process Owner None None None
23
3.3.0 Project Management Update
1 3.3.1.4 – How was the appropriateness of the initial or updated team membership and management
Project & Team
Selection routines confirmed ?
4
2 Team Membership & Confirming Appropriateness Changes needed
Current Situation Management Routines
and Improvement
Opportunity Analysis
Team Membership • Project Charter Review – No Change required
Completion as per timeline
3
Improvement • Stakeholder Matrix Analysis –
Development Work done as per plan
Management Routines • Documentations were found No Change Required
4
in place
Implementation &
Result Verification • Procedures followed
• Proper Communication to all
5
stakeholders were evident
Sustaining &
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 47
24
4.1.0 Stakeholders consideration in Implementation
1 4.1.1.1 – How were the stakeholders involved in planning the solution/improvement implementation ?
Project & Team
Selection 4.1.1.2 – How were the stakeholders involved in implementing the solution / improvement ?
1 2
2
Current Situation
and Improvement
Opportunity Analysis
3
Improvement
Development
4
Implementation &
Result Verification
5
Sustaining &
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 49
4
Implementation &
Result Verification
5
Sustaining &
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 50
25
4.1.0 Stakeholders consideration in Implementation
1 4.1.2.1 – What was done to anticipate resistance before it occurred ?
Project & Team 4.1.2.2 – What types of resistance were actually encountered during the course of solution /
Selection
improvements implementation ? (2/2)
4.1.2.3 – How was the actual resistance identified ? (2/2)
2 1 2 3
Current Situation
and Improvement
Opportunity Analysis
3
Improvement
Development
4
Implementation &
Result Verification
5
Sustaining &
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 51
3
Improvement
Development
4
Implementation &
Result Verification
5
Sustaining &
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 52
26
4.1.0 Stakeholders consideration in Implementation
1
1 4.1.3.1 – How was the actual resistance addressed ? (2/2)
Project & Team
Selection 4.1.3.2 – How did the team know it was successful in addressing the resistance ? (2/2)
1 2
2
2 Current Situation
and Improvement
Opportunity Analysis
3
Improvement
Development
4
Implementation &
Result Verification
5
Sustaining &
Communicating
Results
© Copyright 2017 Tata Steel. All Rights Reserved 53
27
4.2.0 Solution / Improvement Implementation
1 4.2.1.1 – What process or systems were changed or created to implement the solution / improvement ?
Project & Team
Selection 4.2.1.2 – What systems were changed or created to measure and manage the performance of the
implementation ?
2
Current Situation Creation of New SOPs
and Improvement Increasing the Sampling frequency
Opportunity Analysis
Job Cycle Checks and Introduction of Modeling Software Enhancing the grinding system
updating the Old SOPs in Level 2 Automation : MOGADOR, Installation of Above
3 Burden Probe with
and Action Standards Burden Distribution Model Increasing the Size of laval tuyere
Improvement Gas analyser to
Development for higher injection
measure the Gas
Updating Daily
ASAM Testing of Adjusting the Composition across
Management
Burden Systems Processes screening rate in the radial pattern
4 Checklist and
documents stock house
Implementation &
Result Verification HOSIM Testing of Optimize the casting
Training Process
Burden rate to facilitate better
FMEA , Control Strengthened and
1 Implement Solution drainage
Plan and Risk change documents
5 Status Up- identified
Sustaining &
Communicating gradation 2
Measure / Manage the Implementation
Results
© Copyright 2017 Tata Steel. All Rights Reserved 55
28
4.3.0 Project Results
1
Project & Team
4.3.2.1 – What additional benefits were realized from the project ?
Selection
1 Additional Benefits Realized
Reduction of
Reduction from 1.52
Two additional Benefits were Carbon tCO2/thm to
2 Footprint 1.41tCO2/thm
Current Situation realized which were not
and Improvement anticipated earlier
Opportunity Analysis
3
Improvement Reduction of Steam
Reduction of Coke Rate Q - Reduction Reduction of Mean HM Si
Development Consumption from Steam of Mean HM
17,000 tons/month to Consumption Reduction Si from 0.84 to 0.72%
1600 tons/month
4
Implementation &
Result Verification
Increase of
5 Increase of Productivity Productivity
Sustaining &
Communicating from 2.65 to 2.72 t/m3/day
Results
© Copyright 2017 Tata Steel. All Rights Reserved 57
3
Improvement More Feathers were Becoming the Indian Benchmark
Soft Increased gave motivation to the team to
Development added to the cap of I BF Awards and
Morale of
– Recognitions, Awards Accolades Benefits drive for excellence and change –
Team
and Accolades Ripple Effect
4
Implementation &
Result Verification
Seeing the transformation of I Inspiration
BF other departments started to other
5 following the path of I BF – departments
Sustaining &
Communicating Sense of Pride to the Team
Results
© Copyright 2017 Tata Steel. All Rights Reserved 58
29
4.3.0 Project Results
1 4.3.2.3 – How do the actual additional benefits that were realized compare to the expected additional
Project & Team
Selection benefits identified in item 3.2.4 ?
3 Realization of Additional Benefits
Reduction of
2 Carbon
Current Situation All the four additional Footprint
and Improvement benefits were fully
Opportunity Analysis
realized
3
Improvement
Development Reduction of Q-
Steam
Coke Rate Reduction of
Consumption Reduction Mean HM Si
4
Implementation &
Result Verification
Anticipated and Fully
Realized
5 Increase of
Sustaining & Productivity
Communicating Not anticipated
Results realized
© Copyright 2017 Tata Steel. All Rights Reserved 59
30
5.1.0 Sustaining Results Over Time
1 5.1.1.1 – What was done to make sure the process or system changes made during the implementation
Project & Team
Selection
continued to be followed ?
5.1.1.2 –What evidence showed that this became part of the organization’s culture/operating strategy ?
1 Steps to ensure the changes to be 2 Evidence :
2 followed:
Current Situation
and Improvement
Opportunity Analysis Updating the SOPs and Action
Standards and subsequent
Steps for Successful
Training
Sustenance of the
3
Improvement
Improvement
Development
Updating the Daily Updation of SOP Training on the revised SOP
Management Documentation Process Failure Mode and Effect Analysis
4 Sl. No.
1
2
Document
Roles & Objective
Process Flow Chart
Revision History of DM Documents
Doc. No.
TQM/DM/R&O/001
TQM/DM/PFC/002
Revision No.
1
1
Date Reason
30.04.2014 As per BO&S and ABP of FY'15
30.04.2014 As per BO&S and ABP of FY'15
Department: I Blast Furnace
Date : 01.09.2016
Prepared by: Head Operations IBF
Rev. : 03
Implementation &
Failure bility Date
Requirements (Out of 10) (Out of 10) (Out of 10) AXBXC
4 Control Plan TQM/DM/CP/004 1 30.04.2014 As per BO&S and ABP of FY'15
5 KPI Tree IBF/DM/KPI/005 1 30.04.2014 As per BO&S and ABP of FY'15 40.I1 Fluctuation in Wind Volume 3 Online monitoring & follow up with supplier 5 135
6 KPI Tracker IBF/DM/KPI/006 1 30.04.2014 As per BO&S and ABP of FY'15 40.I2 Raw material quality(Sn-RDI, C-Ash,
3 Lab analysis 3 81 Information to supllier CR Opr w.i.e
P-SI)
Result Verification 7 Roles & Objective TQM/DM/R&O/001 2 15.01.2015 New format (Feedback of FY'15)
40.I3 Cooling water Flow 2 Online monitoring & follow up 3 54
subsequent communication
13 Roles & Objective TQM/DM/R&O/001 3 25.04.2015 As per BO&S and ABP of FY'16 quality
14 Process Flow Chart TQM/DM/PFC/002 3 25.04.2015 New process added Hot Metal Si (40.O1) Si < 0.44% 40.I9 Variation in agglomerate percentage 4 Bin level monitoring & adjustment in burden 2 72
15 PFMEA TQM/DM/FMEA/003 3 25.04.2015 New process added Hot Metal S (40.O2) Si >1.04%
Hot Metal 40.I10 High input moisture load 3 CRMT report and adjustment in fuel rate 3 81 Information to supllier CR Opr w.i.e
16 Control Plan TQM/DM/CP/004 3 25.04.2015 New process added 40.I11 %Sn in burden 2 Online monitoring 2 36
Temperature (40.O3)
17 KPI Tree IBF/DM/KPI/005 3 25.04.2015 New process added Furnace S >0.065% 40.I12 Oxygen Enrichment 5 Online monitoring 1 45
40 Slag Chemistry(MgO, MOU Non compliance 9
Operation 40.I13 Burden Distribution 4 Online monitoring 2 72 Information to supllier CR Opr w.i.e
18 KPI Tracker IBF/DM/KPI/006 3 25.04.2015 New process added Al2O3 & B2) (40.O4)
Coke Rate <440 40.I14 Low Sinter basicity 1 Online monitoring 1 9
5
19 Roles & Objective TQM/DM/R&O/001 4 15.09.2015 Audit guidline Coke Rate (40.O5)
kg/thm 40.I15 High Al2O3 in raw material 3 Online monitoring & follow up with supplier 2 54
Hearth liquid level
20 Process Flow Chart TQM/DM/PFC/002 4 25.04.2016 New process added (40.O6) 40.I16 Phosphorus in input raw material 3 Online monitoring(HM) & follow up with supplier 2 54
Sustaining &
21 PFMEA TQM/DM/FMEA/003 4 25.05.2016 New potential cause added 40.I17 Hot Metal Temperature 4 Online monitoring(HM) & follow up with supplier 2 54
22 Control Plan TQM/DM/CP/004 4 25.04.2015 New KPI added 40.P1 SLC 3 Online monitoring & follow up with supplier 3 81
40.P2 Coal Injection 4 RAFT set point and PV 4 144
23 KPI Tracker IBF/DM/KPI/006 4 25.04.2015 For FY'17 40.P3 RAFT 3 Furnace DP and K value at control room 5 135 SOP CR Opr w.i.e
24 Roles & Objective TQM/DM/R&O/001 5 15.04.2016 As per BO&S- FY'17 40.P4 water Circuit make up 2 Make up trend of cooling circuits in control room 5 90 SOP CR Opr w.i.e
Communicating 25
26
27
Roles & Objective
Process Flow Chart
PFMEA
TQM/DM/R&O/001
Updated PMFEA
40.P8 E H2 3 E H2 data from furnace overviw page 2 54
Results
28 Control Plan TQM/DM/CP/004 5 01.09.2016 New format 40.P9 Amount of dust dumped from dust
4 DM log sheet 2 72
29 KPI Tracker IBF/DM/KPI/006 5 01.09.2016 KPI & range revised catcher
40.P10 Heat Flux (Circuit#3 Heat Loss) 7 Heat flux data from staves structure page 1 63
kg/THM
Actual
427
PLAN
408
ABP 405 450 407 415 405 419 415 395 401 401 395 400 409
Opportunity Analysis Actual 390 363 392 356 345 337 355 339 346 334 348 336 353
Adding the Coke Rate and Its Reduce specific clay consumption lit/thm 0.63 0.55
ABP
Actual
ABP
0.55
0.63
7000
0.55
0.64
7000
0.55
0.60
7000
0.55
0.61
7000
0.55
0.71
7000
0.55
0.63
7000
0.55
0.54
7000
0.55
0.48
7000
0.55
0.50
7000
0.55
0.32
7000
0.55
0.26
7000
0.55
0.24
7000
0.55
0.51
7000
kg/THM
15000
35
7000
20
Actual
ABP
10635
20
14182
20
14136
20
15446
20
12357
20
5952
20
5417
20
6283
20
5577
20
4884
20
3904
20
4262
20
8586
20
Actual 22 22 29 18 15 13 25 16 20 11 23 12 19
3 ABP 45.4 43.8 47.0 50.2 47.0 47.0 47.0 53.3 43.8 43.2 47.0 47.0 46.8
Cost
Sustenance of the
Actual 42.0 38.9 40.0 37.0 39.0 42.0 35.0 43.0 42.0 38.9 41.0 43.0 40.2
31
5.2.0 Communication of Results
1 5.2.1.1 – How did the team communicate the results to the various stakeholder groups ?
Project & Team
Selection
1 Communication to Stakeholder
2 - TQM Council Meetings
Current Situation
and Improvement Suppliers - RM Quality Meeting
Opportunity Analysis - Monthly Report Circulation
32
Awards and Accolades
• Achieving the feat. of Indian Benchmark in Monthly Coke rate, coal Rate and carbon
footprint
• The Project was awarded in APEX Level by TQM Division
• Lauded by Senior Management and Ex Tata Steel Management and made them feel proud
of the achievement
• Won in Eastern region in Tata Groups Innovista Competition and represented in Tata Steel in
Finals of Innovista
33