Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Digest BATELEC

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

WRENDOLF C.

JUNTILLA
Natural Resources and Environmental Law
Case Digest 2
August 16, 2019

BATELEC V. ENERGY INDUSTRY ADMINISTRATION BUREAU (IEAB) (2004)


G.R. NO. 135925

Chico-Nazario, J.:
FACTS
BATELEC II is an electric cooperative authorized to distribute electric power
in Rosario, Province of Batangas. Puyat Steel Corporation (PSC) embarked to build
in Rosario, Batangas Province, its new plant.
In November 1997, PSC negotiated with BATELEC for supply of energy. As
the 69 kv transmission lines owned by the NPC are located about 1.4 kilometers
away from the plant, PSC and BATELEC II entered into an agreement wherein the
latter, not having any 69 kv transmission lines at present, shall handle the
construction of the needed 69 kv transmission lines.
In December 1996, BATELEC submitted Bill of Materials amounting to
P2,956,838.56 which PSC approved. BATALEC II vouched to complete the
installation by April 1997 but it failed, and the promise was never fulfilled even
after then.
So in November 1997, PSC then applied to direct connection with the NPC
before the EIAB. The Bureau made a determination that BATALEC was technically
and financially incapable to supply said 69 kv. Eventually, in March 1998, the
Bureau approved PSC’s application.
RTC issued TRO enjoining BATELEC II to desist from committing acts that
would prevent the supply of electric power from NPC to PSC. BATELEC filed
petition for certiorari before the CA. But CA denied the petition.

ISSUE AND RULING


(1) IS IT NPC AND NOT BATELEC II THAT SHOULD SUPPLY POWER TO PSC?
BATELEC II:
NPC is disqualified because PSC plant is located within the franchised area
of BATELEC II. Moreover, NPC is mandated by law to generate and transmit
electric power but not distribute it directly to the consumers like

1
respondent PSC. Invokes National Power Corporation v. Cañares where the
Court stated that the national policy is that if the power franchise holder
can adequately supply the power requirement of industries-consumers at
rates that the latter can obtain from NPC, direct connection with NPC is not
favored.
Supreme Court:
There is nothing in the provisions of Presidential Decree (P.D.) No. 395,
amending P.D. No. 380 and further amending Rep. Act No. 6395,
entitled "An Act Revising the Charter of the National Power
Corporation," which expressly or impliedly allowed or sanctioned the sale in
bulk by the NPC of energy direct to BOI-registered enterprises, such as
respondent PSC, even if it would be violative of the rights of existing
franchise holders.
In other words, the Court, in Cañares, disposed  that the policy of
preference to the franchise holder is premised on the condition that such
franchise holder must in the first place be capable of supplying
adequately the power requirements of the BOI-registered customer and
that such capability must first be ascertained through a hearing in due
course.
The Bureau made the distinct finding that petitioner is not technically and
financially capable of satisfying the power requirements of PSC. This
determination by the Bureau, an administrative government agency which
is tasked to implement a statute, is accorded great respect and ordinarily
controls the construction of the courts.
Finally, we draw attention to the fact that petitioner had the first bite to
service the power needs of respondent PSC, but BATELEC II blew its chance
by reneging on its commitment with PSC.

DOCTRINE
(1) Exclusivity in any public franchise is not highly favored and the rights and
responsibilities are construed without favor to the grantee.

Exclusivity of any public franchise has not been favored by this Court such
that in most, if not all, grants by the government to private corporations,
the interpretation of rights, privileges or franchises is taken against the
grantee. Thus in Napocor v. Court of Appeals and Cagayan Electric Power
and Light Co., Inc.,the Court was most emphatic:

… Exclusivity is given by law with the understanding that the


company enjoying it is self-sufficient and capable of supplying the

2
needed service or product at moderate or reasonable prices. It would
be against public interest where the firm granted a monopoly is
merely an unnecessary conduit of electric power, jacking up prices as
a superfluous middleman or an inefficient producer which cannot
supply cheap electricity to power intensive industries…

The delay caused by petitioner in delivering power supply to PSC translates


to higher costs on its part., i.e., cost of borrowing and lost sales, which
ultimately leads to higher prices of its products to the purchasing public.

Mindful that it is in the public interest when industries dependent on heavy


use of electricity are given reliable and direct power at the lower costs,
thus, enabling the sale of nationally marketed products at prices within the
reach of the masses, the Court in the case at bar, finds no compelling cause
to pronounce any merit in this petition.

You might also like