Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Culvert Design

Download as pdf or txt
Download as pdf or txt
You are on page 1of 27

DESIGN MANUAL FOR ROADS AND BRIDGES

VOLUME 4 GEOTECHNICS AND


DRAINAGE
SECTION 2 DRAINAGE

PART 7

HA 107/04

DESIGN OF OUTFALL AND CULVERT


DETAILS

SUMMARY

This Advice Note gives guidance on detailing of outfall


structures to highway drainage systems and design of
culverts including scour and hydrology but excluding
hydraulic design.

INSTRUCTIONS FOR USE

This is a new document to be inserted into the manual.

1. Remove Contents page from Volume 4.

2. Insert new Contents page for Volume 4 dated


November 2004.

3. Insert HA 107/04 into Volume 4, Section 2.

4. Please archive this sheet as appropriate.

Note: A quarterly index with a full set of Volume


Contents Pages is available separately from The
Stationery Office Ltd.

November 2004
DESIGN MANUAL FOR ROADS AND BRIDGES HA 107/04

THE HIGHWAYS AGENCY

SCOTTISH EXECUTIVE

WELSH ASSEMBLY GOVERNMENT


LLYWODRAETH CYNULLIAD CYMRU

THE DEPARTMENT FOR REGIONAL DEVELOPMENT


NORTHERN IRELAND

Design of Outfall and


Culvert Details

Summary: This Advice Note gives guidance on detailing of outfall structures to highway
drainage systems and design of culverts including scour and hydrology but
excluding hydraulic design.
Volume 4 Section 2
Part 7 HA 107/04 Registration of Amendments

REGISTRATION OF AMENDMENTS

Amend Page No Signature & Date of Amend Page No Signature & Date of
No incorporation of No incorporation of
amendments amendments

November 2004
Volume 4 Section 2
Registration of Amendments Part 7 HA 107/04

REGISTRATION OF AMENDMENTS

Amend Page No Signature & Date of Amend Page No Signature & Date of
No incorporation of No incorporation of
amendments amendments

November 2004
DESIGN MANUAL FOR ROADS AND BRIDGES

VOLUME 4 GEOTECHNICS AND


DRAINAGE
SECTION 2 DRAINAGE

PART 7

HA 107/04

DESIGN OF OUTFALL AND CULVERT


DETAILS

Contents

Chapter

1. Introduction

2. Highway Drainage Outfalls

3. Outfall Details

4. Culverts: Introduction

5. Culverts: Location and Layout

6. Culverts: Flood Estimation

7. Culverts: Scour Issues

8. Culverts: Screen Details

9. Culverts: Environmental Aspects

10. Culverts: Maintenance Issues

11. References and Bibliography

12. Enquiries

Appendix A: Construction Details

Appendix B: Pipes and Culverts Having Diameter or


Span Exceeding 900mm

Appendix C: Culvert Alignment Options

Appendix D: Legal Aspects for Right of Access and


Responsibilities for Maintenance

November 2004
Volume 4 Section 2 Chapter 1
Part 7 HA 107/04 Introduction

1. INTRODUCTION

General Scope

1.1 This Advice Note gives guidance on detailing of 1.6 The principles outlined in this Advice Note apply
outfall structures to highway drainage systems and to all schemes on trunk roads including motorways.
design of culverts including scour and hydrology but They may also be applied generally to other new
excluding hydraulic design. Advice on the hydraulic highway schemes and by other highway authorities for
design of culverts is given in Chapters 5 and 6 of CIRIA use during the preparation, design and construction of
Report 168: Culvert Design Guide (Ref 1). The advice their own comparable schemes.
given in this Advice Note relates to adapting the
guidance, given in the CIRIA document, specifically for Implementation
highway applications. Although the advice should be
fully taken into account in the design of new schemes
1.7 This Advice Note should be used forthwith for all
(see 1.7), this Advice Note contains no mandatory
schemes currently being prepared provided that, in the
requirements.
opinion of the Overseeing Organisation, this would not
1.2 Investigations, following the large scale flooding result in significant additional expense or delay
that occurred over much of England during the Autumn progress. Design Organisations should confirm its
and Winter 2000, showed that some of the drainage application to particular schemes with the Overseeing
outfalls suffered from submersion. Maintenance during Organisation.
these conditions, in particular screen clearing, proved
problematical and in some circumstances posed a
serious hazard to the safety of operatives.

1.3 This Advice Note contains guidance on the


construction of outfalls from highway drainage systems
to, principally, natural channels, watercourses, or
purpose made drainage channels. It is not applicable to
the outlets of edge of pavement run-off discharges to a
piped drainage system. Advice given in HA 78, Design
of Outfalls from Surface Water Channels (DMRB 4.2)
(Ref 2) is not relevant to the outfalls within the scope of
this document.

1.4 The guidance given in this Advice Note


supplements the guidance given in the CIRIA Report
168 on the design of culverts and is applicable to those
constructed as part of highways works. In assessing the
hydraulic design, reference should be made to Chapters
5, 6 and 7 of the CIRIA report, except that for flood
estimation purposes, reference should be made to the
formulae in the Flood Estimation Handbook, FEH,
(Ref 4).

1.5 The advice contained here does not apply to the


design of flood alleviation culverts. Where a highway is
constructed across a floodplain, HA 71: The Effect of
Highway Construction on Floodplains (DMRB 4.2),
should be consulted.

November 2004 1/1


Volume 4 Section 2 Chapter 2
Part 7 HA 107/04 Highway Drainage Outfalls

2. HIGHWAY DRAINAGE OUTFALLS

General from the drain occurs before that in the watercourse. It


may therefore be necessary to protect the bed and banks
2.1 The term outfall is applied to the point where the from scour, (see Chapter 3).
highway drainage system discharges into a different
type of drainage system. This may be a sewer, ditch or 2.7 It is possible that during periods of prolonged
watercourse. For the purposes of this Advice Note, heavy rainfall the flow in the receiving watercourse
outfalls are to either ditches or receiving watercourses. may rise above the invert level of the drain. The design
of the highway drainage system should therefore be
2.2 Where the outfall is to a watercourse, the assessed to investigate the effects of a drowned outlet.
arrangement detail should be determined in consultation
with the relevant environmental protection agency as 2.8 If recent flooding has been experienced, then data
follows: relating flow depth in the channel to flow rate may be
available. The designer should be aware of the accuracy
(a) England and Wales - Environment Agency (EA); of such information and also the difference between the
calculated design flow and the flow depth obtained
(b) Scotland - Scottish Environmental Protection from the recorded data.
Agency (SEPA); or
2.9 The water surface profile can be calculated from
(c) Northern Ireland - Rivers Agency (RA). the backwater length formula:

Lbw = 0.7D/s
Outfall to Ditch
where D is the bank full depth and s is the slope of the
2.3 The ditch will probably drain the carriageway, water surface (or bed surface where that of the water is
verge and the adjacent unpaved area. However, water unavailable). The designer should refer to the CIRIA
from the highway drainage system is likely to discharge Report 168 (Ref 1) Boxes 8.1 and 8.2 for worked
to the ditch long before that from the adjacent land, the examples on the normal calculation method and the
time of concentration being a matter of minutes for the backwater calculation method respectively, and HA 71
highway drain and hours for the adjacent unpaved Chapter 5: Hydraulic assessment of existing water
areas. levels (DMRB 4.2).
2.4 Outfalls to ditches and watercourses will 2.10 Typical Manning’s n values for channel
generally be either from individual pipes or the outlet roughness are tabulated in Table 2.1. This table is more
from an upstream system. Individual pipe outlets can be comprehensive than that forming Table D3 of the
formed from concrete bagwork in accordance with CIRIA Report 618 and it is recommended that designers
Clause 519 of the SHW (MCHW 1), brickwork, cast in use Table 2.1 values in their calculations.
situ concrete, pre-cast concrete units, or other suitable
proprietary products. Typical details are shown as
Figure A1 and Figure A2 in Appendix A.

2.5 The components of the outfall structures are


described in greater detail in Chapter 3.

Outfall to Watercourse

2.6 It is important to determine the top water levels


of the receiving watercourse both in dry and wet
weather conditions. The highway pavement is much
more responsive to rainfall run-off than the surrounding
natural catchment so, generally, the peak discharge

November 2004 2/1


Chapter 2 Volume 4 Section 2
Highway Drainage Outfalls Part 7 HA 107/04

2.11 The use of Ordnance Survey maps to determine


Natural Stream Min Normal Max
watercourse channel gradients should be sufficient,
Lowland Streams
however accurate cross-sectional dimensions will be
1. Clean, straight, full stage, no 0.025 0.030 0.033 necessary.
rifts or pools
2. As above with more stones 0.030 0.035 0.40
Outfall Design
and weeds
3. Clean, winding, some pools 0.033 0.040 0.045
and shoals
2.12 Determine or estimate the top water level in the
receiving watercourse channel for the design storm used
4. As above with some weeds 0.035 0.045 0.050
for the design of the highway drainage system, (HD 33
and stones
DMRB 4.2). The invert level of the outfall pipe should
5. As above, lower stages, more 0.040 0.048 0.055 be at or above this level.
ineffective slopes & sections
6. As 4 above with more stones 0.045 0.050 0.060 2.13 The top water level of the receiving watercourse
7. Sluggish reaches, weedy, 0.050 0.070 0.080 should then be assessed for more intense storms than
deep pools used to design the drainage system and compared with
8. Very weedy reaches, deep 0.075 0.100 0.150 the levels of the proposed design. A 1 in 30 year storm
pools & heavy timber stand profile is recommended. Under these conditions the
Mountain Streams outfall should not become submerged nor should there
1. Bottom: gravels, cobbles, 0.030 0.040 0.050 be a risk of water flowing back into the drainage
and few boulders system. If this occurs during the design of a new
highway drainage system then redesign of the system is
2. Bottom: cobbles with large 0.040 0.050 0.070
required. This should also be considered when
boulders
improving existing systems but improvement may not
Excavated Channel
always be feasible.
1. Gravel, straight uniform, 0.022 0.030 0.033
clean 2.14 Should the outfall pipe be partially submerged
2. Straight, uniform, short grass 0.022 0.027 0.033 under these conditions, then the diameter of the outfall
and weeds length of pipeline may be increased to allow a greater
3. Winding and sluggish, grass 0.025 0.030 0.033 volume of flow to pass. The part-full flow
some weeds characteristics of the partially submerged pipes should
4. Winding, sluggish, dense 0.030 0.035 0.040 be assessed using the Tables for the Hydraulic Design
weeds or plants in deep of Pipes, Sewers and Channels (Ref 8).
channels
5. Winding, sluggish, earth 0.028 0.030 0.035
bottom, rubble sides
6. Winding, sluggish, stony 0.025 0.035 0.040
bottom, weedy banks
7. Winding, sluggish, cobble 0.030 0.040 0.050
bottom, clean sides
8. Dredged light brush on 0.035 0.050 0.060
banks
9. Rock smooth and uniform 0.025 0.035 0.040
10. Rock jagged and irregular 0.035 0.040 0.050
Unmaintained excavated
channel, weeds/brush uncut
1. Dense weeds, high as flow 0.050 0.080 0.120
depth
2. Clean bottom, brush on both 0.040 0.050 0.080
sides
3. As 2, highest stages of flow 0.045 0.070 0.110
4. Dense brush, high stage 0.080 0.100 0.140

Table 2.1: Typical values for Manning’s “n”

2/2 November 2004


Volume 4 Section 2 Chapter 3
Part 7 HA 107/04 Outfall Details

3. OUTFALL DETAILS

General 3.8 Headwalls may be constructed from either


brickwork or reinforced concrete both having a
3.1 How the outfall is constructed and the details that reinforced concrete apron. Brickwork for headwall
need to be considered depend on the size of the construction shall be in accordance with SHW Clause
watercourse and also the range of flow depths within 507.3. Headwalls to pipes discharging to ditches may
the watercourse. In some instances the highway drain also be formed from concrete bagwork in accordance
may be the major contributor of water to the channel. with SHW Clause 519, (see Chapter 2 and Figure A2).

3.2 The outlet pipe should, wherever practical, be Security Screens


directed to discharge in the general direction of flow in
the receiving watercourse (see Figure A1). Discharge at 3.9 Security screens to the outlet pipe are
right angles to the direction of flow should be avoided recommended where there is a risk of access to the
if at all possible. The outlet should never discharge drainage system by children and the pipe is of diameter
against the oncoming flow. greater than 375mm. The screen should comprise mild
steel flat section welded to form the screen and hot dip
3.3 Consideration should be given to the provision of galvanised (see Figure A5).
scour protection to the opposite bank. Where the outfall
is at an angle greater than 45o to the direction of flow 3.10 The screen should be positioned so that the
then scour protection should be provided. maximum angle to the horizontal is 60o and ideally it
should be 45o. A flat section at the top of the screen
3.4 Scour protection to the watercourse bed may also should be provided to facilitate clearing. The screen
be necessary where the flows in the watercourse are should be securely fixed to the headwall using locking
low, even during storm conditions, relative to the nuts.
volume and velocity of the highway drainage discharge
(see Chapter 7).
Flap Valves
Headwall
3.11 Flap valves prevent the back flow of water from
the receiving watercourse into the highway drainage
3.5 The outlet structure should be designed taking systems. Their presence may cause a significant head
account of relevant environmental protection agency loss to the discharge flows and hence the capacity of the
recommendations. Ideally the invert of the outfall pipe
latter sections of the system. An allowance should be
should be at or close to the top water level of the
made during the hydraulic design. Where any pipeline
receiving watercourse to prevent submersion during is at risk of being submerged by the flows in the
storm conditions (see 2.7). watercourse or where the drainage system discharges to
a tidal reach, then a flap valve may be installed. The
3.6 Where the velocity of the peak outflow is in
designer should assess the possible adverse effects that
excess of 1.0 m/s then some form of energy dissipation
may arise due to the use of a flap valve.
will be required (see Figure A3 and 3.13). The pipe line
design should be checked to ensure that velocities at 3.12 Where the outlet may be accessible to members
peak discharge do not exceed 1.4 m/s. Where higher of the public, coplastics (composite plastic) valves
velocities occur and cannot be reduced within the rather than cast or ductile iron may be less susceptible
drainage system, the advice of the Overseeing to vandalism.
Organisation should be sought.

3.7 The headwall should be keyed into the banks and


bed to prevent erosion. The apron should have a vertical
toe that extends 500mm below the bed of the receiving
watercourse. This is to reduce the risk of scour
undermining the structure (See Chapter 7).

November 2004 3/1


Chapter 3 Volume 4 Section 2
Outfall Details Part 7 HA 107/04

Energy Dissipation

3.13 The velocity of the flow within the highway drain


may be sufficient to cause erosion of the bed and bank
of the receiving watercourse. This is more likely to
occur where the gradient of the highway drain is steep
and/or where the peak volume of the flow within the
highway drain is similar to or greater than that of the
receiving watercourse. Note that the peak rate of
discharge from the highway drain will usually occur
well before the peak flow rate of the watercourse.

3.14 Where the peak discharge velocity of the


highway drain is in excess of 1.0 m/s, some form of
energy dissipation will be required. The relevant
environmental protection agency should be consulted as
to the preferred method for the particular watercourse.

3.15 The two principle types are:

• Stilling basin: see Figure A3, is the preferred


option from a maintenance aspect although this
requires a longer structure and hence its use may
be precluded due to land take considerations.

• Concrete baffle blocks: see Figure A4, uses


concrete blocks or teeth cast on to the apron to
interrupt the flow and hence dissipate energy.
Stone blocks may be used in preference to
concrete. There is a maintenance issue in that the
blocks will trap debris, especially from the
watercourse.

3.16 It is often appropriate to reinforce the


watercourse bank opposite the point of discharge in
order to reduce the risk of erosion. Concrete revetment
or stone pitching are the preferred methods rather than a
wall or stone gabions. The relevant environmental
protection agency should be consulted to ensure use of
the most appropriate method.

3.17 Stone pitching or concrete revetment may be


appropriate where there are low flow volumes or
velocities in the receiving watercourse during dry
conditions. Again the relevant environmental protection
agency should be consulted.

3/2 November 2004


Volume 4 Section 2 Chapter 4
Part 7 HA 107/04 Culverts: Introduction

4. CULVERTS: INTRODUCTION

General section will offer greater flow area than a circular pipe
without compromising the cover to the structure.
4.1 The following features are considered good
practice: Pipe Culvert

(i) Adequate size to ensure that design flows are 4.5 Pipe culverts are more applicable to highway
accommodated without surcharge and that debris drainage systems, ditch courses and small watercourses.
can pass through the culvert. Concrete pipes are not normally available in diameters
greater than 2.4 m. Helically wound plastic pipes can be
(ii) No changes of direction within the culvert or manufactured to greater diameters. Helically wound
steps in the invert. corrugated steel pipes are available up to 4.0m in
diameter.
(iii) Constant gradient through the culvert,
maintaining the gradient of the watercourse. 4.6 However large diameter pipes may be
inappropriate for use as highway culverts when the
(iv) Self cleansing, to ensure that no silt is deposited. watercourse is wide and shallow and the carriageway
level is similar to that of the adjacent natural terrain.
(v) Free from internal fittings that may snag debris.
4.7 Culverts longer than 12m should be a minimum
(vi) Accommodates wildlife and fish migration.
of 1.2m in diameter to facilitate access for maintenance.
(vii) Is aesthetically complementary to the adjacent Culverts with diameters of 900mm, and above are
surroundings. classified as structures (Series 2500, MCHW)
(see Table B1 of Appendix B). The minimum culvert
(viii) Presents no safety hazard to maintenance workers diameter should be 450mm as smaller sizes are prone to
or the public. blockage.

(ix) Lowest whole-life costs. 4.8 All plastic pipes are designed to be flexible and
therefore rely on the resistance of the surrounding fill to
4.2 Culverts for conveying a watercourse from one achieve their structural integrity. The likely method of
side of the carriageway to the other have greater design construction of the surrounding material such as an
requirements than those forming part of the highway embankment should be considered during the design.
drainage system. Most of the foregoing conditions are Where plastic pipes in excess of 900mm are proposed,
also applicable to highway drainage culverts, however these may be at a greater risk of vandalism.
due to the fluctuating nature of flows, deposition of silt
is inevitable. The collection of debris is also more likely Box Culvert
and hence trash screens should be considered as a
means of reducing this risk, (see Chapter 8). The 4.9 These may be either cast in situ concrete or pre-
diameters of this type of highway drainage culvert tend cast concrete units and used as either single or multiple
to be small and hence access for maintenance should be bores.
incorporated into the design, (see Chapter 10).
4.10 The joints between pre-cast concrete units can be
Culvert Shape difficult to seal and make watertight. The risk of
exfiltration into embankment foundations should be
4.3 Culverts can be Circular, Rectangular box, Piped considered during the culvert design. If there is a
arch, Arch or Complex, see Table A1. significant risk of water from leaking joints either
softening or washing away the highway foundation,
4.4 Cover beneath the carriageway and the top of the then the designer should consider an alternative form of
pipe is an important factor influencing the choice of pipe system.
culvert type. Where cover is limited a rectangular

November 2004 4/1


Chapter 4 Volume 4 Section 2
Culverts: Introduction Part 7 HA 107/04

4.11 Pre-cast concrete box culverts are manufactured providing cut-waters between the pipes at the culvert
in sizes from 900mm x 900mm up to 6.0m x 6.0m, as in entry. BD 12 (DMRB 2.2) Chapter 15 requires multiple
Table A1 of Appendix A. The minimum size of box corrugated steel arches to be separated by a minimum
culvert may be appropriate for use on highway schemes of 1m.
but the designer should be aware of the freeboard
requirements (see 6.13) and also the need for 4.20 Composite structures incorporate a separate
maintenance access. channel section within the invert of the culvert. This
can be by forming a cast in situ base with a channel in
4.12 Culverts should be designed to be free flowing. the invert or by forming a shelf to one side, see
Culverts on larger streams and rivers should be Table A1 (Appendix A).
designed to accommodate 600mm freeboard (the
difference between the top flood water level and the 4.21 Alternatively the culvert may be constructed with
culvert soffit) to allow floating debris to pass through. a depressed channel invert filled with gravel. This will
be more suitable for allowing the passage of fish.
Pipe Arch
4.22 In particular situations a gravel filled invert can
provide additional capacity during severe flow
4.13 Formed from corrugated steel, piped arches can conditions as the gravel will tend to be scoured out
provide an efficient structural and hydraulic solution. thereby increasing the capacity of the channel. Note
The design of corrugated steel culverts should be that the displaced gravel will be deposited downstream,
undertaken in accordance with Series 2500 Special causing additional maintenance to be undertaken if
Structures of the SHW and BD 12 (DMRB 2.2). hydraulic performance downstream is to be maintained.
4.14 Corrugated steel structures may be constructed 4.23 There are maintenance implications wherever
up to 8.0m span to BD 12 standard. The ends of the gravel filled inverts are constructed and the designer
structure should be shaped to the ground profile of the should ensure that their whereabouts are inserted into
embankment negating the need for inlet and outlet the asset database and recorded in the health and safety
structures. A structural ring is still required as scour plan.
protection unless the bed level is high.

Complex Structures

4.15 These may be multiple barrel structures or single


barrel with a composite invert incorporating, for
example, a dry weather channel.

4.16 Multiple barrel culverts may be appropriate


where there is limited headroom due to relative
carriageway and channel levels or where the channel
profile is particularly wide. Where the channel
cross-sectional area is greater than 5m2 multiple bores
should be considered.

4.17 To avoid problems associated with low flow


velocities, such as silt deposition, that may occur due to
significant variations between dry and wet weather
flows, it may be desirable to restrict dry weather flows
to a single channel.

4.18 Multiple barrels also give the opportunity to


divert flows into a single barrel to facilitate
maintenance.

4.19 There will be a hydraulic head loss at the inlet to


a multiple barrel structure that may be minimised by

4/2 November 2004


Volume 4 Section 2 Chapter 5
Part 7 HA 107/04 Culverts: Location and Layout

5. CULVERTS: LOCATION AND LAYOUT

General 5.5 Off-line construction has advantages of


maintaining the existing channel flows and working in
5.1 The position of a culvert is dependent on its the dry. However diversion of the watercourse through
intended purpose. Although often used for traversing a the new culvert may require the introduction of short
watercourse in place of a bridge, culverts are also used radius bends, particularly where the culvert crossing is
to facilitate crossings of ditches or to transfer the close to 90o to the carriageway.
drainage run from one side of the carriageway to
another. 5.6 The introduction of bends will probably result in
either erosion of the bank on the outside of the bend or
5.2 Culverts to streams or small rivers are of silt deposition on the inside. Watercourse training
necessity larger than those to channels that form part of works may entail significant structures, either
the highway drainage system. The transition from independent of the culvert or forming part of it. Where
watercourse to culvert should take account of the possible these structures should be avoided and the
existing landscape features to ensure that the culvert guidance given in HA 81: Nature Conservation Advice
and structures are not visually intrusive, see DMRB 10, in Respect of Otters (DMRB 9.1) followed.
Part 1, Chapter 22.
5.7 Option 3 shown in Figure C1 of Appendix C
probably offers the better solution, being off-line but
Culvert Alignment
minimising deviation of the channel alignment. The
advice in Chapter 4 should be followed with regard to
5.3 The alignment of the culvert relative to that of the length of the culvert.
the road should aim to minimise its length. Ideally the
crossing would be as direct as possible. However there 5.8 Whichever option is chosen, the designer should
are a number of factors to be considered, see ensure that access for maintenance can be readily
Appendix C, Figure C1: obtained and that the area both upstream and
downstream of the culvert provides sufficient space for
• maintenance of channel flows during the maintenance activities to take place.
construction;

• effects on the watercourse of realignment; Ditch Culverts

• scour or sedimentation problems; 5.9 A typical example of a ditch culvert would be


where the highway drainage ditch at the edge of a rural
• design and cost of river training works; trunk road is crossed by a field access. The flows in the
drainage system will tend to be low both in volume and
• maintenance access and working area. velocity and the channel will also be relatively shallow.
5.4 A culvert constructed along the line of an 5.10 The culvert in this location will be short,
existing watercourse is the better option for maintaining generally a pipe of moderate diameter and have a
existing hydraulic conditions. However the problems minimal cover. It will also be prone to obstruction by
associated with on line construction must be addressed vegetation growth.
during the design stage, and the options are, briefly:
5.11 The pipe should be designed to accommodate the
• pumping or temporary channelling of the design peak flow in the channel without surcharging,
watercourse; ideally having a greater capacity to allow for sediment
deposition within the bore. Advice on channel design is
• removal of the channel bed and in-filling of soft given in HA 106: Drainage of Runoff from Natural
spots. Care must be taken during construction to Catchments (DMRB 4.2). The invert of the pipe culvert
ensure that there is no localised settlement of the should ideally be at least 75mm below the bed of the
culvert. channel. This is to ensure that water does not pond in

November 2004 5/1


Chapter 5 Volume 4 Section 2
Culverts: Location and Layout Part 7 HA 107/04

front of the culvert. There are a number of features to Culverts to Larger Watercourses
take into account at this point:
5.13 Culverts constructed in floodplains should also
(i) The sides of the ditch channel should be higher meet the requirement of HA 71: The Effects of
than the soffit of the culvert pipe. Highway Construction on Floodplains (DMRB 4.2).
(ii) The headwall to the culvert should extend into 5.14 Culverts to large watercourses such as rivers are
the banks of the ditch over the full depth. The likely to be multiple barrel due to the relative width of
headwall may be a simple brick structure, cast in the channel to the depth of the structure, (see 4.15).
situ reinforced concrete or concrete bagwork. All
should be adequately founded below the invert of 5.15 The culvert invert should be set below the bed
the channel to prevent ingress of water and level by around 25% of the pipe diameter or not less
consequent erosion. than 150mm for other structures.
(iii) A small concrete apron should be constructed in
front of the headwall to suppress vegetation
growth immediately upstream of the inlet, and
ideally also at the outlet. On small diameter
culverts, this can be simply achieved using pre-
cast concrete paving slabs.

(iv) Screens to pipes of 600mm or less should not be


necessary in rural locations, however in urban
areas there is a greater risk of children entering
the culvert.

(v) Ensure that the pipe has adequate cover and is of


the appropriate class. Reference to HA 40:
Determination of Pipe and Bedding
Combinations for Highway Drainage (DMRB
4.2), the Simplified Tables of External Loads on
Buried Pipelines (Ref 5) and A Guide to Design
Loadings for Buried Rigid Pipes (Ref 6).

(vi) The height of the headwalls should adequately


support the fill material over the culvert pipe.

Carriageway Crossings

5.12 The alignment of the carriageway relative to the


watercourse can have a significant effect on the design
of the culvert. The length of the culvert should be kept
as short as possible for reasons of:

(i) hydraulics;

(ii) cost;

(iii) habitat migration;

(iv) ease and effectiveness of maintenance.

5/2 November 2004


Volume 4 Section 2 Chapter 6
Part 7 HA 107/04 Culverts: Flood Estimation

6. CULVERTS: FLOOD ESTIMATION

General catchments, areas greater than 0.5 km2 (50 Ha), the
formulae in the FEH (Ref 4) should be used but for
6.1 This Advice Note is not intended to set out the small catchments, measuring less than 50 Ha (hectares)
procedures for the hydraulic design of culverts, then the procedures for small catchments in HA 106
but aims to supplement the guidance given in CIRIA Drainage of Runoff from Natural Catchments, (DMRB
Report 168 (see 1.4) by giving specific guidance on 4.2) should be followed. Note that HA 106 contains
aspects of culvert design that should be taken account guidance on the use of both methods.
of in the design process.
Afflux
6.2 Culverts beneath highways tend to be relatively
short but may have to accommodate restrictions 6.7 This is defined as the increase in the depth of
imposed by carriageway alignment and road water at the upstream end of the culvert due to the
construction, ie. cover to the top of the culvert. The constriction of the flow width. The allowable afflux
presence and probable size of culverts must be should be determined in consultation with the relevant
determined early in the highway design process. environmental protection agency or relevant drainage
authority.
6.3 The design of the culvert should be appropriate
for the life of the structure. Lower flow velocities 6.8 The depth of flow is a function of the
through the culvert require proportionally greater spare cross-sectional area and hence a reduction in channel
capacity. The design should consider measures to width will result in a corresponding increase in
increase the flow velocity through the structure in these upstream flow depth and velocity.
instances.

6.4 The capacity of the culvert should be designed to Scour Protection


accommodate flows which are anticipated to have
between a 1% and 4% risk of occurring annually. The 6.9 The outlet in particular will need to be protected
anticipated flood frequency should be agreed with the from the effects of scour, principally, the erosion of the
relevant environmental protection agency, whose downstream bed. By providing an apron to the outlet,
requirements are normally those shown in Table 6.1 turbulence caused by the transition from culvert to
Flood return periods. channel may be contained. Providing scour protection
beyond the apron will minimise any risk of scour
1 in 100 years Urban areas and villages downstream of the structure, (see Chapter 7).

1 in 50 years Agricultural land of high value 6.10 Scour to the inlet may also occur especially
and isolated properties where there is a change of alignment between the
stream and the culvert. Scour here can undermine
structural integrity.
1 in 25 years Agricultural land (minimum
level of protection)
Tail Water Effects
Table 6.1 Flood return periods
6.11 The tail water depth is the depth of water above
6.5 The maximum discharge velocity under design the culvert invert at the outlet. For free flow conditions
flood flow conditions should not exceed 1.2 m/s unless the tail water depth should be less than the diameter or
erosion protection is installed (see 6.9). vertical dimension of the culvert.

Estimating the Flood 6.12 If the tail water level rises above culvert soffit,
the system will operate under surcharged conditions.
The design must be checked to ensure that the correct
6.6 Before estimating the design flood, the Mean
procedures in CIRIA 168 are followed.
Annual Flood (MAF) should be calculated. For large

November 2004 6/1


Chapter 6 Volume 4 Section 2
Culverts: Flood Estimation Part 7 HA 107/04

Freeboard

6.13 This is defined as the height of the culvert soffit


over the flood water level. Where the culvert is located
on a watercourse that, in England and Wales, is
classified as “Main River”, by the Environment Agency,
a minimum freeboard of 600mm is normally required.
This will enable the passage of large, floating debris
through the culvert. Elsewhere, the designer should
ascertain the requirements of the relevant
environmental protection agency.

6.14 For smaller culverts, a freeboard of 300mm


should be adequate. For freeflow conditions, i.e. when
neither the inlet nor the outlet of the culvert is
submerged at peak design flow, a rough guide is that the
freeboard should be D/4 where D is the diameter for
circular culverts or height, for non-circular.

6/2 November 2004


Volume 4 Section 2 Chapter 7
Part 7 HA 107/04 Culverts: Scour Issues

7. CULVERTS: SCOUR ISSUES

Estimation of Scour Depths 2D Jets

7.1 Flow from outfalls or culverts will generally have Scour Depth
a higher velocity than that of the receiving watercourse
and this can result in erosion of the bed and banks of
the receiving channels. When the depth and/or extent of 7.3 Use the equation due to Hoffmans (1997)
the scour hole is such that it undermines the (Ref 11):
foundations of the outfall structure or its outlet wing
walls, structural damage can occur leading to collapse.
§ 50 · § U ·
Measures are usually necessary to minimise this risk y s = ¨ ¸ ¨¨1 − 2 ¸¸ y1
and can be grouped into the following categories © k ¹ © U1 ¹
(CIRIA Report 168, 1997, gives examples of good
practice) (Ref 1):
where ys is the depth of scour below the invert of the
• Optimisation of layout (in plan, where possible, culvert (in m), y1 is the vertical thickness of the jet
the discharge of the outfall or culvert should be (in m), U1 is the depth-averaged velocity in the jet and
angled in the downstream direction at about 45o). U2 is the depth-averaged velocity in the receiving
channel (both in m/s). k is a non-dimensional scour
• Introduction of outlet arrangements (for example factor dependent on the d90 size of the sediment (for
angled wing walls help expand the flow in a which 90% of the material by weight is fines) in the
gradual manner). channel bed (in mm) and is defined as:
• Inclusion of energy dissipation devices (these
k = 2.95 d 90
1/ 3
for 0.1mm <d90< 12.5mm
may be needed for steep outfalls or culverts and
may consist of baffles across the outfall structure k = 6.85 for d90 > 12.5mm
or of stilling basins for larger, high energy
culverts).
Scour Extent
7.2 The potential for scour should be assessed for all
outfall structures. Formulae for estimating maximum 7.4 The overall length of the scour hole can be
scour depths are given in CIRIA Report C551 (Ref 10), estimated to be 5 to 7 times the scour depth.
among other publications. The maximum scour depth
should be determined for the natural bed material and 3D Jets
then compared with the depth of the outfall or culvert
foundation level to assess the risk of failure. The
following design formulae are suggested for estimating Scour Depth
maximum scour depths, ys, and the extent of the scour
hole, Ls, for the two distinct cases of rectangular 7.5 Use the equation due to Ruff et al (1982)
culverts or pipes producing two dimensional, 2D, jets (Ref 13):
and circular or square culverts producing three
dimensional, 3D, jets: 0.45
§ Q ·
y s = 2.07 D ¨ ¸
¨ g D5 ¸
© ¹

where ys is the depth of scour below the invert of the


outfall or culvert (in m), Q is the flow rate (in m3/s), g is
the acceleration due to gravity (m/s2) and D is the
diameter of the pipe (in m).

November 2004 7/1


Chapter 7 Volume 4 Section 2
Culverts: Scour Issues Part 7 HA 107/04

Scour Extent where U1 is the mean flow velocity at the culvert outlet
and g is the acceleration due to gravity. The length of
7.6 The overall length of the scour hole will be the scour protection blanket, Lp is dependent on the
approximately 7 times the scour depth. value of Fc:

The above formulae apply to horizontal jets. for Fc ≤ 1

Design of Scour Protection Lp


=8
D
7.7 Scour protection measures reduce the
vulnerability of a structure to failure by lining the bed for Fc > 1
material with a more erosion-resistant surface. Together
with optimisation of the outfall layout, this is one of the Lp
most common means of avoiding or controlling scour = 8 + 17 log10 Fc for yT < D/2
problems. One of the most common materials used is D
riprap, or loose quarry stone that is placed in a
controlled way to provide a blanket for scour Lp
protection. = 8 + 55 log10 Fc for yT ≥ D/2.
D
7.8 There is a wide range of proprietary and
non-proprietary scour protection materials and the
choice depends on a range of factors: construction cost/ 7.10 In order to secure the scour protection blanket in
availability, environmental considerations, accessibility place, this should be turned downwards into the bed at
and construction restraints, underwater or dry its downstream end for a distance of at least one pipe
construction, maintenance issues, etc. It should be noted diameter.
that scour protection may need to be extended beyond
the immediate vicinity of the predicted scour hole since 7.11 In some cases it may be more economical to
residual turbulence can affect the stability of the bed include an energy dissipation measure downstream of
and banks of the receiving channel (Refs 9 and 10). the pipe or culvert to reduce the energy of the flow
(see, for example, Peterka, 1978, for design guidance
and layout details) (Ref 12).
Riprap
Other Methods
7.9 Simple guidelines for sizing riprap downstream
of culverts (or outfalls) are given by Bohan (1970) 7.12 For a detailed description of these and alternative
(Ref 14): methods refer to Section 8.10 in CIRIA 168 (Ref 1) and
to CIRIA Report C551, (Ref 10) and proprietary
d literature.
= 0.25 Fc for yT < D/2
D

d
= 0.25 Fc − 0.15 for yT ≥ D/2
D
where d can be taken as the d50 size of the stone, D is
the pipe diameter, yT is tailwater depth and Fc is the
Froude number of the flow discharging from the outfall
or culvert:

U1
Fc =
gD

7/2 November 2004


Volume 4 Section 2 Chapter 8
Part 7 HA 107/04 Culverts: Screen Details

8. CULVERTS: SCREEN DETAILS

General 8.8 Where used as a debris screen the bar spacing


must not be less than 75mm centres.
8.1 The provision of screens to culverted
watercourses should be discussed and agreed with the 8.9 The individual bars of the screen should not be
relevant environmental protection agency. Screens are less than 25mm diameter or, 8x75mm where flats are
not normally necessary for large culverts. used. Bars of circular cross-section offer the better
hydraulic performance but flat bars may provide a more
8.2 Screens can serve two purposes; as a trash screen rigid structure. The maximum bar length before bracing
to retain floating debris and as a security screen to is necessary is 1.5m. Any bracing must be on the inside
restrict access to the culvert by unauthorised persons. face of the screen for ease of raking.
The screen should be readily and safely accessible for
maintenance. Note that a screen must be provided at the Security
inlet to the culvert if a security screen is installed at the
downstream end. 8.10 To prevent unauthorised removal, the screen
should be fixed to the headwall or to the headwall and
8.3 The screen should be inclined at 45o to the wing-walls. All bolts and nuts used for fixing should be
horizontal, however in circumstances where available vandal proof.
space is limited, 60o should be considered as the
maximum. The screen should have a horizontal section 8.11 Nuts should be tack welded to the bolts.
between the inclined face and the headwall. This will
enable debris to be racked up over the screen during 8.12 Screens large enough to permit man entry should
maintenance. A typical screen detail is shown as have an access panel secured with a heavy duty
Figure A5 in Appendix A. padlock. A sliding bar with padlock may afford greater
security than the use of chains (Refer to Plate A5).
8.4 Screens must never be fitted vertically to the
head wall structure. Vertical screens easily trap debris 8.13 There should be a gap of 150mm between the
and the consequent increase in water level/pressure can bottom of the screen and the apron.
cause the screen to deform if installed at the upstream
end. Vertical screens are difficult to clear and may
require operatives to lean over the headwall above the
retained water; this is dangerous. At the downstream
end, vertical screens can trap debris within the culvert
leading to blockages and the deposition of sediment.
Clearing debris from behind such a screen can be
difficult and dangerous.

8.5 It is preferable that vertical screens are


positioned in the channel immediately upstream of the
culvert inlet. These should be of restricted height so
that, if blocked by debris build up, water may flow over
the top.

8.6 A screen in the channel will cause an increase in


water level upstream.

Bar Spacing

8.7 Where used as a security screen, the bar spacing


must not exceed 150mm centres.

November 2004 8/1


Volume 4 Section 2 Chapter 9
Part 7 HA 107/04 Culverts: Environmental Aspects

9. CULVERTS: ENVIRONMENTAL ASPECTS

General Public Access

9.1 The effect a culvert has on the wildlife must be 9.10 Culverts positioned at or close to the highway
taken into consideration. Refer to Volumes 10 and 11 of boundary will be vulnerable to vandalism, investigation
the DMRB. by children, and the accumulation of litter where
adjacent access is available to members of the public.
Fish Screens should be provided, (see Chapter 8).

9.11 Maintenance inspections may need to be more


9.2 The presence of fish within the watercourse
frequent in these circumstances and hence, where
should be established prior to design work and the
possible, a means of access should be constructed,
Fisheries Officer at the relevant environmental
(see Chapter 10).
protection agency consulted. Fisheries protection advice
is given in DMRB 11, Part 10, Chapter 5.

9.3 Fish are reluctant to pass through dark waterways


and consequently fish migration may be impeded
should the culvert be inappropriately designed.
Designers should be aware that the light penetrating the
culvert is a function of its length and diameter.

9.4 Streams and rivers that support fish are generally


too large to be culverted using pipes. Long culverts and
changes of direction within the culvert should be
avoided.

9.5 Without compromising the flow characteristics,


the headwall structures should allow light into the
culvert without casting shadows across the inlet and
outlet.

Otters and Other Mammals

9.6 Mammal runs are required where the watercourse


forms the natural passage from one side of the road to
the other. Refer to HA 81 (DMRB 10.1 Part 9).

9.8 Where larger culverts have a dry weather


channel, the wet weather channel can form the mammal
run. Where no dry weather channel is featured, a run
should be attached to one or both walls. Note that the
run should be accessible from the watercourse edge, see
Figure A6 of Appendix A.

9.9 Culverts, the headwalls and adjacent vegetation


can become roosts for bats. The designer should refer to
DMRB 10.8, Chapter 9 Mitigation Measures. Culverts
of diameter greater than 1.0m can become fly through
routes for bats if located adjacent to roosts or feeding
areas.

November 2004 9/1


Volume 4 Section 2 Chapter 10
Part 7 HA 107/04 Culverts: Maintenance Issues

10. CULVERTS: MAINTENANCE ISSUES

General Desilting

10.1 To reduce operation and maintenance 10.7 Culverts with low dry weather flows may be
requirements Section 4.1 should be adhered to during isolated using stop logs (suitable frame required),
the design. plastic sheet and frame, a portable dam or sand bags
The dam should not be much higher than the water
Safety level and not above the soffit of the culvert so that, in
an emergency, water may flow over the top.
10.2 The culvert and its associated structures should
be designed to facilitate safe access for inspection and
maintenance.

10.3 The design must enable the provisions of the


Health and Safety at Work Act to be met. Provision
must be made for securing safety harnesses.

Access

10.4 Access for inspection and cleaning must be


safely attainable from within the highway boundary
unless there is a specific right of access through
adjacent property. Adequate space should be made
available for carrying out maintenance. The design must
not proceed on the assumption of such a wayleave
subsequently being granted. See Appendix D.

10.5 Where the culvert is located entirely within the


highway boundary, a handrail or balustrade should be
provided across the top of the culvert. This should be
secure and if the headwall is of brick construction,
should not be fixed to the top of the headwall.

10.6 Where the embankment slopes directly down to


the top of the outfall or culvert headwall a handrail
must be provided either along the headwall parapet or
between the slope face and the headwall. Access steps
should be constructed on the embankment above the
headwall to minimise the risk of falls or slips. The step
treads should be textured for grip and a handrail
provided.

November 2004 10/1


Volume 4 Section 2 Chapter 11
Part 7 HA 107/04 References and Bibliography

11. REFERENCES AND BIBLIOGRAPHY

1. RAMSBOTTOM D, DAY D, & RICKARD C, 3 Manual of Contract Documents for Highway


Culvert Design Manual. CIRIA Report 168, Works (MCHW) (The Stationery Office)
Construction Industry Research and Information
Association, London 1997. Volume 1: Specification for Highway Works (SHW)
(MCHW1)
2. Design Manual for Roads and Bridges
(DMRB) (The Stationery Office) Volume 2: Notes for Guidance on the Specification for
Highway Works (NGSHW) (MCHW2)
BD 12 Design of Corrugated Steel Buried
Structures with Spans not Exceeding 8m Volume 3: Highway Construction Details (HCD)
Including Circular Arches (DMRB 2.2) (MCHW3)

BD 31 Buried Concrete Box Type Structures 4. FEH (1999). “Flood Estimation Handbook,
(DMRB 2.2) Volume 2 Rainfall frequency estimation” by Faulkner
D., Institute of Hydrology, UK, ISBN for volume 2:
HD 33 Surface and Sub-surface Drainage Systems 0948540 90 7.
for Highways (DMRB 4.2)
5. YOUNG OC, BRENNAN G, & O’REILLY MP.
HA 37 Hydraulic Design of Road Edge Surface Simplified Tables of External Loads on Buried
Water Channels (DMRB 4.2) Pipelines. Transport and Road Research Laboratory.
Department of Transport, HMSO. 1986.
HA 39 Edge of Pavement Details (DMRB 4.2)
6. YOUNG OC, O’REILLY MP. A Guide to Design
HA 40 Determination of pipe and bedding Loadings for Buried Rigid Pipes. Transport and Road
combinations for drainage works Research Laboratory. Department of Transport. HMSO,
(DMRB 4.2) 1983.

HA 55 Landform and Alignment (DMRB 10.1.1) 7. ACKERS JC, BUTLER D and MAY RWP.
Design of sewers to control sediment problems, CIRIA
HA 71 The effects of highway construction on Report 141, Construction Industry Research and
floodplains (DMRB 4.2) Information Association, London 1996.
HA 78 Design of Outfalls from Surface Water 8. HR WALLINGFORD AND BARR DIH. Tables
Channels (DMRB 4.2) for the hydraulic design of pipes, sewers and channels,
Thomas Telford, ISBN 0 7277 2637 4, London 1998.
HA 81 Nature Conservation Advice in Respect of
Otters (DMRB 10.4) 9. ESCARAMEIA M. (1998). River and channel
revetments. Thomas Telford Publications, London,
Water Quality and Drainage ISBN 0 7277 2691 9.
(DMRB 11.3.10)
10. Construction Industry Research and Information
HA 106 Drainage of runoff from natural Association (2002). Manual on scour at bridges and
catchments (DMRB 4.2) other hydraulic structures. Report C551, London.

11. HOFFMANS GJCM (1997). Jet scour in the


equilibrium phase. Journal of Hydraulic Engineering,
ASCE 124, No. 4, pp 430-437.

November 2004 11/1


Chapter 11 Volume 4 Section 2
References and Bibliography Part 7 HA 107/04

12. PETERKA AJ (1978). Hydraulic design of


stilling basins and energy dissipators. Engineering
Monograph No. 25, US Bureau of Reclamation,
Engineering Research Center (Denver), USA.

13. RUFF JF, ABT SR, MENDOZA C, SHAIK A and


KLOBERDANZ R (1982). Scour at culvert outlets in
mixed bed materials. Report FHWA/RD-82/011.
Colorado State University (Fort Collins), USA.

14. BOHAN J.P. (1970). Erosion and riprap


requirements at culverts and storm drain outlets. US
Army Engineer Waterways Experiment Station.
Research Report H-70-2.

11/2 November 2004


Volume 4 Section 2 Chapter 12
Part 7 HA 107/04 Enquiries

12. ENQUIRIES
All technical enquiries or comments on this Advice Note should be sent in writing as appropriate to:

Chief Highway Engineer


The Highways Agency
123 Buckingham Palace Road
London G CLARKE
SW1W 9HA Chief Highway Engineer

Chief Road Engineer


Scottish Executive
Victoria Quay
Edinburgh J HOWISON
EH6 6QQ Chief Road Engineer

Chief Highway Engineer


Transport Directorate
Welsh Assembly Government
Llywodraeth Cynulliad Cymru
Crown Buildings M J A PARKER
Cardiff Chief Highway Engineer
CF10 3NQ Transport Directorate

Assistant Director of Engineering


The Department for Regional Development
Roads Service
Clarence Court
10-18 Adelaide Street D O’HAGAN
Belfast BT2 8GB Assistant Director of Engineering

November 2004 12/1


Volume 4 Section 2 Appendix A
Part 7 HA 107/04 Construction Details

APPENDIX A: CONSTRUCTION DETAILS

Figure A1: Typical Outfall Headwall

Figure A2: Concrete Bagwork Headwall

Figure A3: Headwall with Stilling Basin

Figure A4: Headwall with Baffle Blocks

Figure A5: Typical Screen Detail

Figure A6: Typical Mammal Run Detail

Table A1: Culvert Barrel Size Ranges

November 2004 A/1


Appendix A Volume 4 Section 2
Construction Details Part 7 HA 107/04

Figure A1: Typical Outfall Headwall

A/2 November 2004


Volume 4 Section 2 Appendix A
Part 7 HA 107/04 Construction Details

Concrete bagwork headwall

Top of headwall to be level with


top of ditch

Extend vertically
as necessary

Bagwork to be keyed
into channel slope

150
300

Over dig and backfill Concrete bagwork to clause 519


with ST4 concrete Hessian bags 450 x 300 x 150
Bagwork founded below channel bed 450 Filled with ST4 concrete
and extended beyond front of wall Each bag spiked to the one below

Figure A2: Concrete Bagwork Headwall

Plate A2: Concrete Bagwork Headwall

November 2004 A/3

You might also like