Chute Design Part 1
Chute Design Part 1
Chute Design Part 1
Symbol
Key Principles
1. The critical design components of a chute are the flow entry into the chute, the maximum
allowable flow velocity down the face of the chute, and the dissipation of energy at the base
of the chute.
2. The critical operational issues are ensuring unrestricted flow entry into the chute, ensuring
flow does not undermine or spill out of the chute, and ensuring soil erosion is controlled at
the base of the chute.
3. Most chutes fail as a result of water failing to enter the chutes properly. It is critical to control
potential leaks and flow bypassing, especially at the chute entrance.
Design Information
The material contained within this fact sheet has been supplied for use by persons experienced
in hydraulic design.
Drainage chutes are hydraulic structures that need to be designed for a specified design storm
using standard hydrologic and hydraulic equations. The hydraulic design can be broken down
into three components:
• Inlet design: flow conditions may be determined using an appropriate weir equation. It is
important to ensure that the water level upstream of the chute’s inlet will be fully contained
by the associated Flow Diversion Banks.
• Chute lining: selection of an appropriate chute lining is governed by the estimated flow
velocity, which can be determined on long chutes through use of Manning’s equation.
• Outlet design: a suitable energy dissipater or outlet structure is required at the base of the
chute. The design of these structures is usually based on the use of standard design charts.
Figure 1 – Hydraulic profile for spillway crest where only minor friction loss occurs
within the approach channel
In cases where the approach channel is short, the upstream water level (H) relative to the chute
crest can be determined from an appropriate weir equation presented in Table 1.
Table 1 – Weir equations for short spillway crest length where only minor friction loss
occurs within the approach channel
Tables 2 and 3 provides the Head–Discharge relationship for a parabolic weir (T = 3.286(Y)0.5),
and a trapezoidal weir with 2:1 (H:V) side slopes and base width (b).
Head (H) Parabolic Crest width (b) of a trapezoidal chute [1] (m)
upstream of the top width =
chute inlet (m) 3.3(y) 0.5 0.3 0.5 1.0 1.5 2.0
0.1 0.065 0.024 0.035 0.062 0.089 0.115
0.2 0.184 0.091 0.121 0.197 0.273 0.349
0.3 0.338 0.208 0.264 0.404 0.543 0.683
0.4 0.521 0.384 0.470 0.685 0.900 1.115
0.5 — 0.626 0.746 1.047 1.347 1.648
0.6 — 0.940 1.098 1.493 1.888 2.283
0.7 — 1.332 1.531 2.029 2.527 3.024
0.8 — 1.807 2.051 2.659 3.267 3.875
0.9 — 2.372 2.662 3.388 4.114 4.839
1.0 — 3.030 3.370 4.220 5.070 5.920
[1] Flat crested, trapezoidal weir profile with 2:1 (H:V) side slopes (m = 2).
Table 4 provides the head–discharge relationship for a rectangular weir with base width (b).
Table 5 – Mean rock size, d50 (mm) for batter chute outlet protection [1]
The pad lengths provided in Table 6 are suitable for temporary, rock-lined outlet structures only.
These rock pad length will not necessarily fully contain all energy dissipation and flow
turbulence; therefore, some degree of scour may still occur downstream of the outlet structure.
Table 6 – Recommended length, L (m) of rock pad for batter chute outlet protection
Figure 5 – Typical layout of a recessed rock pad for a chute (plan view)
Table 7 – Recommended recess depth, Z (m) for batter Chute outlet protection
Note: In circumstances where the outlet structure is located downstream of a smooth surface
chute, e.g. concrete-lined, then the rocks should be grouted in place to avoid displacement.
Reference:
ASCE 1992, Design and construction of urban stormwater management systems. ASCE
Manuals and Reports of Engineering Practice No. 77, and Water Environment Federation
Manual of Practice FD-20, American Society of Civil Engineers, New York.
To ensure appropriate flow entry into a chute, the chute must have a well-defined profile (either
rectangular or trapezoidal) with adequate depth to fully contain the design discharge.
Photo 5 – Spillway chute with well-defined Photo 6 – Turf chute with poorly-defined
inlet profile inlet profile causing flow bypass
The chute must also have sufficient depth and/or scour controls to prevent any erosion resulting
from splash.
Purpose
Chutes are used to transport concentrated
flow down steep slopes. They are most
commonly used on constructed slopes such
as road batters.
The emergency spillways of a Sediment
Basin is a special form of chute.
Limitations
Local topography must allow safe collection
and passage of water into the chute.
Bitumen or asphalt is generally not suitable
as a permanent chute liner.
Advantages
Temporary chutes can be both quick and
cheep to construct.
Chutes typically have a flow capacity
significantly greater than most Slope
Drains.
Disadvantages
Some chute linings have a short service
life.
Significant damage can result from
overtopping flows.
The chute lining may be subject to slippage
caused by poor foundations.
Common Problems
Inappropriate inlet geometry can cause
inflow to bypass or undermine the chute.
Severe rilling along the sides of the chute
can be caused by splash or lateral inflows
being deflected by the edge of the chute.
Erosion at the base of the chute caused by
inadequate energy dissipation.
Special Requirements
Flow Diversion Banks are often required to
control inflows.
Good subsoil drainage and foundations are
required to stabilise the chute lining.
Installation
Maintenance
1. Refer to approved plans for location
and construction details. If there are 1. During the construction period, inspect
questions or problems with the location all chutes prior to forecast rainfall, daily
or method of installation, contact the during extended periods of rainfall, after
engineer or responsible on-site officer significant runoff producing storm
for assistance. events, or otherwise on a weekly basis.
Make repairs as necessary.
2. Construct the subgrade to the
elevations shown on the plans. Remove 2. Check for movement of, or damage to,
all unsuitable material and replace with the chute lining, including surface
stable material to achieve the desired cracking.
foundations.
3. Check for soil scour adjacent the chute.
3. If the chute is temporary, then compact Investigate the cause of any scour, and
the subgrade to a firm consistency. If repair as necessary.
the chute is intended to be permanent,
4. When making repairs, always restore
then compact and finish the subgrade
the chute to its original configuration
as specified within the design plans.
unless an amended layout is required.
4. If the chute is to be lined with rock, then
avoid compacting the subgrade to a Removal
condition that would prevent the rock
1. Temporary chutes should be removed
lining from adequately bedding into the
when an alternative, stable, drainage
subgrade.
system is available.
5. Ensure the subgrade is firm enough to
2. Remove all materials and deposited
minimise water seepage.
sediment, and dispose of in a suitable
6. On fill slopes, ensure that the soil is manner that will not cause an erosion
adequately compacted for a width of at or pollution hazard.
least one metre each side of the chute
3. Grade the area in preparation for
to minimise the risk of soil erosion,
stabilisation, then stabilise the area as
otherwise protect the soil with suitable
specified in the approved plan.
scour protection measures such as turf
or erosion control mats.
7. Place and secure the chute lining as
directed.
8. If concrete is used as a lining, then
keep the subgrade moist at the time
concrete is placed. Form, cut-off walls
and anchor blocks as directed in the
approved plans.
9. Install an appropriate outlet structure
(energy dissipater) at the base of the
chute (refer to separate specifications).
10. Ensure water leaving the chute and the
outlet structure will flow freely without
causing undesirable ponding or scour.
11. Appropriately stabilise all disturbed
areas immediately after construction.