DS13 3 PDF
DS13 3 PDF
DS13 3 PDF
13
Embankment Dams
Chapter 3: Foundation Surface Treatment
Phase 4 (Final)
Embankment Dams
DS-13(3)-2: Phase 4 (Final)
July 2012
In addition to these design standards, designers shall integrate sound engineering judgment,
applicable national codes and design standards, site-specific technical considerations, and
project-specific considerations to ensure suitable designs are produced that protect the public's
investment and safety. Designers shall use the most current edition of national codes and design
standards consistent with Reclamation design standards. Reclamation design standards may
include exceptions to requirements of national codes and design standards.
Proposed Revisions
Reclamation designers should inform the Technical Service Center (TSC), via Reclamation’s
Design Standards Website notification procedure, of any recommended updates or changes to
Reclamation design standards to meet current and/or improved design practices.
Chapter Signature Sheet
Bureau of Reclamation
Technical Service Center
Embankment Dams
Chapter 3: Foundation Surface Treatment
Added definitions
Added appendices
Updated references
1
DS-13(3)-2 refers to Design Standards No. 13, chapter 3, revision 2.
Contents
Page
3.2.6.6-6 Upper Stillwater Dam. After stripping and before cleanup .. 3-32
3.2.6.6-9 Typical core contact surface treatment details, Mica Dam .... 3-33
Dewatering: Removal and control of ground water from pores or other open
spaces in soil or rock formations to allow construction activities to proceed as
intended; includes relief of ground water pressures.
Slush grout: Neat cement grout (for cracks less than ½ inch) or sand-cement
slurry (for cracks greater than ½ inch) that is placed into cracks in the foundation.
3.1 Introduction
3.1.1 Purpose
This chapter discusses foundation preparation for and placement of the first
several layers of earthfill for embankment dams and appurtenant structures.
Preparation includes excavating overburden; initial cleaning and inspection;
removal of unsuitable material; shaping the foundation surface by excavation and
filling; excavation dewatering and unwatering; and final cleanup, inspection, and
foundation approval. Final foundation cleanup is required before fill placement.
3.1.2 Scope
This chapter presents design criteria for surface treatment of an embankment dam
foundation to make it suitable for placement of the overlying embankment.
Criteria are discussed for both soil and rock foundations. Dimensions in this
chapter are listed for guidance and have been used by Reclamation on structures.
Foundation treatment for concrete dams can be found in Design Standards No. 2
(Concrete Dams), Chapter 1 (Introduction). For foundation treatment for
spillways and outlet works for both embankment and concrete dams, refer to
Design Standards No. 14 (Appurtenant Structures for Dams), Chapters 3 (General
Spillway Design Considerations) and 4 (General Outlet Works and Diversion
Design Considerations). Subsurface treatments such as foundation grouting and
cutoff walls can be found in Design Standards No. 13 (Embankment Dams),
Chapters 15 (Foundation Grouting) and 16 (Cutoff Walls). Foundation surface
treatments such as protective filters can be found in Design Standards No. 13
(Embankment Dams), Chapter 5 (Protective Filters).
3.1.5 Applicability
The procedures and recommendations in this chapter are applicable to the
construction of earth fill dams and appurtenant structures founded on either soil or
rock.
Stripping should be performed carefully to ensure the removal of all material that
may be unstable because of saturation, slaking, or decomposition; all material that
may interfere with the creation of a proper bond between the foundation and the
embankment; and all pockets of soil or rock significantly weaker or more
compressible than the average foundation material. Exploratory test pits could be
excavated if the stripping operations indicate the presence of unstable or
otherwise unsuitable material.
Figure 3.2.1-4 Mica Dam. Foundation excavation, typical excavation detail (Pratt et al.,
1972; reproduced in Fell et al., 1992).
Other adverse foundation conditions may be caused by bedded clay and shale
seams, caverns, or springs. Procedures for treating these conditions will vary and
will depend on the characteristics of the particular condition to be remedied.
Foundations such as shale, chalk, mudstone, and siltstone may require protection
against air and water slaking or, in some environments, against freezing. These
excavations may be protected by leaving a temporary cover of unexcavated
material, immediately applying a minimum of 12 inches of cement mortar to the
exposed surfaces, immediately covering with embankment material, coating with
asphalt, or any other method that will prevent damage to the foundation.
Slaking behavior varies with rock type and may require evaluation for each
individual case. Faults, shears, joints, and solution channels may contain erodible
material.
When overburden is stripped to bedrock, carefully clean the rock surface and all
pockets or depressions of soil and rock fragments before the embankment is
placed as shown in figures 3.2.4.2-1, 3.2.4.2-2, 3.2.4.2-4, 3.2.4.2-5, and 3.2.4.2-6.
This may require compressed air or water cleaning and handwork as shown in
figure 3.2.4.2-7. Rock surfaces that slake or disintegrate rapidly on exposure
must be protected immediately with embankment material, concrete (dental,
shotcrete), or by other means such as delaying final excavation until immediately
before fill placement. Foundation rock should be shaped to remove overhangs
and steep surfaces (figure 3.2.4.2-8). High rock surfaces must be stable during
construction and should be cut back to maintain a smooth, continuous profile to
minimize differential settlement and stress concentrations within the
embankment. Final slopes should be 0.5H:1V or flatter. Beneath the impervious
zone, all overhangs should be removed; stepped surfaces steeper than 0.5H:1V
and higher than 0.5 foot should be excavated or treated with dental concrete to a
slope of 0.5H:1V or flatter (figure 3.2.4.2-9). Outside the impervious zone, all
overhangs should be removed, and stepped surfaces steeper than 0.5H:1V and
higher than 5 feet should be excavated or treated with dental concrete to a slope of
0.5H:1V or flatter. These are guidelines. The final decision on shaping rock
surfaces should be made during the foundation inspection and approval process.
Figure 3.2.4.2-1 Upper Stillwater Dam. Features such as this shear zone
create foundation irregularities that require treatment. The surface should
be cleaned of all loose and weathered rock, and the shear zone should be
filled with dental concrete. Alternatively, the surface might be reformed by
smooth blasting techniques.
Figure 3.2.4.2-2 Ridges Basin Dam. This dam foundation was shaped to
ensure proper compaction of fill and to prevent stress irregularities in the
overlying embankment.
Figure 3.2.4.2-3 Extensive use of dental concrete used to fill potholes, grooves,
and channels in rock surface.
Figure 3.2.4.2-6 Ridges Basin Dam. Foundation after stripping and before
cleanup.
Slush grout or joint mortar should be used to fill narrow cracks in the foundation
as shown in figures 3.2.4.2-10 and 3.2.4.2-11. However, they should not be used
to cover exposed areas of the foundation. Slush grout and joint mortar are
composed of Portland cement and water generally for openings less than ½ inch
or, in some cases, Portland cement, sand, and water generally for openings greater
than ½ inch. The slush grout is preferably used just before fill placement to
eliminate potential for hardened grout to crack under load as the fill is placed.
Dental concrete should be used to fill potholes and grooves created by bedding
planes and other irregularities such as previously cleaned shear zones and large
joints or channels in rock surfaces as shown in figure 3.2.4.2-3. Formed dental
concrete can be used to fillet steep slopes and fill overhangs.
Figure 3.2.4.2-9 Teton Dam. The stepped surface in this right abutment key trench
could result in cracking and seepage problems in overlying embankment.
Embankment may differentially settle adjacent to these surfaces, resulting in
cracks.
Stepped surfaces that are steeper than 0.5H:1V and higher than 0.5 foot should be
excavated or treated with dental concrete to a resultant slope of 0.5H:1V or flatter,
depending on the fill material.
Figure 3.2.4.2-10 Ridges Basin Dam. Open stress relief joint in foundation
requires filling with slush grout.
Figure 3.2.4.2-11 Slush grout being applied to an open joint in a dam foundation.
If shaping requires blasting, proper blasting procedures are essential to ensure that
the permeability and strength of the rock are not adversely affected and that the
rock can stand on the slopes and handle the imposed loads. Existing fractures and
If the material cannot be excavated with a hydraulic excavator fitted with a rock
bucket, grout nipples can be set directly in the competent foundation. An
intensely weathered zone can be grouted effectively by leaving the foundation
high and setting grout nipples through the unsuitable material. Long grout nipples
may be necessary in poor quality rock. Excavation to final foundation grade is
completed after grouting.
Openings wider than 2 inches and narrower than 5 feet should be cleaned
to a depth of three times the width of the opening or to a depth where the
opening is 0.5 inch wide or less, but usually not to a depth exceeding
5 feet and treated by filling.
Shape the foundation to ensure proper compaction of fill and to prevent stress
irregularities in the overlying embankment (see figures 3.2.4.2-2 and 3.2.4.2-8).
The foundation surface should be shaped by excavating or by filling with concrete
to obtain a smooth, continuous surface.
Whenever possible, locate well points and sumps outside the area to be excavated
to avoid work interference. Avoid loosening soil or creating a "quick" bottom
caused by the upward flow of water or equipment vibration. Avoid locating
sumps and associated drainage trenches and pipes within the impervious zone
because of the difficulty in properly grouting them after fill placement and due to
the danger of damaging the impervious zone/foundation contact. Trenches and
pipes, if used, should not be aligned in the upstream to downstream direction.
Special cleanup procedures are required for foundation materials that deteriorate
(slake) when exposed to air or water. The foundation must be kept moist if
deterioration is caused by exposure to air and kept dry if deterioration is caused
by exposure to water. Cleaning the surface and placing a lean concrete “mud
slab” approximately 4 inches thick may be effective. Usually, removing the last
few inches (or feet) of material and doing final cleanup just before first placement
of fill is the best approach. A maximum time interval may also be specified
between the time of exposure of the final grade and the time that the foundation is
protected with earthfill or a suitable protective coating.
Cleanup outside the core footprint is typically less critical. Loose material should
be removed so that the embankment is in direct contact with suitable rock. If
defects are small and outside the core, they may not require cleaning and refill. If
defects are continuous upstream to downstream, they require cleaning similar to
the foundation beneath the core.
3.2.6.1 Cleaning
Foundation cleanup is labor intensive (as shown in figure 3.2.6.1-1) and costly yet
necessary. When cleaning is neglected, it results in substandard foundations that
do not meet design requirements. As appropriate, rock foundations should be
cleaned by:
Figure 3.2.6.1-1. Foundation cleanup is labor intensive and costly but should not
be neglected.
The choice of using air, air and water, or a water jet spray for cleaning is site
specific. Rock materials such as slaking shales and chalks should be cleaned with
air jets because they may be damaged by water. Where plastic soils cover rock,
surfaces cleaned with combined air and water jet sprays or water sprays are more
practical. In such cases, air is usually ineffective. Water-only sprays apply the
greatest cleaning force to the surface and are preferred in cleaning strong and
highly irregular rock surfaces. Weaker rocks such as thinly bedded sandstone
may be damaged by powerful water sprays and are often better cleaned using an
air/water mixture, which has less impact than a water-only jet. This blowdown
can be supplemented with high volume vacuum (vacuum truck) to clean the
surface of large areas, or small volume vacuum (shop vacuum) in small areas.
In areas where the rock is prone to slaking, the foundation cleanup should be
completed before slaking occurs, and foundation cleanup should not commence
until fill materials or concrete are available to be placed on the foundation.
Unless this backfill concrete has undergone most of its volumetric shrinkage at
the time overlying embankment is placed, cracks can occur in the overlying
embankment near the boundaries of the backfill concrete. Loss of support occurs
because of continuing shrinkage of the backfill concrete. Where dental work is
extensive, the backfill concrete should be placed and cured before embankment is
placed over the area.
Concrete mix proportions should provide a 28-day strength of 3,000 pounds per
square inch. The maximum aggregate size should be less than one-third the
thickness of slabs or one-fifth the narrowest dimension between the side of a form
and the rock surface. Cement type will depend on the concentration of sulfates in
the foundation materials and ground water. Low-alkali cement is required for
alkali-reactive aggregates. Aggregate and water quality should be equal to that
required in structural concrete.
The rock surface should be thoroughly cleaned and moistened before concrete
placement to obtain a good bond between the concrete and the rock surface.
When overhangs are filled with dental concrete, the concrete must be well bonded
to the upper surface of the overhang. The overhang should be shaped to allow air
to escape during concrete placement and to prevent air pockets between the
concrete and the upper surface of the overhang. The concrete must be formed and
placed so that the top of the concrete is higher than the upper surface of the
overhang so that the pressure creates a tight fit. Grout pipes should be installed in
the dental concrete for later filling of the air voids. If grouting through dental
concrete takes place, pressures should be closely controlled to prevent jacking the
concrete or fracturing the fill.
Finished dental concrete slabs should have a roughened, broomed finish for
satisfactory bonding of fill to concrete. Dental concrete should be cured by water
or an approved curing compound for 7 days or covered by earthfill. Earthfill
placement may not be permitted over dental concrete for a minimum of 72 hours
or more after concrete placement (or until 70 percent of design strength is
achieved) to allow concrete time to develop sufficient strength to withstand stress
caused by placing and compacting earthfill. Inadequate curing may cause the
concrete to crack.
The type of cement required will depend on the concentration of sulfates in the
foundation materials and ground water. Low-alkali cement is required for alkali
sensitive aggregates. Sand and water quality should be equal to that required for
structural concrete. Reclamation uses type K cement that contains anhydrous
calcium aluminate, an expanding agent that counteracts shrinkage.
Clean out cracks as described above. All cracks should be wetted before placing
slush grout. Slush grout may be applied by brooming over surfaces containing
closely spaced cracks or by troweling, pouring, rodding, or funneling into
individual cracks. Brooming slush grout is best done just before material
placement so that cracking will not occur during compaction.
3.2.6.5 Shotcrete
Shotcrete is concrete or mortar that is sprayed in place. Some shotcrete is mixed
with synthetic fibers to obtain a stronger product and so it can adhere to steeper
slopes. The quality of the shotcrete depends on the skill and experience of the
crew, particularly regarding the amount of rebound, thickness, feather edges, and
ensuring adequate thickness over protrusions on irregular surfaces. Shotcrete
should be placed in thin lifts (2 inches or less) to ensure intimate contact with the
foundation rock. Areas that have not yet been prepared can be inadvertently
covered because of the ease and rapidity of placement. Shotcrete should be used
beneath impervious zones only when site conditions preclude using dental
concrete. If shotcrete is used, close inspection and caution are necessary.
Shotcrete can be an acceptable alternative to dental concrete outside the core
contact area (figure 3.2.6.5-1).
Figure 3.2.6.6-3 Foundation for outlet works structure was shaped and
treated with dental concrete.
Figure 3.2.6.6-6 Upper Stillwater Dam. After stripping and before cleanup.
Figure 3.2.6.6-7 New Waddell Dam. After initial cleanup. Before any
treatment.
Figure 3.2.6.6-9 Typical core contact surface treatment details, Mica Dam (Pratt et al., 1972; as
reproduced in Fell et al., 1992)
The lead embankment designer has evaluated the foundation and has
determined that the foundation conforms to the design intent; that shaping,
treatment, and cleaning are adequate; and that the foundation is acceptable
for commencement of embankment placement.
The foundation should be segmented into manageable areas if the area is too
large.
Figures 3.3.1 and 3.3.2 illustrate geologic mapping and photographic methods to
document foundation conditions.
Site conditions
Foundation geology
Geotechnical considerations
Many times, the geologic features outside of the dam footprint are critical to dam
stability. For example, some very important features may not actually be exposed
in the foundation but could pass underneath it, such as low angle joints, shears, or
faults.
Figure 3.3-1 Photographic records are critical! Photos should be labeled and
related to the foundation geologic map.
Cemented and highly overconsolidated soils that break into hard chunks may
require special procedures. In some cases, they can be left in place and should not
be reworked or disked to mix foundation and core material. The first lift of
embankment material should be placed in a manner similar to that required for
rock foundations.
Soil foundation compaction requirements beneath filter and shell zones should be
the same as those outlined here, except bonding the foundation to the overlying
fill is not required.
All embankment materials should be protected from eroding into coarser soil
zones in the foundation by transitions satisfying filter criteria or by filter material
as needed. (The reverse may also be necessary if coarse fill is to be placed over
finer foundation soils.) Transition zones or filters on the downstream face of the
cutoff trench and beneath the downstream zones should prevent movement of fine
material in the foundation into the embankment.
scarifying the lift surfaces to obtain a bond between lifts. The tamping roller can
be used when the fill is sufficiently thick and regular to protect the foundation
from the tamping feet. Unit weight and moisture should be carefully monitored in
the foundation contact zone, and placing and compacting operations should be
carefully inspected. For an illustration of the process of placing embankment fill
on a rock foundation, see figures 3.4.2-4 through 3.4.2-6.
Figure 3.4.2-1 After final cleanup, the foundation is moistened prior to placing and
compacting embankment fill.
For irregular surfaces and hard to reach areas, site-specific conditions determine
whether hand-compacting earthfill or filling with dental concrete is the best
solution. The fill compaction method used depends on the steepness of the
surface, the nature of the irregularities in the foundation surface, and the fill
material.
Figure 3.4.2-4 Ridges Basin Dam. Final foundation cleanup and placing the
first lift of embankment fill.
Figure 3.4.2-5 Ridges Basin Dam. Final foundation cleanup, wetting, and
placing first lift.
The feet of the roller must not penetrate the first layer of earthfill and damage the
foundation. Penetration can be prevented by using a rubber-tired roller or loader
to compact the first few lifts above the foundation surface with scarification
between lifts. Earthfill specially compacted by pneumatic-tired equipment is
typically placed in 6-inch-maximum compacted lifts. Placement of horizontal
lifts against mildly sloping rock surfaces can result in feathering of the earthfill
lift near the edge of the lift. Placement of the initial lift parallel to the foundation
surface (as opposed to a horizontal lift) for foundation surfaces flatter than
10H:1V is acceptable if the compactor climbing up the slope does not loosen or
disturb the previously compacted earthfill.
Earthfill placed against remaining, small, uneven surfaces should be plastic and
deformable so that the material is forced (squeezed) into all irregularities on
the foundation surface by compaction or subsequent loading as shown in
figure 3.4.2-3. The soil moisture content at the first layer should range from 0 to
2 percent wet of optimum. Select material with a required plasticity range is
commonly specified. A soil plasticity index ranging from 16 to 30 is preferred
Figure 3.4.2-7 Feather edge of first lift of compacted fill removed, cleaned, and
ready for fill placement.
dispersive material, the dispersion potential generally varies greatly over short
distances. Selectively excavating nondispersive material from a deposit
containing dispersive materials is frequently difficult and unreliable. Lime can be
added to dispersive materials to reduce dispersivity or convert the soil to a
nondispersive material. The amount of lime required to treat the dispersive soil
should be established by performing dispersivity tests on samples of soils treated
with varying percentages of lime. Adding lime to a soil results in reduced
plasticity and a more brittle soil; therefore, the lime content should be the
minimum required to treat the soil. Do not treat material that has naturally low
plasticity with lime if it is not necessary.
3.5 Bibliography
Acker, Richard C., and Jack C. Jones. “Foundation and Abutment Treatment for
Rockfill Dams.” Journal of the Soil Mechanics and Foundations Division,
Proceedings of the American Society of Civil Engineers, Vol. 98, No. SM10,
pp. 995-1016.
Burke, Harris H., Charles S. Content, and Richard L. Kulesza. 1972. “Current
Practice in Abutment and Foundation Treatment.” Journal of the Soil
Mechanics and Foundations Division, Proceedings of the American Society of
Civil Engineers, Vol. 98, No. SM10, pp. 1033-1052.
Cato, Kerry D., Pete Shaffner, and Norman R. Tilford. June 23, 2000 draft.
Guidance for Preparing Dam Foundations. Special Publication, Dam
Foundation Committee, U.S. Committee on Large Dams.
Rizzo, Paul C., and John Charlton. 2008. Foundation Preparation for RCC Dams
Founded on Difficult Foundation Conditions. Presented at Hydro2008 in
Lubljana, Slovenia, October 6-8, 2008.
Sherard, J.L., R.J. Woodward, S.F. Gizienski, and W.A. Clevenger. 1963. Earth
and Rockfill Dams. John Wiley and Sons, Inc, New York, New York.
Walker, Fred C., and R.W. Bock. 1972. “Treatment of High Embankment Dam
Foundations.” Journal of the Soil Mechanics and Foundations Division,
Proceedings of the American Society of Civil Engineers, Vol. 98,
No. SM10, pp. 1099-1113.
Wallace, B.J., and J.I. Hilton. 1972. “Foundation Practices for Talbingo Dam,
Australia.” Journal of the Soil Mechanics and Foundations Division,
Proceedings of the American Society of Civil Engineers, Vol. 98,
No. SM10, pp. 1081-1098.
Position Paper
Date: 9/15/2008 .
Revised
Background and History
The Bureau of Reclamation has a long history of protecting structures from the adverse
impacts of construction blast vibrations. However, as experienced technical and
construction staff leave through retirement, the agency is in danger of losing expertise in
this area and having to re-learn the lessons of the past. This is evidenced by several
recent construction specification reviews where the vibration limits in the standard
specifications were reduced, with the only justification being a desire to be “more
conservative” without a clear idea of how this would affect the cost of the project or what
level of conservatism was really achieved. In some cases this may have resulted from a
belief that the values should lie closer to the conservative values in the Reclamation
Safety and Health Standards (RSHS). In addition, changes have been made to the RSHS
manual without consulting the technical staff, resulting in unrealistic blast vibration limits
and unclear airblast limits. Currently the agency is not allowing anything in the RSHS
document to be overridden by the construction specifications without a lengthy and time-
consuming waiver process, no matter how costly or unreasonable it might be on a
specific job. In the past, the construction specifications could override the RSHS blast
vibration limits, as discussed below.
1
noted that the type of damage observed was largely cosmetic, such as cracking of plaster,
drywall, or mortar joints between masonry blocks. In addition, these blasts were
typically large quarry blasts with the houses located at some distance from the blasting
with various foundation conditions.
About the time the Blasting Review Team was formed, the Bureau of Mines was
expanding its research into the effects of quarry blasting on residential structures. Word
leaked out that they were going to come out with more restrictive criteria. The Office of
Surface Mining reacted to this by publishing a peak particle velocity limit of 1 in/s in a
1979 edition of the Federal Register [3]. Presumably, this was intended to be an interim
guideline until the Bureau of Mines study was published. At that time the RSHS
document was being updated, and the blast vibration limit of 1 in/s from the Federal
Register was included in the revision. The Blasting Review Team recommended that this
be taken out of the RSHS, but the decision was made to leave it in, the rationale being
that it would serve as a fall back position in cases where there were no specifications
paragraphs to cover blast vibrations. Thus, the wording “unless otherwise specified by
the Bureau” was included in the RSHS document. As noted by the Blasting Review
Team report, “The Construction Safety Standards guideline provides conservative control
of blast vibrations in the absence of a specifications paragraph.” This provision was later
removed for some unknown reason.
When the Blasting Review Team Report was published in 1979, it was noted that “Due to
numerous reasons (usually short distance from blast site to a structure), it is often difficult
to maintain low peak particle velocities . . . (and) most structures can tolerate a higher
particle velocity without damage for small charges close to the structure because the
motion occurs at a higher frequency.” As a result, the team recommended allowing peak
particle velocities as high as 4 in/s for substantial structures.
When the updated Bureau of Mines criteria were published in 1980 [4], the value of 2
in/s was retained to protect residential structures when the blast vibration frequencies are
greater than 40 Hz, which is typically where construction blasts fall. At lower, more
damaging frequencies, lower vibration limits were recommended, depending on the
condition of the structure.
2
vibration, but required the blasting to be kept at a distance of 100 feet from any
structures. A concrete diversion structure was also required that eventually would
become embedded in the main roller-compacted concrete (RCC) dam. A diversion
channel through natural rock (less than 100 feet from the diversion channel) was to be
maintained until the diversion structure was constructed and river flows diverted through
it, and then the rock forming the channel was to be removed to foundation grade. The
contractor, Tyger Construction Co, claimed the 100-foot distance could not be
maintained, and the excavation could not be reasonably completed under a blast vibration
limit of 1 in/s. The contractor hired Lew Oriard, a blasting expert, and was preparing to
submit a large claim.
The design team quickly reviewed as much information as could be found on the effects
of blasting on concrete structures. To no one’s surprise, Lew Oriard had done significant
research into this topic in the early 1980’s, and had a major hand in developing blast
vibration specifications for the Tennessee Valley Authority (TVA). These specifications
allowed up to 20 in/s peak particle velocity at close distances for massive concrete
structures where the concrete was more than 10 days old. Other cases were found in the
literature where no damage was reported for concrete structures exposed to blast
vibrations up to 8 in/s. Very few cases of concrete structures damaged by blast vibrations
could be found, and those that could be found were for very green concrete (less than 2
days old) at vibrations from 6 to 20 in/s, or were old concrete in questionable condition
damaged by high vibrations exceeding 30 in/s. Based on this review, criteria were
proposed at Upper Stillwater that allowed a peak particle velocity of 8 in/s for blasting
adjacent to the diversion structure. This was accepted by the contractor, and construction
proceeded as planned. In fact, the diversion structure was exposed to blast vibrations as
high as 9 in/s with no apparent damage [5].
At Buffalo Bill Dam, the work included excavating a new gate chamber within the lower
body of the dam, demolishing some old penstock sections, and excavating a short section
of new penstock tunnel in the left abutment adjacent to the dam. Blast vibration
3
monitoring stations were established at some distance from the blasting. Blast vibrations
up to 4 in/s were allowed at these locations. Although this value was never exceeded, it
was recognized that blast vibrations in the concrete just beyond the gate chamber
excavation were considerably higher. For example, vibrations one foot beyond the
excavation line were estimated to be as high as 100 to 150 in/s based on the recordings
that were made [6], but these vibrations would be at extremely high frequencies and not
damaging. Indeed, a smooth surface was obtained with very little damage beyond the
controlled perimeter of the excavation.
At Folsom Dam, severe cavitation occurred in the outlet works during large releases. The
remedy to this situation included excavating an additional air supply tunnel through the
concrete dam. The spillway gate trunnion anchors needed to be protected, as they were
embedded within the mass concrete of the dam structure, and the tunnel passed within
close proximity of the anchors. In all, six blasts produced a peak particle velocity at the
trunnion anchors in excess of 5 in/s, with a maximum recorded value of 7.2 in/s, with no
damage noted [7]. These vibrations occurred at high frequencies. It should be noted that
strain gages were placed on four of the trunnion anchors to monitor strains within the
steel during the blasting, and all strains were below damaging levels.
Recommendations
Reclamation has developed considerable experience and expertise in blast vibration
monitoring and limits over the past 30 years. This expertise is in danger of being lost due
to retirement of experienced personnel. Given the decline in Reclamation blasting
expertise, and especially that related to blast vibration limits and monitoring, it is
recommended the following steps be taken to help ensure the agency remains credible
and that reasonable limits are placed on contractors to obtain competitive bid prices:
1. Allow the specifications paragraphs to once again over-ride the RSHS for air
blast and blast vibrations. Airblast limits are primarily related to preventing
cracked windows and tripping of sensitive switches. The limits to be placed on
airblast levels are dependent on the frequency response of the monitoring
instruments, as shown in the following table. The RSHS document is silent on the
instrumentation to be used. Hence, the airblast limits in the RSHS are not very
meaningful.
The blast vibration limits currently in the RSHS were taken from a 1979 interim
guideline from the Office of Surface Mining, and are not found in any other
guidelines currently in use. These limits are overly restrictive in most cases.
4
Once again, the RSHS document is silent on the instrumentation characteristics to
be used in measuring peak particle velocity. As originally specified, there was a
clause that allowed these limits to be overridden by the specifications paragraphs.
That clause was removed for some unknown reason.
Notes:
1. Specify where the blast monitoring will be performed. Indicate which structures
will be monitored, and where the seismographs will be positioned relative to each.
2. Do not lower the recommended values without performing an economic
evaluation of the likely impacts to the blasting operations. Lowering the vibration
limits will result in the need to add more delays and possibly more blasts.
3. For close-in blasting (e.g. less than 50 to 100 feet), it may be necessary to raise
these limits in order to accomplish the blasting. Vibrations from such blasting
will be at a high frequency, and will be less damaging. Therefore, higher values
can be tolerated. Consult with a blasting specialist when in doubt.
5
References
[1] Nichols, H.R., C.F. Johnson, and W.I. Duvall, “Blasting Vibrations and their Effects
on Structures,” Bureau of Mines Bulletin 656, 1971.
[2] Roehm, L.H., et al, “Blasting Review Team Report,” Dams Branch, Bureau of
Reclamation, Revised February 1980.
[4] Siskind, D.E., M.S. Stagg, J.W. Kopp, and C.H. Dowding, “Structure Response and
Damage Produced by Ground Vibration from Surface Mine Blasting,” Bureau of
Mines, Report if Investigation RI 8507, 1980.
[5] Scott, G.A., “Concrete and Grout Damage Control for Blasting at Upper Stillwater
Dam,” ASCE National Convention, Boston, MA, 1986.
[6] Scott, G.A., and D.L. Hinchliff, “Blasting in and Adjacent to Concrete at Buffalo Bill
Dam,” ASCE Geotechnical Earthquake Engineering and Soil Dynamics Conference,
Seattle, WA, 1998.
[7] Scott, G.A., “Blasting the Outlet Works Air Intake Tunnel through Folsom Dam,”
Technical Memorandum No. FOL-8110-CS-98-1, Bureau of Reclamation, Denver,
CO, June 1998.
6
Appendix B
Foundation Inspection
Documentation and Approval
No. 5 of Zone 1 Foundation
U. S. BUREAU OF RECLAMATION
DECISION MEMORANDUM NO. DEC-RB-8311-29
DATE: June 7, 2006
Area: Zone 1 footprint on the lower left and right abutments up to approximate
elevation 6700.
The left abutment is approved between approximate elevations 6662 and 6700, above a
line identified by Stations 22+10, 3’DS to 22+23, 225’US and below a line identified by
Stations 22+93, 204’ US to 22+90, 100’ US to 14+36, 3’ DS.
The right abutment is approved between approximate elevations 6662 and 6700, above a
line identified by Stations 15+65, 3’DS to 14+13, 225’US and below a line identified by
Stations 13+69, 204’US to 14+28, 100’ US to 14+25, 10’ US to 14+36, 3’ DS (see
attached foundation approval drawing and geologic maps).
This memorandum describes the conditions for dam foundation acceptance for final
cleaning of the exposed dam foundation beneath the Zone 1 embankment. No specific
site inspection was performed for the entire portion of the foundation described in this
document. Portions of this area were inspected by design team members prior to final
excavation and cleanup on April 25th and 26th, 2006 and during occasional site visits
during May and June. Subsequent foundation cleanup, preparation, and Zone 1
placement without the Designer present was accomplished using the attached checklist.
Initial foundation approval was granted on April 26th for both abutments between
elevations 6662 and 6700 with the following stipulations:
Final foundation approval was granted on June 7, 2006 based on occasional site visits,
email, photographic documentation, and conference call discussions. Zone 1
embankment was placed on foundation in these areas during April, May, and June 2006.
DESIGN INTENT:
The intent of the foundation is to provide a sound, competent and properly shaped surface
upon which to place dam core material. In addition, all material in the foundation which
is susceptible to piping should be removed. Potential seepage paths that could affect the
core material should be treated to eliminate/isolate them from the core.
The foundation has been excavated to bedrock within the area of acceptance. The
foundation material was generally found to be in excellent condition. Bedrock of the
Lewis Shale (unit L1) exposed in the excavation will meet the design intent at the
currently excavated depths provided that final foundation preparation is performed as
described below. The Lewis Shale is composed primarily of siltstone with some
interbedded shale and ranges from moderately hard to moderately soft.
Initial foundation excavation included the removal of the overlying alluvium and
weathered or loose bedrock. This excavation was performed primarily using Caterpillar
365 and 385 trackhoes. Excavation of the left abutment was completed in January, 2005
and was followed by cleanup for geologic mapping during February and March, 2005.
Excavation of the right abutment was completed in April and May, 2005 with the
removal of the temporary diversion channel. Excavation was followed by removal of the
remaining rubble and slaked material by backhoe bucket mounted with a butterbar.
Blowdown using high pressure air was performed to complete cleanup for geologic
mapping. Foundation grouting took place in this area from August to November 2005
and final foundation excavation and cleanup for placement of embankment was
performed in April, May, and June, 2006. The final cleanup consisted of scraping with a
Caterpillar 325 trackhoe with butterbar to perform final foundation excavation, followed
by cleanup with compressed air.
LEFT ABUTMENT
Final cleanup on the left abutment was performed in strips (roughly 5 feet in elevation)
extending upstream to downstream along the lower portions of the abutments. The
foundation in this area consists of the Lewis Shale. Several “A” joints trending
approximately N20-30W are exposed in this area of the foundation. The joints are
predominantly tight to slightly open to 1/16-inch but occasionally contain weathered
siltstone to a width of 1- to 2-inches. Where this material is weathered and soft, it is
removed by either compressed air or rock pick to a depth of three times the width and the
opening is slush grouted immediately prior to placement of Zone 1. The removal of this
material often creates an opening with a depth of 1- to 4-inches and the material generally
becomes firm and the joint tightens with depth. The slush grout is a cement/sand/water
mixture which is mixed thin enough to penetrate the joint being treated.
Photograph 1. Weathered rock materials have been excavated from an “A” joint on the left
abutment at approximate Station 22+58, 132' US in preparation for slush grouting. The weathered
materials have become firm throughout most of the exposed joint at the excavated depth.
May 23, 2006 (Photo by J. Gates) Reference Image Only
Photograph 2. Crew finishes preparing the foundation for Zone 1 placement on the lower left
abutment at approximate Station 22+30, 150' US. View looking downstream.
May 5, 2006 (photo by R. Christianson) Reference Image Only
Final cleanup for Zone 1 placement commenced on April 25th, 2006 within the
acceptance area. A Caterpillar 325 trackhoe with a butterbar initially scraped slaked and
weathered material from the previously exposed foundation surface (3- to 6-inches
average). This material was hauled to placement in Zone 5. Near vertical ledges were
scraped down to less than 1-foot in height with the trackhoe. Grout nipples were either
removed or cutoff at the surface. A blow-down crew followed the rock scraping as final
foundation cleanup progressed in approximate 5-foot high strips. The edges of the
previously placed Zone 1 is trimmed with either a backhoe or shovels to expose fresh
moist clay. The Zone 1 is then scarified prior to wheel rolling the new lift onto the
foundation. The material utilized at the foundation/embankment interface is Zone 1 from
the center of Borrow Area A, having a PI of generally greater than 18 and a moisture
content which has averaged about 3 percent wet of optimum. This material is wheel-
rolled onto the foundation using either a Caterpillar 980 or a Volvo 220D loader.
Dental concrete within this approval area of the left abutment was limited to one small
area requiring less than 2 cubic yards. This occurred near Station 22+25, 15’ US where
a near vertical ledge could not practically be excavated to a height less than 1-foot.
Sandbags and a 8” piece of plywood were used at the base of the pour to hold the
concrete in place. The location of the dental concrete is shown on the attached geologic
maps.
RIGHT ABUTMENT
A Caterpillar 365 excavator has been used to excavate weathered and fractured rock
along the right abutment between approximate Stations 14+60, 125’ US and 14+10, 215’
US. The fractured rock was originally identified during geologic mapping in June 2005
as requiring removal prior to placement of dam embankment. The fractured rock is
adjacent to a clay filled joint trending upstream/downstream along the right abutment.
The joint was identified during geologic mapping as JR234 (N84W, 68NE) and is
representative of the “C” Joint set. Joint JR 244, also mapped in this area, was similar in
nature and indicated that additional excavation was necessary. The decision was made at
that time to leave the material in place during the foundation grouting operation and
remove it as the embankment was brought up. There was no additional excavation until
late April 2006, when initial scraping for final cleanup was performed with a Caterpillar
325 excavator equipped with a butterbar, revealing a significant, clay-filled (up to 2
inches) joint. Attempts at removing the intensely fractured rock overlying the joint using
the 325 excavator were unsuccessful. The 365 track-hoe was mobilized to excavate the
rock mass on May 1st, 2006 and again May 9th and 10th, 2006.
Photograph 3. Upstream view of fractured rock prior to additional excavation taking place above
approximate elevation 6665 on the upstream right abutment. Geologist and inspectors are standing
at approximate Station 14+55, 135’ upstream of centerline.
April 27, 2006 (Photo R. Christianson) Reference Image Only
Photograph 4. Caterpillar 365 excavator beginning the additional excavation on the right abutment
to remove fractured Lewis Shale.
May 1, 2006 (Photo by J. Gates) Reference Image Only
The additional excavation has resulted in the exposure of a joint face along the abutment.
The joint strikes from N88W to N65E, and dips toward the valley at 51 to 68 degrees.
Dental concrete was used along the upstream portion of the joint face where it intersects
bedding.
Photograph 5. Additional excavation is being accomplished using a Caterpillar 365 trackhoe and is
exposing a prominent joint face on the upstream right abutment. The excavator can be seen
working on the upstream transition.
May 10, 2006 (Photo by J. Gates) Reference Image Only
Foundation grouting was performed in the area upstream of the joint face in the fall of
2005 with some of the blanket holes in the area having moderate takes in the 0 to 15- foot
stages. Many of the joints near the blanket holes were exposed during final foundation
cleanup and were filled with grout. However, it appears the grout travel in the upstream
direction was limited by the clay joint fillings.
Stress relief “exfoliation” joints are common within a section of the Lewis Shale which is
approximately 20 to 40 feet below the contact of the overlying Pictured Cliffs Sandstone
and is most prevalent along the lower portion of the grouting stairway. The jointed rock
has locally required additional excavation of up to about 4- to 6-feet. The joints roughly
parallel the excavated slope trending N60E to N80E, dipping about 50 to 60 degrees
toward the north with spacings ranging from 0.2 to 1.5 feet. The joints are predominantly
tight to slightly open to about 1/16th inch with an occasional clay filling. Minor
groundwater seepage of less than ½ gpm appears along the exposed joint traces near
Station 15+50, 50’ upstream of dam centerline. Grout from the foundation grouting
program is often seen penetrating the joints in thicknesses ranging from about 1/16th to
3/4 inch. Exposed joint traces are generally less than 3 feet long and are slush grouted
where open.
Photograph 6. Joint on right abutment near Station 14+55, 130’ US that is filled with grout from
foundation pressure grouting operations. The grout reaches a maximum thickness of about ¾ inch.
Grout can also be seen along a joint at the upper right of photo. View looking downstream.
Final cleanup in this acceptance area is predominantly within the Lewis Shale with the
exception of the extreme downstream Zone 1 footprint near the right abutment ravine
area where the Pictured Cliffs is exposed. The upper portions of the Lewis Shale remains
classified as a siltstone although it becomes increasingly sandy approaching the contact
with the overlying unit P1 of the Pictured Cliffs Sandstone. This gradational contact
between the sandy siltstone and the interbedded sandstone, siltstone, and shale, of unit P1
can be seen near the green and orange line in the following photograph.
Photograph 7. Slush grout being placed in preparation for Zone 1 embankment. This area
represents the gradational contact between the Lewis Shale and the overlying Pictured Cliffs Unit P1.
Slush grout has been required in occasional open joints along the base of the right
abutment. Most of the joints are classified within the “C” joint set and trend roughly
N65E, dipping 50-70 degrees northwest toward the valley center. Dental concrete was
required in two locations to flatten the slope to less than 0.5:1.
Photograph 6. Unformed dental concrete at the base of the exposed joint face on the right abutment
between approximate Stations 14+15, 168’ US and 14+98, 190’ US.
May 22, 2006 (Photo by J. Gates) Reference Image Only
During the foundation inspection and other site visits, methods observed which resulted
3) cleaning of discontinuities;
6) removal of any remaining rock chips or fragments that remained after the initial
These steps (methods and criteria) are described in detail in the attached foundation
cleanup checklist and are used as the basis for this and future foundation acceptance.
GEOTECHNICAL CONSIDERATIONS:
The three key functions of the bedrock foundation material beneath the Zone 1
foundation is that it must 1) not provide a weak seam of material that will form a shear
plane beneath the core of the embankment 2) provide cutoff for seepage and 3) not
contain seepage that can adversely affect the core.
The conditions exposed will provide the needed functionality after final foundation
preparation is performed (see below).
Decision:
The foundation within the limits prepared for this inspection is acceptable and meets
design intent, pending foundation preparation as established above and within the
attached foundation cleanup checklist.
H:\69-403\69-403-63.dwg, 6/7/2006 11:36:26 AM, DWF6 ePlot.pc3
H:\69-403\69-403-6 thru 23.dwg, 6/7/2006 10:13:04 AM, DWF6 ePlot.pc3