Saep 1650 PDF
Saep 1650 PDF
Saep 1650 PDF
1 Scope............................................................ 3
2 Applicable Documents................................... 3
3 Definitions...................................................... 3
4 Instructions.................................................... 4
5 Responsibilities........................................... 12
Appendix A......................................................... 14
Appendix B......................................................... 16
Appendix C........................................................ 18
Appendix D........................................................ 20
Appendix E......................................................... 21
1 Scope
This Saudi Aramco Engineering Procedure (SAEP) defines the methodology and
responsibilities for the execution of Process Automation System (PAS) projects
utilizing the Main Automation Contractor (MAC) concept.
This procedure is applicable to all Saudi Aramco capital projects, Maintain Potential
and Master Appropriations projects which include Process Automation Systems.
2 Applicable Documents
The requirements contained in the following documents apply to the extent specified in
this procedure:
3 Definitions
3.1 Acronyms
COTS Commercial Off the Shelf Equipment
DBSP Design Basis Scoping Paper
DCS Distributed Control System
DSS Decision Support System
ESD Emergency Shut Down System
Page 2 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
3.2 Terms
Page 3 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
Project Types:
Expansion:
a) Units: Adding process unit(s) within an existing operating facility
b) Equipment: Adding additional process equipment within an
existing operating facility
4 Instructions
4.1 Applicability
4.1.1 MAC shall apply to all Saudi Aramco capital projects, Maintain
Potential and Master Appropriations projects involving Process
Automation Systems.
4.1.2 For all project types, MAC should be pre-selected by SAPMT with the
MAC scope clearly defined and rolled directly under the LSTK
contractor(s).
Commentary Note:
SAPMT may elect to contract directly with a MAC for project types limited
to PA equipment expansion, upgrade, total replacement and
modernization if it has been determined that an LSTK contractor is not
deemed necessary.
4.1.3 In Projects with multiple LSTK contractors, the MAC scope shall be
shared by all LSTK contractors. Each LSTK scope shall cover the PA
scope specific to its area. One LSTK contractor shall have the overall
responsibility for PA system integration.
4.1.4 MAC shall be the single point responsible body for the overall PA
system scope including integration, rationalization and standardization.
Page 4 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
Once a project DBSP is approved, SAPMT shall detail the PA section of the
DBSP in order to generate a MAC bid package as outlined in Section 4.4 of this
procedure.
The MAC bid package should be developed by SAPMT with the assistance of a
specialized PA Design contractor during the time after the approval of DBSP
and prior to PP award.
Page 5 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
The documents that the MAC develops during the Project Proposal will
constitute the MAC/LSTK scope for the process automation part of the
project.
Page 6 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
Within the two week grace period of LSTK contract(s) award, each
LSTK should verify the Process Automation scope under its
responsibility. Identified changes and clarifications shall be discussed
and resolved by SAPMT, MAC, and LSTK contractor(s). Based on the
validation process, changes affecting MAC and LSTK scopes shall be
adjusted accordingly.
Page 7 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
Page 8 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
4.5.3.2 Equipment
Page 9 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
4.6 TimeLine
4.6.1 DBSP: DBSP is developed per current procedures and will serve as the
base line for starting MAC execution process.
The MAC Bid Package should be completed six weeks after DBSP
approval and no later than two weeks after the start of the Project
Proposal.
4.6.3 MAC Bid Slate Approval: MAC bid slate and execution plan shall be
developed and submitted for approval in parallel with the development
of the MAC bid package.
4.6.4 MAC Selection: The MAC bidding, evaluation, and selection should be
completed within eight weeks from the issuance of the MAC bid
package.
4.6.6 Project Proposal: MAC should be onboard with the PP design contractor
to develop the PP package no later than twelve weeks from the start of PP.
4.6.7 MAC Scope Adjustment: MAC should adjust any scope changes during
PP development and prior to issuance of LSTK bid package per the
approved project schedule.
Page 10 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
4.6.8 LSTK Selection: MAC should be part of the project team supporting job
explanation, clarifications, and evaluation during LSTK selection.
DBSP
Completed
PP
Completed
Design Prep./
Basic design Project Proposal phase Implementation Phase
Page 11 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
5 Responsibilities
5.2 P&CSD
a) Review/Comment on MAC Bid package
b) Participate in MAC Bids Review and selection process
c) Review/comment on MAC Scope Package
d) Support project per SAEP-16
5.3 FPD
a) Review/Comment on MAC Bid package
b) Participate in MAC Bids Review and selection process
c) Review/comment on MAC Scope Package
d) Support project per SAEP-16
5.4 Purchasing
a) Review MAC Bid Slate
b) Review Purchase Order Terms and Conditions
c) Participate in MAC Bids Review and selection process
d) Support project per SAEP-16
Page 12 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
Revision Summary
11 July 2012 Revised the “Next Planned Update.” Reaffirmed the content of the document, and
reissued with editorial changes and to replace primary contact person.
26 November 2012 Editorial revision to correct definition of OTS as Operator Training Simulator.
Page 13 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
Appendix A
Page 14 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
e) ASM
f) Etc.
14. Quantities and types of:
a) Instruments
b) Input/output points
c) Reports
d) Graphics
e) etc.
15. Lengths of cables
16. Applicable Standards
17. Inspection Requirements
18. Non Material requirements (NMR)
Page 15 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
Appendix B
Page 16 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
b) Information Systems
c) Simulation Systems
i. Operator Training Simulator
ii. Maintenance Training System
d) Advance Control
e) Alarm Management
f) Environmental Control
Page 17 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
Appendix C
Page 18 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
c) Points
d) Logic
e) Third Party Systems
f) Reports
g) Databases
h) Etc.
14. Analyzer Systems
15. PLC Design & Programming
16. Plant Network and Communication
17. Commissioning Spare Parts Planning, Purchase and Management
18. FAT and Integration Testing
19. PA Installation Plans
Page 19 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
Appendix D
Construction services outside the boundary of this appendix and not directly related to
Process Automation Systems (i.e., building construction, etc.) should be obtained via
applicable company contracting procedures.
Construction Services" that fall outside the guidelines contained in Supply Chain
Management Manual Procedures CU02.02 Requesting Services ("Requesting Installation
Services with Material") and CU02.03 Requesting Services ("Requesting Incidental
Service Visits to Saudi Arabia") shall be obtained via applicable company contracting
procedures
Page 20 of 21
Document Responsibility: Process Control Standards Committee SAEP-1650
Issue Date: 26 November 2012
Next Planned Update: 11 July 2017 Main Automation Contractor
Appendix E
MAC should submit unit rates and prices for operational services as a separate line item
in the bid package. These services will not be part of the project scope and will be
executed directly with the operating organization.
1. Training
2. Maintenance
3. Operational Spares
4. After sale support for MAC and 3rd party equipment
Page 21 of 21