CURRICULAM VITAE

ELECTRICAL CONSTRUCTION SUPERVISOR
FIROZ AHMAD
Mob, +917260061974/+919430580735
E-mail:  firoz.ahmed2006@gmail.com
Shmsfiroz73@gmail.com
OBJECTIVE
Around Nineteen years of experience in Construction and Brownfield pipeline project in Oil & Gas Industries,
Petro-chemical Industries Seeking a position  as an Electrical Supervisor in a stable organization engaged in
construction where I can perform my skills what I have achieved from my past and be the part of  that
organization.

WORK EXPERIENCE:

From 23/01/2014 to  29/10/2014
Company : sepam
Project : NDIA  Project  (Qatar)
Client : parsons
Designation: Electrical Supervisor

Job Responsibilities:
Responsible for E&I Construction GIS 220 KV and Substation comprising of two 35/10KV, 6MVA, four
6.6/415KV,2MVA and Transformers 6.6KV and 10kv switchgear & soft starter panels LV panels lighting
Panels IRP UPS control Panels and Desks installation of aviation Light & installation of Battery with
Electrolyte Field Work in CPF & Inlet Facilities installation of lighting DB, JB & MOV panels Heat tracing
And cathodic protection and Installation of HV, MV &LV Switchboard & motors fin fan Cable
Termination and Hi-pot test, cable laying And Monitor Workforce Progress Provide Technical input to
Facilitate and assist Subcontractor to safely Work Prepare the three Week forecast for submission to
The Planning department for review and to Draw up the final Execution Plan for the Electrical Depart
Initial project meeting with the Management & Superintendent to Ensure the Entire Requirement
Preparation of materials as per site Requirement Serve as day-to-day interface with Contractor electrical
Craft labor providing a focus on safety and Quality· Ensure that procedures and processes are
Understood and followed by the Construction Personnel· Monitor and ensure compliance with
Specification, procedures,and plans provide on-site Knowledge of project specific electrical installation
Requirements Champion project HSE initiatives and Ensure compliance with Company's and Contractor's
HSE plans and procedures· Interface with QA/QC Personnel to address quality issues/progress· Monitor
Workforce progress as Relative to schedule· Verify Arrival of procured equipment and engineering
Equipment· Implement Field Surveillance plans· Assist With incident response case management· Assist
With change process At the Work site· Ensure Contractors on site planning activities are appropriate to
Meet objectives Provide safety monitoring Leadership/coaching as well as participate in safety
Meetings· Participate, Coach and assist Contractor Personnel in effective pre-task planning measures in
JSA's, and toolbox Meetings· Participate in on site Risk Assessments and JSA development· Assist in

Page 1 of 6
Implementation of Emergency response & Coordinate mobilization of vendors and sub contractor onsite
Installation of marshalling cabinet DCS & plc panel operation console panel equipments such As PT FT LT
TT temperature, sensors, vibrations and gas detector control valve rotation check PAGA systems etc

From 01/11/2012 to 07/11/2013
Company : Sepam (Qatar)
Project : pmp Project Qatar  Gas(Raslafan)
Client : Tcjv
Designation: Electrical Supervisor
Nature of work
This project was involved on pipeline around 150 km  Brownfield construction of 135 Megawatt CCGT
Cogeneration power projects with Laying of 115 KV high voltage cable from GIS substation to power
Transformer  installation & erection of switchgear power and control panels UPS System fire and gas system
16.5/115kv 250 Mva  power transformer 5000 ampere isolated bus duct from CGTG to transformer low voltage
& medium Voltage and installation of GIS cable laying cable tray for power lighting welding outlet field lighting
Glanding Termination in switchgear,  motor and solo run test low & medium voltage  motor, cathodic  protection
Initial project meeting with the management & superintendent to ensure the entire requirement
Utilize and control the manpower in accordance to given the work scheduled to subcontractor.
Periodic monitoring time to time to subcontractors Preparation of materials as per site requirement and
Project specification given by Saudi aramco Provide work scheduled as per priority of requirement of
Project according to management Always conscious about the quality control of work force as per work
Scheduled and priority. Monitoring and preservation all of the olefins project for requirement such of
Power transformer LV & Mv motor, distribution transformer 13.8 kV & low voltage switchgear Effective
Manage interfaces between new and existing facilities ensure adherence to company golden HSE
Policies and aramco specification, without effective the subcontractor’s schedule .Review Energization
Energization and PMC PTW and LOTO to ensure work are carried out safely. Review B Check-sheets and
Testing Method Statements for PMC activities Attend and witness system testing as required. Provide
Technical input to facilitate and assist Contractor to safely energize all electrical systems. Develop trust
And positive team spirit within the Elect. Group Develop effective working relationship with contractor
Contractors and encourage them by commendations when so deserving Ensure Contractor adheres to
All Drawings and details thereon to erect facilities in accordance with specifications Contractors’ valid
RFIs And TQs shall be promptly addressed to avoid delays. Participate in site progress meetings and
Highlight Areas of concern which could impact schedule to management team. Ensure all interfaces
Issues are promptly addressed. Track and report daily/weekly progress and provide monthly summaries

From NOV 2008 to JuLY 2010
Company : Sepam
Project : Kyan Petrochemical(Jubail-K.s.a)
Client : KBR
Designation : E&I supervisor
Job responsibilities:
This Project is involved on full construction of 34.5/4.16  kV Substation and FAR building with the 4 no’s,
10 mva & 14nos 2.5mva transformer installation of switchgear medium and Low voltage marshaling
Cabinet Also installation of cable tray Installation of complete sub Station building work including MCC,
Relay panel & patch panel fire alarm System Annuciator panel, bus duct installation 4.16 kV & 480 volts
And ups battery charger field site Installation of lighting Earth system HV MV&LV instrument cable laying
Dressing and Glanding and termination And PAGA System and installation of street light Preparation of
Materials as per site requirement and Project Specification given by shell Provide work Scheduled as per
Priority of requirement of project According to management always conscious about the quality control
Of work force as per work Scheduled and priority for requirement such of Motor, Power transformer,
Distribution transformers Switchgear low & Medium Voltage and submitting Report to client

Page 2 of 6
From May 2007 to August 2008
Company: PM&C (Rabigh K.s.a)
Client : Mitsui Engineering & Ship Building Arabia  Ltd.
Project : Petro Rabigh Plant  Pc2
Designation: Electrical Supervisor

Nature of work:
Responsible for Construction installation, of Sub-station comprising of two 33/6.6KV, 6MVA, four
6.6/.415KV,2MVA And Two 6.6/415 Transformers, 6.6KV panels, LV panels, lighting Panels, IRP, RTU,
UPS, BC panels and Field work in CPF and Inlet Facilities, power & control cable Laying and glanding
Termination & installation of lighting DB cable tray, GI, RGS & EMT Conduit & Street light structural
Lighting etc, MV/ LV motors termination & splicing, cable lying, carry out Substation and new, elect.
Modification job in Main Control Building Besides, Electrical Equipment Preservation for all Project
Equipment also cathodic protection under ground, above ground system Installation and eraction of
CTR Rectifier, anode with JB test station

From April 2006 to Jan2007
Company : PM&C Saudi Arabia
Client : AMC Construction Company Ltd.
Project : AR-RAZI  METHNOL (Jubail K.s.a)
Designation : Electrical supervisor
Job Responsibility:
Supervision of electrical Construction installation work with proper quality within shortest time
Perform Non-deliverable activities such as survey, studies, review, and preparation of documents like
drawing, specifications And coordination Testing and commissioning of above said well within the time
scheduled This project involved installation of HV,MV LV switchgear MCC panel & IRP UPS , lighting &
distribution Board, 750 KVA transformer 5 HP to 50HP LT motors, HT/ LT cable laying termination and
installation of Lighting fixture Ladder cable tray conduit & HVAC cable termination & lightening system.

From Oct 2004 to Nov 2005
Company : PM & C Saudi Arabia
Client : TRG
Project : Aramco DHT  Complex Yanbu
Designation : Electrical supervisor
Job Responsibility;
Preparation of daily Construction work schedule and accordingly splitting the team Installation of
Electrical MV & LV panel, Transformer Periodic monitoring of works likes electrical fittings, erection of
lighting pole lighting fixture & etc. This project involved installation of MV panels,& installation of
switchgear MV & LV, cable laying, termination, earthlings, installation of lighting & power cable Tray,
lighting fixture, lighting & lighting panel

From July 2004 to Sep2004
Company : PM & C Saudi Arabia
Project : Aramco,  Abu-Safa  Oil Field Offshore  (K.s.a)
Clients : Worley Petrocon Construction Ltd.
Designation : Electrical Supervisor
Job Responsibility :
Perform difficult technical work supervising and scheduling the maintenance and repair of a variety of
Equipment Resource planning for execution of scheduled activities. Installation and commissioning of
Electrical equipment like main panels, Transformer Frequent supervision of electrical service Meeting
With client and contractor to sort out the problems arising at the time of execution Preparation of joint
Measurement with client and contractor Installation, eraction of transformer, MV & LV cable laying

Page 3 of 6
From May 2003 to Feb 2004
Company : Mazco-Sepam
Project : Jubail United Petrochemical (K.s.a)
Clients : Flour Arabia  Company Ltd.
Designation : Electrical Supervisor

Nature of work:
Installation of Transformers, Generators, and Switch gear Panels, Motor Control Centers, and UPS
Systems, Switchyard Equipments Successful installation of Cable Trays, Conduits, Cable lying, Glandi ng
And Termination of HV, LV, and Control Cables Involved in Grounding Systems, Cathodic Protection
Systems systematically planned and executed set-up of Industrial and Domestic Wiring lighting systems
Managed Foundation Heating Systems Air Handling Units, Motors, Pumps, Blowers and MOV

From Sep 2002 to April 2003
Company : Mazco-Sepam Saudi Arabia
Project : Crystal Expansion Project Yanbu (k.s.a)
Clients : Sudi Binladin
Designation: Electrical Supervisor
Nature of work:
Responsible for Construction installation, of Sub-station comprising of two 33/6.6KV, 6MVA, four
6.6/.415KV,2MVA And Two 6.6/415 Transformers, 6.6KV panels, LV panels, lighting Panels, IRP, RTU,
UPS, BC panels and Field work in CPF and Inlet Facilities, power & control cable Laying and glanding
Termination & installation of lighting DB cable tray, GI, RGS & EMT Conduit & Street light structural
Lighting etc, MV/ LV motors termination & splicing, cable lying, carry out Substation and new, elect.
Modification job in Main Control Building Besides, Electrical Equipment Preservation for all Project
Equipment also cathodic protection under ground, above ground system Installation and eraction of
CTR Rectifier, anode with JB test station

From-Nov 2001 to August 2002
Company : Mazco-Sepam
Client : Daelim Engineering & Construction
Project : AR-RAZI  METHNOL (Jubail K.s.a)
Designation : Electrical supervisor
Job Responsibility:
Non-deliverable activities such as survey, studies, review, and preparation of documents like drawing,
specifications And coordination Testing and commissioning of above said well within the time scheduled
This project involved installation of HV,MV LV switchgear MCC panel & IRP UPS , lighting &
distribution Board, 750 KVA transformer 5 HP to 50HP LT motors, HT/ LT cable laying termination and
installation of Lighting fixture Ladder cable tray conduit & HVAC cable termination & lightening system

From-July 2000 to May 2001
Company : Mazco-Sepam
Client : Siemens company Ltd.
Project : IBN-ZAHAR PP-2 Expansion Project  (Jubail K.s.a)
Designation : Electrical supervisor
Job Responsibility:
Onsite & Offsite Construction Commissioning Maintenance work. ELECTRICAL SUPERVISOR for F&G And
E&I, Cabling Erection, and Installation works. Onsite & Offsite MV, LV Substation , FAS, Cabling, Equipment
Transformers (AREVA,  BRUSH),  switchgears (ABB Switchgears),MCC, PMCC Control centers, Batteries,
UPS, Earthling Erection, Installation works to Supervise and Executive with workers team and coordinate

Page 4 of 6
with Engineers. Coordinate with Commissioning team for Startup Testing, Pre -commissioning and
Commissioning Activities, This project is involved on constructi on of two 6.6 / 4.16 kV substation with the
4 no’s, 10 mva & 14 nose, 2.5 mva transformer, installation of switchgear

From-Dec 1998 to May 2000
Company : Mazco-Sepam
Client : AMC Industrial construction company Ltd.
Project : Yanpet Expansion Project (Yanbu- K.s.a)
Designation : Electrical supervisor
Job Responsibility:
Job involved planning, conducting survey and calculating the material requirement and intimating the project
Manager,  follow  up of  drawing,  execution of  project according to the project specifications, installation, eraction  of
transformer,  MV & LV cable laying, , plant grounding .

From-Sep 1995 to May 1997
Company : UB Engineering
Client : Reliance  Petrochemical Jamnagar-India
Project : Reliance Petrochemical Jamnagar-India
Designation  : Electrical Foreman
Job Responsibility
 . Preparation of daily work schedule.
 Resource planning for execution of scheduled activities.
 Installation and commissioning of Electrical equipment like main panels, Transformer.
 Frequent supervision of electrical service.
 Execution of projects according to the tender  specification.
 Meeting with client and contractor to sort out the problems arising at the time of execution
Preparation of joint measurement with  client and contractor.
From-Sep 1995 to May 1997
Company : Artson Engineering
Client : Artson Engineering
Project : J.N.P.T Sheva Uran Dist-Raigadh,Maharastra-India
Designation : Electrical Foreman
Nature of work:
Job involved planning, conducting survey and calculating the material requirement and intimating the project
Manager,  follow  up of  drawing,  execution of  project according to th e project specifications, installation, eraction of
transformer,  MV & LV cable laying, , plant grounding .
Trainings and Seminars Educational Qualification:

Diploma in Electrical Engineering
Isc (10+2) Bihar Educational Council

Personal Skill and Competencies:
Technical: Engineering, Quality Control Analysis, Troubleshooting, Equipment Selection, Installation of Electrical
and Instrumentation equipments and utilities, Operation and Control.
Organizational and Others: Teamwork, Hardworking and Leadership.
Personal Details:
Name : Firoz Ahmad
Fathers ‘Name : Late- Mohammad Shamsul
Date of Birth : Dec, 30, 1973
Passport  no. / Palace of Issue: : F7226694 / Riyadh – K.s.a
Date of Issue / Date of Expiry : January, 07, 2008 / January, 06, 2018

Page 5 of 6
Marital Status : Married
Language : English, Arabic, Urdu & Hindi
Nationality : Indian
Permanent  Address:
Shams Manzil ,Mansha Tola
Bettiah,West-Champaran
Bihar-845438 India
Experience  Profile
I have 19 years experience in Oil Refinery, Petrochemical, Fertilizer and NGL Plant
Construction, and Shutdown. Worked as an E&I Supervisor I am fully conversant with the
International Code such as NEC and Saudi Aramco Engineering Standards and Procedure
Sabic Engineering and procedure.
Declaration:
I hereby declare that all the statements  mentioned above in my  CV are true and correct to the best of my
knowledge and belief.

Firoz Ahmad

Page 6 of 6